HomeMy WebLinkAbout1991-07-17; Planning Commission; Resolution 3282I/ e 0 I/ PLANNING COMMISSION RESOLUTION NO. 3282
1
2
3
4
5
6
A RESOLUTION OF THE PLANNING COMMISSION OF THE CITY OF
CARLSBAD, CALIFORNIA, RECOMMENDING APPROVAL OF AN
AMENDMENT TO THE LOCAL FACILITIES MANAGEMENT PLAN FOR ZONE
24 ON PROPERTY GENEWLY LOCATED ON THE WEST SIDE OF EL
CAMINO REAL, NORTH OF CAMINO HILLS DRIVE.
APPLICANT: EAGLE CANYON
CASE NO: LOCAL FACILITIES MANAGEMENT PLAN - ZONE 24(A)
WHEREAS, a verified application has been filed with the City of Carlsbad and referrec
7 to the Planning Commission, and
8 WHEREAS, the City Council passed Resolution No. 8797 adopting the 1986 Citywidc
9 Facilities and Improvements Plan establishing facility zones and performance standards fo
lo public facilities, and
11 WHEREAS, the City Council adopted Ordinance No. 9808 requiring the processin1
12
13 ll of a Local Facilities Management Plan, and
14
15
16
Proposition E approved on November 4, 1986 by the citizens of Carlsbad, and
noticed public hearing as prescribed by law to consider said request; and I"
WHEREAS, the Planning Commission did, on the 17th day of July, 1991 , hold a duk
WHEREAS, the City Council adopted Ordinance No. 8110 and 9829 implementinj
l8 11 WHEREAS, at said public hearing, upon hearing and considering all testimony an(
19 I arguments, if any,, of all persons desiring to be heard, said Commission considered all factor
relating to an amendment to the Open Space Exhibit as well as related text of the Locz
20
21
22
NOW, TH:EREFORE, BE IT HEREBY RESOLVED by the Planning Commission a 23
Facilities Management Plan for Zone 24.
24 follows:
25
26
27
28
A) That the above recitations are true and correct.
B) That based on the evidence presented at the public hearing, the Commissio
recommends APPROVAL of the amendment to the Open Space exhibit and relate
text for Local Facilities Management Plan - Zone 24, based on the following finding
and subject to the following conditions:
II 0 0
Findinns:
1 1. That the amendment to the open space exhibit and related text for the Local Facilities
Management Plan for Zone 24 will not preclude the zone from meeting the Open
2 Space Performance Standard.
3
4
5
6
7
8
9
10
11
12
2. That the amendment to the Local Facilities Management Plan for Zone 24 is
consistent vvith the Land Use Element, the Public Facilities Element, and the other
Elements contained in Carlsbad's General Plan.
3. That the amendment to the Local Facilities Management Plan for Zone 24 is
consistent with Section 21.90 of the Carlsbad Municipal Code (Growth Management),
and with the adopted Citywide Facilities and Improvements Plan
4. This project will not cause any significant environmental impacts and a Negative
Declaration has been issued by the Planning Director on January 3, 1991.
Conditions:
1. Approval is granted for an amendment to the Open Space Exhibit and related text
changes to the Local Facilities Management Plan - Zone 24 as on Exhibit "Z" dated
July 17,1991, attached hereto, and incorporated herein by reference.
13
Commission of the City of Carlsbad, California, held on the 17th day of July, 1991, by the l4
PASSED, APPROVED, AND ADOPTED at a regular meeting of the Planning
l5 11 following vote, to wit:
16
17
AYES: Chairperson Holmes, Commissioners; Schlehuber, Savary, Erwin, Noble
and Hall.
l8 /I NOES: None.
19 I
20
21
22
ABSENT: Commissioner Schram2wm, ...."._ ,"
ABSTAIN: None. .. (1
I.
'kj ROBERT HOLMES, Chairperson
23
24
ATTEST:
CARLSBAD PLANNING COMMISSION
25
26
27
28
PC RES0 NO. 3282 -2 -
/I
a 0 EXHIBIT "2"
dated July 17, 1991
ZONE 24 LFMP AMEM)"I' - TABLE OF CHANGES
CHAPTER 1 PAGE 1 CHANGED INFORMATION I' I I
- Introduction
Changed boundaries and associated acreage on OS-1 and added RLM-8 tc 27 Build Out
Changed Open Space boundaries to reflect City General Plan 24
Constraints Map. Changed Summary to reflect new Exhibit 10
Build Out Changed Exhibit 10 to reflect change in Land Uses (ie RLM-8 and OS-I) 28
(Added footnote of explanation) It /I Bui1d Out ll 33 Changed Exhibit 12 to reflect addition of RLM-8 and associated acreage
(Added footnote of explanation) I1 I - /I II Build Out 34 Updated Exhibit 13 to reflect addition of RLM-8 and associated Build
Out DU Projections (Added footnote of explanation) IL - 11 ~ Build Out I 35 ~~ 1 Updated Exhibit 14 to reflect addition of RLM-8 and associated Build
Out Population Projections (Added footnote of explanation)
~~ ~ ~~ _~~~~_~ ~ " .I
-
I9 I I ~~ ~ ~~ ~~~ ~~~~ ~~ II H Phasing Updated p. 3 of Exhibit 15 to reflect phasing of additional Dus generated
by KM-8 for %ne 24 and Totals of Adopted LFMPs (Added footnote of explanation)
~ ~ ~~ ~~~ ~
Phasing Updated Exhibit 16 to reflect phasing of additional Dus generated by 41
RLM-8 for Zone 24 and Totals of Adopted LFMPs (Added footnote of
explanation)
Phasing Updated Exhibit 17 to reflect additional Dus generated by RLM-8 for 42
Zone 24 and Totals of Adopted LFMPs (Added footnote of explanation)
Administrative
24 Build Out year to reflect new totals and Phasing Schedule due to the Facilities
Updated Projected Population, PeSormance Standard Demand, and Zone 45
addition of 32 Dus in RLM-8
I1 ~~~-~~~~ ~
Administrative
Population Increases, and Adopted Phasing Adequacy Analysis due to the Facilities
Updated Exhibit 19 to reflect new Phasing Schedule, DU totals, 49
additional 32 Dus generated in RLM-8
Library 24 Build Out year to reflect new totals and Phasing Schedule due to the Facilities
Updated Projected Population, Performance Standard Demand, and Zone 52
addition of 32 Dus in RLM-8 II I ~ ~ ~~~ ~ ~~~
' Updated Exhibit 22 to reflect new Phasing Schedule, DU totals, 57 Library Facilities Population Increases, and Adopted Phasing Adequacy Analysis due to the
additional 32 Dus generated in RLM-8
t
1
d. 0 0
n Park Facilities
Projected Build Out Population and Performance Standard Park Demand
due to the addition of 32 Dus in RLM-8. Also change Park District 1
and Zone 24 Build Out year to reflect new totals and Phasing Schedule
Updated Zone 24 Projected Population, Performance Standard Demand, 67
Park Facilities Updated Park district 1 Build Out Demand and Projected Adequacy/ 71
Inadequacy
Park Facilities Updated Exhibit 30 to reflect new phasing schedule, DU totals, 74
Population Increases, and Adopted Phasing Adequacy Analysis due to the
additional 32 Dus generated in EM-8 (added footnote to explain new
phasing schedule)
Park Facilities Updated Exhibit 31 to reflect new phasing schedule, DU totals, 75
Population Increases, and Adopted Phasing Adequacy Analysis due to the
additional 32 Dus generated in RLM-8 (added footnote to explain new
phasing schedule)
Open Space 108 Updated Exhibit 44 to show new Open Space boundaries and totals (due to Eagle Canyon Development and revised Evan’s Point Open Space
designations)
Open Space Updated Exhibit 45 to show reduction in OS-1 and Future Open Space 109
required per the redesignation of portions of OS-1 to RLM
Open Space Changed Performance Standard acreage for Zone 24 Build Out, change 110
Space, and change Existing Acres of Performance standard Open Space
DevelopedApproved Acres and Required Performance Standard Open
Open Space Changed existing Deficiency of Performance Standard Open Space, 11 1
amount of Required Future Open Space, amount of Provided Future
Open Space, and updated adequacy findings to reflect how much Open
space Zone 24 must provide in the future
School Changed DU totals and Build Out Population 113
School 116 Updated Exhibit 48 by adding 32 Dus for RLM-8 and project breakdown
for future and Build Out Projections for Elementary, Junior H. S. and
H.S. I I I I
School I 11’ I Changed total Dus and Student population to reflect an additional 32 units
from RLM-8 II I I
School Changed breakdown of total students to reflect new student totals for 118
Zone 24
L
2