HomeMy WebLinkAbout2019-12-17; Municipal Water District; Resolution 1628RESOLUTION NO. 1628
A RESOLUTION OF THE BOARD OF DIRECTORS OF THE CARLSBAD
MUNICIPAL WATER DISTRICT OF THE CITY OF CARLSBAD, CALIFORNIA,
APPROVING AMENDMENT NO. 1 TO THE PROFESSIONAL SERVICES
AGREEMENT (PSA) WITH VALLEY CM, INC. FOR ADDITIONAL
CONSTRUCTION MANAGEMENT AND INSPECTION SERVICES IN AN
AMOUNT NOT TO EXCEED $184,400 FOR THE RECYCLED WATER PHASE Ill
PIPELINE EXPANSION SEGMENT 5, CAPITAL IMPROVEMENT PROGRAM (CIP)
PROJECT NO. 5208-B AND THE MISCELLANEOUS PIPELINE REPLACEMENTS,
CIP PROJECT NO. 3904.
WHEREAS, on Oct. 16, 2018, the Board of Directors of the Carlsbad Municipal Water District
(Board) of the City of Carlsbad, California approved a PSA with Valley CM, Inc. (Consultant) to provide
construction management and inspection services for construction of the Recycled Water Phase Ill
Pipeline Expansion Segment 5, CIP Project No. 5208-B, and Miscellaneous Pipeline Replacements, CIP
Project No. 3904 (Project), in an amount not to exceed $899,620; and
WHEREAS, numerous underground utilities conflicts were discovered by the construction
contractor during pre-construction investigation activities for the Project, which resulted in contract
delays and the need to redesign the contracted construction work; and
WHEREAS, the Board has determined that additional construction management and inspection
services are necessary to support the redesigned Project; and
WHEREAS, Consultant has tendered a proposal for these additional construction management
and inspection services in an amount not to exceed $184,400; and
WHEREAS, approval of Amendment No. 1 with Consultant requires Board approval as it exceeds
the executive manager's approval authority under Carlsbad Municipal Code section 3.28.040.D.3; and
WHEREAS, the current PSA expires on Oct. 17, 2020, and the parties desire to exercise the one-
year extension to Oct. 17, 2021, to ensure that the Consultant's services are available during
completion of the redesigned Project; and
WHEREAS, Amendment No. 1 to the PSA has been prepared for the president of the Board's
signature and is attached hereto as Attachment A.
Dec. 17, 2019 Item #13 Page 8 of 14
NOW, THEREFORE, BE IT RESOLVED by the Carlsbad Municipal Water District Board of Directors
of the City of Carlsbad, California, as follows:
1. That the above recitations are true and correct.
2. That the president is authorized and directed to execute Amendment No. 1 to the PSA
with Valley CM, Inc., which is attached hereto as Attachment A, to extend the PSA by
one year and provide additional construction management and inspection services for
the Project in an amount not to exceed $184,400.
PASSED, APPROVED AND ADOPTED at a Special Meeting of the Carlsbad Municipal Water
District of the City of Carlsbad on the 17th day of December 2019, by the following vote, to wit:
AYES: Hall, Blackburn, Bhat-Patel, Schumacher.
NAYS: None.
ABSENT: None.
---+-~~-=--s=-----=-=----=-.J~:..i.a..:::L!!: 1 &'PlrJi 2 /
BARBARA ENGLESON, SECRETARY Dtpll!_j
(SEAL) Ci!j
c,Jen<
Dec. 17, 2019 Item #13 Page 9 of 14
PSA 19-620TRAN
AMENDMENT NO.1 TO EXTEND AND AMEND
AGREEMENT FOR RECYCLED WATER PHASE Ill PIPELINE EXPANSION
SEGMENT 5 CONSTRUCTION MANAGEMENT & INSPECTION SERVICES
VALLEY CM, INC.
This Amendment No.1 is entered into and effective as of the ~ day of U (<m.'o,g, c:'. , 20l<t extending and amending the agreement dated October 17, 2018
(the "Agreement") by and between the Carlsbad Municipal Water District, a Public Agency
organized under the Municipal Water Act of 1911, and a Subsidiary District of the City of Carlsbad,
("CMWD"), and VALLEY CM, INC., a California corporation ("Contractor") (collectively, the
"Parties") for .
RECITALS
A. The Parties desire to alter the Agreement's scope of work to increase the
construction management and inspection services hours to cover recent change orders to the
contract; and
B. The Parties desire to extend the Agreement for a period of one (1) year ending in
October 17, 2021; and
C. The Parties have negotiated and agreed to a supplemental scope of work and fee
schedule, which is attached to and incorporated in by this reference as Exhibit "A", Scope of
Services and Fee, for a total amount of one hundred eighty-four thousand, four hundred dollars
($184,400).
NOW, THEREFORE, in consideration of these recitals and the mutual covenants
contained herein, CMWD and Contractor agree as follows:
1. In addition to those services contained in the Agreement, as may have been
amended from time to time, Contractor will provide those services described in Exhibit "A". With
this Amendment, the total annual Agreement amount shall not exceed one million, eighty-four
thousand, twenty dollars ($1,084,020).
2. CMWD will pay Contractor for all work associated with those services described in
Exhibit "A" on a time and materials basis not-to-exceed one hundred eighty-four thousand, four
hundred dollars ($184,400). Contractor will provide CMWD, on a monthly basis, copies of invoices
sufficiently detailed to include hours performed, hourly rates, and related activities and costs for
approval by CMWD.
3. Contractor will complete all work described in Exhibit "A" by October 17, 2021.
4. All other provisions of the Agreement, as may have been amended from time to
time, shall remain in full force and effect.
5. All requisite insurance policies to be maintained by the Contractor pursuant to the
Agreement, as may have been amended from time to time, shall include coverage for this
Amendment.
General Counsel Approved Version 1/30/13
1 of 3
Dec. 17, 2019 Item #13 Page 10 of 14
PSA 19-620TRAN
6. The individuals executing this Amendment and the instruments referenced on
behalf of Contractor each represent and warrant that they have the legal power, right and actual
authority to bind Contractor to the terms and conditions hereof of this Amendment.
CONTRACTOR
VALLEY CM, INC.,
a California Corporation
/) (sign here)
Galina Mochel, President
(print name/title)
CARLSBAD MUNICIPAL WATER
DISTRICT, a Public Agency organized
under the Municipal Water Act of 1911,
and a Subsidiary District of the City of
Carlsbad
By:
~ (sign here) ~ ~ J-/eclif(;ctY¥2. {}G/WJ
fc,r Barbara Engleson, Secretary 7 Ct~
Paul Mochel, Secretary
(print name/title)
If required by CMWD, proper notarial acknowledgment of execution by contractor must be
attached. If a corporation, Agreement must be signed by one corporate officer from each of the
following two groups.
Group A
Chairman,
President, or
Vice-President
Group B
Secretary,
Assistant Secretary,
CFO or Assistant Treasurer
Otherwise, the corporation must attach a resolution certified by the secretary or assistant
secretary under corporate seal empowering the officer(s) signing to bind the corporation.
APPROVED AS TO FORM:
CELIA A. BREWER, General Counsel
By Dep~d:~el
General Counsel Approved Version 1/30/13
2 of 3
Clhi<
Dec. 17, 2019 Item #13 Page 11 of 14
November 15, 2019
Valerie Airey, MPA, LEED AP
Municipal Projects Manager
Public Works
City of Carlsbad
1635 Faraday A venue
Carlsbad, CA 92008
V
V/\LLEY
c□nstruc:tlon Management
SUBJECT: Recycled Water Phase 3 Pipeline Expansion Segment 5 Project
Construction Management & Inspection Amendment Request #1
Dear Ms. Airey:
PSA 19-620TRA
Exhibit "A"
lnfo@valleycm.com 1866 966 2720
Valley CM's original budget was based on twenty-four (24) months of construction. However,
recent change orders to the contract have extended the project duration 5 months that are not
included in our scope of work. We respectfully request an amendment to our contract to
accommodate the contractor's extended contract duration.
Fee Proposal
Project Executive -Paul Mochel, PE, CCM
40 Hours (5 months@ 8 hours/month)@ $155hour
Construction Manager -Lisa Laszlo, CCM
440 Hours (5 months@ 88 hours/month)@ $145/hour
Inspector -James Gaddis
880 Hours (5 months @ 176 hours/month) @ $ 130/hour
Please call me if you have any questions.
Sincerely,
Valley Construction Management
e~
Paul Mochel, PE, CCM
Principal Construction Manager
ESTIMATED FEE
$6,200
$63,800
$114,400
$184,400
--------------------www.ValleyCM.com --------------------
son Diego • El Centro • Mexico
3 of 3 Dec. 17, 2019 Item #13 Page 12 of 14
C-22
RECYCLED WATT~
SEGMEN
SEE ABOVE RIGHT
D WATER SEGMENT 5-1 RECYCLE
C-19
C-20
t
CONFORMED
SET
C-33
t
Dec. 17, 2019 Item #13 Page 13 of 14
RECYCLED WATER SEGMENT 5-3
/
C-48
' '
' I
' I
\ POTABLE WATER
FLO\AJER FIELDS
SEE BELOW RIGHT
C-45
C-42
RECYCLED WATER SEGMENT 7
POTABLE WATER FLOWER FIELDS
C-61
"RECORD DRAWING"
fsirul CITY OF CARLSBAD ~ UTILITIES Dl\llSION
KEY MAP/I