PLANNING COMMISSION RESOLUTION NO. 1973
A RESOLUTION OF THE PLANNING COMMISSION OF THE CITY
OF CARLSBAD, CALIFORNIA, RECOMMENDING APPROVAL OF
A ZONE CHANGE TO P-M, PLANNED INDUSTRIAL, ON PROPERT
GENERALLY LOCATED ON THE NORTH SIDE OF PALOMAR
AIRPORT ROAD, SOUTH AND WEST OF PALOMAR AIRPORT,
APPROXIMATELY 3500' WEST OF EL CAMINO REAL.
APPLICANT: SIGNAL LANDMARK/CARLTON BROWNE
CASE NO: ZC-250
WHEREAS, a verified application for certain property
wit:
A portion of Lot "G" of Rancho Agua Hedionda, in the
County of San Diego, according to Map thereof No. 82
filed in the Office of the County Recorder, November
1896
11
12
has been filed with the city of Carlsbad, and referred to the
Planning Commission; and
13
14 June, 1982, hold a duly noticed public hearing as prescribed
15 to consider said request; and
16
17 considering all testimony and arguments, if any, of all perso
18 desiring to be heard, said Commission considered all factors
19 relating to the Zone Change; and
WHEREAS, the Planning Commission did on the 9th, day
WHEREAS, at said public hearing, upon hearing and
20 1 NOW, THEREFORE, BE IT HEREBY RESOLVED by the Plannin
21
B) That based on the evidence presented at the public hearin 23
A) That the foregoing recitations are true and correct. 22
Commission as follows:
Commission recommends APPROVAL of ZC-250, based on the fo
24 findings and subject to the following conditions:
25 IFindings:
26
27
1) That the zoning to P-M is consistent with the PI, (Planne
28 2) That the subject lots are adequate in size and shape to
Industrial) designation for this property as established
Land Use Element of the General Plan.
accommodate uses permitted in the zone, as discussed in t
staff report.
c -,
- I; 0 0
1
5) That the project is consistent with all city public faci * as discussed in the staff report. accommodate any increase in traffic generated by these z 3
4) That the street system serving the project is adequate t 2
3) That the zoning would not adversely impact surrounding
5
properties, as discussed in the staff report.
policies and ordinances since:
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
a) The Planning Commission has, by inclusion of an
appropriate condition to this zone change insured th
building permits will not be approved unless the Cit
Council finds that sewer service is available to ser
project. Since building cannot occur within the pro
unless sewer service remains available, the Planning
Commission is satisfied that the requirements of the public facilities element of the General Plan have b met insofar as they apply to sewer service for this
change.
b) All necessary public improvements have been provided
will be required as conditions of approval.
c) The applicant has agreed and is required by the incl of an appropriate condition to pay a public faciliti fee. Performance of that contract and payment of th
will enable this body to find that public facilities
be available concurrent with need as required by the
General Plan.
6) An Environmental Impact Report has been prepared and the Planning Commission has recommended, by minute motion, certification of the EIR to the City Council. The Draft Environmental Impact Report has been amended to include comments and documents of those testifying at the public
hearing and responses thereto. The Planning Commission certifies that the Environmental Impact Report has been completed in conformance with the California Environment
Quality Act and the State guidelines and that the Planni
Commission has reviewed, considered and evaluated the information contained in the report. The Environmental Report as so amended and evaluated is recommended for
acceptance as the Final Environmental Impact Report, and the Final Impact Report as recommended is adequate and
provides reasonable information on the project and all reasonable and feasible alternatives thereto, including project . 'I ////
26 //// I!
27 /I////
28 //// PC RES0 NO. 1973 -2-
* -, . 0 0
1
2
Conditions:
3
June 9, 1982, incorporated by reference and on file in t
1) Approval is granted for ZC-250, as shown on Exhibit "X",
shown unless otherwise noted in these conditions. Planning Department. Development shall occur substanti
4
5
6
7
2) This project is approved upon the express condition that
building permits will not be issued for development of t
subject property unless the City Engineer determines tha
facilities are available at the time of application for sewer permits and will continue to be available until tj
occupancy.
8 3,
9
20
11
12
13
This project is approved upon the express condition that
applicant shall pay a public facilities fee as required
Council Policy No. 17, dated April 2, 1982, on file wit City Clerk and incorporated herein by reference, and acc
to the agreement executed by the applicant for payment o
fee a copy of that agreement dated October 29, 1980, and amended on May 28, 1982, is on file with the City Clerk
incorporated herein by reference. If said fee is not pa promised, this application will not be consistent with t
General Plan and approval for this project shall be void
PASSED, APPROVED AND ADOPTED at a regular meeting of
l4lIPlanning Commission of the city of Carlsbad, California, held
151)9th day of June, 1982, by the following vote, to wit:
16
17
AYES : Commissioners Marcus, Schlehuber, Jose and Rawlins.
l8 /I NOES : None .
19 I\
20
21
22
23
ABSENT: Chairman Farrow, Commissioners Friestedt a Rombotis.
ABSTAIN: None. n b-4-
CLARENCE SCHLEHUBER, Vlce-Chalrman
CARLSBAD PLANNING COMMISSION
24 ATTEST : I!
RLSBAD PL
28
PC RES0 NO. 1973 -3-