A RESOLUTION OF THE PLANNING COMMISSION OF THE CITY OF
CARLSBAD, CALIFORNIA, APPROVING THE THIRD ADDENDUM TO
ENVIRONMENTAL IMPACT REPORT 03-05(A) FOR THE DESALINATION
PLANT PROJECT (STATE CLEARINGHOUSE NO. 2004041081) TO SHIFT
THE PREVIOUSLY APPROVED LOCATION OF THE 54-INCH DIAMETER
PIPELINE APPROXIMATELY 600 FEET TO THE SOUTH OF THE
INTERSECTION OF FARADAY AVENUE AND CANNON ROAD AND
CONSTRUCT ANCILLARY FACILITIES EAST OF FARADAY AVENUE, WITHIN
THE CITY’S FUTURE VETERANS MEMORIAL PARK, IN THE MELLO II
SEGMENT OF THE LOCAL COASTAL PROGRAM AND IN LOCAL FACILITIES
MANAGEMENT ZONE 8.
CASE NAME: DESALINATION PROJECT CHANGES
CASE NO.: EIR 03-05(B)
WHEREAS, San Diego County Water Authority (SDCWA), “Developer” has filed a
verified application with the City of Carlsbad regarding property owned by the City of Carlsbad,
“Owner,” described as
Properties and right-of-way generally located within a portion of
Macario Canyon, Veterans Memorial Park and right-of-way of Faraday
Avenue identified by Assessor’s Parcel Numbers 212-010-05 and 212-
010-15
(“the Properties”); and
WHEREAS, on June 13, 2006, the City Council of the City of Carlsbad certified
Environmental Impact Report (EIR) 03-05, adopted the Candidate Findings of Fact, Statement of
Overriding Considerations, and the Mitigation Monitoring and Reporting Program for the Desalination
Plant (“Project”); and
WHEREAS, on September 15, 2009, the City Council of the City of Carlsbad certified the
First Addendum to EIR 03-05 - EIR 03-05(A), as modified with minor and immaterial design modifications
to the site plan and appurtenant facilities; and
WHEREAS, on November 29, 2012 the SDCWA approved a Second Addendum to EIR 03-
05, as SDCWA determined that minor changes to the previously approved off-site distribution system
were necessary for greater operational flexibility and efficiency in receiving and delivering the product
water from the desalination plant to the Agency’s Twin Oaks Valley Water Treatment Plant and regional
distribution system; and
PLANNING COMMISSION RESOLUTION NO. 7018
PC RESO NO. 7018 -2-
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
WHEREAS, in compliance with the California Environmental Quality Act (“CEQA”), a
Third Addendum to EIR 03-05 – EIR 03-05(B) (“Addendum”), attached to this Resolution, was prepared
by SDCWA to determine if the preparation of a subsequent or supplemental EIR was required for the
Desalination Project Changes; and
WHEREAS, on September 26, 2013, the SDCWA approved a Third Addendum to EIR 03-
05, as SDCWA had to revise the project to bury the section of pipeline proposed to be exposed and
installed below the Cannon Road bridge, and to enhance the safety and reliability of deliveries from the
desalination plant to the SDCWA’s aqueduct system; and
WHEREAS, the Planning Commission did on November 6, 2013, hold a duly noticed
public hearing as prescribed by law to consider said request; and
WHEREAS, the Addendum was presented to the Planning Commission and the Planning
Commission reviewed and considered the information contained in EIR 03-05(B) prior to approving the
Project; and
WHEREAS, at said public hearing, upon hearing and considering all testimony and
arguments, examining the Addendum, analyzing the information submitted by staff, and considering
any written or oral comments received, the Planning Commission considered all factors relating to the
Addendum.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the Planning Commission as follows:
A) That the foregoing recitations are true and correct.
B) That based on the evidence presented at the public hearing, the Planning Commission
hereby APPROVES the Addendum based on the following findings that are supported by
substantial evidence in the Record:
Findings:
1. The Planning Commission of the City of Carlsbad does hereby find:
a. it has reviewed, analyzed, and considered the Addendum to EIR 03-05(A) the
environmental impacts therein identified for this project and any comments thereon
prior to APPROVAL of the project; and
PC RESO NO. 7018 -3-
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
b. the Addendum has been prepared in accordance with requirements of the California
Environmental Quality Act, the State Guidelines and the Environmental Protection
Procedures of the City of Carlsbad; and
c. it reflects the independent judgment of the Planning Commission of the City of
Carlsbad; and
d. based on the EIA and comments thereon, there is no substantial evidence the project
will have a significant effect on the environment.
2. The Planning Commission of the City of Carlsbad does hereby find that approving the
Addendum is appropriate and in conformance with CEQA in this case because some
changes or additions to EIR 03-05(A) are necessary, but none of the conditions described
in Section 15162 of the CEQA Guidelines calling for preparation of a subsequent EIR have
occurred, in that:
a. There are no significant new environmental effects and no substantial increase in the
severity of a previously identified significant effect. The analysis and mitigation
contained in EIR 03-05(A) remain adequate to address all modifications proposed
with the off-site pipeline realignment. Although a new pipeline alignment is
proposed that was not considered in the EIR, the alignment does not present new
impacts not already considered or addressed as necessary by existing mitigation
measures.
b. There has been no substantial change with respect to the circumstances under which
the Project is being undertaken which would require major revisions to EIR 03-05(A).
c. There is no new information of substantial importance that was not known and
could not have been known with the exercise of reasonable diligence at the time EIR
03-05(A) was certified.
d. The Project will not have any significant effects not discussed in the EIR 03-05(A).
e. There are no new or additional mitigation measures that need to be added and there
are no mitigation measures previously found not to be feasible that are now found
to be feasible that would substantially reduce one or more significant effects of the
Project.
3. The Addendum is incorporated by reference herein, and the findings and substantial
evidence presented in the Addendum are adopted as findings to these proceedings.
NOTICE TO APPLICANT
An appeal of this decision to the City Council must be filed with the City Clerk at 1200 Carlsbad Village
Drive, Carlsbad, California, 92008, within ten (10) calendar days of the date of the Planning
Commission’s decision. Pursuant to Carlsbad Municipal Code Chapter 21.54, section 21.54.150, the
appeal must be in writing and state the reason(s) for the appeal. The City Council must make a
determination on the appeal prior to any judicial review.
. . .
1
2
3
4
5
6
7
8
9
10
11
12
13
14
PASSED, APPROVED, AND ADOPTED at a regular meeting of the Planning Commission of
the City of Carlsbad, California, held on November 6, 2013, by the following vote, to wit:
AYES:
NOES:
ABSENT:
ABSTAIN:
Chairperson Siekmann, Commissioners Anderson, Black, L'Heureux,
Schumacher, Scully and Segall
~ K s,;14n,. ... .,
K£RRYK:SiKMANN, Chairpers~\
CARLSBAD PLANNING COMMISSION
ATIEST:
~~
DON NEU
15 City Planner
16
17
18
19
20
21
22
23
24
25
26
27
28 PC RESO NO. 7018 -4-
THIRD ADDENDUM
PRECISE DEVELOPMENT PLAN AND DESALINATION PLANT PROJECT
FINAL ENVIRONMENTAL IMPACT REPORT (EIR 03-05)
CITY OF CARLSBAD, CALIFORNIA
State Clearinghouse No. 2004041081
EIR Certified June 13, 2006
Prepared for:
San Diego County Water Authority
4677 Overland Avenue San Diego, California 92123
Prepared by:
Dudek 605 Third Street
Encinitas, California 92024
September 2013
EXHIBIT 1
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum i
TABLE OF CONTENTS
Section Page No.
ACRONYMS AND ABBREVIATIONS ............................................................................. I
1.0 INTRODUCTION/PROJECT BACKGROUND ..................................................... 1
2.0 CEQA REQUIREMENTS ..................................................................................... 5
3.0 PROJECT LOCATION AND REGIONAL SETTING ............................................ 7
4.0 DESCRIPTION OF APPROVED PROJECT ...................................................... 13
5.0 DESCRIPTION OF PROPOSED CHANGES TO THE PROJECT ..................... 15
6.0 SAN DIEGO COUNTY WATER AUTHORITY ACTIONS .................................. 23
7.0 IDENTIFICATION OF ENVIRONMENTAL EFFECTS ....................................... 25
8.0 ANALYSIS ......................................................................................................... 27
9.0 CUMULATIVE IMPACTS ................................................................................... 43
10.0 GROWTH-INDUCING IMPACTS ....................................................................... 49
11.0 CONCLUSION ................................................................................................... 51
12.0 REFERENCES ................................................................................................... 53
FIGURES
1 Regional Map .................................................................................................................... 9
2 Vicinity Map ..................................................................................................................... 11
3 Macario Tunnel Easements–City Of Carlsbad Option .................................................... 17
4 Proposed Macario Tunnel Design Station 101+50.00 to Station 117+73.72 .................. 19
5 Faraday Avenue Macario Tunnel Pit Site Plan ............................................................... 21
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum ii
ACRONYMS AND ABBREVIATIONS
CARB California Air Resources Board
CCC California Coastal Commission
CCR California Code of Regulations
CEQA California Environmental Quality Act
CO2 carbon dioxide
dB decibel
EIR Environmental Impact Report
EIS Environmental Impact Statement
EPS Encina Power Station
ERP Emergency Response Plan
FEIR Final Environmental Impact Report
GHG greenhouse gas
GHG Plan Energy Minimization and Greenhouse Gas Reduction Plan
mgd million gallon per day
MMRP Mitigation and Monitoring Reporting Program
PDP Precise Development Plan
REC Renewable Energy Credit
SDG&E San Diego Gas and Electric
SWPPP Stormwater Pollution Prevention Plan
TOVWTP Twin Oaks Valley Water Treatment Plant
Water Authority San Diego County Water Authority
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 1
1.0 INTRODUCTION/PROJECT BACKGROUND
The City of Carlsbad prepared and certified the Carlsbad Precise Development Plan (PDP) and
Desalination Plant Final Environmental Impact Report (FEIR) (City of Carlsbad 2006), and
approved a First Addendum (City of Carlsbad 2009). Subsequently, the San Diego County
Water Authority prepared and approved a Second Addendum (Water Authority 2012) for the
Carlsbad Desalination Project (Project). The FEIR analyzed all components of the Project,
including a 50 million gallon per day (mgd) seawater desalination plant and off-site water
conveyance facilities located within the cities of Carlsbad, Oceanside, and Vista. The First
Addendum documented changes to the footprint of the desalination plant and off-site water
conveyance facilities. The Second Addendum documented the change in environmental
impacts associated with the Twin Oaks Valley Water Treatment Plant (TOVWTP) modifications
(located in unincorporated San Diego County), Pipeline 3 relining, aqueduct connection point
modifications, Pipeline 4 vent replacement and pipeline interconnect, and the Macario Canyon
pipeline alignment modification and pumping well. Pursuant to Section 15367 of the California
Environmental Quality Act (CEQA), the City of Carlsbad was the lead agency for the preparation
of the FEIR and First Addendum. The FEIR documented that agencies other than the City of
Carlsbad will use the FEIR when making a decision on aspects of the Project that require their
approval. As noted in Section 3.4.2 of the FEIR, the product water created at the seawater
desalination plant would be transmitted to local and/or regional storage and distribution
systems. The delivery area for the product water was expected to include a number of local
water agencies, municipalities, and the San Diego County Water Authority (Water Authority) and
its member agencies. The Project described in the FEIR included the construction of new off-
site pipelines that would need to be constructed to convey the product water to the City of
Carlsbad, neighboring water agencies, and/or the Water Authority. Although multiple alternative
pipeline alignments were analyzed by the City of Carlsbad in the FEIR, the analysis did not
include potential impacts associated with modifying the Water Authority’s facilities that would
convey product water to the Water Authority distribution facilities (City of Carlsbad 2006).
The Water Authority has determined that minor changes to the Macario Canyon pipeline
alignment are preferred in order to allow for greater pipeline operational efficiency and reliability,
while also relocating the pumping well from the center of Macario Canyon to a location east of
Faraday Avenue and outside of Macario Canyon. Pursuant to Section 15381 of CEQA, the
Water Authority is a responsible agency for the preparation of this Third Addendum to the
Project’s FEIR. The purpose of this Third Addendum is to evaluate the potential for
environmental effects of the Water Authority’s proposed minor modifications to the approved
project and to determine if these modifications would result in any new significant impacts or
any substantial increase in the severity of impacts addressed under the certified FEIR, as
amended by the First Addendum and the Second Addendum.
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 2
To enhance the reliability of deliveries from the Project to the Water Authority’s aqueduct
system, the Water Authority is proposing minor modifications to the Project scope previously
approved in the FEIR, First Addendum and Second Addendum. Specifically, this includes an
alternative pipeline alignment and facilities additions near Cannon Road and Faraday Avenue.
These improvements are under consideration to ensure the desalinated product water can be
reliably integrated into the Water Authority’s existing regional distribution system. A description
and purpose for each of these modifications is further discussed in Section 5.0.
On June 13, 2006, the City of Carlsbad approved the FEIR for the land use approvals to construct
and operate the approximately 50 mgd Carlsbad Seawater Desalination Plant (desalination plant)
adjacent to the Encina Power Station (EPS). The FEIR also analyzed 17.4 miles of off-site
conveyance pipelines, as well as ancillary facilities to carry and store product water from the
desalination plant (City of Carlsbad 2006). The FEIR included analysis of multiple options for the
water conveyance pipelines, to allow for flexibility in the final design. To ensure that all impacts
associated with the ultimate pipeline alignment were addressed, the FEIR considered at an equal
level of detail the impacts associated with two primary pipeline alignment options, as well as
several sub-alignments, though only one alignment was actually going to be built.
On September 15, 2009, the City of Carlsbad approved an Addendum to the FEIR (First
Addendum), which documented changes to the footprint of the desalination plant and off-site
water conveyance facilities. The pipeline alignment considered under the First Addendum
consisted of approximately 16.2 miles of pipeline (a 7% reduction from the pipeline length
analyzed in the FEIR). Additionally, with the pipeline alignment addressed under the First
Addendum, environmental impacts associated with several segments of pipeline that were
evaluated and mitigated for in the FEIR were avoided. Thus, the proposed project under the
First Addendum represented reduced environmental impacts as compared to the impacts
covered under the FEIR (City of Carlsbad 2009).
On November 29, 2012, the Water Authority approved the Second Addendum to the FEIR,
which documented changes to the footprint associated with the TOVWTP modifications,
Pipeline 3 relining, aqueduct connection point modifications, Pipeline 4 modifications, and the
Macario Canyon pipeline alignment modification and pumping well. Modifications to TOVWTP
included a new valve vault structure on Pipeline 3, a new pipeline to connect Pipeline 3 to
existing water storage tanks, a chemical injection and monitoring station and pump well, as
well as a new flow-control facility and pipeline. Pipeline 3 modifications included the
replacement of a 500 ft section and the relining of a 5.5 mile segment. Aqueduct Connection
Point modifications included the installation of valves in Pipelines 3 and 4, a flow meter and
appurtenant piping. Pipeline 4 modifications included the replacement of a vent structure
along the pipeline, and the addition of a pipeline to connect Pipelines 3 and 4. The Macario
Canyon Pipeline modifications included a shift in the location of the pipeline approximately
1,000 feet to the south and the addition of a pumping well to be installed alongside the
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 3
pipeline. No new significant impacts and no substantial increase in impacts were found to
result from these modifications (Water Authority 2012). The proposed project under the
Second Addendum represented reduced environmental impacts as compared to the impacts
covered under the FEIR.
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 4
INTENTIONALLY LEFT BLANK
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 5
2.0 CEQA REQUIREMENTS
California Code of Regulations (CCR), Title 14 (CEQA Guidelines), Sections 15162 through
15164 discuss a lead or responsible agency’s responsibilities in handling new information that
was not included in a Project’s FEIR. The provisions of Section 15164 apply to the Water
Authority as the responsible agency under CEQA because the proposed modifications to the
Project involve actions that are under the purview of the Water Authority.
Section 15162 of the CEQA Guidelines provides:
(a) When an EIR has been certified…for a project, no subsequent EIR shall be prepared for
that project unless the lead agency determines, on the basis of substantial evidence in
the light of the whole record, one or more of the following:
1. Substantial changes are proposed in the project which will require major
revisions of the previous EIR…due to the involvement of new significant
environmental effects or a substantial increase in the severity of previously
identified significant effects;
2. Substantial changes occur with respect to the circumstances under which the
project is undertaken which will require major revisions of the previous EIR …
due to the involvement of new significant environmental effects or a substantial
increase in the severity of previously identified significant effects; or
3. New information of substantial importance, which was not known and could not
have been known with the exercise of reasonable diligence at the time the
previous EIR was certified as complete…shows any of the following:
(A) The project will have one or more significant effects not discussed in the
previous EIR;
(B) Significant effects previously examined will be substantially more severe
than shown in the previous EIR;
(C) Mitigation measures or alternatives previously found not to be feasible
would in fact be feasible and would substantially reduce one or more
significant effects of the project, but the project proponents decline to
adopt the mitigation measure or alternative; or
(D) Mitigation measures or alternatives which are considerably different from
those analyzed in the previous EIR would substantially reduce one or
more significant effects on the environment, but the project proponents
decline to adopt the mitigation measure or alternative.
Alternatively, where some changes or additions are necessary to the previously approved FEIR, but
none of the changes or additions meet the standards as provided for, a subsequent EIR pursuant to
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 6
CEQA Guidelines, Section 15162, then the lead or responsible agency is directed to prepare an
addendum to the FEIR. (CEQA Guidelines, Section 15164). Further, the addendum should include
a “brief explanation of the decision not to prepare a subsequent EIR pursuant to Section 15162,”
and that “explanation must be supported by substantial evidence.” (CEQA Guidelines, Section
15164(e)). The addendum need not be circulated for public review, but may simply be attached to
the FEIR (CEQA Guidelines, Section 15164(c)).
This Third Addendum to the FEIR fulfills and conforms to the provisions of CEQA (California Public
Resources Code, Section 21000 et seq.) and the CEQA Guidelines, Section 15164, providing for
the preparation of an addendum. The CEQA Guidelines allow the preparation of an addendum to an
EIR under the following circumstances (14 CCR 15000 et seq.):
1. Only minor technical changes or additions are necessary to make the EIR under
consideration adequate;
2. The changes and additions to the EIR do not raise important new issues about
significant effects on the environment;
3. None of the conditions described in Section 15162, CEQA Guidelines, calling for the
preparation of a subsequent EIR have occurred.
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 7
3.0 PROJECT LOCATION AND REGIONAL SETTING
The Macario Canyon Pipeline Alignment Modification would be located south of the intersection of
Cannon Road and Faraday Avenue, in the City of Carlsbad, and ancillary facilities would be installed
in an open space area outside of Macario Canyon, east of Faraday Avenue, in the City of Carlsbad
(see Figure 1, Regional Map and Figure 2, Vicinity Map) . The major ancillary facilities include an
access road off of Faraday Avenue, a pump well and air release vault, a blow off valve vault, several
vents, and a storm drain with a riprap energy dissipater.
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 8
INTENTIONALLY LEFT BLANK
Project Site
P a c f c
0 c e a n
0 15
lllll•llllt==:ill•lllllll Miles
5 10
DUDEK FIGURE 1
Regional Map
7662 Third Addendum, Precise Development Plan and Desalination Plant Project, Final Environmental Impact Report (EIR 03-0 )
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 10
INTENTIONALLY LEFT BLANK
"0 )( E u > N
en ii:
DUDEK
7662
FIGURE 2
Vicinity Map
Third Addendum. Precise Development Plan and Desalination Plant Project. Final Environmental Impact Report (EIR 03-0
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 12
INTENTIONALLY LEFT BLANK
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 13
4.0 DESCRIPTION OF APPROVED PROJECT
In 2006, the City of Carlsbad approved an amendment to the PDP for the EPS to obtain land use
approvals to construct and operate an approximately 50 mgd desalination plant and other
appurtenant and ancillary water and support facilities to produce potable water. The Carlsbad
Desalination Plant is to be located on the EPS site, adjacent to the existing power plant, located
immediately south of the Agua Hedionda Lagoon, within the City of Carlsbad, in northern San
Diego County. As approved in 2006, several pipeline routes would distribute product water from
the Carlsbad Desalination Plant to the City of Carlsbad and various local and regional water
agencies, including the Water Authority.
The FEIR analyzed multiple off-site pipeline alignments through portions of Carlsbad,
Oceanside, and Vista. In 2009, the City of Carlsbad approved the First Addendum to
document minor modifications to the desalination plant site layout and the off-site product
water pipeline routes. In 2012, the Water Authority approved the Second Addendum to
document modifications to the off-site water conveyance facilities. The proposed pipeline
crossing Macario Canyon was analyzed as two different alignments in the FEIR: one using
trenchless construction methods north of Cannon Road (within open space), and one laying
the pipelines within the existing roadway/bridge. The Coastal Development Permit for the
Project further indicated that the pipelines would hang underneath the Cannon Road Bridge in
the event that the trenchless option was not selected. Per the currently approved project (as
analyzed in the Second Addendum), the pipeline would be installed underground within
Macario Canyon, south of the intersection of Cannon Road and Faraday Avenue, instead of
the two aforementioned options proposed in the FEIR, and would require a permanent
pumping well in the center of Macario Canyon.
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 14
INTENTIONALLY LEFT BLANK
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 15
5.0 DESCRIPTION OF PROPOSED CHANGES TO THE PROJECT
The goal of the proposed Project changes is to enhance pipeline operational efficiency and
reliability as well as reduce the impacts to sensitive habitat within Macario Canyon associated with
the previous proposals. The Macario Canyon Pipeline Alignment Modifications involve
underground trenchless pipe installation crossing Macario Canyon. As stated previously, ancillary
facilities would be installed east of Faraday Avenue, within the City of Carlsbad’s future Veteran’s
Memorial Park. The ancillary facilities include an access road off of Faraday Avenue, a pump well
and air release valve vault, a blow off valve vault, several vents, and a storm drain with a riprap
energy dissipater. The FEIR analyzed this segment of pipeline under two scenarios: open
trenching within Cannon Road coupled with attaching the pipeline to the Cannon Road bridge;
and trenchless construction just north of Cannon Road across Macario Canyon. The Second
Addendum analyzed this segment of pipeline using trenchless construction south of the
intersection of Cannon Road and Faraday Avenue. Since the installation of this portion of the
Macario Canyon pipeline route was included in the FEIR and the Second Addendum using
trenchless construction, no further analysis of the underground pipeline installation beneath
Macario Canyon is required under CEQA. The minor change in alignment and similar construction
techniques beneath sensitive wetland areas would not represent a substantial change in the
Project or its effects.
The Project modifications shift the location of the pipeline in this area approximately 800 feet to
the south of the intersection of Faraday Avenue and Cannon Road and relocate ancillary facilities
east of Faraday Avenue, within the City of Carlsbad’s future Veteran’s Memorial Park, to allow for
operation and maintenance of the pipeline outside of Macario Canyon. A gated and paved
access road will be constructed to allow access to facilities east of Faraday Avenue. These
facilities include an approximately 225 square foot pump well and air release vault, an 80 square
foot blow off valve vault, several vents, and a storm drain with a riprap energy dissipater (Figures
3 through 5).
Construction of the trenchless tunnel for the pipeline would occur beneath an open space area
in Macario Canyon with portals located within the center median on Cannon Road and an open
space area within the future Veteran’s Memorial Park east of Faraday Avenue. The Water
Authority will establish a 40 foot wide subsurface easement for the pipeline under Macario
Canyon between the Cannon Road and Faraday Avenue portals, as well as an 80 by 80 foot
permanent easement for the ancillary facilities, and a 200 by 200 foot temporary construction
easement for the tunnel portal and staging area, east of Faraday Avenue. Importantly, the
pumping well in the center of Macario Canyon (proposed as part of the Second Addendum) has
been relocated to the permanent easement immediately east of Faraday Avenue.
Consequently, no ground disturbance would occur within Macario Canyon and impacts to
sensitive habitats would be avoided. No access to Macario Canyon will be required for
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 16
construction, operation, or maintenance of the pipeline. Construction of the pipeline and
ancillary facilities would take approximately 15 months and is anticipated to begin in early 2014.
A 24-foot by 12-foot tunnel pit will be constructed near the center median of Cannon Road as
the western entry location for the trenchless operation. From this location, excavation will
proceed using a roadheader tunnel excavator which would move through the excavated tunnel,
cutting earth with an articulated boom fitted with cutting teeth. Rubber tired underground loaders
with 2 cubic yard capacity would move the excavated material out of the tunnel.
From the eastern end, a tunnel boring machine will be launched from an 18 foot diameter tunnel
pit east of Faraday Avenue. A tunnel shield or tunnel boring machine (TBM) would be advanced
using hydraulic jacks against the tunnel ground supports (tunnel ribs). As the TBM advances the
tunnel support exits the tail shield and the ring steel set is then expanded using hydraulic jacks.
The TBM will tunnel into the completed western tunnel and be removed on skids to the Cannon
Road shaft where the TBM would be removed in sections.
Pipe loading in the western end of the tunnel would be by rubber tire pipe dolly and a pipe
saddle. Pipe joints will be taken in one at a time and welded to the previously installed pipe joint.
From the eastern end, a concrete slab will be placed on the floor of the tunnel to facilitate the
installation of the carrier pipe by direct jacking the pipe on redwood skids or casing spacers as
each joint is welded at the Faraday Avenue pit location.
Pipe joints are expected to be 20 feet, but other joint lengths can be used depending upon the
dimensions of the tunnel launching pit and interference in the shafts. Each pipe joint would be
supported on a precast concrete block near the pipe joint as the pipe is installed. The blocks are
constructed to allow for jacking and shimming each joint of pipe to final grade.
Low density cellular concrete would be pumped into the annular space between the pipe and
the tunnel. Bulkheads would be constructed at the low point of the tunnel reaches and backfill
would proceed upgrade to the receiving pit bulkheads. This tunneling method, as opposed to
horizontal directional drilling or microtunneling, does not require pressurized grout as part of the
tunneling method. Therefore, frac-out and caving are not expected to be an issue.
E ~ i
I ~ i ~ DUDEK
~1-------~
i ~ 7662
c
SOURCE: TETRA TECH 2013
Third Addendum, Precise Development Plan and Desalination Plant Project, Final Environmental Impact Report (EIR 03-05)
FIGURE3
Macario Tunnel Easements-City Of Carlsbad Option
~----------~----------------------------------------------------------------------------------------------------------------------------------------------------------------------~
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 18
INTENTIONALLY LEFT BLANK
J I
5 " ID S G 2
_WT VEL J IN rs PE 46.9
rn JdD" "'T " niA lto;~D '"'' 1'\
-~ 140 E T 457. -.~ --t-:: ~ 1--~
t-::i -l ./ v -""~ :~"" -L'~)
-~ 100 J
I\
I
\
lD
1\.! ci .... ....
"·' -~ 60
z
t
'-' ) I" \ rflN SH D GR D C E -,:;
-~ 20
~E DCC45 OR
.... .... ~v•
PC pu:-iRo n c
\-0"1 '11 ") A I I + .5
I E 8. 7
100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117
N
+
I~
~I
.I'-
tlll3
1'-
Z IU.
Ia,
I~
z
0
118
..._ ID Nk ..
N:W20 E OY
I
I
I
I
I
1 r 140 -IL
CITY OF CARLSBAD -
-
-DATE P.E. __ EXP. __ -
REVIEWED BY: -
INSPECTOR DATE -
I I I I r 1 OO -I I I I L
I I I I
0 20 40 80
SCALE: HDRIZ 1 "=80'
0 4 8 16
SCALE: VERT 1"= 16'
I
lr
IL
I . TUNNELING SUB CONTRACTOR SHALL CALCULATE
INVERT ELEVATIONS OF TIJNNEL BASED ON
SPACER SYSTEM AND PROVIDE FOR AS-BUILTS.
60 -
M
T"""
0 ~ 0 M -co
0 -z
C)
(f) w
0
"\.. ~O~'.Jx 200' TEMPORARY
CONSTRUCTION EASEMENT
~
0
0
T"""
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 20
INTENTIONALLY LEFT BLANK
E -e i i -e i ~ ~ §
~ ~ ~
"'· ~
I
I
NOTES:
so PROTEC~V.i, 2£
EXIST S~.LET
1. SOUND WALLS AND OTHER SOUND MITIGATION MEASURES WILL BE IMPLEMENTED
WHEN NESTING BIRDS ARE DOCUMENTED WITHIN 500 FT OF CONSTRUCTION AREA.
2. CONTRACTOR TO INSTALL LOW FENCING OR CONSTRUCTION FENCING DELINEATING
AREAS OF PROTECTED HABITAT. SIGNAGE SHALL INDICATE THAT THIS IS AN
ENVIRONMENTALLY PROTECTED AREA AND PERSONNEL ARE NOT TO EN~R.
5 0
SCALE: 1"=1 o·
2
z
(!)
en
UJ
0
cf2.
0 0
~
~~[)--lJ __ [) __ E_J( __ ~-so_u_RC-E:-~-T-AA-TE-C-H2-0-13---------------------------------------------------------------------------------------------------------------------------------------F-IG_U_R_E_S--~
~ f---------1 Faraday Avenue Macario Tunnel Pit Site Plan
i 7662 § Third Addendum, Precise Development Plan and Desalination Plant Project, Final Environmental Impact Report (EIR 03-05)
L-----------~------------------------------------------------------------------------------------------------------------------------------------------------------------------------------~
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 22
INTENTIONALLY LEFT BLANK
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 23
6.0 SAN DIEGO COUNTY WATER AUTHORITY ACTIONS
To process the proposed changes, the following Water Authority actions are required:
1. EIR 03-05(B) – Third Addendum to the Project’s certified FEIR; as a responsible
agency under CEQA, the Water Authority will be approving this Third Addendum
2. Approval of an amendment to the Design-Build Agreement for Product Water Pipeline
Improvements Relating to the Carlsbad Seawater Desalination Project entered into on
December 20, 2012, between the San Diego County Water Authority and Poseidon
Resources (Channelside) LP, and authorizing construction of the facilities described in
this Third Addendum.
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 24
INTENTIONALLY LEFT BLANK
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 25
7.0 IDENTIFICATION OF ENVIRONMENTAL EFFECTS
Documents containing the environmental analysis supporting the City of Carlsbad and Water
Authority’s action in approving the Project include the FEIR, First Addendum, Second Addendum,
Mitigation Monitoring and Reporting Program, CEQA Findings, and additional responses provided
for comments submitted after publication of the FEIR.
The Third Addendum analyzes all 11 environmental issue areas that were included in the FEIR,
First Addendum, and Second Addendum, and discusses whether the proposed Project
modifications described in Section 5.0 would trigger significance criteria identified in the CEQA
Guidelines, Sections 15162 and 15163, in each of these areas. For each environmental issue
area, this Third Addendum provides a comparative analysis of the impacts presented in the
FEIR, First Addendum, and Second Addendum. The analysis includes a determination
regarding the occurrence of any new significant impacts or an increase in the severity of
previously identified impacts. Finally, an analysis is presented to determine whether there are
any changed circumstances or new information relative to the revised Project.
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 26
INTENTIONALLY LEFT BLANK
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 27
8.0 ANALYSIS
The following environmental analysis supports the Water Authority’s determination that approval
and implementation of the proposed Project modifications would not result in any new significant
environmental impacts or a substantial increase in the severity of previously disclosed impacts
covered under the FEIR, First Addendum and Second Addendum. This environmental analysis
is subject to all applicable mitigation measures outlined in the FEIR, First Addendum, Second
Addendum and related Mitigation Monitoring and Reporting Programs.
As stated in Section 1.0, activities associated with the proposed modifications are subject to
the requirements and mitigation measures identified in the FEIR, First Addendum, and
Second Addendum. Where such requirements apply and are relevant, they are noted in the
discussion below.
The FEIR, First Addendum, Second Addendum, and Mitigation Monitoring and Reporting
Program (MMRP) are on file at the Water Authority’s office, 4677 Overland Avenue, San Diego,
California, 92123,
The following presents the environmental analysis of impacts associated with the proposed
Project modifications. In instances where the impacts resulting from several Project components
would be similar, their corresponding analyses have been grouped together. In instances where
impacts differ by Project component, they are discussed separately.
Aesthetics
Analysis of aesthetic impacts and EIR-identified mitigation measures of the approved Project
are contained in the FEIR, Section 4.1, pages 4.1-3 through 4.1-12. See also FEIR CEQA
Findings, pages 10 and 11.
In addition, the Carlsbad Desalination FEIR, First Addendum and Second Addendum concluded
that because aesthetic impacts from construction activities would be short-term and within
limited areas, construction-related impacts to visual resources would be considered less than
significant. Similarly, the construction activities associated with the proposed Project
modifications would also be temporary and within limited areas and, therefore, would also result
in less-than-significant impacts to aesthetics/visual resources.
Analysis of the Revised Project
Other than the temporary nature of construction-related visual impacts, no significant permanent
visual impacts will occur as a result of the Macario Canyon Pipeline Alignment Modification
changes. The ancillary facilities’ pump well and air release valve vault (225 square feet) and
blow off valve vault (80 square feet) located on the east side of Faraday Avenue will be
approximately 4 feet and 2 feet above ground, respectively. The vaults will also have several 3
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 28
foot tall air vents and an air release valve that will be located on the top of the vaults, as well as
an access ladder. The storm drain will have exclusion bars and a riprap energy dissipater. The
approximately 80 by 80 foot ancillary facilities area will be enclosed with bollards and a 4 foot
high access gate. There would be approximately 12 bollards that will be painted a greenish blue
color, Federal Standard 595, Color # 34300. The ancillary facilities will have a minor visual
impact in a limited area, and would be visible from a very limited number of vantage points due
to its size and the natural topography of the area. Therefore, the inclusion of these features
would result in less-than-significant impacts to aesthetics/visual resources.
Substantial Changes With Respect to the Circumstances Under Which the Project is
Undertaken/New Information of Substantial Importance
There are no changes with respect to circumstances under which the Project would be
undertaken, and there is no new information of substantial importance that has become
available relative to visual or aesthetic resources. No substantial changes in the aesthetic or
visual environment have occurred since certification of the FEIR, approval of the First
Addendum and Second Addendum and no substantial new sensitive receptors or scenic
resources have been identified within the vicinity of the proposed Project modifications.
Conclusion
Based on the above, no new significant aesthetic impacts or a substantial increase in previously
identified aesthetic impacts would occur as a result of the proposed modifications. All mitigation
measures previously adopted for the approved Project will apply to the proposed Project described
herein, as applicable. Therefore, the impacts to aesthetic resources and the proposed Project
modifications do not meet the standards for a subsequent or supplemental EIR as provided
pursuant to CEQA Guidelines, Sections 15162 and 15163.
Air Quality
Analysis of air quality impacts of the approved Project are contained in the FEIR, Section 4.2,
pages 4.2-10 through 4.2-21. See also FEIR CEQA Findings, page 11.
The Carlsbad Desalination FEIR, First Addendum and Second Addendum concluded that
impacts to air quality as a result of construction and operation of the approved Project were less
than significant. The FEIR had originally assumed that seven segments of 1,000 feet of pipeline
would be constructed simultaneously. Emission calculations were based on two crews placing
base material, four crews laying the pipeline in the trench, and three crews backfilling the trench
at any given time.
Analysis of the Revised Project
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 29
Construction of the proposed Project modifications would result in temporary increases in
criteria pollutant emissions associated with construction equipment. These temporary increases
were previously contemplated in the FEIR, First Addendum, and Second Addendum, and the
proposed Project modifications would require trenchless construction methods which would
have similar air emissions characteristics as the Macario Canyon tunnel construction analyzed
in the Second Addendum. As such, similar to the findings of the FEIR, First Addendum, and
Second Addendum the construction-related air pollution emissions from the proposed Project
modifications would be temporary and would not be expected to have a permanent significant
impact on ambient air quality.
The Project modifications do not propose any changes to the operational characteristics of the
desalination plant or pipeline; therefore, there are no potential increased direct or indirect
emissions associated with operation of the desalination plant or pipeline that were not discussed
in the Carlsbad FEIR, First Addendum and Second Addendum.
Substantial Changes With Respect to the Circumstances Under Which the Project is
Undertaken/New Information of Substantial Importance
As discussed in the First Addendum to the FEIR, Assembly Bill 32 (AB 32) requires the
California Air Resources Board (CARB), the state agency charged with regulating statewide air
quality, to adopt rules and regulations that would achieve greenhouse gas (GHG) emissions
equivalent to statewide levels in 1990 by 2020. GHG emissions were addressed in the First
Addendum in 2009 through the California Coastal Commission’s (CCC’s) conditional approval of
the Project’s Energy Minimization and Greenhouse Gas Reduction Plan (GHG Plan). The GHG
Plan provides for the assessment, reduction, and mitigation of GHG emissions, and establishes
a protocol for identifying, securing, monitoring, and updating measures to eliminate the Project’s
net carbon footprint. Once the Project is operational and all measures to reduce energy use at
the site have been taken, the protocol involves the following steps, completed each year:
1. Determine the energy consumed by the Project for the previous year
2. Determine San Diego Gas and Electric (SDG&E) emission factor for delivered electricity
from its most recently published Annual Emissions Report
3. Calculate the Project’s gross indirect GHG emissions resulting from Project operations
by multiplying its electricity use by the emission factor
4. Calculate the Project’s net indirect GHG emissions by subtracting emissions avoided as
a result of the Project (Avoided Emissions) and any existing offset projects and/or
Renewable Energy Credits (RECs)
5. If necessary, purchase carbon offsets or RECs (or pay an in-lieu fee) to zero-out the
Project’s net indirect GHG emissions.
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 30
The following are elements of the plan, based on a draft “Greenhouse Gas Emissions Template”
provided by the CCC:
A. Increased Energy Efficiency (such as use of a pressure-exchanger energy recovery system
that captures energy from the discharge stream and high-energy efficiency pumps)
B. GHG Emission Reduction by Green Building Design
C. On-Site Solar Power Generation
D. Recovery of CO2 (carbon dioxide in a gaseous form will be added to the reverse osmosis
permeate in combination with calcium hydroxide or calcium carbonate in order to form
soluble calcium bicarbonate which adds hardness and alkalinity to the drinking water for
distribution system corrosion protection)
E. Avoided Emissions from Reducing Energy Needs for Water Reclamation (reduced
salinity of source water would reduce the need to remove salts from wastewater to meet
recycled water requirements)
F. Avoided Emissions from Displaced Imported Water
G. Avoided Emissions through Coastal Wetlands (carbon sequestration).
All energy use required to deliver product water would be incurred by pumps at the Carlsbad
Desalination Plant, and this energy use was previously analyzed in the FEIR, First Addendum
and Second Addendum for the Carlsbad Desalination Plant Project. GHG emissions from
construction activities associated with the proposed Project modifications would not exceed
those identified in the FEIR, and 25,000 metric tons of carbon offsets as mitigation for
construction-related emissions from the construction of the desalination plant will be purchased,
which far exceeds the offsets that would actually be needed for construction-related impacts,
even with the addition of these modifications.
The proposed Project modifications would not result in an increase in overall GHG emissions. The
Project’s GHG Plan was approved by the CCC in August 2008. With implementation of the GHG
Plan, the Project will demonstrate a “net zero” impact on GHG emissions from indirect sources
(electrical energy consumption). The Project as revised would, therefore, not increase the severity
of previously identified air quality impacts, nor would it result in any new significant effects related
to air pollutant emissions that were not previously identified in the FEIR, First Addendum and
Second Addendum.
Conclusion
The proposed Project modifications are consistent with the GHG Plan requirement
demonstrating a “net zero” impact on GHG emissions from indirect sources (electrical energy
consumption). The proposed Project as revised would not increase the severity of previously
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 31
identified air quality impacts, nor would it result in any new significant effects related to air
emissions that were not previously identified in the FEIR, First Addendum, and Second
Addendum. Additionally, in light of the wide range of global warming activity prior to the
certification of the FEIR in June 2006, there are no substantial changes to the circumstances
under which the Project will be undertaken, and no new information of substantial importance
which was not known and could not have been known when the FEIR was certified and the First
Addendum and Second Addendum were approved, has since been identified. Therefore, the
impacts to air quality and the proposed Project modifications do not meet the standards for a
subsequent or supplemental EIR as provided pursuant to CEQA Guidelines, Sections 15162
and 15163.
Biological Resources
Analysis of biological resources impacts and EIR-identified mitigation measures of the approved
Project are contained in the FEIR, Section 4.3, pages 4.3-18 through 4.3-54. See also FEIR
CEQA Findings, pages 12 through 14.
Analysis of the Revised Project.
Implementation of the proposed Project modifications would result in temporary impacts to
approximately 0.92 acre and permanent impacts to 0.15 acre of non-native annual grassland at
the proposed temporary construction and permanent easement location shown on Figure 3. All
work will be contained within this temporary work area footprint, in addition to the portal location
within Cannon Road.
Among those impacts addressed in the FEIR were 3.71 acres of impact to annual grassland.
The 3.71 acres of impact to annual grassland were mapped along the potential pipeline
segments located just north of Palomar Airport and in the Shadowridge area. Since the impacts
to annual grassland that would occur as a result of the currently proposed Project modifications
in open space adjacent to Macario Canyon would be less than the total acres anticipated to be
impacted under the FEIR, the impacts associated with the Project modification are within the
scope of the analysis of the FEIR. With implementation of FEIR Mitigation Measure 4.3-1,
temporary impacts to approximately 0.92 acre and permanent impacts to 0.15 acre of
annual non-native grassland in the open space east of Faraday Avenue are considered less
than significant.
Construction activities would also result in indirect impacts to adjacent sensitive habitats and wildlife,
including potential impacts from construction-generated dust, siltation, and noise. Implementation of
FEIR Mitigation Measures 4.3-3, 4.3-4, and 4.3-5 would ensure that impacts remain below a level of
significance. Consistent with the FEIR, First Addendum and the Second Addendum with
implementation of mitigation, indirect impacts from construction activities would be considered less
than significant.
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 32
Based on the above analysis, the modifications to the pipeline tunnel and ancillary facilities
would not result in impacts that were not previously identified and mitigated per the FEIR, First
Addendum and Second Addendum. With mitigation, impacts to biological resources would be
similar to those discussed in the FEIR, First Addendum and Second Addendum and would
remain less than significant with the proposed Project modifications.
Substantial Changes With Respect to the Circumstances Under Which the Project is
Undertaken/New Information of Substantial Importance
There are no changes with respect to circumstances under which the Project will be undertaken,
and there is no new information of substantial importance that has become available relative to
biological resources. The additional mitigation imposed by the CCC and the Regional Water
Quality Control Board does not constitute a changed circumstance or new information of
substantial importance, as indicated in the First Addendum and Second Addendum. The
mitigation acreage required by these two agencies was imposed pursuant to their respective
responsibilities under separate regulatory schemes, i.e., the Coastal Act and the California Water
Code, both of which employ different standards of review than CEQA’s “significant impact”
threshold. Thus, the additional mitigation acreage did not involve new significant environmental
effects or a substantial increase in the severity of previously identified significant effects.
Conclusion
None of the proposed Project changes or additions regarding biological resources involve new
significant impacts or a substantial increase in previously identified impacts. Additionally, there
are no substantial changes to the circumstances under which the Project will be undertaken,
and no new information of substantial importance regarding biological resources which was not
known and could not have been known when the FEIR was certified, and the First Addendum
and Second Addendum approved has since been identified. Therefore, the biological resources
impacts and the proposed Project modifications do not meet the standards for a subsequent or
supplemental EIR as provided pursuant to CEQA Guidelines, Sections 15162 and 15163.
Cultural Resources
Analysis of cultural impacts and EIR-identified mitigation measures of the approved Project are
contained in the FEIR, Section 4.4, pages 4.4-14 through 4.4-27. See also FEIR CEQA
Findings, pages 14 and 15.
The FEIR, First Addendum and Second Addendum concluded that cultural resource impacts
were less than significant with mitigation implemented in previously undisturbed areas near
known archaeological and paleontological resources sites.
Analysis of the Revised Project
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 33
The proposed temporary construction and permanent easement location east of Faraday
Avenue was surveyed by a Dudek archaeologist, and no cultural resources were identified. As
a result, implementation of project work at this location would not have an effect on cultural
resources. Any work conducted at this site would also be subject to the mitigation in Section
4.4.4 of the FEIR, as applicable. Implementation of these mitigation measures would ensure
that impacts remain less than significant. Therefore, the proposed Project modifications would
not result in new significant impacts or increase the severity of impacts identified in the FEIR,
First Addendum and Second Addendum and therefore would not change the FEIR, First
Addendum and Second Addendum conclusions.
Substantial Changes With Respect to the Circumstances Under Which the Project is
Undertaken/New Information of Substantial Importance
The potential for significant impacts on cultural resources within the area of potential effect of
the Project has not changed since the time of certification of the FEIR, First Addendum and
Second Addendum. Therefore, no changes in circumstances and no new information of
substantial importance relative to cultural resources have been identified.
Conclusion
None of the proposed Project modifications involve new significant impacts or a substantial
increase in previously identified impacts regarding cultural resources. Additionally, there are no
substantial changes to the circumstances under which the Project will be undertaken, and no new
information of substantial importance regarding cultural resources which was not known and could
not have been known when the FEIR was certified and the First Addendum and Second
Addendum were approved has since been identified. Therefore, the impacts to cultural resources
as a result of the proposed Project modifications do not meet the standards for a subsequent or
supplemental EIR as provided pursuant to CEQA Guidelines, Sections 15162 and 15163.
Geology and Soils
Analysis of geology/soils impacts and EIR-identified mitigation measures of the approved
Project are contained in the FEIR, Section 4.5, pages 4.5-10 through 4.5-17. See also FEIR
CEQA Findings, pages 15 and 16.
The FEIR, First Addendum and Second Addendum found that long-term impacts due to
unstable soil types and seismic-related geologic hazards would be less than significant with
mitigation measures incorporated. The FEIR, First Addendum and Second Addendum also
found that during construction activities, erosion could be accelerated, which could undermine
slopes, cause siltation of surface waters, and expose and damage underground facilities. This
impact was found to be less than significant with implementation of mitigation measures.
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 34
Additionally, the FEIR, First Addendum and Second Addendum found that impacts to mineral
resources would be less than significant.
Analysis of the Revised Project
Geologic impacts of the proposed Project modifications would be mitigated to a less-than-
significant level with the implementation of Mitigation Measure 4.5-2, which requires that a pre-
construction geotechnical investigation be prepared to address geotechnical considerations. All
recommendations of the geotechnical investigation will be implemented.
The erosion potential for the proposed Project modifications would be similar to the approved
Project. Impacts would remain less-than-significant with the implementation of Mitigation
Measures 4.7-1 and 4.7-2, which require that the Project prepare a Stormwater Pollution
Prevention Plan (SWPPP) and a Stormwater Management Plan, respectively.
The Project area is not suitable for mineral extraction. Therefore, the proposed Project
modifications would not result in impacts to geology and soils beyond what was originally
evaluated in the FEIR, the First Addendum and the Second Addendum.
Substantial Changes With Respect to the Circumstances Under Which the Project is
Undertaken/New Information of Substantial Importance
There is no potential for significant changes in geological, seismic, soils, or mineral resource
conditions within the area of potential effect of the Project since the time of certification of the
FEIR, and approval of the First Addendum and Second Addendum because such resources are
relatively static. Additionally, no new information regarding unknown geologic hazards,
conditions, or resources has become available. Therefore, no changes in circumstances and no
new information of substantial importance relative to geology have been identified.
Conclusion
None of the changes or additions to the proposed Project modifications involve new significant
impacts or a substantial increase in previously identified impacts to geology, soils, or mineral
resources. In addition, there are no substantial changes to the circumstances under which the
Project will be undertaken and no new information regarding geological resources which was
not known and could not have been known when the FEIR was certified and the First
Addendum and the Second Addendum were approved has since been identified. Therefore, the
geology/soils impacts and the proposed Project modifications do not meet the standards for a
subsequent or supplemental EIR pursuant to CEQA Guidelines, Sections 15162 and 15163.
Hazards and Hazardous Materials
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 35
Analysis of hazards impacts and EIR-identified mitigation measures of the approved Project are
contained in the FEIR, Section 4.6, pages 4.6-9 through 4.6-17. See also FEIR CEQA Findings,
pages 16 and 17.
The FEIR, First Addendum and the Second Addendum determined that Project construction
would require grading and trenching that could potentially disturb and release hazardous
materials into the environment from sites located in proximity to the construction areas. Potential
for release or exposure of existing subsurface contamination could result during construction.
The FEIR, First Addendum and Second Addendum included measures to mitigate this potential
for exposure to existing contamination sites during construction. Specifically, FEIR Mitigation
Measure 4.6-1 would mitigate the potential for exposure of existing contamination by requiring
construction monitoring in areas identified as having potential risks, and appropriate actions to
be taken if contamination is encountered.
Analysis of the Revised Project
During construction, ground-disturbing activities such as grading or excavation associated
with the proposed Project modifications are not anticipated to encounter contaminated soils.
The proposed Project modifications would occur along a previously approved pipeline
alignment underneath a biological preserve. However, to ensure that impacts would remain
less than significant, the proposed Project modifications would be subject to FEIR Mitigation
Measure 4.6-1 mentioned above.
During construction, gasoline, diesel fuel, lubricating oil, grease, solvents, paint, and welding
gases would be used at all proposed Project locations. The Project would implement FEIR
Mitigation Measure 4.7-1, which requires that the Project prepare and implement an SWPPP that
will include both construction and post-construction pollution prevention and pollution control
measures. Additionally, during operations, the proposed facilities would be subject to the Water
Authority’s Emergency Response Plan (ERP), which requires that the Water Authority, in
conjunction with the local fire department, take appropriate response actions in the case of an
accidental release of hazardous materials during transportation, use, or disposal of hazardous
materials. With the implementation of the Water Authority’s ERP and FEIR Mitigation Measure
4.7-1, potential impacts related to hazards and hazardous materials during construction and
operation would be similar to the approved Project and would remain less than significant with the
proposed Project modifications.
As concluded in the FEIR, First Addendum and Second Addendum, the use of pipelines to
distribute potable water would not pose a hazardous risk to the public or the environment. Long-
term hazardous risks associated with the Macario Canyon Pipeline Alignment Modification and
ancillary facilities would be similar to the impacts associated with the off-site pipeline impacts
under the approved Project and, therefore, impacts would remain less than significant.
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 36
Substantial Changes With Respect to the Circumstances Under Which the Project is
Undertaken/New Information of Substantial Importance
There are no substantial changes to the circumstances under which the Project will be
undertaken, and there is no new information of substantial importance relative to hazards or
hazardous materials that has become available since the certification of the FEIR and the
approval of First Addendum and Second Addendum.
Conclusion
With consideration of the above discussion, the hazards and hazardous materials impacts and
the proposed Project modifications do not meet the standards for a subsequent or supplemental
EIR as provided pursuant to CEQA Guidelines, Sections 15162 and 15163.
Hydrology and Water Quality
Analysis of hydrology/water quality impacts and EIR-identified mitigation measures of the
approved Project are contained in the FEIR, Section 4.7, pages 4.7-10 through 4.7-25. See also
FEIR CEQA Findings, pages 17 through 20.
The FEIR, First Addendum and Second Addendum concluded that construction of the approved
Project could result in significant short-term surface water quality impacts associated with
exposed soils, fuels, lubricants, and solid and liquid wastes that would be used and stored
within active construction areas. Mitigation Measures 4.7-1 and 4.7-2, which require that the
Project prepare an SWPPP and, if appropriate, a Stormwater Management Plan (if grading or
building permits are determined to be necessary) were found to reduce water quality impacts to
less than significant.
The FEIR, First Addendum and Second Addendum concluded that impacts to hydrology and water
quality due to installation of the off-site pipelines and associated infrastructure would be less than
significant. The majority of the proposed Project modifications would be installed or repaired
underground and, therefore, similar to the approved Project, would not cause increases in
impervious surfaces or runoff. Long-term impacts to hydrology and water quality from the proposed
Project modifications would therefore also be less than significant.
Similar to the approved Project, the proposed changes could also result in short-term
construction-related surface water impacts that would be reduced to less-than-significant levels
with implementation of FEIR Mitigation Measures 4.7-1 and 4.7-2.
Portions of the Macario Canyon Pipeline Alignment Modifications are within the flood zone that
is a tributary to Aqua Hedionda Creek (FEMA 2012). However, these portions of the project are
all located belowground; aboveground features such as the proposed temporary construction
and permanent easement location east of Faraday Avenue would be located outside of the flood
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 37
zone. The FEIR determined that impacts may occur along certain pipeline alignments that are
located within a 100-year flood zone. In these areas, implementation of Mitigation Measure 4.7-
3, which requires that construction activities occur during the dry months between May 1 and
September 30, ensures that impacts would remain below a level of significance. Consistent with
the FEIR, the Project with the proposed modifications would also implement Mitigation Measure
4.7-3 and would not result in impacts associated with flood zones.
Substantial Changes with Respect to the Circumstances Under Which the Project is
Undertaken/New Information of Substantial Importance
There are no substantial changes to the circumstances under which the Project will be
undertaken, and there is no new information of substantial importance relative to hydrology or
water quality that has become available since the certification of the FEIR and the approval of
the First Addendum and Second Addendum.
Conclusion
The proposed Project modifications would not result in any new significant hydrologic/water
quality impacts, and no substantial increase in previously identified hydrologic/water quality
impacts would occur with implementation of applicable laws, regulation, and mitigation as
discussed above. Therefore, the impacts from the proposed Project modifications regarding
hydrology and water quality do not meet the standards for a subsequent or supplemental EIR
pursuant to CEQA Guidelines, Sections 15162 and 15163.
Land Use/Planning
Analysis of land use impacts and EIR-identified mitigation measures of the approved Project are
contained in the FEIR, Section 4.8, pages 4.8-10 through 4.8-20. See also FEIR CEQA
Findings, page 20.
The FEIR, First Addendum and Second Addendum concluded that land use impacts would be
less than significant, because short-term construction related effects that could cause land use
conflicts were determined to be less-than-significant, and because the project would not conflict
with zoning or land use policies.
Analysis of the Revised Project
The evaluation and findings from the FEIR, First Addendum and Second Addendum do not
change with the proposed Project modifications. Construction would result in short-term impacts
to surrounding land uses. Short-term impacts would include traffic delays, noise, visual effects,
and dust, all of which are within the scope of the analysis contained in the FEIR, First Addendum
and Second Addendum, as noted in the appropriate sections of this Addendum. Land use impacts
associated with the proposed Project modifications would be similar to the approved Project;
these impacts were found to be less than significant.
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 38
It is important to note that zoning ordinances do not apply to the location or construction of
facilities used for the production, generation, storage, or transmission of water (California
Government Code Section 53091). The policies and goals in both the Land Use Element and the
Public Facility Element of the County’s General Plan promote the efforts of the Water Authority
and water districts to provide for storage, treatment, and transmission facilities to meet demand
(County of San Diego 2010). The small footprint of the aboveground facilities within Veteran’s
Memorial Park would not represent a substantial amount of land being removed from recreational
use. Lastly, construction within existing roadways would not preclude future use of roads following
construction, as all of these project components would be located underground.
Substantial Changes With Respect to the Circumstances Under Which the Project is
Undertaken/New Information of Substantial Importance
There are no substantial changes to the circumstances under which the Project will be
undertaken, because there are no new land uses or substantial changes in land use policies or
requirements that would affect the Project. No new information of substantial importance relative
to land use has become available since the certification of the FEIR and the approval of the First
Addendum and Second Addendum.
Conclusion
Based on the above, no new significant land use impacts or a substantial increase in previously
identified land use impacts would occur as a result of the proposed Project modifications.
Therefore, the impacts to land use and the proposed Project modifications do not meet the
standards for a subsequent or supplemental EIR pursuant to CEQA Guidelines, Sections 15162
and 15163.
Noise and Vibration
An analysis of noise impacts and EIR-identified mitigation measures of the approved Project are
contained in the FEIR, Section 4.9, pages 4.9-5 through 4.9-14. See also FEIR CEQA Findings,
pages 20 and 21. The FEIR, First Addendum and Second Addendum, analysis indicated that all
Project-related construction activities would comply with the local jurisdictions’ noise ordinance
for allowable construction hours. Due to compliance with construction noise restrictions, it is not
anticipated that excavation and installation of the pipeline using tunnelling methods or
construction of the ancillary facilities would result in a significant noise impact based on the
applicable significance criteria. It was estimated in the FEIR that maximum noise levels would
range up to approximately 85 decibels (dB), while the average sound level for an 8-hour work
day was expected to range up to approximately 75 dB.
Further, the FEIR, First Addendum and Second Addendum, indicate that trenchless methods
would be used at several areas. Noise impacts associated with trenchless operations are similar
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 39
to open trench pipeline construction. However, rather than the construction noise progressing
linearly, the noise would be confined to the excavated pits. Thus, noise impacts could last for
several weeks rather than a few days at the areas adjacent to the pits. Trenchless equipment
would involve the construction methods discussed in Section 5.0. Excavating the launch and
receiving pits would generally be the most intense noise source. Thereafter, the noise impact
would be less intense but a persistent noise source. The construction specifications will require
the contractor to comply with the applicable noise ordinance. Construction noise would not exceed
established standards. Therefore, the noise impact is not anticipated to be significant.
Analysis of the Revised Project
As discussed in the FEIR, First Addendum and Second Addendum trenchless construction activities
generate maximum noise levels of 85 dBA at approximately 50 feet. The actual sound level for an
eight-hour work day would be substantially less due to the intermittent use of specific pieces of
equipment during the work day, and would range up to approximately 75 dB at 50 feet. The FEIR
concluded that due to the intermittent nature of construction noise and the requirement in the
construction specification to comply with all applicable local noise ordinances, impacts to sensitive
receptors during construction of the pipelines using trenchless construction methods would be less
than significant. The nearest noise sensitive receptor to the proposed Macario Canyon pipeline
alignment modifications consist of apartments located approximately 600 feet to the north, across
from Faraday Avenue. At this distance construction noise impacts would be substantially less than
those previously analyzed in the FEIR, First Addendum and Second Addendum. Therefore, the
proposed modifications along the pipeline route would not result in any new significant noise
impacts or more severe construction noise impacts than those considered in the FEIR, First
Addendum and Second Addendum.
Additionally, consistent with the FEIR, implementation of Mitigation Measures 4.3-3, 4.3-4,
and 4.3-5, would ensure that indirect noise impacts to sensitive habitats and species remain
below a level of significance. Therefore, the Macario Canyon pipeline alignment modification
and ancillary facilities would not result in new significant indirect noise impacts or increase
the severity of impacts identified in the FEIR, First Addendum and Second Addendum and
would not change the FEIR, First Addendum and Second Addendum conclusion.
Once construction is complete the pump well would only be used in infrequent circumstances,
for limited periods of time and would not generate a substantial amount of noise, and impacts
would not be beyond the scope of the FEIR, First Addendum and Second Addendum analysis.
Similar to the approved Project, operational noise impacts of the proposed Project modifications
would be less than significant.
Substantial Changes With Respect to the Circumstances Under Which the Project is
Undertaken/New Information of Substantial Importance
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 40
There are no substantial changes to the circumstances under which the proposed Project
modifications will be undertaken, because there are no new substantial changes in noise or
vibration policies or requirements that would affect the Project. No new substantial sources of
noise or vibration would be introduced within the area, and no new information of substantial
importance relative to noise and vibration has become available since the certification of the FEIR
and the approval of the First Addendum and Second Addendum.
Conclusion
Based on the above, no new significant noise or vibration impacts or a substantial increase in
previously identified noise or vibration impacts would occur as a result of the proposed Project
modifications. Therefore, noise and vibration impacts and the proposed Project modifications do
not meet the standards for a subsequent or supplemental EIR pursuant to CEQA Guidelines,
Sections 15162 and 15163.
Transportation and Traffic
Analysis of traffic impacts and EIR-identified mitigation measures of the approved Project are
contained in the FEIR, Section 4.10, pages 4.10-4 through 4.10-13. See also FEIR CEQA
Findings, pages 21 and 22.
The FEIR, First Addendum and Second Addendum concluded that the approved Project would
result in short-term construction traffic impacts associated with the portions of the off-site pipeline
that is to be located within existing roadways. Temporary construction traffic trips include crew
vehicles and deliveries of pipeline and other materials. The FEIR, First Addendum and Second
Addendum included Mitigation Measures 4.10-1 and 4.10-2 that require that construction will not
result in unacceptable levels of service during peak hour periods on any affected roadways, and
that specific traffic control measures as set forth within an approved traffic control plan are
implemented. With implementation of these mitigation measures, traffic impacts were considered
less than significant.
The FEIR, First Addendum, and Second Addendum also concluded that long-term traffic
impacts from inspection and monitoring activities would be less than significant, due to the small
percentages that these activities would add to total daily traffic on affected roadways.
Analysis of the Revised Project
The proposed Project modifications would have similar short-term construction related impacts
as those disclosed in the FEIR, First Addendum and particularly the Second Addendum. Since
the proposed Project modifications would change the location of an approved pipeline, trips
associated with inspection of these facilities are considered previously approved and are not
considered new traffic trips. The proposed Project modifications would not result in a substantial
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 41
increase in traffic on local roadways. Therefore, long-term impacts to transportation and traffic
would be similar to the approved Project and impacts would remain less than significant.
Substantial Changes With Respect to the Circumstances Under Which the Project is
Undertaken/New Information of Substantial Importance
There are no substantial changes under which the Project will be undertaken, because there are
no substantial changes in traffic characteristics or requirements from what was in place at the time
that the FEIR was certified and the First Addendum and the Second Addendum were approved.
No new information of substantial importance relative to traffic has become available since the
certification of the FEIR, and the approval of the First Addendum and Second Addendum.
Conclusion
Based on the above, no new significant traffic impacts or a substantial increase in previously
identified traffic impacts would occur as a result of the proposed Project modifications.
Therefore, the traffic impacts and the proposed Project modifications do not meet the standards
for a subsequent or supplemental EIR pursuant to CEQA Guidelines, Sections 15162 and
15163.
Public Utilities and Service Systems
Analysis of public utilities and service impacts and EIR-identified mitigation measures of the
approved Project are contained in the FEIR, Section 4.11, pages 4.11-6 through 4.11-22. See
also FEIR CEQA Findings, pages 23 through 25.
The analysis of public services and utilities in the Carlsbad Desalination FEIR, First Addendum
and Second Addendum concluded that the water treatment plant and associated infrastructure
would not result in significant impacts to fire protection services, schools, wastewater treatment
facilities, landfills, stormwater drainage facilities, or electric power services.
Analysis of the Revised Project
The proposed Project modifications would not result in residential, commercial, or industrial
growth, and therefore, similar to the approved Project, would not require additional services or
utilities. The revised Project would not result in an increase in the maximum energy use that
was contemplated in the FEIR, First Addendum and Second Addendum. All energy use required
to deliver product water to the components of the proposed Project modifications would be
incurred by pumps at the Carlsbad Desalination Plant, and this energy use was previously
analyzed in the FEIR, First Addendum and Second Addendum.
Substantial Changes With Respect to the Circumstances Under Which the Project is
Undertaken/New Information of Substantial Importance
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 42
There are no substantial changes under which the Project will be undertaken, because there are
no substantial changes in public utilities or services, or to the requirements of agencies that
provide such services, from what was in place at the time that the FEIR was certified and the
First Addendum and Second Addendum were approved. No new information of substantial
importance relative to public utilities or services has become available since the certification of
the FEIR.
Conclusion
Based on the above, no new significant public utilities and service system impacts or a
substantial increase in previously identified public utilities and service system impacts would
occur as a result of the proposed Project modifications. Therefore, the public utilities and service
system impacts and proposed Project modifications do not meet the standards for a subsequent
or supplemental EIR pursuant to CEQA Guidelines, Sections 15162 and 15163.
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 43
9.0 CUMULATIVE IMPACTS
Analysis of cumulative impacts and EIR-identified mitigation measures of the approved Project
are contained in the FEIR, Section 5.0, pages 5-1 through 5-13. See also FEIR CEQA Findings,
pages 25 through 27.
Analysis of the Revised Project
The type and extent of construction activities and the operational characteristics of the proposed
Project modifications would not be substantially different from what was evaluated in the FEIR,
First Addendum and Second Addendum for the approved Project. Therefore, no changes relative
to the analysis or conclusions regarding cumulative impacts would occur with the proposed Project
modifications, and the findings of the FEIR, First Addendum and Second Addendum remain the
same for the revised Project.
Substantial Changes with Respect to the Circumstances under Which the Project is
Undertaken/New Information of Substantial Importance
Since certification of the FEIR and approval of the First and Second Addendum additional
cumulative development may have been proposed and/or constructed. However, the analysis
contained in the First Addendum and Second Addendum occurred during a severe economic
downturn, which has resulted in a virtual curtailment of development activities within the Project
area. The minor amount of land development projects that have been proposed and/or
developed in the intervening time since the preparation of the First Addendum and Second
Addendum is not considered to be substantial. The following provides a cumulative analysis of
the proposed Project modifications.
Aesthetics
Because the proposed Project modifications are minor and they have been designed to have
minimal visual impacts, the incremental effect of the proposed Project modifications on any
potential significant cumulative impact would not be cumulatively considerable.
There are no substantial changes to the circumstances under which the Project will be
undertaken and no new information of substantial importance relative to cumulative aesthetic
impacts which was not known and could not have been known when the FEIR was certified and
First and Second Addendum were approved that has since been identified. Therefore, the
effects of additional cumulative development regarding cumulative aesthetic impacts do not
meet the standards for a subsequent or supplemental EIR pursuant to CEQA Guidelines,
Sections 15162 and 15163.
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 44
Air Quality
The Project’s contribution to temporary regional air quality impacts is not considered to be
significant. In addition, because Project construction occupies a relatively small area at any
given time, it is not anticipated that any significant localized cumulative impacts will result. This
is primarily due to the short-term nature of cumulative effects within any given location along the
Project construction route. Any additional cumulative development would not change these
conclusions because the scope of the cumulative development is relatively small within the
context of the air basin, and because as noted in the FEIR, First Addendum and Second
Addendum construction-related emissions would be short-term in nature. There would be no
new operational air pollutant emissions not already considered in the FEIR, First Addendum or
Second Addendum.
There are no substantial changes to the circumstances under which the Project will be
undertaken and no new information of substantial importance relative to cumulative air quality
impacts which was not known and could not have been known when the FEIR was certified and
the First Addendum and Second Addendum were approved, that has since been identified.
Therefore, the effects of additional cumulative development regarding cumulative air quality
impacts do not meet the standards for a subsequent or supplemental EIR pursuant to CEQA
Guidelines, Sections 15162 and 15163.
Biological Resources
As noted in this Addendum, the proposed Project modifications do not involve new
significant impacts or a substantial increase in previously identified impacts. This
conclusion would not be changed with additional cumulative development due to the
limited scope of cumulative development.
There are no substantial changes to the circumstances under which the Project will be
undertaken and no new information of substantial importance relative to cumulative biological
impacts which was not known and could not have been known when the FEIR was certified and
the First Addendum and Second Addendum were approved, that has since been identified.
Therefore, the effects of additional cumulative development regarding cumulative biological
impacts do not meet the standards for a subsequent or supplemental EIR pursuant to CEQA
Guidelines, Sections 15162 and 15163.
Cultural Resources
The FEIR, First Addendum and Second Addendum cumulative impacts analysis for cultural
resources concluded that impacts on cultural resources related to cumulative development
could be significant if important cultural resources are destroyed as a result of development.
The mitigation measures required for the proposed Project provides for avoidance,
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 45
documentation, and/or recovery of important cultural resources, and as a result, all impacts
related to cultural resources are reduced to less-than-significant levels. These same measures
would apply to any additional cumulative development, and therefore the level of cumulative
impact and required mitigation measures would not change.
There are no substantial changes to the circumstances under which the Project will be
undertaken and no new information of substantial importance relative to cumulative cultural
resource impacts which was not known and could not have been known when the FEIR was
certified and the First Addendum and Second Addendum were approved, that has since been
identified. Therefore, the effects of additional cumulative development regarding cumulative
cultural resource impacts do not meet the standards for a subsequent or supplemental EIR
pursuant to CEQA Guidelines, Sections 15162 and 15163.
Geology and Soils
The FEIR, First Addendum and Second Addendum concluded that the Project will require
relatively minor site preparation and excavation of soils. Project mitigation to control and
address erosion and seismic and soils hazards, in conjunction with similar standard measures
required of cumulative development, would reduce cumulative impacts to less-than-significant
levels. Any additional cumulative development would have similar levels of impact on geology
and soils and would be subject to similar requirements and mitigation measures.
There are no substantial changes to the circumstances under which the Project will be
undertaken and no new information of substantial importance relative to cumulative
geology/soils impacts which were not known and could not have been known when the FEIR
was certified and the First Addendum and Second Addendum were approved, that has since
been identified. Therefore, the effects of additional cumulative development regarding
cumulative geology/soils impacts do not meet the standards for a subsequent or supplemental
EIR pursuant to CEQA Guidelines, Sections 15162 and 15163.
Hazards and Hazardous Materials
The Project, as well as other cumulative development, would be subject to regulatory controls
that would result in minimization of hazards, and therefore the FEIR, First Addendum and
Second Addendum concluded that the Project would not contribute to cumulative considerable
increases in hazards or hazardous materials. Any additional cumulative development would
have similar regulatory controls.
There are no substantial changes to the circumstances under which the Project will be
undertaken and no new information of substantial importance relative to cumulative hazard
impacts which was not known and could not have been known when the FEIR was certified and
the First Addendum and Second Addendum were approved, that has since been identified.
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 46
Therefore, the effects of additional cumulative development regarding cumulative hazards
impacts do not meet the standards for a subsequent or supplemental EIR pursuant to CEQA
Guidelines, Sections 15162 and 15163.
Hydrology and Water Quality
The FEIR, First Addendum and Second Addendum concluded that water quality and hydrology
issues would be temporary (construction-related) in nature and would not contribute to
cumulatively significant impacts. Impacts of any additional cumulative development would be
similar, and in fact would be subject to newer more stringent regulatory control measures.
There are no substantial changes to the circumstances under which the Project will be
undertaken and no new information of substantial importance relative to cumulative
hydrology/water quality impacts which was not known and could not have been known when the
FEIR was certified and the First Addendum and Second Addendum were approved, that has
since been identified. Therefore, the effects of additional cumulative development regarding
cumulative hydrology/water quality impacts do not meet the standards for a subsequent or
supplemental EIR pursuant to CEQA Guidelines, Sections 15162 and 15163.
Land Use and Planning
The FEIR, First Addendum and Second Addendum concluded that the Project would not
contribute to significant impacts resulting from cumulative development that may have the effect
of dividing an established community or conflicting with land use or environmental policies.
Therefore, the incremental effect of the Project on any potential significant cumulative impact
would not be cumulatively considerable. This conclusion would also apply to any additional
cumulative development.
There are no substantial changes to the circumstances under which the Project will be
undertaken and no new information of substantial importance relative to cumulative land use
impacts which was not known and could not have been known when the FEIR was certified and
the First Addendum and Second Addendum were approved, that has since been identified.
Therefore, the effects of additional cumulative development regarding cumulative land use
impacts do not meet the standards for a subsequent or supplemental EIR pursuant to CEQA
Guidelines, Sections 15162 and 15163.
Noise and Vibration
The FEIR, First Addendum and Second Addendum identified cumulative noise and vibration
impacts to be primarily related to construction noise. However, within the time frame of Project
construction, it is not anticipated that those cumulative effects would reach a level of
significance because of noise restrictions required for construction projects, and because the
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 47
time frame for construction of the proposed Project is relatively short. Any additional cumulative
development would not change these conclusions because of the short duration for construction
of the proposed Project modifications.
There are no substantial changes to the circumstances under which the Project will be
undertaken and no new information of substantial importance relative to cumulative noise and
vibration impacts which was not known and could not have been known when the FEIR was
certified and the First Addendum and Second Addendum were approved, that has since been
identified. Therefore, the effects of additional cumulative development regarding cumulative
noise and vibration impacts do not meet the standards for a subsequent or supplemental EIR
pursuant to CEQA Guidelines, Sections 15162 and 15163.
Transportation and Traffic
The cumulative impacts analysis for transportation and traffic considered the intersections and
road segments to which the Project could contribute to a cumulative impact. Similar to noise
impacts, Project traffic impacts are primarily associated with construction. Since the time frame
for construction is relatively short and traffic control plans to minimize traffic impacts are
required, it is not anticipated that a substantial increase in current traffic levels resulting from
cumulative development will occur prior to completion of Project construction. Therefore,
temporary traffic impacts associated with the Project will cease prior to any substantial
cumulative traffic impacts being realized on local roadways. Any additional cumulative
development would not change these conclusions because the construction travel routes for the
additional projects are not anticipated to substantially conflict with cumulative construction traffic
of the proposed Project.
There are no substantial changes to the circumstances under which the Project will be
undertaken and no new information of substantial importance relative to cumulative traffic
impacts which was not known and could not have been known when the FEIR was certified and
the First Addendum and Second Addendum were approved, that has since been identified.
Therefore, the effects of additional cumulative development regarding cumulative traffic impacts
do not meet the standards for a subsequent or supplemental EIR pursuant to CEQA Guidelines,
Sections 15162 and 15163.
Public Utilities and Service Systems
The cumulative impacts analysis for energy and wastewater were considered to be less than
significant, primarily based on capacity and reliability features built into existing systems. The
additional cumulative development would not change the analysis or conclusions of the FEIR,
First Addendum and Second Addendum because they would not result in substantial additional
demand on such systems.
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 48
There are no substantial changes to the circumstances under which the Project will be
undertaken and no new information of substantial importance relative to cumulative
utilities/services impacts which were not known and could not have been known when the FEIR
was certified and the First Addendum and Second Addendum were approved, that has since
been identified. Therefore, the effects of additional cumulative development regarding
cumulative utilities/services impacts do not meet the standards for a subsequent or
supplemental EIR pursuant to CEQA Guidelines, Sections 15162 and 15163.
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 49
10.0 GROWTH-INDUCING IMPACTS
Analysis of growth-inducing impacts of the approved Project are contained in the FEIR, Section
9.0, pages 9-1 through 9-7. See also FEIR CEQA Findings, pages 54 and 55.
Analysis of the Revised Project
The proposed Project changes consist of minor modifications to the desalination water
distribution system. The operation of the Project will not change from what was evaluated in the
FEIR, First Addendum and Second Addendum. Therefore, no changes relative to the analysis
or conclusions related to growth inducement would occur with the proposed Project revisions.
Substantial Changes with Respect to the Circumstances Under Which the Project is
Undertaken/New Information of Substantial Importance
There are no substantial changes under which the Project will be undertaken, because there are
no substantial changes in growth potential or growth planning that would affect the analysis
contained in the FEIR, First Addendum and Second Addendum. No new information of
substantial importance relative to growth inducement has become available since the
certification of the FEIR and the approval of the First Addendum and Second Addendum.
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 50
INTENTIONALLY LEFT BLANK
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 51
11.0 CONCLUSION
Impacts associated with the proposed Project modifications would not result in a new significant
impact or substantial increase in the severity of previously identified impacts per the Carlsbad
Desalination Plant 2006 FEIR, the 2009 First Addendum, or the 2012 Second Addendum. There
are no substantial changes to the circumstances under which the Project will be undertaken,
and no new information of substantial importance which was not known and could not have
been known when the FEIR was certified and the First and Second Addendums were approved,
and that have since been identified. Therefore, the proposed Project modifications do not meet
the standards for a subsequent or supplemental EIR as provided pursuant to CEQA Guidelines,
Sections 15162 and 15163. As such, this Third Addendum to the FEIR satisfies CEQA
requirements for the proposed Project modifications.
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 52
INTENTIONALLY LEFT BLANK
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 53
12.0 REFERENCES
City of Carlsbad. 2006. Carlsbad Precise Development Plan and Desalination Plant Final
Environmental Impact Report. Certified June 13, 2006.
City of Carlsbad. 2009. CEQA Addendum for the Precise Development Plan and Desalination
Plant Project Final EIR. August 2009.
County of San Diego. 2010. General Plan, as amended. Accessed March 31, 2010.
http://www.sdcounty.ca.gov/dplu/docs/existgp/landuse.pdf.
FEMA. (Federal Emergency Management Agency). 2012. Flood Insurance Rate Map, San
Diego County, California and Incorporated Areas, Panel 768 of 2375. Map Number
06073C0768G. Map Revised May 16, 2012.
SDCRWQCB (San Diego County Regional Water Quality Control Board. 2012. San Diego
Region (9) Hydrologic Basin Planning Area. Revised April 1995. Accessed on February
1, 2012 at http://www.swrcb.ca.gov/sandiego/water_issues/programs/basin_plan/.
Water Authority (San Diego County Water Authority). 2012. CEQA Addendum for the Precise
Development Plan and Desalination Plant Project Final EIR. November 2012.
Precise Development Plan and Desalination Plant Project September 2013
Third CEQA Addendum 54