HomeMy WebLinkAboutCass Construction Inc; 2004-11-03; 34461 Part 1 of 2r Recording requested by:
CITY OF CARLSBAD
When recorded mail to:
City Clerk
City of Carlsbad
1200 Carlsbad Village Dr.
Carlsbad, CA 92008
DOC# 2006-0427696
JUN16, 2006 9:26 AM
OFFICIAL RE CORDS
SAN DIEGO COUNTY RECORDER'S OFFICE
G Fi E G 0 RY J S MIT H. CO IJ N TY R E CO R D E R
FEES: 0.00
PAGES: 1
Space above this line for Recorder's Use
NOTICE OF COMPLETION
Notice is hereby given that:
1. The undersigned is owner of the interest or estate stated below in the property
hereinafter described.
2. The full name of the undersigned is Carlsbad Municipal Water District (CMWD), a
municipal corporation.
3. The full address of the undersigned is 1200 Carlsbad Village Drive, Carlsbad, California
92008.
4. The nature of the title of the undersigned is: In fee.
5. A work of improvement on the property hereinafter described was completed on
February 3, 2006.
6. The name of the contractor for such work of improvement is Cass Construction, Inc.
7. The property on which the work of improvement was completed is in the City of
Carlsbad, County of San Diego, State of California, and is described as the El Camino
Real Domestic Water and Recycled Water Transmission Mains, Project Nos. 3446 and
3887-H.
CITY OF CARLSBAD
GLENN PRUIM
Deputy Public Works Director
VERIFICATION OF SECRETARY
I, the undersigned, say:
I am the Secretary of the Carlsbad Water Municipal District, 1200 Carlsbad Village
Drive, Carlsbad, California, 92008. The Board of Directors of said District on w**jt~s /3
2006, accepted the above described work as completed and ordered that a N«$6^ of Completion
be filed.
I declare under penalty of perjury that the foregoing is true and correct.
Executed on Ap+xs^1 /"T- , 2006, at Carlsbad, California.
1^ CARLSBAD MUNICIPAL WATER DISTRICT
Zii;E
.. .
CITY OF CARLSBAD
CONTRACT CHANGE ORDER TRANSMITTAL -C/0 5 ~
PROJECT: 3446-1, 3887-1~ EL CAMINO REAL AND CASSIA ROAD DOMESTIC
AND RECYCLED WATER TRANSMISSION MAINS
Date Routed:
Reason for change:
To:
City Engineer
Engineering lnsp~
Finance Directo~
City Manager/Mayor
Engineering Inspection
Item 1: The Project Plans identify a proposed connection point (POC) @ Sta. 160+80
from the temporary high-line to the existing 12" recycled water line but upon
excavation discovered the condition of the existing 12" recycled water lateral
had deteriorated. The lateral had been previously disconnected from the
existing 12" recycled water line but not indicated as such on the as-built
drawing.
Item 2: The Project Plans do not provide for water service to the temporary recycled
water pump station on El Camino Real @ Camino Vida Roble.
Item 3: The Project Plans do not provide for adjustment of existing water valve boxes
to finish surface.
Item 4: Although the Contract references the requirement of submitting a detailed
schedule listing sequence and duration of the proposed connections, the
actual duration of virtually every connection took longer than anticipated due
to a myriad of reasons, essentially limiting the Contractor to one connection a
week. These impacts to the Contractor's schedule were not anticipated prior
to bid.
Project: 3446-1, 3887-1 H, EL Camino Real and Cassia Road Domestic and Recycled
Water Transmission Mains
Change Order No. 5
COST ACCOUNTING:
Original contract amount ................................................................ $3,392,703.00
Total amount this c/o ..................................................................... $ 19,129.42
Total amount of previous c/o's ........................................................ $ 433,977.52
Total c/o's to date ........................................................................... $ 453,106.94
New Contract Amount .................................................................... $3,845,809.94
Total c/o's as % of original contract ........................................................... 13.35 %
Contingency monies encumbered ............................................ $ 276,000.00
Contingency increase or decrease .................................................. $ 324,433.00
Contingency Subtotal ...................................................................... $ 600,433.00
Total c/o's to date ............................................................................ $ 453,106.94
Contingency Balance ....................................................................... $ 147,326.06
' •• 11
CITY OF CARLSBAD
PROJECT: 3446-1, 3887-1 H, EL CAMINO REAL AND CASSIA ROAD DOMESTIC
AND RECYCLED WATER TRANSMISSION MAINS
CONTRACT CHANGE ORDER NO. 5
CONTRACT NO. 3446-1, 3887-1 H
ACCOUNT NO. 50570009060/34469066; 50270009060/38879066
CONTRACTOR: Cass Construction, Inc
100 Wagner Drive
El Cajon, Ca 92020-3047
P.O. NO. 114835
The Contractor is directed to make the following changes as described herein.
Changes shall include all labor, materials, equipment, contract time extension, and all
other goods and services required to implement this change. Payment stated on this
change order includes all charges, direct or indirect, arising out of this additional work
and is expressly agreed between the City and the Contractor to be the complete and
final costs hereof. The requirements of the specifications, where pertinent and not in
conflict with this change order, shall apply to these changes. This change order is not
effective unless signed by the City Manager and/or the Mayor.
Pursuant to Subsection 3-2.2.3 Agreed Prices, SSPWC 2003, and the Provisions of this
Contract, perform the following:
Item 1: Provide and set up the necessary traffic control to facilitate the installation of a
6" ductile iron gate valve (RW) and the necessary 6" ductile iron pipe and
fittings to complete a 6" connection from the existing 12" recycled water line to
the temporary high line, price to include removal and replacement of the
existing median curb and stamped concrete median for the lump sum price of
$14,856.42.
Increase to contract cost. ..................................................... $ 14,856.42
Item 2: Provide and set up the necessary traffic control to facilitate the installation of a
1" water service including the wet tap to the 6" steel water main at Station
23+35 and connect to the existing meters for the lump sum price of$ 2,598.96.
Increase to contract cost. ....................................................... $ 2,598.96
Item 3: Provide and set up necessary traffic control to locate and adjust to finish
surface the valve boxes on an existing valve cluster and blow-off assembly per
CMWD Standard Drawing. No. W13 and W6 respectively for the lump sum
price of $1,647.04.
Increase to contract cost. ........................................................ $ 1,674.04
••
Project: 3446-1, 3887-1 H, El Camino Real and Cassia Road Domestic and Recycled
Water Transmission Mains
Change Order No 5
Item 4: Extend Contract by 15 working days.
Increase to contract cost. .............................................................. $ 0.00
TOTAL INCREASE TO CONTRACT COST ............................................. $19, 129.42
TIME FOR COMPLETION OF ALL WORK UNDER THIS CONTRACT SHALL BE
INCREASED BY 15 WORKING DAYS.
RECOMMENDED BY:
~ 4/10/o?,
CONSTRUCTION MANAGER(DATE)
ENGINEER ~a
FINANCE DIRECTOR
DISTRIBUTION:
INSPECTION FILE (ORIGINAL)
PURCHASING
CONTRACTOR
DEPUTY CITY ENGINEER, DESIGN
(DATE)
(DATE)
APPROVED BY:
~-~
ITMA~GER/MAYOR
bl°'3
(DATE)
•
CITY OF CARLSBAD
CONTRACT CHANGE ORDER TRANSMITTAL -C/0 4
Project: 3446-1/3887-1H, EL CAMINO REAL AND CASSIA ROAD DOMESTIC
AND RECYCLED WATER TRANSMISSION MAINS
Date Routed:
Reason for change:
City Engineer
Engineering lnsp~n
Finance Director~
City Manager/Mayor
Engineering Inspection
Item 1: During trench excavation, encountered unidentified, abandoned concrete
encased utility conduits.
Item 2: During trench excavation, encountered farming debris that required removal
and disposal and replacement with suitable materials.
COST ACCOUNTING:
Original contract amount ................................................................ $3,392,703.00
Total amount this c/o .......................................................................... $39,000.00
Total amount of previous c/o's ........................................................... $394,977.52
Total c/o's to date .............................................................................. $433,977.52
New Contract Amount .................................................................... $3,826,680.52
Total c/o's as% of original contract ............................................................ 12.67%
Contingency monies encumbered ...................................................... $276,000.00
Contingency increase or decrease ..................................................... $324,433.00
Contingency Subtotal ......................................................................... $600,433.00
Total c/o's to date ............................................................................... $433,977.52
Contingency Balance .......................................................................... $166,455.48
CITY OF CARLSBAD
PROJECT: 3446-1/3887-1 H, EL CAMINO REAL AND CASSIA ROAD DOMESTIC
AND RECYCLED WATER TRANSMISSION MAINS
CONTRACT CHANGE ORDER NO. 4
CONTRACT NO. 3446-1/3887-1 H
ACCOUNT NO. 50570009060/34469066: 50270009060/38870966
CONTRACTOR: Cass Construction, Inc
1100 Wagner Drive
El Cajon, Ca 92020-3047
P.O. NO.P114835
The Contractor is directed to make the following changes as described herein.
Changes shall include all labor, materials, equipment, contract time extension, and all
other goods and services required to implement this change. Payment stated on this
change order includes all charges, direct or indirect, arising out of this additional work
and is expressly agreed between the City and the Contractor to be the complete and
final costs hereof. The requirements of the specifications, where pertinent and not in
conflict with this change order, shall apply to these changes. This change order is not
effective unless signed by the City Manager and/or the Mayor.
Pursuant to Section 3-3 Extra Work, SSPWC 2000, and the Provisions of this Contract,
perform the following:
Item 1: Provide traffic control as necessary, remove and dispose of the interfering concrete
and conduits.
Estimated increase to contract cost. .................................................. $4,000.00
Item 2: Provide traffic control as necessary, remove and dispose of the unsuitable materials
from Station 82+ 79 to Station 83+59 Cassia Road and replace with suitable
material.
Estimated increase to contract cost. ................................................. $35,000.00
TOTAL ESTIMATED INCREASE TO CONTRACT COST ................................ $39,000.00
Page 2
Project: 3446-1/3887-1 H, El Camino Real and Cassia Road Domestic and Recycled
Water Transmission Mains
Change Order No. 4
TIME FOR COMPLETION OF ALL WORK UNDER THIS CONTRACT SHALL BE
INCREASED BY 10 DA VS.
RECOMMENDED BY:
~ z(ufob
CONSTRUCTION MANAGER (DATE)
c~,I,,, 4 zlz1'-6
DEPUTYCIY ENGINEER (DATE)
d&
CITY ENGINEER
,~
FINANCE DIRECTOR
DISTRIBUTION:
INSPECTION FILE (ORIGINAL)
PURCHASING
CONTRACTOR
DEPUTY CITY ENGINEER, DESIGN
~' (DA E)
APPROVED BY:
/~~-..,.
(,C(jNTRACTOR
~~~~ TYMANAGER/ MAYOR (DATE)
CITY OF CARLSBAD
CONTRACT CHANGE ORDER TRANSMITTAL -C/0 3
PROJECT: 3446-1/3887-1 H, EL CAMINO REAL AND CASSIA ROAD DOMESTIC
AND RECYCLED WATER TRANSMISSION MAINS
Date Routed:
Reason for change:
City Engineer
Engineering lnspe~
Finance Director ~
City Manager/Mayor
Engineering Inspection
Item 1: Engineering staff has requested that the north and southbound lanes of El
Camino Real between PAR and Cassia Lane be repaired in preparation of the
asphalt over-lay project scheduled for next year.
COST ACCOUNTING:
Original contract amount ............................................................... $ 3,392,703.00
Total amount this c/o ....................................................................... $ 313,546.38
Total amount of previous c/o's ............................................................. $77,184.32
Total c/o's to date .............................................................................. $390,740.70
New Contract Amount .................................................................... $3,783,443.37
Total c/o's as % of original contract. .............................................. 11.52 %
Contingency monies encumbered ...................................................... $276,000.00
Contingency increase or decrease ..................................................... $333,281.00
Contingency Subtotal ......................................................................... $609,281.00
Total c/o's to date ............................................................................... $390,740.70
Contingency Balance .......................................................................... $218,540.30
CITY OF CARLSBAD
PROJECT: 3446-1/3887-1 H, EL CAMINO REAL AND CASSIA ROAD DOMESTIC
AND RECYCLED WATER TRANSMISSION MAINS
CONTRACT CHANGE ORDER NO. 3
CONTRACT NO. 3446-1/3887-1H P.O. NO. P114835
ACCOUNT NO. 50570009060/34469066; 50270009060/38879066
CONTRACTOR: Cass Construction, Inc
1100 Wagner Drive
El Cajon, CA 92020-3047
The Contractor is directed to make the following changes as described herein.
Changes shall include all labor, materials, equipment, contract time extension, and all
other goods and services required to implement this change. Payment stated on this
change order includes all charges, direct or indirect, arising out of this additional work
and is expressly agreed between the City and the Contractor to be the complete and
final costs hereof. The requirements of the specifications, where pertinent and not in
conflict with this change order, shall apply to these changes. This change order is not
effective unless signed by the City Manager and/or the Mayor.
Pursuant to Subsection 3-2.2.3 Agreed Prices, SSPWC 2003, and the Provisions of this
Contract, perform the following:
Item 1: Provide traffic control as necessary to accomplish a 3" x 146,517 SF grind
and C2-AR-4000 asphalt mix overlay of the north and southbound lanes of El
Camino Real between Palomar Airport Road and Cassia Road at $2.14 per square
foot for a lump sum price of $313,546.00. The price includes disposal of asphalt
and other materials generated by the 3" grind.
Increase to contract cost. ............................................................. $313,546.38
TOTAL INCREASE TO CONTRACT COST ............................................. $313,546.38
' .
Page 2
Project: 3446-1 /3887-1 H, El Camino Real and Cassia Road Domestic and Recycled
Water Transmission Mains
Change Order No. 3
TIME FOR COMPLETION OF ALL WORK UNDER THIS CONTRACT SHALL BE
INCREASED BY 20 DAYS.
RECOMMENDED BY:
~ ta/21/of
CONSTRUCTION MANAGER (DATE)
ell~"' 1olz~k
DEPUTY CITY ENGINEER (DATE)
d,/:;/ ~}
<'./~ )~
CITY ENGINEER
~!&~
FINANCE DIRECTOR
DISTRIBUTION:
INSPECTION FILE (ORIGINAL)
PURCHASING
CONTRACTOR
DEPUTY CITY ENGINEER, DESIGN
///ft')
(DATE)
APPROVED BY:
c:fucTOR
/~IC //'//::!~S~J
~~ER/MAYOR (DATE)
CITY OF CARLSBAD
CONTRACT CHANGE ORDER TRANSMITTAL -C/0 2
PROJECT: 3446-1/3887-1H, EL CAMINO REAL AND CASSIA ROAD DOMESTIC
AND RECYCLED WATER TRANSMISSION MAINS
Date Routed:
ll/')ID5' E IZ/lt,/01'
Reason for change:
City Engineer
Engineering Inspection
Finance Director
City Manager/Mayor
Engineering Inspection
Item 1: The Project Engineer and Water Operations has requested the substitution of
the pipe material specified by the Contract for Schedule "A" Bid Item A-11 and
extending the 14" water line, as depicted in Connection Detail 1 Plan Sheet C-
8, an additional 340 LF to replace an existing deteriorating water line.
Item 2: Referencing Item 1 above, delete Bid Item A-11 from the Contract. The
deletion is necessary because the pipe material substitution has changed the
scope of work and created a cost differential in completing the work as
described in the original bid item.
Item 3: Referencing Item 2 above, add new Bid Item A-11a. The new bid Item shall
encompass all construction necessary to complete the connection as described
in Bid Item A-11, less the cost differential of the pipe materials as specified in
the original bid item and the cost of the pipe materials as specified by the
Engineer in the new bid item.
Project: 3446-1/3887-1 H, El Camino Real and Cassia Road Domestic and Recycled
Water Transmission Mains
Change Order No. 2
COST ACCOUNTING:
Original contract amount ............................................................... $ 3,392,703.00
Total amount this c/o ......................................................................... $ 52,662.83
Total amount of previous c/o's ............................................................ $28,768.31
Total c/o's to date ................................................................................ $81,431.14
New Contract Amount ................................................................... $3,474,134.14
Total c/o's as% of original contract. ...................................................... 2.4%
Contingency monies encumbered .............................................. $276,000.00
Contingency increase or decrease ................................................................ $0.00
Contingency Subtotal ......................................................................... $276,000.00
Total c/o's to date ................................................................................. $81,431.14
Contingency Balance .......................................................................... $194,568.86
..
CITY OF CARLSBAD
PROJECT: 3446-1/3887-1 H, EL CAMINO REAL AND CASSIA ROAD DOMESTIC
AND RECYCLED WATER TRANSMISSION MAINS
CONTRACT CHANGE ORDER NO. 2
CONTRACT NO. 3446-1/3887-1H P.O. NO. P114835
ACCOUNT NO. 50570009060/344619066; 50270009060/388719066
CONTRACTOR: Cass Construction, Inc
1100 Wagner Drive
El Cajon, Ca 92020-3047
The Contractor is directed to make the following changes as described herein.
Changes shall include all labor, materials, equipment, contract time extension, and all
other goods and services required to implement this change. Payment stated on this
change order includes all charges, direct or indirect, arising out of this additional work
and is expressly agreed between the City and the Contractor to be the complete and
final costs hereof. The requirements of the specifications, where pertinent and not in
conflict with this change order, shall apply to these changes. This change order is not
effective unless signed by the City Manager and/or the Mayor.
Pursuant to Subsection 3-2.2.3 Agreed Prices, SSPWC 2003, and the Provisions of this
Contract, perform the following:
Item 1: Install+/-340 LF of 14" Class 150 PVC pipe starting @ CL Station 259+80 and
culminating at the existing valve, 15 LF of 6" Class 150 PVC pipe, one (1) 14" x
14" x 6" PJ x PJ x FL Tee, one (1) 6" FL x PJ gate valve, two (2) fourteen-inch
(14") 45° bends, and one (1) PJ x FL adapter for the connection to the existing
valve, for the lump sum price of$ 57,009.65.
Increase to contract cost. ......................................................... $57,009.65
Item 2: Delete Schedule "A" Bid Item A-11.
Decrease to contract cost. ..................................................... ($93,100.00)
Item 3: Add Bid Item A-11a; Construct the connection to the existing 16", 14" and 6"
diameter distribution lines at Station 80+09 at the intersection of El Camino
Real and Cassia Road for the lump sum price of $88,753.18. The decrease in
price includes the cost differential in specified pipe materials.
Increase to contract cost. ........................................................ $88,753.18
TOTAL INCREASE TO CONTRACT COST ............................................ $52,662.83
•
Page 3
Project: 3446-1/3887-1 H, El Camino Real and Cassia Road Domestic and Recycled
Water Transmission Mains
Change Order No. 2
TIME FOR COMPLETION OF ALL WORK UNDER THIS CONTRACT SHALL NOT BE
AFFECTED BY THIS CHANGE ORDER.
RECOMMENDED BY:
~ K/2?>/os
CONSTRUCTION MANAGER (DATE)
C.Ja,....,~ &h.,fes
DEPUTY CITY ENGINEER (DATE)
AL ~ //f>?I·• CITY ENGINEER (DATE)
~~ J~P/os-
FINANCE DIRECTOR
DISTRIBUTION:
INSPECTION FILE (ORIGINAL)
PURCHASING
CONTRACTOR
DEPUTY CITY ENGINEER, DESIGN
(DATE)
APPROVED BY:
~=-~
CITY MANAGER/ MAYOR (DATE)
CITY OF CARLSBAD
CONTRACT CHANGE ORDER TRANSMITTAL -C/0 1
PROJECT: 3446-1/3887-1H, EL CAMINO REAL AND CASSIA ROAD DOMESTIC
AND RECYCLED WATER TRANSMISSION MAINS
Date Routed:
g/'!)/0~
8/,/0~ 8/24/a,;
SEP 1 2 2005
9/1Z/o5
Reason for change:
City Engineer
Engineering lnspe~n
Finance Director ~
City Manager/Mayor
Engineering Inspection
Item 1: The Project Engineer requested installation of a tee and valve for
connection to future pump station.
Item 2: The Project Plans incorrectly depicted an existing 30" inch flange for
proposed connection at this location.
Item 3: Due to elevation conflicts with existing gas and fuel lines, the water line
elevation had to be raised, leaving the pipe with inadequate cover.
Item 4: During trench excavation, concrete slurry was encountered.
Item 5: Due to the existing deteriorated road conditions, emergency road repairs
were required.
Item 6: Conflict with an existing improvement required realignment of the
proposed water line.
' .
Project: 3446-1/3887-1 H, El Camino Real and Cassia Road Domestic and Recycled
Water Transmission Mains
Change Order No. 1
COST ACCOUNTING:
Original contract amount ............................................................... $ 3,392,703.00
Total amount this c/o ......................................................................... $ 28,768.31
Total amount of previous c/o's ..................................................................... $ 0.00
Total c/o's to date ............................................................................... $ 28,768.31
New Contract Amount ................................................................... $ 3,421,471.31
Total c/o's as% of original contract.. .......................................................... 0.848%
Contingency monies encumbered ...................................................... $276,000.00
Contingency increase or decrease ................................................................ $0.00
Contingency Subtotal ........................................................................... $276,00.00
Total c/o's to date ................................................................................. $28,768.31
Contingency Balance .......................................................................... $247,231.69
CITY OF CARLSBAD
PROJECT: 34461/3887-1 H, EL CAMINO REAL AND CASSIA ROAD DOMESTIC
AND RECYCLED WATER TRANSMISSION MAINS
CONTRACT CHANGE ORDER NO. 1
CONTRACT NO. 34461/3887-1H P.O. NO. P114835
ACCOUNT NO. 50570009060/344619066; 50270009060/388719066
CONTRACTOR: Cass Construction Inc.
1100 Wagner Drive
El Cajon, CA 92020-3047
The Contractor is directed to make the following changes as described herein.
Changes shall include all labor, materials, equipment, contract time extension, and all
other goods and services required to implement this change. Payment stated on this
change order includes all charges, direct or indirect, arising out of this additional work
and is expressly agreed between the City and the Contractor to be the complete and
final costs hereof. The requirements of the specifications, where pertinent and not in
conflict with this change order, shall apply to these changes. This change order is not
effective unless signed by the City Manager and/or the Mayor.
Pursuant to Subsection 3-2.2.3 Agreed Prices, SSPWC 2003, and the Provisions of this
Contract, perform the following:
Item 1: Install one (1) 20" x 20" x 20" ML&C steel Tee, one (1) 20" flanged BF valve,
one (1) 20" blind flange and connect to the existing 20" water line at Station
70+ 74.70 for the lump sum price of $10,550.00.
Increase to contract cost. ........................................................ $10,550.00
Item 2: Install one (1) 30" SOWO steel flange including interior and exterior grouting at
Station 84+29.66 for the lump sum price of$ 2,000.00.
Increase to contract cost. .......................................................... $2,000.00
Item 3: Concrete encase 30 LF of 24" steel water main, including %" thick expansion
joint filler at the ends of encasement per attached drawing at Station 70+40 for
the lump sum price of$ 7,096.80.
Increase to contract cost. ......................................................... $7, 096.80
Item 4: Remove concrete slurry from trench line of the 24" steel water line at Station
70+50 for the lump sum price of$ 1,812.12.
Increase to contract cost. ......................................................... $1 , 812. 12
Page 2
Project: 3446-1 /3887-1 H, El Camino Real and Cassia Road Domestic and Recycled
Water Transmission Mains
Change Order No.1
Item 5: Repair potholes on the north bound lanes of El Camino Real between Cassia
Road and Palomar Airport Road, including all necessary traffic control, for the
lump sum price of$ 2,541.12.
Increase to contract cost. ......................................................... $ 2,541.12
Item 6: Install two (2) twelve-inch (12") 45° bends with concrete thrust blocks and
restraints to facilitate connection of the new 12" recycled Water Line A-1 to the
existing 12" Tee at Station 1+43 for the lump sum price of$ 4,768.2.
Increase to contract cost .......................................................... $ 4,768.27
TOTAL INCREASE TO CONTRACT COST .................................................... $28,768.31
Page 3
Project: 34461/3887-1 H, El Camino Real and Cassia Road Domestic and Recycled
Water Transmission Mains
Change Order No. 1
TIME FOR COMPLETION OF ALL WORK UNDER THIS CONTRACT SHALL NOT BE
AFFECTED BY THIS CHANGE ORDER.
RECOMMENDED BY:
~ i/t./oS
CONSRUCTIONMANAGER • (DATE)
DE'~~ 4-
y4iF-.CITY ENGINEE
K~ ~'-'LA-91i o 10.,
'FINANCE DIRECTOR (DATE)
DISTRIBUTION:
INSPECTION FILE (ORIGINAL)
PURCHASING
CONTRACTOR
DEPUTY CITY ENGINEER, DESIGN
APPROVED BY:
CARLSBAD MUNICIPAL
WATER DISTRICT
San Diego County
California
CONTRACT DOCUMENTS AND
SUPPLEMENTAL PROVISIONS
FOR
EL CAMINO REAL AND
CASSIA ROAD DOMESTIC AND RECYCLED
WATER TRANSMISSION MAINS
CONTRACT NOS. 34461 AND 38871-H
PW S04- 40 EN G
Revised 10/08/03 Contract No. 34461 & 3887-H Page 1 of 85 Pages
. . item
Notice Inviting Bids ........................................................................................................................
Contractor’s Proposal ....................................................................................................................
Bid Security Form ..........................................................................................................................
Bidder‘s Bond To Accompany Proposal .......................................................................................
Guide For Completing The “Designation Of Subcontractors’’ Form .............................................
Designation Of Subcontractor and Amount Of Subcontractor’s Bid Items .................................
Bidder‘s Statement Of Financial Responsibility ............................................................................
Bidder’s Statement Of Technical Ability And Experience .............................................................
Bidder‘s Certificate Of Insurance For General Liability. Employers’ Liability. Automotive
Liability And Workers’ Compensation ...........................................................................................
Bidder’s Statement Of Re Debarment ..........................................................................................
Bidder’s Disclosure Of Discipline Record .........................................................................
7
Non-Collusion Affidavit To Be Executed By Bidder And Submitted With Bid ..............................
Contract Public Works ..................................................................................................................
Labor And Materials Bond ............................................................................................................
Faithful PerformanceNVarranty Bond ...........................................................................................
Optional Escrow Agreement For Surety Deposits In Lieu Of Retention ......................................
7
11
29
30
32
34
35
36
37
38
39
41
42
48
50
52
@ Revised 10/08/03 Contract No . 34461 & 3887-H Page 2 of 85 Pages
SUPPLEMENTAL PROVISIONS
Part 1
Section 1 1-1 1-2 1-3
Section 2 2-3 2-4 2-5
2-9 2-1 0
Section 3 3-2 3-3 3-4 3-5
Section 4
4- 1 4-2
Section 5 5-1
-c 5-4
Section 6 6-1 6-2 6-6 6-7 6-8 6-9
Section 7
7-3 7-4 7-5 7-7 7-8 7-1 0 7-1 3
Section 9 9-1 9-3
General Provisions
Terms. Definitions Abbreviations And Symbols Terms .................................................................................................................... Definitions ............................................................................................................. Abbreviations ........................................................................................................
Scope And Control Of The Work Subcontracts ......................................................................................................... Contract Bonds ..................................................................................................... Plans And Specifications ...................................................................................... Surveying .............................................................................................................. Authority Of Board And Engineer .........................................................................
Changes In Work Changes Initiated by the Agency .......................................................................... Extra Work ............................................................................................................ Changed Conditions ............................................................................................. Disputed Work ......................................................................................................
Control Of Materials Materials And Workmanship .................................................................................
Materials Transportation, Handling and Storage ..................................................
Utilities Location ................................................................................................................. Relocation .............................................................................................................
Prosecution. Progress And Acceptance Of The Work Construction Schedule And Commencement Of Work ........................................ Prosecution Of Work ............................................................................................. Delays And Extensions Of Time ........................................................................... Time of Completion ...............................................................................................
Completion And Acceptance ................................................................................ Liquidated Damages .............................................................................................
Responsibilities Of The Contractor Liability Insurance ................................................................................................. Workers' Compensation Insurance ...................................................................... Permits .................................................................................................................. Cooperation and Collateral Work ......................................................................... Project Site Maintenance ...................................................................................... Public Convenience And Safety ........................................................................... Laws To Be Observed ..........................................................................................
Measurement and Payment Measurement Of Quantities For Unit Price Work ................................................. Payment ................................................................................................................
55
56 56
57 57 58 ~~ 60 62
63 63 63 64
67 67
68 68
68 74 74 75 75 75
76 76 76 76 76 77 82
82 82
d Revised 10/08/03 Contract No . 34461 & 3887-H Page 3 of 85 Pages
Part 2
1
State of California. Water Resource Control Board Contract Requirements
.-
State Wage Rate Clause ............................................................................................... BP1
.
.
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
22
23
24
25
Labor Code Section 1776; Complete Payroll Records; Certified and Available ........... BP1
Labor Code Section 1777.5; Employment of Properly Registered Apprentices .......... BP2
Labor Code Section 181 0; Definition: A Legal Day's Work ........................................... BP4
Labor Code Section 181 3; Penalty for Overtime on any Public Works Contract .......... BP4
Labor Code Section 181 5; Minimum Overtime Pay ...................................................... BP4
Labor Code Section 1860; Contract Provision .............................................................. BP4
Labor Code Section 1861; Contractor Certification to Labor Code Section 3700 ........ BP4
Cultural Resource Protection ......................................................................................... BP4
State MBENVBE Provisions; includes Attachment A and Attachment B ...................... BP6
MUST BE SUBMITTED WITH BID TO BE RESPONSIVE
The Subletting and Subcontracting Fair Practices Act ................................................ BP13
Equal Opportunity Clause (40 CFR 608.4(b)) ............................................................. BP13
Nondiscrimination Clause ............................................................................................ BP14
Construction Contractors - Affirmative Action Requirements (41 CFR 604) .............. BP15
Elimination of Segregated Facilities ............................................................................ BPI 9
Certification of Non-Segregated Facilities ........... : ....................................................... BP20
Drug-Free Workplace Certification .............................................................................. BP21
Use of Debarred Contractors Prohibited ..................................................................... BP22
Responsibility for Removal. Relocation. or Protection of Existing Utilities .................. BP24
(Government Code Section 421 5)
Submitting of Bids and Agreeing to Assign (Government Code Section 4552) .......... BP25
Affirmative Action and Equal Employment Opportunity minority participation table ... BP26
Labor Code Section 6500 ............................................................................................ BP27
Public Contract Code Section 7105 ............................................................................. BP27
Public Contract Code Section 9203 ............................................................................. BP28
;f;i Revised 10/08/03 Contract No . 34461 & 3887-H Page 4 of 85 Pages
Part 3
TECHNICAL SPECIFICATIONS
TABLE OF CONTENTS
rc
c
Section No. Title
01 001
01 002
01 005
01010
0101 1
01 025
01 040
01 047
01 048
01 200
01 300
01 31 0
01 340
01 400
01 41 0
01 500
01 520
01 530
01 550
01 570
01 580
01 590
01 600
01610
01 630
Dl 700
01 71 0
Revised 10/08/03
DIVISION 1 : GENERAL REQUIREMENTS
Standard Drawings, Standard Specifications and Approved
Materials List
Contractor’s Insurance Certification
Coordination with Design Engineer and Owner
Summary of Work
General Construction Sequence
Measurement and Payment
Coordination
Connections to Existing Facilities
Special Construction Conditions and Procedures - General
Project Meetings
Shop Drawing Submittals
Progress Schedule, Submittal Schedule, and Schedule of Values
Shop Drawing, Product Data and Samples
Quality Control
Testing and Inspection of Earthwork and Concrete
Construction Facilities and Temporary Controls
Maintenance of Traffic and Detours
Protection of Existing Utilities
Traffic Control and Re-Striping
Maintenance and Protection of Traffic
Project Identification and Signs
Field Offices and Sheds
Material and Equipment
Supplier’s/Manufacturer’s Special Services
Product Options and Substitutions
Contract Closeout
Cleaning and Final Cleaning
Contract No. 34461 & 3887-H Page 5 of 85 Pages
.-
Section No. Title
01 720 Record Drawings
01 730 Operating and Maintenance Data and Training
DIVISION 2: SITE WORK
021 30
02223 Trenching, Backfilling and Compacting
02225 Utility Crossings
0251 0 Asphaltic Concrete Pavement
Removal and Resurfacing of Pavement Surfaces
DIVISION 3: CONCRETE
03300 Concrete Construction
DIVISION 9: FINISHES
09870
09900 Painting and Coating
09902 Petrolatum Wax Tape Coating
Tape Wrap and Concrete Mortar Coating
DIVISION 13: CATHODIC PROTECTION
13120 Cathodic Protection
DIVISION 15: MECHANICAL
15000
15040
15056
15064
15066
15076
15092
151 00
General Piping System and Appurtenances
Testing, Flushing and Disinfection
Ductile Iron Pipe and Fittings
PVC Pressure Pipe and Fittings (AWWA C900)
PVC Pressure Pipe and Fittings (AWWA C905)
Cement Mortar-Lined and Coated Steel Pipe
Miscellaneous Couplings, Pipe and Appurtenances
* Valves
Revised 10/08/03 Contract No. 34461 & 3887-H Page 6 of 85 Pages
CARLSBAD MUNICIPAL WATER DISTRICT
NOTICE INVITING BIDS
Until 4:OO PM on July 27 2004, the Carlsbad Municipal Water District shall accept sealed bids,
clearly marked as such, at the Faraday Center, 1635 Faraday Avenue, Carlsbad, CA 92008-7314,
Attn: Purchasing Officer, by mail, delivery service or by deposit in the Bid Box located in the first floor
lobby, at which time they will be opened and read, for performing the work as follows:
CONTRACT NO. 34461
EL CAMINO REAL AND CASSIA ROAD
30” AND 24” POTABLE WATER TRANSMISSION MAINS
CONTRACT NO. 3887-H
EL CAMINO REAL AND CASSIA ROAD
18” AND 20” RECYCLED WATER TRANSMISSION MAINS
This bid and the terms of the Contract Documents and Supplemental Provisions constitute an
irrevocable offer that shall remain valid and in full force for a period of 90 days and such additional
time as may be mutually agreed upon by the Carlsbad Municipal Water District and the Bidder.
The work shall be performed in strict conformity with the plans and specifications as approved by the
Directors of the Carlsbad Municipal Water District on file with the Engineering Department.
The specifications for the work include the Standard Specifications for Public Works Construction,
2003 Edition, hereinafter designated “SSPWC” as issued by the Southern California Chapter of the
American Public Works Association and as amended by the supplemental provisions sections of this
contract. Reference is hereby made to the plans and specifications for full particulars and description
of the work.
-
The Carlsbad Municipal Water District encourages the participation of minority and women-owned
businesses.
The Carlsbad Municipal Water District encourages all bidders, suppliers, manufacturers, fabricators
and contractors to utilize recycled and recyclable materials when available, appropriate and
approved by the Engineer.
The Carlsbad Municipal Water District may disqualify a contractor or subcontractor from participating
in bidding when a contractor or subcontractor has been debarred by the Carlsbad Municipal Water
District or another jurisdiction in the State of California as an irresponsible bidder.
No bid will be received unless it is made on a proposal form furnished by the Purchasing
Department. Each bid must be accompanied by security in a form and amount required by law.
The bidder‘s security of the second and third next lowest responsive bidders may be withheld until
the Contract has been fully executed. The security submitted by all other unsuccessful bidders shall
be returned to them, or deemed void, within ten (IO) days after the Contract is awarded. Pursuant to
the provisions of law (Public Contract Code section 10263), appropriate securities may be
substituted for any obligation required by this notice or for any monies withheld by the District to
ensure performance under this Contract. section 10263 of the Public Contract Code requires monies
or securities to be deposited with the District or a state or federally chartered bank in California as the
escrow agent. The escrow agent shall maintain insurance to cover negligent acts and omissions of
the agent in connection with the handling of retentions under this section in an amount not less than
$1 00,000 per contract.
I
@ Revised 10/08/03 Contract No. 34461 & 3887-H Page 7 of 85 Pages
The documents which comprise the Bidder's proposal and that must be completed and properly
executed including notarization where indicated are:
1. Contractor's Proposal
2. Bidder's Bond
3. Non-Collusion Affidavit
4. Designation of Subcontractors and Amount of Subcontractor Bid 5. Bidder's Statement of Financial Responsibility
6. Bidder's Statement of Technical Ability and Experience
7. Acknowledgement of Addendum(a)
8. Certificate of Insurance. The riders covering the City, its officials, employees and volunteers may
be omitted at the time of bid submittal but shall be provided by the Bidder prior to award of this contract.
9. Bidder's Statement Re Debarment 1O.Bidder's Disclosure Of Discipline Record
1 1 .Escrow Agreement for Security Deposits - (optional, must be completed if the Bidder wishes to use the Escrow Agreement for Security)
All bids will be compared on the basis of the Engineer's Estimate. The estimated quantities are
approximate and serve solely as a basis for the comparison of bids. The Engineer's Estimate is
$3,593,000 ($1,944,000 - Bid Schedule No. I); ($1,649,000 - Bid Schedule No. 2).
Except as provided herein a bid submitted to the City by a Contractor who is not licensed as a
contractor pursuant to the Business and Professions Code shall be considered nonresponsive and
shall be rejected by the City. In all contracts where federal funds are involved, no bid submitted shall
be invalidated by the failure of the bidder to be licensed in accordance with California law. Where
federal funds are involved the contractor shall be properly licensed at the time the contract is
awarded. In all other cases the contractor shall state their license number, expiration date and
classification in the proposal, under penalty of perjury. This invitation to bid does involve federal
funds. The following classifications are acceptable for this contract: "A". General Engineering -
If the Contractor intends to utilize the escrow agreement included in the contract documents in lieu of
the usual looh retention from each payment, these documents must be completed and submitted
with the signed contract. The escrow agreement may not be substituted at a later date.
Sets of plans, supplemental provisions, and Contract documents may be obtained at the Cashier's
Counter of the Faraday Center located at 1635 Faraday Avenue, Carlsbad, California 92008-7314,
for a non-refundable fee of $50.00 per set. If plans and specifications are to be mailed, the cost for
postage should be added.
Any prospective bidder who is in doubt as to the intended meaning of any part of the drawings,
specifications or other contract documents, or finds discrepancies in or omissions from the drawings
and specifications may submit to the Engineer a written request for clarification or correction.
Any response will be made only by a written addendum duly issued by the Engineer a copy of which
will be mailed or delivered to each person receiving a set of the contract documents. No oral
response will be made to such inquiry. Prior to the award of the contract, no addition to,
modification of or interpretation of any provision in the contract documents will be given by
any agent, employee or contractor of the City of Carlsbad except as hereinbefore specified.
No bidder may rely on directions given by any agent, employee or contractor of the City of
Carlsbad except as hereinbefore specified.
The Carlsbad Municipal Water District reserves the right to reject any or all bids and to waive any
minor irregularity or informality in such bids.
CTi Revised 10/08/03 Contract No. 34461 & 3887-H Page 8 of 85 Pages
The general prevailing rate of wages for each craft or type of worker needed to execute the Contract
shall be those as determined by the Director of Industrial Relations pursuant to the sections 1770,
1773, and 1773.1 of the Labor Code. Pursuant to section 1773.2 of the Labor Code, a current copy
of applicable wage rates is on file in the Office of the City Engineer. The Contractor to whom the
Contract is awarded shall not pay less than the said specified prevailing rates of wages to all workers
employed by him or her in the execution of the Contract.
The Prime Contractor shall be responsible for insuring compliance with provisions of section 1777.5
of the Labor Code and section 4100 et seq. of the Public Contracts Code, "Subletting and
Subcontracting Fair Practices Act." The City Engineer is the City's "duly authorized officer" for the
purposes of section 41 07 and 41 07.5.
The provisions of Part 7, Chapter 1, of the Labor Code commencing with section 1720 shall apply to
the Contract for work.
A pre-bid meeting and tour of the project site will not be held.
All bids are to be computed on the basis of the given estimated quantities of work, as indicated in this
proposal, times the unit price as submitted by the bidder. In case of a discrepancy between words
and figures, the words shall prevail. In case of an error in the extension of a unit price, the corrected
extension shall be calculated and the bids will be computed as indicated above and compared on the
basis of the corrected totals.
All prices must be in ink or typewritten. Changes or corrections may be crossed out and typed or
written in with ink and must be initialed in ink by a person authorized to sign for the Contractor.
P Bidders are advised to verify the issuance of all addenda and receipt thereof one day prior to
bidding. Submission of bids without acknowledgment of addenda may be cause of rejection of bid.
The Contractor shall provide bonds to secure faithful performance and warranty of the work in an
amount equal to one hundred percent (100%) of the Contract price on this project. The Contractor
shall provide bonds to secure payment of laborers and materials suppliers, in an amount equal to:
1) One hundred percent (100%) of the total amount payable by the terms of the contract when the total amount payable does not exceed five million dollars ($5,000,000).
2) Fifty percent (50%) of the total amount payable by the terms of the contract when the total amount payable is not less than five million dollars ($5,000,000) and does not exceed ten million
dollars ($1 0,000,000).
3) Twenty-five percent (25%) of the total amount payable by the terms of the contract if the contract exceeds ten million dollars ($1 0,000,000).
These bonds shall be kept in full force and effect during the course of this project, and shall extend in
full force and effect and be retained by the City until they are released as stated in the Supplemental
Provisions section of this contract. All bonds are to be placed with a surety insurance carrier admitted
and authorized to transact the business of insurance in California and whose assets exceed their
liabilities in an amount equal to or in excess of the amount of the bond. The bonds are to be
accompanied by the following documents:
1) An original, or a certified copy, of the unrevoked appointment, power of attorney, by laws, or other instrument entitling or authorizing the person who executed the bond to do so.
2) A certified copy of the certificate of authority of the insurer issued by the insurance commissioner.
c If the bid is accepted, the District may require copies of the insurer's most recent annual statement
and quarterly statement filed with the Department of Insurance pursuant to Article IO (commencing
with section 900) of Chapter 1 of Part 2 of Division 1 of the Insurance Code, within 10 calendar days
Revised 10/08/05 Contract No. 34461 & 3887-H Page 9 of 85 Pages
of the insurer's receipt of a request to submit the statements.
Insurance is to be placed with insurers that:
1) Have a rating in the most recent Best's Key Rating Guide of at least A-:V
2) Are admitted and authorized to transact the business of insurance in the State of California by the Insurance Commissioner.
-
Auto policies offered to meet the specification of this contract must:
1) Meet the conditions stated above for all insurance companies.
2) Cover any vehicle used in the performance of the contract, used onsite or offsite, whether owned, non-owned or hired, and whether scheduled or non-scheduled. The auto insurance certificate
must state the coverage is for "any auto" and cannot be limited in any manner.
Workers' compensation insurance required under this contract must be offered by a company
meeting the above standards with the exception that the Best's rating condition is waived. The City
does accept policies issued by the State Compensation Fund meeting the requirement for workers'
compensation insurance.
The Contractor shall be required to maintain insurance as specified in the Contract. Any additional
cost of said insurance shall be included in the bid price.
The award of the contract by the Board of Directors is contingent upon the Contractor submitting the
required bonds and insurance, as described in the contract, within twenty days of bid opening. If the
Contractor fails to comply with these requirements, the District may award the contract to the second
or third lowest bidder and the bid security of the lowest bidder may be forfeited.
The prime contractor and all subcontractors are required to have and maintain a valid City of
Carlsbad Business License for the duration of the contract.
c
Approved by the Board of Directors of the Carlsbad Municipal Water District by Carlsbad Municipal
Water District Resolution No. 1212, adopted the 8* day of June, 2004
ISABELLE PAULSEN, CMC
Deputy Secretary
DATED: June 17,2004
e Revised 10/08/03 Contract No. 34461 & 3887-H Page 10 of 85 Pages
CARLSBAD MUNICIPAL WATER DISTRICT
c
c
I
CONTRACT NO. 34461
EL CAMINO REAL AND CASSIA ROAD
30” AND 24” POTABLE WATER TRANSMISSION MAINS
CONTRACT NO. 3887-H
EL CAMINO REAL AND CASSIA ROAD
18” AND 20” RECYCLED WATER TRANSMISSION MAINS
CONTRACTOR’S PROPOSAL
Board of Directors
Carlsbad Municipal Water District
5950 El Camino Real
Carlsbad, California 92008
The undersigned declares he/she has carefully examined the location of the work, read the Notice
Inviting Bids, examined the Plans, Specifications, Supplemental Provisions and addenda thereto,
and hereby proposes to furnish all labor, materials, equipment, transportation, and services required
to do all the work to complete Contract No. 34461 and Contract No. 3887-H in accordance with the
Plans, Specifications, Supplemental Provisions and addenda thereto and that he/she will take in full
payment therefor the following unit prices for each item complete, to wit:
BID SCHEDULE “A”
DOM ESTlC WATER TRAN SM lSSl0 N MA1 NS
CONTRACT NO. 34461
Approximate
Item Quantity Unit - No. DescriDtion And Unit - Price - Total
A-1 . Mobilization, demobilization, LS Lumpsum $ 53!cm4
providing project sign, compliance
with all General and Supplementary
conditions and providing cleanup of
construction site complete in place at
It Fry G& * SA&uh <* h& aka
c\nL~A.ns *%t.n
Dollars (Lump Sum)
@ Revised 10/08/03 Contract No. 34461 & 3887-H Page 11 of 85 Pages
--
I
e-
Item
No. -
A-2.
A-3.
A-4.
A-5.
A-6.
BID SCHEDULE “A”
DOMESTIC WATER TRANSMISSION MAINS
CONTRACT NO. 34461
Description
Perform Exploratory Excavations for
underground utilities at
Tc? /wkm buup 72cp rlry)hrg
hNbk hlMr e%d
Dollars (Lump Sum)
/
Construct 30-inch diameter CML tape
wrapped and mortar coated steel
pipe transmission main at
fl&ZC tb~+%?~a &QM SAJ
U7/I!S.r ‘Yfbt2
Dollars per Linear Foot
Provide all necessary and required
traffic control to perform construction
in Bid Item No. 3 at
BAU %SA &A 516 b&dr 4d,
~0~1~~ +- w/&-
Dollars (Lump Sum)
Construct 24-inch diameter CML tape
wrapped and mortar coated steel
pipe transmission main at
OPEtfUkbRt39 Si %Tl/GdL
I)bLIC 6 ZGhd
Dollars per Linear Foot
Provide all necessary and required
traffic control to perform construction
in bid Item No. 5 at
%W2-*5hN6 %&
hbldkefl &ti M 5 -4- “bJ/Cc..,
Dollars (Lump Sum)
Approximate
Quantity Unit
And Unit - Price - Total
420 LF $ 3q7.15
@ Revised 10/08/03 Contract No. 34461 & 3887-H Page 12 of 85 Pages
Item No.
A-7,
A-8.
A-9.
A-1 0.
BID SCHEDULE “A’
DOMESTIC WATER TRANSMISSION MAINS
CONTRACT NO. 34461
Approximate
Quantity Unit
Description And Unit - Price - Total
Construct 12-inch diameter LS Lumpsum $ Ja,/m PVC C900 domestic water main stub-
out at Station No. 48+78 at
7&hTk 7;;ro fl 6t5- 0 lv38 Mv&h,?c13
&I/’kZE uq/W
Dollars (Lump Sum)
Construct 12-inch diameter PVC LS
C900 domestic water main at Station
No. 60+23.92 at
TN~?,V~V bdE %.%3~-& /ulrJG #our)p~
bUi&?s 4-7,c
Dollars (Lump Sum)
Construct the connection to the
existing 20-inch diameter water main
at Station No. 70+74.70 at
LS
7-H lATIr/ Tm b- !fi dG ’ k*AQjb r lSvr\Ap5 d- “/IC
Dollars (Lump Sum)
Construct the 8-inch diameter PVC LS Lumpsum $ h’,bm- C900 interconnection from Sta. No.
0+66 to Sta. No. 1+00, to the existing
16-inch diameter distribution line at
Sta. No. 48+78 at
boi\pr(Lo -= Wtw
Dollars (Lump Sum)
6m-d %M sMhuaR&
Revised 10/08/03 Contract No. 34461 & 3887-H Page 13 of 85 Pages
Item
No. -
A-1 1.
A-1 2.
A-1 3.
A-1 4.
BID SCHEDULE “A”
DOMESTIC WATER TRANSMISSION MAINS
CONTRACT NO. 34461
Approximate
Quantity Unit
DescriDtion And Unit - Price - Total
Construct the connection to the LS Lumpsum $ 93,/m* existing 16-inch, 14-inch and 6-inch
diameter distribution lines at Station
No. 80+09 at the intersection of El Camino Real and Cassia Road at
/VIA?? flPeC flUll*a, oue tt!vw&n
f)oilk$E r9klv
Dollars (Lump Sum)
Construct the connection to the
existing 30-inch diameter
transmission main along Cassia
Road at approximate Station No.
84+29 and abandonment of existing
18-inch transmission main at
cJcwk^u7L r.4 naLs4-4-a Jol(A?ts ,Y+i
Dollars (Lump Sum)
Construct the connection to the existing 8-inch diameter water main
along Cassia Road at approximate
Station No. 83+91 .OO at
6Frid TLW*Y~ SF ~WAW
&I&& *@/uY
Dollars (Lump Sum)
LS
Furnish and construct a 2-inch air 7 EA $ G.,W-- $ 456-9- release and vacuum relief valve
assembly per Carlsbad Municipal
Water District Standard Drawing No. W7 at
Sf6 7b-V 5 cr^lrs 6d&5 ttC)NDAen
Qb11MS m/r /
Dollars Each
Revised 10/08/03 Contract No. 34461 8,3887-H Page 14 of 85 Pages
Item
No.
A-1 5.
A-1 6.
A-1 7.
A-I a.
BID SCHEDULE “A”
DOMESTIC WATER TRANSMISSION MAINS
CONTRACT NO. 34461
Description
Furnish and construct a 2-inch
manual air release valve per
Carlsbad Municipal Water District
Standard Drawing No. W6 at
-fwo flaw 6 i? Ctow, Prss
DolkS & ehcr
Dollars Each
Furnish and construct a 4-inch blow-
off assembly per Carlsbad Municipal
Water District Standard Drawing
No. W11 at
GY%w ONS hMR&
LWtnas 4 Eey/clJc
Dollars Each
Furnish and install 6-inch diameter
steel pipe and fire hydrant assembly
at station 23+35 at
6LmN Gw sF4a bDIG-pG *%#
Dollars (Lump Sum)
Furnish and install 30-inch butterfly
valve per Carlsbad Municipal Water
District Standard Drawing No. W 17 at
EuUcrd %asAwlb T&C hAAbAMD
ODIIAer + %Go
Dollars Each
Approximate
Quantity Unit
And Unit - Price - Total
3 EA $ 4/00’
Revised 10/08/03 Contract No. 34461 & 3887-H Page 15 of 85 Pages
Item
No. -
A-1 9.
A-20.
A-21.
A-22.
BID SCHEDULE “A”
DOMESTIC WATER TRANSMISSION MAINS
CONTRACT NO. 34461
Approximate
Quantity Unit
DescriDtion And Unit - Price - Total
Furnish and install a 24-inch butterfly 8 EA $ z7m‘ $ b&@+- valve per Carlsbad Municipal Water
District Standard Drawing No. W 17 at
9v€w *e%w st$m h!v rvnkm
Dollars Each
lkRL -rey/cc
Furnish and install an 14-inch 1 EA $ 2,9m $ 2,w -
butterfly valve per Carlsbad Municipal
Water District Standard Drawing No.
W17 at
7@ 7lm yk/r3 ”tg th.W#e ld
bl/Lh25 r9;d
Dollars Each
Furnish and install a 16-inch butterfly 2 EA $ $9- $ .z--
valve per Carlsbad Municipal Water
District Standard Drawing No. W 17 at
RlG *5%w FjjE ))v/uiJl2Mo
\ e*//& -
Dollars Each
Furnish and install a 12-inch resilient 2 EA urn- $ t’,4m0
wedge gate valve per Carlsbad
Municipal Water District Standard
Drawing No. W16 at
7z;c T;102( SM % #u kale&
QsllIres WW
Dollars Each
Revised 10/08/03 Contract No. 34461 & 3887-H Page 16 of 85 Pages
Item
No. -
A-23,
A-24.
A-25.
A-26.
BID SCHEDULE "A"
DOMESTIC WATER TRANSMISSION MAINS
CONTRACT NO. 34461
Approximate
Quantity Unit
DescriDtion And Unit - Price - Total
Furnish and install 8-inch resilient 3 EA $pm- $ 39s'
wedge gate valve per Carlsbad
Municipal Water District Standard
Drawing No. W 16 at
D0Il-s 4- q/#f
bW*W&Wk .N olearo
Dollars Each
Furnish and install cathodic LS Lumpsum $ .50,6c*
protection for 30-inch and 24-inch
CML tape wrapped and mortar
coated steel pipe transmission mains
at
aSLwn'0 3nc h&S(rW
D@.l/IrBRT t--9/6r
Dollars (Lump Sum)
Provide permanent traffic video
detection system and all work
associated for installation at
M noicwrc;. t%c
Dollars Each
Construction Schedule at LS
HWue hJ *- Slf
&I\he4 .t WlW
Dollars (Lump Sum)
Revised 10/08/03 Contract No. 34461 & 3887-H Page 17 of 85 Pages
BID SCHEDULE “A”
DOMESTIC WATER TRANSMISSION MAINS
CONTRACT NO. 34461
Approximate
Item Quantity Unit - No. DescriDtion And Unit - Price - Total
A-27. Provide and prepare drawings for LS Lumpsum $ ZZ~~
SWPPP and BMP permits. Furnish
and install erosion and water pollution
control devices per approved shop
drawing submittals at
/ p il
Dollars (Lump Sum)
A-28. Provide excavation safety measures LS Lumpsum $ 4,4&aH
including sheeting, shoring and
bracing, or equivalent method for the
protection of life and limb in trenches
and open excavation in conformance
with applicable safety orders at
5,s- b UUNYmdb
Dollars (Lump Sum)
DollA-Qs +%Lo-
Total amount of bid in words for Schedule “A’ (Item Nos. A-1 through A-28): UNCF MI~U~ d/6d7
c HUAUI~EQ I$OWL~,UQ 7’ LkD ffUkbjlt5-b ICUL-NTY T&& b//MS + 9m
Total amount of bid numbers for Schedule “A (Item Nos. A-1 through A-28): $ 1, 01 I 223
Revised 10/08/03 Contract No. 34461 & 3887-H Page 18 of 85 Pages
I BID SCHEDULE “8”
18” / 20” PVC PIPE RECYCLED WATER TRANSMISSION MAINS
CONTRACT NO. 38871-H
Approximate
Item Quantity Unit
No. DescriDtion And Unit - Price - Total
B-1 . Mobilization, demobilization, LS Lump Sum $ ; q’s~ - providing project sign, compliance 1
with all General and Supplementary
conditions and providing cleanup of
construction site complete in place
at
6% i”utwp a-asthiwb Figt? f&.4&, ,&A &bl/mz r*/i
Dollars (Lump Sum)
8-2. Perform Exploratory Excavations for LS Lumpsum $ ZG(ft*’
c underground utilities at - T&J~ sir 71~n*<m rnNsi w Atia Q~ILAL &!t W
Dollars (Lump Sum)
8-3. Construct 20-inch diameter (2-905 5,705 LF $ /+f3/ $ 827:ZSFf
Class 235 PVC pipe recycled water
main (Line A) in El Camino Real
from Station No. 1 OO+OO to
approximate Station No. 157+85 at
Doillhaa t OD//‘-
Dollars per Linear Feet
6-4. Provide traffic control as necessary LS LumpSum $ $‘O./W~
and required for performing the work
and associated work in Item No. 3 at
4r almf
BCJP oNEhdQ~b
Dollars (Lump Sum)
@ Revised 10/08/03 Contract No. 34461 & 3887-H Page 19 of 85 Pages
Item No. -
6-5.
6-6.
B-7.
6-8.
c
BID SCHEDULE “B”
18” / 20” PVC PIPE RECYCLED WATER TRANSMISSION MAINS
CONTRACT NO. 38a7i-~
Approximate
Quantity Unit
DescriDtion And Unit - Price Total
Provide High line for by-passing 12”
recycled water main from Station
No. 10040 to approximate Station
No. 1 1340. Connections at
Existing pump station and existing
lateral at approximate Street CL
Station 260+85 at
-n+,nT21 - -- SLY- h.w
&l\fwL t%w
Dollars (Lump Sum)
Construct 12-inch diameter C-900
Class 150 PVC pipe recycled water
main lateral (Line Al) and
appurtenances to the east at
approximate Station 1 12+90 at
*SmJ TL w mkm~
Mh$.& VId
Dollars (Lump Sum)
Construct 1 0-inch diameter C-900
PVC pipe recycled water main stub-
out (Line A2) and appurtenances to
the west at approximate Station
No. 124+77 (Camino Vida Robles)
at
*&;hlT&fhi %uw La kum
bll rhlL.5 Y b”///uy‘
Dollars (Lump Sum)
Construct 12-inch diameter C-900
PVC pipe recycled water main (Line
A3) and appurtenances to the east
at approximate Station No. 138+78
(Town Garden Road) at
%LVG rn%> nNO ki.h!Mt&
hnll ‘sp 4 4- Q?/iuf
Dollars (Lump Sum)
LS Lumpsum $ dY,Vo’
Revised 10/08/03 Contract No. 34461 & 3887-H Page 20 of 85 Pages
c
BID SCHEDULE “B”
18” / 20” PVC PIPE RECYCLED WATER TRANSMISSION MAINS
CONTRACT NO. 38871 -H
Approximate
I tem Quantity Unit - No. DescriDtion And Unit - Price - Total
c B-9. Construct 30-inch diameter CML LS Lumpsum $ %2,gm
and taped CMC recycled water main
(Line A4) and appurtenances to the
east at approximate Station
No. 150+00 (Gateway Road) at
&7?, 3lf%%S frwuu An-
Dollars (Lump Sum)
hhM< * c”//Lc
B-10. Construct 20-inch diameter C-905 LS Lump Sum $ 337m-
CL 235 PVC pipe recycled water
main stub-out (Line A5) and
appurtenances to the east at
approximate Station No. 157+85 at
-1 7haarTkmM 4L;v&&P
r UbkPpkD 9011x725 t ”4w-
Dollars (Lump Sum)
I B-11. Construct 18-inch diameter C-905 425 LF $ /37- $ 58,ZU’
CL 235 PVC pipe recycled water
main in El Camino Real from
approximate Station 157+85 to
Station 162i-08, provide
appurtenances and connection to
existing 16-inch recycled water main
at
L?U4 h&,SR60 m~+) 4wsJ
brines aCtJlar
Dollars per Linear Foot
B-12. Provide traffic control as necessary LS Lumpsum $ /,zm’
and required for petforming the work
and associated work in item No. 11
at
OAJG%~~()N~ r- kM&
Odk 6 Ytw
Dollars (Lump Sum)
- Q Revised 10/08/03 Contract No. 34461 8,3887-H Page 21 of 85 Pages
Item
No. -
6-1 3.
B-14.
6-1 5.
6-1 6.
BID SCHEDULE "By'
18" / 20" PVC PIPE RECYCLED WATER TRANSMISSION MAINS
CONTRACT NO. 38871-H
Approximate
Quantity
DescriDtion And Unit
Construct 18-inch diameter C-905
Class 235 PVC ductile iron pipe
recycled water main (Line B) in
Cassia Road from Station No.
170+00 to approximate Station No.
175+00 at
6.oa h~AORun 5k& UfQW 5W&*J
udth2s a-WIc3-
Dollars per Linear Feet
500 LF
Provide traffic control as necessary LS
and required for performing the work
and associated work in Item No. 13
at
Brr'as *4w3 (hCkA&ea
boilML HI cw-
Dollars (Lump Sum)
Construct connection to the existing
18-inch diameter recycled water
main along Cassia Road at Station
No. 175+00 at
T&Uts TL-b s44 IhiaGW
&iWL +"thm-
Dollars (Lump Sum)
.S
Furnish and construct 2-inch air
release and vacuum release valve
assembly per Carlsbad Municipal
Water District Standard Drawing No.
W7 at
23 EA
sm !&K-7 IYtUARkfi
D61/MS 4- *//w
Dollars Each
Unit - Price
Lump Sum
@ Revised 10/08/03 Contract No. 34461 & 3887-H
Lump Sum
w
- Total
$
$ hm-
Page 22 of 85 Pages
Item
No. -
B-17.
B-18.
B-19.
B-20.
BID SCHEDULE "B"
18" / 20" PVC PIPE RECYCLED WATER TRANSMISSION MAINS
CONTRACT NO. 388714
Approximate
Quantity Unit
Description And Unit - Price - Total
Furnish and construct a 2-inch 1EA $ /$9W0 $ /,!%V"
manual air release valve or blow-off
assembly per Carlsbad Municipal
Water District Standard Drawing No.
W6 at
&k- ;fl(rrc%Na &/&? #u W&@
pmrsn3 e
Dollars Each
Furnish and construct 4-inch blow- 9 EA $ @t~~ $ 60~~ off assembly per Carlsbad Municipal
Water District Standard Drawing No.
W11 at
5H%b5prrs C1LYHhA4SRtd
&/(kRs cc"/cu-
Dollars Each
Furnish and install a 20-inch 13EA $ 4,523- $ c4,w-
diameter butterfly valve per
Carlsbad Municipal Water District
Standard Drawing No. W 17 and
W13 at
Ell< v3.e- Krn#dN&?&
Dollars Each
h1lA-m C~h-
Furnish and install an 18-inch
diameter butterfly valve per
Carlsbad Municipal Water District
Standard Drawing No. W17 and
W13 at
Sh~v5~h lh-
Doll&&+- oc%r
Dollars Each
e Revised 10/08/03 Contract No. 34461 & 3887-H Page 23 of 85 Pages
BID SCHEDULE “8”
18” / 20” PVC PIPE RECYCLED WATER TRANSMISSION MAINS
CONTRACT NO. 38871 -H
Approximate
Item Quantity Unit - No. Description And Unit 7 Price - Total
8-21 . Furnish and install a 12-inch resilient 2EA $ ,;?,2d- $ ‘%q@‘
wedge gate valve per Carlsbad
Municipal Water District Standard
Drawing No. W 16 and W 13 at
<rn%%cfLUo hmbQm
2)eildRE +- c?&m-
Dollars Each
8-22. Furnish and install an 1 O-inch 1 EA $ L9m4 $ i,qmk
resilient wedge gate valve per
Carlsbad Municipal Water District
Standard Drawing No. W 16 and
W13at
U@.rbT7laLSpND MA& &kPk%o
&I/&S -b%kf
Dollars Each
8-23. Furnish and construct a 1 -inch
meter recycled water irrigational
service per Carlsbad Municipal
Water District Standard Drawing No.
W4 at
mts*9wh $6 &&mO
Dollars Each
D07/snc r%d
8-24. Furnish and construct a 2-inch
meter recycled water irrigational
service per Carlsbad Municipal
Water District Standard Drawing No.
W4 at
fiPW &J dm c, M hdnmo
Qef1~5
Dollars Each
- @ Revised 10/08/03 Contract No. 34461 & 3887-H Page 24 of 85 Pages
BID SCHEDULE "B"
18" / 20" PVC PIPE RECYCLED WATER TRANSMISSION MAINS
CONTRACT NO. 38871 -H
Approximate
Item Quantity Unit
No. Description And Unit - Price - Total
Provide excavation safety measures LS Lumpsum $ 6,~.
bracing or equivalent method for the
8-25. including shoring, sheeting and
protection of .life and limb in
trenches and open excavation in
conformance with applicable safety
orders at
PIK a*%?Wu jGii2 k;UO/Lcn3
&37k?S w-Lcc?-
Dollars (Lump Sum)
OPENED, WITNESSED E,X:3 I:XXRDED:
7-2
DATE \
. c 8,
- Total amount of bid in words for Schedule "B' (Item Nos. B-1 through B-25): 4~6 M~~itud 6crdhdRa
/vf&T'/ 06 rn KvyMpbn &HV &maPs a"%Jv-
I I
Total amount of bid in numbers for Schedule "B (Item Nos. B-1 through 8-25): $ 4 gf/, V&O -
- Total amount of bid in words including schedules "A and Schedule "B : 7- MtUt 013 7%W@
bma NjUkvY TruD*sW 5w M &n nRfsl? IobllMs 4- %e -
Total amount of bid in numbers including schedules "A and Schedule "B" : 3, 34 z., 763
The basis of award will be the sum of Schedule "A" and "B". -
Price(s) given above are firm for 90 days after date of bid opening.
hadhave been received and idare included in this .- Addendum(a) NO(~).
proposal.
--
- The Undersigned has carefully checked all of the above figures and understands that the District will
not be responsible for any error or omission on the part of the Undersigned in preparing this bid.
- The Undersigned agrees that in case of default in executing the required Contract with necessary
bonds and insurance policies within twenty (20) days from the date of award of Contract by the Board
of Directors of the Carlsbad Municipal Water District, the District may administratively authorize
award of the contract to the second or third lowest bidder and the bid security of the lowest bidder
may be forfeited.
-_
-
-
Revised 10/08/03 Contract No. 34461 & 3887-H Page 25 of 05 Pages
- The Undersigned bidder declares, under penalty of perjury, that the undersigned is licensed to do
business or act in the capacity of a contractor within the State of California validly licensed under
license number PW336 , classification which expires on
an affidavit.
,-
-. 4/3q of , and that this statement is true and correct and has the legal effect of
A bid submitted to the District by a Contractor who is not licensed as a contractor pursuant to the
Business and Professions Code shall be considered nonresponsive and shall be rejected by the City 5 7028.1 5(e). In all contracts where federal funds are involved, no bid submitted shall be invalidated
by the failure of the bidder to be licensed in accordance with California law. However, at the time the
contract is awarded, the contractor shall be properly licensed. Public Contract Code 5 201 04.
--
The Undersigned bidder hereby represents as follows:
1. That no Board of Directors member, officer agent, or employee of the Carlsbad Municipal Water
District is personally interested, directly or indirectly, in this Contract, or the compensation to be paid
hereunder; that no representation, oral or in writing, of the Board of Directors, its officers, agents, or
employees has inducted him/her to enter into this Contract, excepting only those contained in this
form of Contract and the papers made a part hereof by its terms; and
- 2. That this bid is made without connection with any person, firm, or corporation making a bid for the
same work, and is in all respects fair and without collusion or fraud.
- Accompanying this proposal is 8,aoec 43u 84Jn (Cash, Certified Check, Bond or
Cashier's Check) for ten percent (10%) of the amount bid.
c
I The Undersigned is aware of the provisions of section 3700 of the Labor Code which requires every
employer to be insured against liability for workers' compensation or to undertake self-insurance in
accordance with the provisions of that code, and agrees to comply with such provisions before
commencing the performance of the work of this Contract and continue to comply until the contract is
complete.
The Undersigned is aware of the provisions of the Labor Code, Part 7, Chapter 1, Article 2, relative
to the general prevailing rate of wages for each craft or type of worker needed to execute the
Contract and agrees to comply with its provisions.
IF A SOLE OWNER OR SOLE CONTRACTOR SIGN HERE:
(1) Name under which business is conducted
(2) Signature (given and surname) of proprietor
(3) Place of Business
City and State
(4) Zip Code pAZo// Telephone No. hlq- 5qo-0929
@ Revised 10/08/03 Contract No. 34461 & 3887-H Page 26 of 85 Pages
License Detail Page 1 of 2
IClass
IK'WELL
/A
License Detail CALIFORNIA CONTRACTORS STATE LICEN
Contractor License # 298336
Description
DRtLLING (WATER)
GENERAL ENGINEERING CONTRACTOR
DISCLAIMER
A license status check provides information taken from the CSLB license data base. Beforc
on this information, you should be aware of the following limitations:
CSLB complaint disclosure is restricted by law (B&P 7124.6). If this entity is subject tc
complaint disclosure, a link for complaint disclosure will appear below. Click on the lin
button to obtain complaint and/or legal action information.
Per B&P 7071.17, only construction related civil judgments known to the CSLB are di
Arbitrations are not listed unless the contractor fails to comply with the terms of the
arbitration .
Due to workload, there may be relevant information that has not yet been entered ont
Board's license data base.
Extract Date: 07/27/2004
* * * Bonding Information * * *
of $10,000 with the bonding company CONTRACTOR'S BOND: This license filed Contractor's Bond number GCL1208319 in the
http://www2.cslb.ca.gov/CSLB_LIBRARY/License+Detail. asp 7/27/2004
License Detail Page 2 of 2
INTERNATIONAL BUSINESS AND MERCANTILE REASSURANCE COMPANY.
Effective Date: 01 /01/2004
Contractor's Bondina History
BOND OF QUALIFYING INDIVIDUAL(1): The Responsible Managing Officer (RMO) JlMM
NELSON certified that he/she owns 10 percent or more of the voting stock/equity of the cor A bond of qualifying individual is not required.
Effective Date: 10/08/1991
BQl's Bondina History
* * * Workers Compensation Information * * *
This license has workers compensation insurance with the
Policy Number: WC367699500 Effective Date: 07/03/2004 Expire Date: 07/03/200f
ZURICH AMERICAN INSURANCE COMPANY (4581-5)
Workers Compensation Histom
Personnel listed on this license (current or disassociated) are listed on other lice1
_.______ License Number Request Contractor Name Request Personnel Name Request
Salesperson Request Salesperson Name Request
0 2004 State of California. Conditions of Use Privacy Policy
7/27/2004
Personnel List Page 1 of 1
License Number Regluest
! Personnel List CALIFORNIA CONTRACTORS STATE-LlCEN
Contractor Name Request Personnel Name Request
Contractor License # 298336
Click on the person's name to see a more detailed page of information on that person.
Salesperson Request
Association Disassociation Date Date Name Title
Salesperson Name Request
1JIMMIERA.UL NEL-S0.N RMO/CEO/PRES 09/27/1974 A I ILAURA MICHELE NELSON OFFICER 09/27/1974 I
A -- 05/03/1985 - _" - PAUL IMON NELSON 0 FFI C E R 09/27/1974 I..... -- II I" ROBERT NORMAN
SIEMERS OFFICER 09/27/1974 08/22/1979
KYLEPAUL NELSON OFFICER 03/11 /2002
0 2004 State of California. Conditions of Use Privacy Policy
http://www2.cslb.ca.gov/CSLB_LIBRARY/Personnel+List.asp?LicNum=29S3 36 7/27/2004
IF A PARTNERSHIP, SIGN HERE:
(1) Name under which business is conducted
(2) Signature (given and surname and character of part
F
(3) Place of Business
(Street and Number)
Telephone No.
IF A CORPORATION, SIGN HERE:
(1) Name under which business is conducted c&5 COIJYTRU~O~J ,-c.
(2) &3$2??257=/’7
c (Signature)
Impress Corporate Seal here
-- (3) Incorporated under the laws of the State of CA-tl ?A
(4) Place of Business //OD #t?hJ@e dPrc/E
(Street and Number)
City and State L6-d CP 42020
(5) Zip Code 42oLO Telephone No. G 19 - 590 - @? 2 4
Revised 10/08/03
r-
Contract No. 34461 & 3887-H Page 27 of 85 Pages
- NOTARIAL ACKNOWLEDGMENT OF EXECUTION BY ALL SIGNATORIES MUST BE ATTACHED
- List below names of president, vice president, secretary and assistant secretary, if a corporation; if a
partnership, list names of all general partners, and managing partners:
@ Revised 10/08/03 Contract No. 34461 & 3887-H Page 28 of 85 Pages
BID SECURITY FORM
(Check to Accompany Bid)
CONTRACT NO. 34461
EL CAMINO REAL AND CASSIA ROAD
30” AND 24” POTABLE WATE
CONTRACT NO. 3887-H
EL CAMINO REAL A
18” AND 20” RECYCLED WATER
(NOTE: The following form shall be used if check acco
Accompanying this proposal is a *Certified *Cashie
MUNICIPAL WATER DISTRICT, in the sum of
-
- this amount being ten perce
become the property of the
action of its legally constitu
contract and furnish the req
coverage within the stipul
The proceeds of this chec
withdraw his or her bid wit
unless otherwise required
t of the bid. The proceeds of this check shall
sal shall be accepted by the District through
and the undersigned shall fail to execute a
and Payment Bonds and proof of insurance
eck shall be returned to the undersigned.
erty of the District if the undersigned shall
after the date set for the opening thereof,
ward of the contract to another bidder.
I 7
BIDDER
- *Del& the inapplicable word. - (NOTE: If the Bidder desires to use a bond instead of check, the Bid Bond form on the following pages shall be executed--the sum of this bond shall be not less than ten percent (10%) of the total amount of the bid.)
I
c @ Revised 10/08/03 Contract No. 34461 & 3887-H Page 29 of 05 Pages
1,
.- BIDDER’S BOND TO ACCOMPANIY PROPOSAL
CONTRACT NO. 34461
EL CAMINO REAL AND CASSIA ROAD
30” AND 24” POTABLE WATER TRANSMISSION MAINS
CONTRACT NO. 3887.H
EL CAMINO REAL AND CASSIA, ROAD
18” AND 20” RECYCLED WATER TRANSMISSION MAINS
KNO’N ALL PERSONS BY THESE PRESENTS:
That we, CASS CONSTRUCTION, INC. , as Principal, and PAFECO INSURANCE COMPANY OF AMERICe,
as S~rety are held and firmly bound unto the Carlsbad Municipal Water District, California, in an
amoiint as follows: (must be at least ten percen’t (10%) of the bid amount) - TEN PERCENT OF BID (10% OF BID) for which payment, well and truly made, we bind ourselves, our
heirs, executors and administrators, successors or assigns, jointly and severally, fi rrnly by these
presimts.
THE CONDITION OF THE FOfiEGOlNG OBLIGATION IS SUCH that if the proposal of the above- bourden Principal fort
CONTRACT NO, 34461
EL CAMINO REAL AND CASSIA ROAD
30” AND 24” POTABLE WATER TRANSMISSION MAINS
CONTRACT NO. 3887-HI
EL CAMINO REAL AND CASSIA ROAD
18” AND 20” RECYCLED WATER TRANSMISSION MAINS
in fh3 City of Carlsbad, is accepted by the Board of Directors, and if the Principal shall duly enter into
and execute 8 Contract including required bonds and insurance policies within twenty (20) days from
the date of award of Contract by the Board of Dlrectors of the Carlsbad Municipal Water District of
the :Xy of Carlsbad, being duly notified of said award, then this obligation shall become null and
void: otherwise, it shall be and remain in full force and effect, and the amount specified herein shall
be forfeited to the said District.
... ...
.-. ..- ... ... ... .. .
+*
... ... ...
a I’ %lb Revised 10/08/03 Contract No. 34.461 & 3887-H Paoe 30 of 85 Panes
-- In Ihe event Principal executed this bond as an individual, it is agreed that the death of Principal shall
no't exonerate the Surety from its obligations under this bond.
Exixuted by PRINCIPAL this day of .rl 20--
PH I NCI PAL:
day Executed by SURETY this 8TH -. CASS CONSTRUCTION, INC.
JULY ,20 04 I (nz me of Bn ip I)
(si ghere)
of -
SURETY:
By .A+ 22fiX2-
- _.. AClc & /? # c L SU,d
(print name here)
- &SF-. J,L
SAFECO INSURANCE COMPANY OF AMERICA
(name cd Suretvl
p 263 7 y77.g 7- L As 5 <Gd&7/7~ 4330 N. BRAND BLVD . , SUITE 1000 (Title and Organization of Signatory) LK CLENDALE, CA 91203 --
(address of Surety)
(81 8) 956-4242
By: A mr 4.A
_.. L4cll"d I Ahfs0/7
_. ScrelCqp,, 6 f cqss 6n54ruLYiD4,
(sign hers)
(pi int name here)
(tilie and orgahzation of signatory) 74 c JACK G. LUP I EN, ATTORNEY - I N-FACT
' (printed name of Attorney-in-Fact)
7
(Altach corporate resolution showing current power of attorney.)
(Froper notarial acknowledgrrmt of execution by PRINCIPAL and SURETY must be attached.)
(F resident or vice-president trnd secretary or assistant secretary must sign for corporations. If only
orie officer signs, the corporation must attach a resolution certified by the secretary or assistant
sticretary under corporate seal empowering that officer to bind the corporation,)
A?PROVED AS TO FORM:
R3NALD R. BALL
General Counsel
B ,I:
Deputy General Counsel
State of California )
County of San Diego )
On July 8, 2004 before me, Tara Bacon, Notary Public, personally appeared
Jack G. Lupien, personally known to me to be the person whose name is
subscribed to the within instrument and acknowledged to me that he executed
the same in his authorized capacity, and that by his signature on the
instrument the person(s), or the entity upon behalf of which the person acted,
executed the instrument.
-
WITNESS my hand and official seal.
POWER
T 9 A E OFATTQRNEY
SAFECO INSURANCE COMPANY OF AMERICA
GENERAL INSURANCE COMPANY OF AMERICA
HOME OFFICE: SARCO PLAZA
SEATTLE. WASHINGTON 98185
No. 5528
KN5W ALL BY THESE PRESENTS:
its true and lawfurl attotneyfs)-iwfad, with full authority to execute on its behalf fidelity and surety bonds or undertakings and other documents of e similar charar
issued in the course of its business. and io bind the mspeclke company thereby.
1N WtTNESS WHEREOF, SAFECO INSURANCE COMPANY OF AMERICA and GENERAL lNSLlRAPlCE COMPANY OF AMERICA have sach executed and
attested !hose presents
this 4 day of Jnnwq , 1993
R.A. PIERSON, SECRETARY W. RANDALL STODDARD, PRESIDENT
CERTIFICATE
Exlraci from the By-Laws dBAFE%O tNSURMICE COMPANY OF AMERICA
and of GENERAL INSURANCE COMPANY OF AMERICA:
"Article V, Section 13. - FlDfUTY AND SURETY BONDS ... Ihe President, my Vice President, the Secretary, and any Assistant Vice President appointed for lhat
purpose by lhe officer in charge ol surely operations, shab each haw aulhbdly to appoht individuals as attorneys-in-fact or under other appropriata titles with auhrity to
execule on behalf of the wmpany fidelity and surely bonds and Other doarmenls af similar character issued bv the company in Ure course of ils business .. On any
instrument making at evidencing such appointment, Ihe s$$nalures my ba affixed by facsimile. On any instrument confarrlng such aulhocily or on any bond or
I undertaklng of Vw company, Ihe seal, or a facsimile lhereof. may be .mprs%ed or afflKed or in any other manner reproduced; provided, however. that Ihe seal shall not
necessary to the validity of any such instrument or undertaking."
Extract from a Resatution ofthe Board of Difecttlrs df SAFECO INSURANCE COMPANY OF AMERICA
and of GENERAL lNSURANCE COMPANY OF AMERICA adopted July 28,1970.
*on any cerfihcate exeurtsd by the Secretary or an essisfanf secretary of the Cwnpany setling oul.
(i) The provisions of Article V, Section 13 d Me By-law$. and
(ii) A copy of the power-of-afforney appoinlmenl executed pursuanl thercta. and
(iii) CediFying that said power-of-altomey appoinlment is in full force and effect,
the signalure of Lhe certifying offcer may be by facslmlle, and the seal of me Company may be a facsimile thereof."
I. R.A. Piersan, Secretary of SAFECO INSURANCE COMPANY OF AMERlCA and of GENERAL INSURANCE COMPANY OF AMERICA, do hereby certify that the foregoing exlracfs of the By-Laws and af a Resolution ofthe bard of Directors of M'iese corporations, and of a Power of Atlomey issued pursuant thereto, are true and
correct. and that both the By-Laws. the Resolulion and the Power of Atlcmy am still in full force and effect.
IN WITNESS WHEREOF, I have hereunto sel my hand and affixed the fawhile seal of said corporation
this 8TH *YOf JULY , 2004 I
-d?"-
RA. PIERSON, SECRETARY -
S0974tSAEF 7/98 @Registerad Uedirmsrk of SAFECO Corporaion.
11/11/1999 PDF
BOND NO, NJA
IMPBRTANT NOTICE TO SURETY BONO CUSTOMERS REGARDING
THE TERRORISM RISK INSURANCE ACT OF 2002
As a surety bond customer of one of the SAFECO insurance companies (SAFECO Insurance Company of
America, General Insurance Company of America, First National Insurance Company of America, American
States Insurance Company or American Economy Insurance Company). It. is our duty to notify you that the
Terrorism Risk Insurance Act of 2002 extends to "sum€y insurance". This means that undet certain circum-
stances we may be eligible for reimbursement of cerbin surety bond losses by the United States government
under a formula established by this Act.
Under this formula, the United States government pays 90% of losses caused by certified acts of terrorism that
exceed a statutorily established deductible to be paid by the insurance company providing the bond. The Act
also establishes a $1 00 billion cap for the total of all losses to be paid by ail insurers for certified acts of
terrorism. Losses on some or all of your bonds may be subject to this cap.
This notice does not modify any of the existing terms and conditions of this bond. the underlying agreement
guaranteed by this bond, any statutes governing the terms of this bond or any generally applicable rules of iaw.
At this time there is no premium change resulting from this Act.
State of California
-.-
County of San Diego
On July 27, 2004 before me, Shannon Burke, Notary
Public, personally appeared Kyle P. Nelson,
personally known to me to be the person whose name
is subscribed to the within instrument and
acknowledged to me that he executed the same in his
authorized capacity, and that by his signature on
the instrument the person, or the entity upon
behalf of which the person acted, executed the
instrument.
Witness my hand and official seal.
(SIGNATURE)
Company Profile Page I of 2
Company Profile
SAFECO INSURANCE COMPANY OF
AMERICA
STATE FILINGS C-2 SAFECO PLAZA
SEATTLE, WA 98 185
800-332-3226
Former Names for Company
Old Name: SELECTIVE AUTO & F INS CO AMER Effective Date: 11-02-1953
Agent for Service of Process
DAWN JEWORSKI, 120 VANTIS SUITE 130 ALISO VIEJO, CA 92656
Unable to Locate theAgent for Service of Process?
Reference Information
NAIC #: 24740
NAIC Group #: - 0163
*.- .. California Company ID #: 1442-3
Date authorized in California: October 07, 1953 -.. License Status: UNLIMITED-NORMAL '
Company Type: Property & Casualty - - ._ -.
State of Domicile: WASHINGTON ''-
1
Lines of Insurance Authorized to Transact
The company is authorized to transact business within these lines of insurance. For an explanation of
any of these terms, please refer to the glossary.
AIRCRAFT
AUTOMOBILE
BOILER AND MACHINERY
BURGLARY
COMMON CARRIER LIABILITY
CREDIT
FIRE
http://cdinswww.insurance.ca.gov/pls/wu~co~prof/idb~co~prof~ut~.get~co~prof?p~EID=3 ... 7/27/2004
Company Profile Page 2 of 2
LIABILITY
MARINE
MISCELLANEOUS
PLATE GLASS
SPRINKLER
SURETY
TEAM AND VEHICLE
WORKERS' COME'ENS ATION
Company Complaint Information
Company Enforcement Action Documents
Company Performance & Comparison Data
Composite Complaint Studies
Want More?
Help Me Find a Company Representative in MY Area
Financial Rating Organizations
Last Revised - April 26,2004 02:22 PM
Copyright Q California Department of Insurance
Disclaimer
http://cdinswww.insurance.ca.gov/pls/wu~co~prof/idb~co~prof~utl.get~co~prof?p~EID=3 ... 7/27/2004
GUIDE FOR COMPLETING
THE “DESIGNATION OF SUBCONTRACTORS” FORM
REFERENCES Prior to preparation of the following Subcontractor disclosure form Bidders are urged
to review the definitions in section 1-2 of the SSPWC (“Greenbook”) and in the Supplemental
Provisions to this Contract, especially, “Bid”, “Bidder”, ‘Contract”, “Contractor”, “Contract Price”,
“Contract Unit Price”, “Engineer”, “Subcontractor” and ‘‘Work“ and the definitions in section 1-2 of the
Supplemental Provisions especially “Own Organization.” Bidders are further urged to review sections
2-3 SUBCONTRACTS of the Greenbook and section 2-3.1 of these Supplemental Provisions.
CAUTIONS This form will be used by the Agency to determine the percentage of work that the
Bidder proposes to perform. Bidders are cautioned that failure to provide complete and correct
information may result in rejection of the bid as non-responsive. Any bid that proposes performance
of more than 50 percent of the work by subcontractors or otherwise to be preformed by forces other
than the Bidder‘s own organization will be rejected as non-responsive. Specialty items of work that
may be so designated by the Engineer on the “Contractor’s Proposal” are not included in computing
the percentage of work proposed to be performed by the Bidder.
INSTRUCTIONS The Bidder shall set forth the name and location of business of each and every
subcontractor whom the Bidder proposes to perform work or labor or render service in or about the
work or improvement, and every subcontractor licensed as a contractor by the State of California
whom the Bidder proposes to specially fabricate and install any portion of the work or improvement
according to detailed drawings contained in the plans and specifications in excess of one-half of one
percent (0.5%) of the Bidder’s total bid or, in the case of bids or offers for the construction of streets
and highways, including bridges, in excess of one-half of one percent (0.5%) or ten thousand dollars
($1 0,000) whichever is greater. Said name(s) and location@) of business of subcontractor(s) shall be
set forth and included as an integral part of the bid offer.
The Designation of Subcontractors form must be submitted as a part of the Bidder’s sealed bid.
Failure to provide complete and correct information may result in reiection of the bid as non-
responsive.
Suppliers of materials from sources outside the limits of work are not subcontractors. The value of
materials and transport of materials from sources outside the limits of work, as shown on the plans,
shall be assigned to the Contractor or the Subcontractor as the case may be, that the Bidder
proposes as installer of said materials. The value of material incorporated in any Subcontractor-
installed bid item that is supplied by the Bidder shall be included as a part of the work that the Bidder
proposes to be performed by the Subcontractor installing said item.
When a Subcontractor has a Carlsbad business license, the number must be entered on the proper
form. If the Subcontractor does not have a valid business license, enter “NONE” in the appropriate
space.
When the Bidder proposes using a Subcontractor to construct or install less than 100 percent of a
bid item, the Bidder shall attach an explanation sheet to the Designation of Subcontractor form.
The explanation sheet shall clearly apprise the City of the specific facts that show the Bidder
proposes to perform no less than fifty percent (50%) of the work with its own forces.
Revised 10/08/03 Contract No. 34461 & 3887-H Page 32 of 85 Pages
Determination of the subcontract amounts for purposes of award of the contract shall be determined
by the Board of Directors in conformance with the provisions of the contract documents and the
Supplemental Provisions. The decision of the Board of Directors Council shall be final. F
Contractor is prohibited from performing any work on this project with a subcontractor who is
ineligible to perform work on a public works project pursuant to Labor Code Sections 1771.1 or
1777.7.
Bidders shall make any additional copies of the disclosure forms as may be necessary to provide the
required information. The page number and total number of additional form pages shall be entered in
the location provided on each type of form so duplicated.
Revised 10/08/03 Contract No. 34461 & 3887-H Page 33 of 85 Pages
DESIGNATION OF SUBCONTRACTOR AND
AMOUNT OF SUBCONTRACTOR’S BID ITEMS
CONTRACT NO. 34461
EL CAMINO REAL AND CASSIA ROAD
30” AND 24” POTABLE WATER TRANSMISSION MAINS
CONTRACT NO. 3887-H
EL CAMINO REAL AND CASSIA ROAD
18” AND 20” RECYCLED WATER TRANSMISSION MAINS
The Bidder certifies that it has used the sub-bid of the following listed subcontractors in preparing this bid for the Work and that the listed subcontractors will be used to perform the portions of the Work as designated in this list in accordance with applicable provisions of the specifications and section 4100 et seq. of the Public Contract Code, “Subletting and Subcontracting Fair Practices Act.” The Bidder further certifies that no additional subcontractor will be allowed to perform any portion of the Work in excess of one-half of one percent (0.5%) of the Bidder’s total bid, or in the case of bids or offers for construction of streets and highways, including bridges, in excess of one-half of one
percent (0.5%) or ten thousand dollars ($10,000), whichever is greater, and that no changes in the subcontractors listed work will be made except upon the prior approval of the Agency.
SUBCONTRACTOR’S BID ITEMS
bJtADDL1? kubcontractor’s License NOj’
Page / of I pages of this Subcontractor Designation form
* Pursuant to section 4104 (a)(2)(A) California Public Contract Code, receipt of the information preceded by an asterisk may be submitted by the Bidder up to 24 hours after the deadline for submitting bids contained in the “Notice Inviting Bids.”
@ Revised 10/08/03 Contract No. 34461 & 3887-H Page 34 of 85 Pages
.e I.
BIDDER’S STATEMENT OF FINANCIAL RESPONSIBILITY
(To Accompany Proposal)
CONTRACT NO. 34461
EL CAMINO REAL AND CASSIA ROAD
30” AND 24” POTABLE WATER TRANSMISSION MAINS
CONTRACT NO. 3887-H
EL CAMINO REAL AND CASSIA ROAD
18” AND 20” RECYCLED WATER TRANSMISSION MAINS
Copies of the latest Annual Report, audited financial statements or Balance Sheets may be
submitted under separate cover marked CONFIDENTIAL.
Revised 10/08/03 Contract No. 34461 8t 3887-H Page 35 of 85 Pages
BIDDER’S STATEMENT OF
TECHNICAL ABILITY AND EXPERIENCE
(To Accompany Proposal)
CONTRACT NO. 34461
EL CAMINO REAL AND CASSIA ROAD
30” AND 24” POTABLE WATER TRANSMISSION MAINS
CONTRACT NO. 3887-H
EL CAMINO REAL AND CASSIA ROAD
18” AND 20” RECYCLED WATER TRANSMISSION MAINS
The Bidder is required to state what work of a similar character to that included in the proposed
Contract he/she has successfully performed and give references, with telephone numbers, which will
enable the City to judge hidher responsibility, experience and skill. An attachment can be used.
Date Amount
Completed of the Employer of Person to Contract Type of Work Contract
Contract Name and Address Name and Phone No. of
@ Revised 10/08/03 Contract No. 34461 & 3887-H Page 36 of 85 Pages
'a iii 5 w
3 M e3 OD 0 -0
0 . .
-L Q M
0 8 ii co 8 -4 83 .
a ,-
3 E. 3 c 3 0 3
a
9,
A in 8 0
- BIDDER’S CERTIFICATE OF INSURANCE FOR
GENERAL LIABILITY, EMPLOYERS’ LIABILITY, AUTOMOTIVE
- LIABILITY AND WORKERS’ COMPENSATION
-
(To Accompany Proposal)
CONTRACT NO. 34461
EL CAMINO REAL AND CASSIA ROAD
30” AND 24” POTABLE WATER TRANSMISSION MAINS
CONTRACT NO. 3887-H
EL CAMINO REAL AND CASSIA ROAD
18” AND 20” RECYCLED WATER TRANSMISSION MAINS
As a required part of the Bidder’s proposal the Bidder must attach either of the following to this page.
1) Certificates of insurance showing conformance with the requirements herein for each of:
-
Comprehensive General Liability
Automobile Liability
Workers Compensation
Employer’s Liability
2) Statement with an insurance carrier’s notarized signature stating that the carrier can, and upon payment of fees and/or premiums by the Bidder, will issue to the Bidder Policies of insurance for
Comprehensive General Liability, Automobile Liability, Workers Compensation and Employer’s
Liability in conformance with the requirements herein and Certificates of insurance to the Agency
showing conformance with the requirements herein.
All certificates of insurance and statements of willingness to issue insurance for auto policies offered
to meet the specification of this contract must:
1) Meet the conditions stated in The Notice Inviting Bids, the Standard Specifications for Public Works Construction and the Supplemental Provisions for this project for each insurance
company that the Contractor proposes.
2) Cover anv vehicle used in the performance of the contract, used onsite or offsite, whether owned, non-owned or hired, and whether scheduled or non-scheduled. The auto insurance certificate
must state the coverage is for “any auto” and cannot be limited in any manner.
@ Revised 10/08/03 Contract No. 34461 & 3887-H Page 37 of 85 Pages
ACORD,. CERTIFICATE OF LIABILITY INSURANCE 07/03/2005
INSURED ,049993 Cass Construction, Inc. PO Box 309
El Cajon CA 92022
DATE (#M/DDNY)
09/23/2004
~
INSURERA St. Paul Fire & Marine
INSURER E Zurich American Ins. Co.
INSURER C
ERD.
PRODUCER Lockton Insurance Brokers of San Diego, Inc
4275 Executive Square, Suite 600
License #OD95554 La Jolla CA 92037
-
(858) 587-3100
THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS CERTIFICATE DOES NOT AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW.
INSURERS AFFORDING COVERAGE
'L AGGREGATE LIMIT APPLIES PER:
LOC
POLICY EFFECTIVE POLICY EXPIRATION POLICY NUMBER DATE (MMIDWYY) DATE (MM/DWWl
A
LIMITS
AUTOMOBILE LIABILITY
ANY AUTO
SCHEDULED AUTOS
INSR LTR
A
NON-OWNED AUTOS
TYPE OF INSURANCE
GENERAL LIABILITY x- COMMERCIAL GENERAL LIABILITY 7 CLAIMSMADE OCCUR
~
IH
09/01/2005
tL. GARAGE LIABILITY
EACH OCCURRENCE $ 1,000,000
FIRE DAMAGE (~ny one fire) s 100,000
MED EXP (Any one person) $ 5,000
PERSONAL 8 ADV INJURY $ 1,000,000
GENERAL AGGREGATE $ 2,000,000
PRODUCTS - COMPIOP AGG $ 2,000,000
I M ANYAUTO
WC3676995-00 B
$ xxxxxxx
$ 1,000,000
07/03/2004 07/03/2005 X l~~~&~~s I
E.L. EACH ACCIDENT
E.L. DISEASE - EA EMPLOYEE $ ~,ooo,ooo
E.L. DISEASE - POLICY LIMIT $ ~,ooo,ooo
EXCESS LIABILITY
DEDUCTIBLE
RETENTION
WORKERS COMPENSATION AND
EMPLOYERS LIABILITY
- 21 12382
City of Carlsbad
Attn: Purchasing Department
1635 Faraday Avenue Carlsbad CA 92008
i I
I /OTHER
SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE EXPIRATION
DATE THEREOF, THE ISSUING INSURER WILL ENDEAVOR TO MAIL 30 DAYS WRITTEN
NOTICE TO THE CERTIFICATE HOLDER NAMED TO THE LEFT,BUT FAILURE TO DO SO SHALL
IMPOSE NO OBLIGATION OR LIABILITY OF ANY KIND UPON THE INSURER. ITS AGENTS OR
REPRESENTATIVES.
AUTHORIZED REPRESENTATIVE
I/ v
KC06 100 190 09/01 12004
KC06 100 1 90
BODILY INJURY (Per person) 18 xxxxxxx I
BODILY INJURY (Per accident) 1s xxxxxxx [ I$ xxxxxxx I PROPERN DAMAGE (Per accident)
~~
NOT APPLICABLE
NOT APPLICABLE
AUTO ONLY:
EACHOCCURRENCE $ xxxxxxx
AGGREGATE $ xxxxxxx
xxxxxxx
IICLESWCLUSIONS ADDED BY ENDORSEMENTlSPECIAL PROVISONS DESCRIPTION OF OPERATIONSLOCATION~ *IO Day Notice of Cancellation for Non Payment. Re: Job # 1781 / El Camino Real & Cassia Road Domestic & Recycled Water Transmission Mains. Certificate
holder is named as additional insured for general liability per attached endorsement.
- ADDITIONAL PROTECTED PERSONS ENDORSEMENT - CONTRACTORS
GENERAL LIABILITY - INCLUDING COMPLETED WORK
This endorsement changes your Contractors Commercial General Liability Protection
The St Paul
How Coveracle is Chancled
There are two changes which are described below.
The following is added to the Who is Protected Under This Agreement section. This change adds certain protected persons and limits their protection.
Additional protected person. The person or organization named below is an additional protected person as required by a contract or agreement entered into by you. But only for covered injury or damage arising out of: Your work for that person or organization;
Your completed work for that person or organization if your contract or agreement requires such coverage; Premises you own, rent or lease from that person or organization; or
Your maintenance, operation, or use of equipment leased from that person or organization.
We explain what we mean by your work and your completed work in the Products and competed work total limit
section.
If the additional protected person is an architect, engineer , or surveyor, we won't cover injury or damage arising out of the performance or failure to perform.
Architect, engineer, or surveyor professional services.
Architect, engineer, or surveyor professional services includes:
and
The preparation of maps, drawings, opinions, reports, surveys, change orders, designs, or specification;
Supervisory, inspection, or engineering services.
-
The following is added to the Other primary insurance section. This change broadens coverage.
We'll consider this insurance to be primary to and non-contributory with the insurance issued directly to the
additional protected persons listed below if:
contributory insurance; or
insurance.
Your contract specifically requires that we consider this insurance to be primary or primary and non-
Your request before a loss that we consider this insurance to be primary or primary and non-contributory
Other Terms
All other terms of your policy remain the same.
Person Or Organization: The City of Carlsbad, its officials, employees and volunteers.
Re: Job # 1781 I El Camino Real & Cassia Road Domestic and Recycled Water Transmission Mains
Name of Insured: Policy Number: Effective Date: 9/1/2004
Cass Construction, Inc. KC061001 90 Processing Date: 9/1/2004 _-
GO322 Rev. 12-97 Printed in U.S.A. Endorsement
OSt. Paul Fire and Marine Insurance Co. 1997 All Rights Reserved
Certificate ID : 2112382
Misc Attachment : M51376
ADDITIONAL INSURED ENDORSEMENT - COMMERCIAL AUTO TheSt Paul c
This endorsement changes your Auto Liability Protection
How Coverage is Changed
There are two changes which are described below.
The following is added to the Who is Protected Under This Agreement section of your Auto
Liability Protection. This change broadens coverage
a Additional protected person. The person or organization named below is an additional
protected person as required by a contract or agreement entered into by you. But only
for covered injury or damage that results from the ownership, maintenance, use,
loading or unloading of a covered auto by:
e You;
a An employee of yours
e Anyone who drives a covered auto with your permission or with the permission of one of
your employees or agents. But this doesn't include the person or organization named
below, or one of their employees or agents
Other Terms
All other terms of your policy remain the same.
c
Person Or Organization:
The City of Carlbad, its officials, employees and volunteers
Re: Job # 178 1 / El Camino Real & Cassia Road Domestic & Recycled Water Transmission
Mains
We'll consider this insurance to be primary to and non-contributory with the insurance issued
directly to the additional protected persons listed below if
a Your contact specifically requires that we consider this insurance to be primary or
primary and non-contributory insurance; or
a Your request before a loss that we consider this insurance to be primary or primary and
non-contributory insurance.
Name of Insured: Policy Number: Effective Date: 9/1/2004
Cass Construction, Inc. KC06100190 Processing Date: 9/1/2004
CA019 ED. 07-91 Printed in U.S.A. Endorsement
QSt. Paul Fire and Marine Insurance Co. 1997 All Rights Reserved
Page 1 of 1
Certificate ID : 21 12382
Misc Attachment : M51603
BIDDER’S STATEMENT RE DEBARMENT
(To Accompany Proposal)
CONTRACT NO. 34461
EL CAMINO REAL AND CASSIA ROAD
30” AND 24” POTABLE WATER TRANSMISSION MAINS
CONTRACT NO. 3887-H
EL CAMINO REAL AND CASSIA ROAD
18” AND 20” RECYCLED WATER TRANSMISSION MAINS
1) Have you or any of your subcontractors ever been debarred as an irresponsible bidder by another jurisdiction in the State of California? J
no
2) If yes, what wadwere the name(@ of the agency(ies) and what wadwere the period(s) of debarment(s)? Attach additional copies of this page to accommodate more than two debarments.
party debarred party debarred - -
agency agency
period of debarment period of debarment
BY CONTRACTOR: m GMW Cl&oJ,Z&.
(name of Contractor)
Page of pages of this Re Debarment form
- a Revised 10/08/03 Contract No. 34461 & 3887-H Page 38 of 85 Pages
-_ -- .
BIDDER’S DISCLOSURE OF DISCIPLINE RECORD
(To Accompany Proposal)
CONTRACT NO. 34461
EL CAMINO REAL AND CASSIA ROAD
30” AND 24” POTABLE WATER TRANSMISSION MAINS
CONTRACT NO. 3887-H EL CAMINO REAL AND CASSIA ROAD 18” AND 20” RECYCLED WATER TRANSMISSION MAINS
Contractors are required by law to be licensed and regulated by the Contractors’ State License Board which has jurisdiction to investigate complaints against contractors if a complaint regarding a patent act or omission is filed within four years of the date of the alleged violation. A complaint regarding a latent act or omission pertaining to structural defects must be filed within 10 years of the date of the
alleged violation. Any questions concerning a contractor may be referred to the Registrar, Contractors’ State License board, P.O. Box 26000, Sacramento, California 95826.
1) Have you ever had your contractor‘s license suspended or revoked by the California Contractors’ State license Board two or more times within an eight year period? J c
Yes no
2) Has the suspension or revocation of your contractors license ever been stayed? -
J
no
3) Have any subcontractors that you propose to perform any portion of the Work ever had their contractor’s license suspended or revoked by the California Contractors’ State license Board two or more times within an eight year period? J Yes no
4) Has the suspension or revocation of the license of any subcontractor‘s that you propose to perform any portion of the york ever been stayed?
no
5) If the answer to either of 1. or 3. above is yes fully identify, in each and every case, the party disciplined, the date of and violation that the disciplinary action pertain to, describe the nature of the violation and the disciplinary action taken therefor.
-
-. (If needed attach additional sheets to provide full disclosure.)
Page - 1 of 1 pages of this Disclosure of Discipline form
-
Revised 10/08/03 Contract No. 34461 & 3887-H Page 39 of 85 Pages
BIDDER’S DISCLOSURE OF DISCIPLINE RECORD
(CONTINUED)
(To Accompany Proposal)
CONTRACT NO. 34461
EL CAMINO REAL AND CASSIA ROAD
30” AND 24” POTABLE WATER TRANSMISSION MAINS
CONTRACT NO. 3887-H
EL CAMINO REAL AND CASSIA ROAD
18” AND 20” RECYCLED WATER TRANSMISSION MAINS
6) If the answer to either of 2. or 4. above is yes fully identify, in each and every case, the party who’s discipline was stayed, the date of the violation that the disciplinary action pertains to,
describe the nature of the violation and the condition (if any) upon which the disciplinary action
was stayed.
._ (If needed attach additional sheets to provide full disclosure.)
BY CONTRACTOR:
CMS Ce)Nsmew, twc.
(name of Contract&)
“ -
c ,/&C6.- A. x/asu..-/ /A -qz 4CC F.??&JZP<+x--
(print namehitie) /- - - Page I of \ pages of this Disclosure of Discipline form
- a Revised 10/08/03 Contract No. 34461 & 3887-H Page 40 of 85 Pages
NON-COLLUSION AFFIDAVIT TO BE EXECUTED
PUBLIC CONTRACT CODE SECTION 7106
BY BIDDER AND SUBMllTED WITH BID
CONTRACT NO. 34461
EL CAMINO REAL AND CASSIA ROAD
30” AND 24” POTABLE WATER TRANSMISSION MAINS
CONTRACT NO. 3887-H
EL CAMINO REAL AND CASSIA ROAD
18” AND 20” RECYCLED WATER TRANSMISSION MAINS
State of California )
County of 54d ~WO )
) ss.
, being first duly sworn, deposes
(Name of Bidder) -
and says that he or she is A%&+- Ute jdmp
(Title)
of CASS CO~~~O~ ,TU&.
-
(Name of Firm) - -
the party making the foregoing bid that the bid is not made in the interest of, or on behalf of, any
undisclosed person, partnership, company, association, organization, or corporation; that the bid is
genuine and not collusive or sham; that the bidder has not directly or indirectly induced or solicited
any other bidder to put in ‘a false or sham bid, and has not directly or indirectly colluded, conspired,
connived, or agreed with any bidder or anyone else to put in a sham bid, or that anyone shall refrain
from bidding; that the bidder has not in any manner, directly or indirectly, sought by agreement,
communication, or conference with anyone to fix the bid price of the bidder or any other bidder, or to
fix any overhead, profit, or cost element of the bid price, or of that of any other bidder, or to secure
any advantage against the public body awarding the contract of anyone interested in the proposed
contract; that all statements contained in the bid are true; and, further, that the bidder has not,
directly or indirectly, submitted his or her bid price or any breakdown thereof, or the contents thereof,
or divulged information or data relative thereto, or paid, and will not pay, any fee to any corporation,
partnership, company association, organization, bid depository, or to any member or agent thereof to
effectuate a collusive or sham bid.
I declare under penalty of perjury that the foregoing is true and correct and that this affidavit was
executed on the 17 R
Sig&t6e of Bidder
- Subscribed and sworn to before me on the Gw day of SkbA- , 20.4 .
--
c
”
(NOTARY SEA
-
Revised 10/08/03 Contract No. 34461 81 3887-H Page 41 of 85 Pages
CONTRACT
PUBLIC WORKS
This agreement is made this 3ncc/ dayof , 209
by and between the Carlsbad Municipal Water District of Carlsbad, California, a munici al
corporation, (hereinafter called “Districf‘),
and CASS CONSTRUCTION INC. whose principal place of business
is 1100 WAGNER DRIVE EL CAJON CA 92020
(hereinafter called “Contractor”).
District and Contractor agree as follows:
1.
for:
Description of Work. Contractor shall perform all work specified in the Contract documents
CONTRACT NO. 34461
EL CAMINO REAL AND CASSIA ROAD
30” AND 24” POTABLE WATER TRANSMISSION MAINS
CONTRACT NO. 3887-H
EL CAMINO REAL AND CASSIA ROAD
18” AND 20” RECYCLED WATER TRANSMISSION MAINS
(hereinafter called “project”)
2. Provisions of Labor and Materials. Contractor shall provide all labor, materials, tools,
equipment, and personnel to perform the work specified by the Contract Documents.
3. Contract Documents. The Contract Documents consist of this Contract, Notice Inviting Bids,
Contractor’s Proposal, Bidder’s Bond, Designation of Subcontractors, Designation of Owner
Operator/Lessors, Bidder‘s Statements of Financial Responsibility, Technical Ability and Experience,
Re Debarment, Non-collusion Affidavit, Escrow Agreement, Release Form, the Plans and
Specifications, the Supplemental Provisions, addendum(s) to said Plans and Specifications and
Supplemental Provisions, and all proper amendments and changes made thereto in accordance with
this Contract or the Plans and Specifications, and all bonds for the project; all of which are
incorporated herein by this reference.
Contractor, her/his subcontractors, and materials suppliers shall provide and install the work as
indicated, specified, and implied by the Contract Documents. Any items of work not indicated or
specified, but which are essential to the completion of the work, shall be provided at the Contractor‘s
expense to fulfill the intent of said documents. In all instances through the life of the Contract, the
City will be the interpreter of the intent of the Contract Documents, and the City‘s decision relative to
said intent will be final and binding. Failure of the Contractor to apprise subcontractors and materials
suppliers of this condition of the Contract will not relieve responsibility of compliance.
e-
@ Revised 10/08/03 Contract No. 34461 & 3887-H Page 42 of 85 Pages
4. Payment. For all compensation for Contractor's performance of work under this Contract, District shall make payment to the Contractor per section 9-3 PAYMENT of the Standard
Specifications for Public Works Construction (SSPWC) 2003 Edition, hereinafter designated "SSPWC", as issued by the Southern California Chapter of the American Public Works Association, and as amended by the Supplemental Provisions section of this contract. The Engineer will close the estimate of work completed for progress payments on the last working day of each month.
-
5. Independent Investigation. Contractor has made an independent investigation of the jobsite, the soil conditions at the jobsite, and all other conditions that might affect the progress of the
work, and is aware of those conditions. The Contract price includes payment for all work that may be done by Contractor, whether anticipated or not, in order to overcome underground conditions. Any
information that may have been furnished to Contractor by District about underground conditions or other job conditions is for Contractor's convenience only, and District does not warrant that the conditions are as thus indicated. Contractor is satisfied with all job conditions, including underground conditions and has not relied on information furnished by District.
6. Hazardous Waste or Other Unusual Conditions. If the contract involves digging trenches or other excavations that extend deeper than four feet below the surface Contractor shall promptly, and before the following conditions are disturbed, notify District, in writing, of any:
A. Hazardous Waste. Material that Contractor believes may be material that is hazardous waste,
as defined in section 251 17 of the Health and Safety Code, that is required to be removed to a Class I, Class II, or Class Ill disposal site in accordance with provisions of existing law.
B. Differing Conditions. Subsurface or latent physical conditions at the site differing from those indicated.
C. Unknown Physical Conditions. Unknown physical conditions at the site of any unusual nature, different materially from those ordinarily encountered and generally recognized as inherent in work of the character provided for in the contract.
City shall promptly investigate the conditions, and if it finds that the conditions do materially so differ, or do involve hazardous waste, and cause a decrease or increase in contractor's costs of, or the time
required for, performance of any part of the work shall issue a change order under the procedures described in this contract.
In the event that a dispute arises between District and Contractor whether the conditions materially differ, or involve hazardous waste, or cause a decrease or increase in the contractor's cost of, or time required for, performance of any part of the work, contractor shall not be excused from any scheduled completion date provided for by the contract, but shall proceed with all work to be performed under the contract. Contractor shall retain any and all rights provided either by contract or
by law which pertain to the resolution of disputes and protests between the contracting parties.
7. Immigration Reform and Control Act. Contractor certifies it is aware of the requirements of the Immigration Reform and Control Act of 1986 (8 USC sections 11 01 -1 525) and has complied and will comply with these requirements, including, but not limited to, verifying the eligibility for employment of all agents, employees, subcontractors, and consultants that are included in this Contract.
8. Prevailing Wage. Pursuant to the California Labor Code, the director of the Department of Industrial Relations has determined the general prevailing rate of per diem wages in accordance with California Labor Code, section 1773 and a copy of a schedule of said general prevailing wage rates is on file in the office of the City Engineer, and is incorporated by reference herein. Pursuant to
California Labor Code, section 1 775, Contractor shall pay prevailing wages. Contractor shall post copies of all applicable prevailing wages on the job site.
Revised 10/08/03 Contract No. 34461 & 3887-H Page 43 of 85 Pages
4-
9. Indemnification. Contractor shall assume the defense of, pay all expenses of defense, and
indemnify and hold harmless the District, and its officers and employees, from all claims, loss,
damage, injury and liability of every kind, nature and description, directly or indirectly arising from or
in connection with the performance of the Contract or work; or from any failure or alleged failure of
Contractor to comply with any applicable law, rules or regulations including those relating to safety
and health; and from any and all claims, loss, damages, injury and liability, howsoever the same may
be caused, resulting directly or indirectly from the nature of the work covered by the Contract, except
for loss or damage caused by the sole or active negligence or willful misconduct of the District or
City. The expenses of defense include all costs and expenses including attorneys' fees for litigation,
arbitration, or other dispute resolution method.
Contractor shall also defend and indemnify the District and the City against any challenges to the
award of the contract to Contractor, and Contractor will pay all costs, including defense costs for the
District and the City. Defense costs include the cost of separate counsel for the District, if District or
City requests separate counsel.
Contractor shall also defend and indemnify the District and City against any challenges to the award
of the contract to Contractor, arising in whole or in part from alleged inaccuracies or
misrepresentation by the Contractor, whether intentional or otherwise, and Contractor will pay all
costs, including defense costs for the District and City. Defense costs include the cost of separate
counsel for District City, if District or City requests separate counsel.
10. Insurance. Contractor shall procure and maintain for the duration of the contract insurance
against claims for injuries to persons or damage to property which may arise from or in connection
with the performance of the work hereunder by the Contractor, his or her agents, representatives,
employees or subcontractors. Said insurance shall meet the District's policy for insurance as stated
in Resolution No. 91-403.
(A) Coverages And Limits Contractor shall maintain the types of coverages and minimum limits indicted herein:
a. Comprehensive General Liability Insurance: $1,000,000 combined single limit per occurrence
for bodily injury and property damage. If the policy has an aggregate limit, a separate aggregate in
the amounts specified shall be established for the risks for which the District and City or its agents,
officers or employees are additional insured.
b. Business Automobile Liability Insurance: $1,000,000 combined single limit per accident for
bodily injury and property damage. In addition, the auto policy must cover any vehicle used in the
performance of the contract, used onsite or offsite, whether owned, non-owned or hired, and whether
scheduled or non-scheduled. The auto insurance certificate must state the coverage is for "any auto"
and cannot be limited in any manner.
c. Workers' Compensation and Employers' Liability insurance: Workers' compensation limits
as required by the Labor Code of the State of California and Employers' Liability limits of $1,000,000
per incident. Workers' compensation offered by the State Compensation Insurance Fund is
acceptable to the City.
(B) Additional Provisions. Contractor shall ensure that the policies of insurance required under
this agreement with the exception of Workers' Compensation and Business Automobile Liability
Insurance contain, or are endorsed to contain, the following provisions.
,-
Revised 10/08/03 Contract No. 34461 & 3887-H Page 44 of 85 Pages
a. The District and the City, its officials, employees and volunteers are to be covered as additional
insured as respects: liability arising out of activities performed by or on behalf of the Contractor;
products and completed operations of the contractor; premises owned, leased, hired or borrowed by
the contractor. The coverage shall contain no special limitations on the scope of protection afforded
to the District or City, its officials, employees or volunteers. All additional insured endorsements must
be evidenced using separate documents attached to the certificate of insurance; one for each
company affording general liability, and employers' liability coverage.
-
b. The Contractor's insurance coverage shall be primary insurance as respects the District and
City, its officials, employees and volunteers. Any insurance or self-insurance maintained by the
District or City, its officials, employees or volunteers shall be in excess of the contractor's insurance
and shall not contribute with it.
c.
to the District, its officials, employees or volunteers.
Any failure to comply with reporting provisions of the policies shall not affect coverage provided
d. Coverage shall state that the contractor's insurance shall apply separately to each insured
against whom claim is made or suit is brought, except with respect to the limits of the insurer's
liability.
(C) Notice Of Cancellation. Each insurance policy required by this agreement shall be endorsed to
state that coverage shall not be nonrenewed, suspended, voided, canceled, or reduced in coverage
or limits except after thirty (30) days' prior written notice has been given to the City by certified mail,
return receipt requested.
(D) Deductibles And Self-Insured Retention (S.I.R.) Levels. Any deductibles or self-insured
retention levels must be declared to and approved by the City. At the option of the City, either: the
insurer shall reduce or eliminate such deductibles or self-insured retention levels as respects the
City, its officials and employees; or the contractor shall procure a bond guaranteeing payment of
losses and related investigation, claim administration and defense expenses.
(E) Waiver Of Subrogation. All policies of insurance required under this agreement shall contain a
waiver of all rights of subrogation the insurer may have or may acquire against the City or any of its
officials or employees.
(F) Subcontractors. Contractor shall include all subcontractors as insured under its policies or shall furnish separate certificates and endorsements for each subcontractor. Coverages for
subcontractors shall be subject to all of the requirements stated herein.
(G) Acceptability Of Insurers. Insurance is to be placed with insurers that have a rating in Best's
Key Rating Guide of at least A-:V. Insurers must also be authorized to transact the business of
insurance by the State of California Insurance Commissioner as admitted carriers as evidenced by a
listing in the official publication of the Department of Insurance of the State of California and/or under
the standards specified by the City Council in Resolution No. 91 -403.
(H) Verification Of Coverage. Contractor shall furnish the City with certificates of insurance and
original endorsements affecting coverage required by this clause. The certificates and endorsements
for each insurance policy are to be signed by a person authorized by that insurer to bind coverage on
its behalf. The certificates and endorsements are to be in forms approved by the City and are to be
received and approved by the City before the Contract is executed by the City.
(I) Cost Of Insurance. The Cost of all insurance required under this agreement shall be included in the Contractor's bid.
/c
@ Revised 10/08/03 Contract No. 34461 & 3887-H Page 45 of 85 Pages
11. Claims and Lawsuits. All claims by contractor for $375,000 or less shall be resolved in
accordance with the provisions in the Public Contract Code, Division 2, Part 3, Chapter 1, Article 1.5
(commencing with section 201 04) which are incorporated by reference. A copy of Article 1.5 is
included in the Supplemental Provisions I section. The contractor shall initially submit all claims over
$375,000 to the City using the informal dispute resolution process described in Public Contract Code
subsections 201 04.2(a), (c), (d). Notwithstanding the provisions of this section of the contract, all
claims shall comply with the Government Tort Claim Act (section 900 et seq., of the California
Government Code) for any claim or cause of action for money or damages prior to filing any lawsuit
for breach of this agreement.
-
(A) Assertion of Claims. Contractor hereby agrees that any contract claim submitted to the District must be asserted as part of the contract process as set forth in this agreement and not in anticipation
of litigation or in conjunction with litigation.
(B) False Claims. Contractor acknowledges that if a false claim is submitted to the District, it may be considered fraud and the Contractor may be subject to criminal prosecution.
(C) Government Code. Contractor acknowledges that California Government Code sections 12650
et seq., the False Claims Act, provides for civil penalties where a person knowingly submits a false
claim to a public entity. These provisions include false claims made with deliberate ignorance of the
false information or in reckless disregard of the truth or falsity of the information.
(D) Penalty Recovery. If the City of Carlsbad seeks to recover penalties pursuant to the False
Claims Act, it is entitled to recover its litigation costs, including attorney’s fees.
(E) Debarment for False Claims. Contractor hereby acknowledges that the filing of a false claim may subject the Contractor to an administrative debarment proceeding wherein the Contractor may
be prevented from further bidding on public contracts for a period of up to five years.
(F) Carlsbad Municipal Code. The provisions of Carlsbad Municipal Code sections 3.32.025, 3.32.026, 3.32.027 and 3.32.028 pertaining to false claims are incorporated herein by reference.
(G) Debarment from Other Jurisdictions. Contractor hereby acknowledges that debarment by
another jurisdiction is grounds for the City of Carlsbad to disqualify the Contractor or subcontractor
from participating in future contract bidding.
(H) Jurisdiction. Contractor agrees and hereby stipulates that the proper venue and jurisdiction for
resolution of any disputes between the parties arising out of this agreement is San Diego County,
California.
I have’read and understand all provisions of Section 11 above. !h’ init &F 11 init
12. Maintenance of Records. Contractor shall maintain and make available at no cost to the
City, upon request, records in accordance with sections 1776 and 1812 of Part 7, Chapter 1, Article 2, of the Labor Code. If the Contractor does not maintain the records at Contractor‘s
principal place of business as specified above, Contractor shall so inform the City by certified
letter accompanying the return of this Contract. Contractor shall notify the City by certified mail of
any change of address of such records.
13. Labor Code Provisions. The provisions of Part 7, Chapter 1, commencing with section 1720 - of the Labor Code are incorporated herein by reference.
@ Revised 10/08/03 Contract No. 34461 & 3887-H Page 46 of 85 Pages
14. Security. Securities in the form of cash, cashier's check, or certified check may be substituted
for any monies withheld by the City to secure performance of this contract for any obligation established by this contract. Any other security that is mutually agreed to by the Contractor and the City may be substituted for monies withheld to ensure performance under this Contract.
15. Provisions Required by Law Deemed Inserted. Each and every provision of law and clause required by law to be inserted in this Contract shall be deemed to be inserted herein and included herein, and if, through mistake or otherwise, any such provision is not inserted, or is not correctly inserted, then upon application of either patty, the Contract shall forthwith be physically amended to make such insertion or correction.
c
16. Additional Provisions. Any additional provisions of this agreement are set forth in the "General Provisions" or "Supplemental Provisions" attached hereto and made a part hereof.
NOTARIAL ACKNOWLEDGMENT OF EXECUTION BY ALL SIGNATORIES MUST BE
AlTACHED
(CORPORATE SEAL)
CONTRACTOR:
CP55 tOW~AC~,C\d, a&.
(name of Contracfgr)
- VE P . ~uzca - A2i. dice &s ,&d (print name and title)
(sign here)
(print dame and title)
By: ...r M-n+
JkL /&/-QuA=4/
R DISTRICT, a
ATTEST:
Secretary
President or vice-president and secretary or assistant secretary must sign for corporations. If only one officer signs, the corporation must attach a resolution certified by the secretary or assistant secretary under the corporate seal empowering that officer to bind the corporation.
APPROVED AS TO FORM:
RONALD R. BALL General Counsel
By: Ddputy General Cobnsel
@ Revised 10/08/03 Contract No. 34461 & 3887-H Page 47 of 85 Pages
State of California -
County of San Diego
On October 19, 2004 before me, Robert A. Merrick,
Notary Public, personally appeared Kyle P. Nelson
and Laura M. Nelson, personally known to me to be
the persons whose names are subscribed to the
within instrument and acknowledged to me that they
executed the same in their authorized capacities,
and that by their signature on the instrument the
persons, or the entity upon behalf of which the
persons acted, executed the instrument.
Witness my hand and official seal.
(SIGNATURE)
I EXECUTED IN DUPLICATE BOND NO. 6261520
PREMIUM: $24,797.00
FAITHFUL PERFORMANCENVARRANTY BOND
WHEREAS, the Board of Directors of the Carlsbad Municipal Water District of the City of Carlsbad,
State of California, by Resolution No. 1223 , adopted September 14, 2004 , has awarded to
CASS CONSTRUCTION INC. , (hereinafter designated as the
“Principal”), a Contract for:
CONTRACT NO. 34461
EL CAMINO REAL AND CASSIA ROAD
30” AND 24” POTABLE WATER TRANSMISSION MAINS
CONTRACT NO. 3887-H
EL CAMINO REAL AND CASSIA ROAD
18” AND 20” RECYCLED WATER TRANSMISSION MAINS
in the Carlsbad Municipal Water District, in strict conformity with the contract, the drawings and
specifications, and other Contract Documents now on file in the Office of the Secretary of the Board
of Directors (City Clerk of the City of Carlsbad), all of which are incorporated herein by this reference.
WHEREAS, Principal has executed or is about to execute said Contract and the terms thereof
require the furnishing of a bond for the faithful performance and warranty of said Contract;
NOW, THEREFORE, WE, CASS CONSTRUCTION INC., as Principal, (hereinafter
designated as the “Contractor“), and SAFECO INSURANCE COMPANY OF AMERICA , as Surety,
are held and firmly bound unto the Carlsbad Municipal Water District, in the sum of THREE
MILLION, THREE HUNDRED NINETY-TWO THOUSAND, SEVEN HUNDRED THREE Dollars
($3,392,703.00), said sum being equal to one hundred percent (100%) of the estimated amount of
the Contract, to be paid to District or its certain attorney, its successors and assigns; for which
payment, well and truly to be made, we bind ourselves, our heirs, executors and administrators,
successors or assigns, jointly and severally, firmly by these presents.
.c_
THE CONDITION OF THIS OBLIGATION IS SUCH that if the above bounden Contractor, their heirs,
executors, administrators, successors or assigns, shall in all things stand to and abide by, and well
and truly keep and perform the covenants, conditions, and agreements in the Contract and any
alteration thereof made as therein provided on their part, to be kept and performed at the time and in
the manner therein specified, and in all respects according to their true intent and meaning, and shall
indemnify and save harmless the Carlsbad Municipal Water District, its officers, employees and
agents, as therein stipulated, then this obligation shall become null and void; otherwise it shall
remain in full force and effect.
As a part of the obligation secured hereby and in addition to the face amount specified therefore,
there shall be included costs and reasonable expenses and fees, including reasonable attorneyk
fees, incurred by the District in successfully enforcing such obligation, all to be taxed as costs and
included in any judgment rendered.
Surety stipulates and agrees that no change, extension of time, alteration or addition to the terms of
the Contract, or to the work to be performed thereunder or the specifications accompanying the
same shall affect its obligations on this bond, and it does hereby waive notice of any change,
extension of time, alterations or addition to the terms of the contract or to the work or to the
specifications.
c
em
tdRevised: 10/08/03 Contract No. 34461 & 3887-H Page 50 of 85 Pages
In the event that Contractor is an individual, it is agreed that the death of any such Contractor shall
not exonerate the Surety from its obligations under this bond. _-
Executed by CONTRACTOR this 2‘Y ’*
CONTRACTOR:
CASS CONSTRUCTION, INC.
(name of Contractor)
(sign he re) L/
\,dLG 9. h)wa
(print name here)
A557. \I& Pn e& kG, JJzrErUcno$ .5 Mc.
(Title and Organization of Signatory)
\ - (sign here)
/QclW m. X/p/safl
(print name here) ~r ~5./reoo+y I 0 f
(Title and Organization of sbnatory)
v ;e
-55 CoVlsJ flee L ft’Jn, c17 c ,
Executed by SURETY this 23RD dayof
SEPTEMBER 12004
SURETY:
SAFECO INSURANCE COMPANY OF AMERICA
(name of Surety)
330 N. BRAND BOULEVARDy SUITE 1000
CLENDALE, CA 91203
(address of Surety)
81 8-956-4200
(telephone number of Surety)
/ (signature,.at/Atth$ey-in-Fact)
JACK C. LUP I EN ATTORNEY - I N-FACT
(printed name of Attorney-in-Fact)
(Attach corporate resolution showing current
power of attorney.)
(Proper notarial acknowledgment of execution by CONTRACTOR and SURETY must be attached.)
(President or vice-president and secretary or assistant Secretary must sign for corporations. If only
one officer signs, the corporation must attach a resolution certified by the secretary or assistant
secretary under corporate seal empowering that officer to bind the corporation.)
APPROVED AS TO FORM:
RONALD R. BALL
General Counsel
By:
Deputy GenerarCouhsel(
Revised 10/08/03 Contract No. 34461 & 3887-H Page 51 of 85 Pages
State of California
County of San Diego
On October 1, 2004 before me, Shannon Burke, Notary
Public, personally appeared Kyle P. Nelson,
personally known to me to be the person whose name
is subscribed to the within instrument and
acknowledged to me that he executed the same in his
authorized capacity, and that by his signature on
the instrument the person, or the entity upon
behalf of which the person acted, executed the
instrument.
Witness my hand and official seal.
1 (SIGNATURE)
State of California
/"-
County of San Diego
On October 1, 2004 before me, Shannon Burke, Notary
Public, personally appeared Laura M. Nelson,
personally known to me to be the person whose name
is subscribed to the within instrument and
acknowledged to me that she executed the same in
her authorized capacity, and that by her signature
on the instrument the person, or the entity upon
behalf of which the person acted, executed the
instrument.
Witness my hand and official seal.
(SIGNA=)
P
State of California )
County of San Dieno )
On September 23, 2004 before me, Maria Hallmark, Notary Public,
personally appeared Jack G. Lupien, personally known to me to be the person
whose name is subscribed to the within instrument and acknowledged to me
that he executed the same in his authorized capacity, and that by his signature
on the instrument the person(s), or the entity upon behalf of which the person
acted, executed the instrument.
WITNESS my hand and official seal.
POWER r A E O' OFATTORNEY
SAFECO INSURANCE COMPANY OF AMERICA
GENERAL INSURANCE COMPANY OF AMERICA
HOME OFFICE: SAFECO PLAZA SEAITLE. WASHINGTON 98ia5
No. 5528
KNOW ALL BY THESE PRESENTS:
That SAFECO INSURANCE COMPANY OF AMERICA and GENERAL INSURANCE COMPANY OF AMERICA, each a Washington corporation, does each
hereby appoint
********JACK G LUPIEN; DALE G. HARSHAW; GEOFFREY SHELTON; TARA BACON; CAROL.YN M KERL; WILLIAM L POPE; San Diego. California*********
its true and lawful attomey(s)-in-fact, with full authority to execute on its behalf fdeiity and surety bonds or undertakings and other documents of a similar
character issued In the course of its business, and to bind the respective company thereby.
IN WITNESS WHEREOF, SAFECO INSURANCE COMPANY OF AMERICA and GENERAL INSURANCE COMPANY OF AMERICA have each executed and
attested these presents
this 28th day of July , 2004
CHRISTINE MEAD, SECRETARY MIKE MCGAVICK, PRESIDENT
CERTIFICATE
Extract from the By-Laws of SAFECO INSURANCE COMPANY OF AMERICA
and of GENERAL INSURANCE COMPANY OF AMERICA:
"Article V. Section 13. - FIDELITY AND SURETY BONDS ... the President, any Vice President, the Secretary, and any Assistant Vice President appointed for that
purpose by the officer in charge of surety operations, shall each have authority to appoint individuals as attorneys-in-fact or under other appropriate titles with
authority to execute on behalf of the company fidelity and surety bonds and other documents of similar character issued by the company in the course of its
business ... On any instrument making or evidencing such appointment, the signatures may be affixed by facsimile. On any Instrument conferring such authority
or on any bond or undertaking of the company, the seal, or a facsimile thereof, may be impressed or affixed or In any other manner reproduced; provided, however, that the seal shall not be necessary to the validity of any such instrument or undertaking "
Extract from a Resolution of the Board of Directors of SAFECO INSURANCE COMPANY OF AMERICA
and of GENERAL INSURANCE COMPANY OF AMERICA adopted July 28,1970.
"On any certificate executed by the Sacretary or an assistant secretary of the Company setting out,
(i) The provisions of Arllde V, Section 13 of the By-Laws, and
(ii) A copy of the power-of-attorney appointment, executed pursuant thereto, and
(iii) Certifying that said power-of-attorney appointment is in full force and effect, the signature of the certifying officer may be by facsimile, and the seal of the Company may be a facsimile thereof."
I, Christine Mead, Secretary of SAFECO INSURANCE COMPANY OF AMERICA and of GENERAL INSURANCE COMPANY OF AMERICA, do hereby certifi
that the foregoing extracts of the By-Laws and of a Resolution of the Board of Directors of these corporations, and of a Power of Attorney Issued pursuant thereto,
are true and correct, and that both the By-Laws, the Resolution and the Power of Attorney are still in full force and effect
IN WITNESS WHEREOF, I have hereunto set my hand and affixed the facsimile seal of said corporation
this 23RD day of SEPTEMBER , 2004 .
CHRISTINE MEAD, SECRETARY -
SD974lSAEF 2/01 8 A registered trademark 01 SAFECO Corpmtlon
0712a12004 PDF
EXECUTED IN DUPLICATE
LABOR AND MATERIALS BOND
BOND NO. 6261520 PREMIUM: INCLUDED IN PERFORMANCE BOND
WHEREAS, the Board of Directors of the City of Carlsbad, State of California, by Resolution No.
1223 , adopted SeDtember 14,2004, has awarded to CASS CONSTRUCTION INC.
(hereinafter designated as the “Principal”), a Contract for:
CONTRACT NO. 34461
EL CAMINO REAL AND CASSIA ROAD
30” AND 24” POTABLE WATER TRANSMISSION MAINS
CONTRACT NO. 3887-H
EL CAMINO REAL AND CASSIA ROAD
18” AND 20” RECYCLED WATER TRANSMISSION MAINS
in the City of Carlsbad, in strict conformity with the drawings and specifications, and other Contract
Documents now on file in the Office of the Secretary of the Board of Directors (City Clerk of the City
of Carlsbad) and all of which are incorporated herein by this reference.
WHEREAS, Principal has executed or is about to execute said Contract and the terms thereof
require the furnishing of a bond, providing that if Principal or any of their subcontractors shall fail to
pay for any materials, provisions, provender or other supplies or teams used in, upon or about the
performance of the work agreed to be done, or for any work or labor done thereon of any kind, the
Surety on this bond will pay the same to the extent hereinafter set forth. I
NOW, THEREFORE, WE, CASS CONSTRUCTION INC. , as Principal,
(hereinafter designated as the “Contractof), and SAFECO INSURANCE COMPANY OF AMERICA as Surety,
are held firmly bound unto the Carlsbad Municipal Water District in the sum of THREE MILLION,
THREE HUNDRED NINETY-TWO THOUSAND, SEVEN HUNDRED THREE Dollars
($3,392,703.00), said sum being an amount equal to: One hundred percent (100%) of the total
amount payable under the terms of the contract by the Carlsbad Municipal Water District, and for
which payment well and truly to be made we bind ourselves, our heirs, executors and administrators,
successors, or assigns, jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH that if the Contractor or hidher subcontractors
fail to pay for any materials, provisions, provender, supplies, or teams used in, upon, for, or about the
performance of the work contracted to be done, or for any other work or labor thereon of any kind,
consistent with California Civil Code section 3181, or for amounts due under the Unemployment
Insurance Code with respect to the work or labor performed under this Contract, or for any amounts
required to be deducted, withheld, and paid over to the Employment Development Department from
the wages of employees of the contractor and subcontractors pursuant to section 13020 of the
Unemployment Insurance Code with respect to the work and labor, that the Surety will pay for the
same, and, also, in case suit is brought upon the bond, reasonable attorney’s fees, to be fixed by the
court consistent with California Civil Code section 3248.
This bond shall inure to the benefit of any of the persons named in California Civil Code section
3181, so as to give a right of action to those persons or their assigns in any suit brought upon the
bond.
Surety stipulates and agrees that no change, extension of time, alteration or addition to the terms of the Contract, or to the work to be performed thereunder or the specifications accompanying the
em
\#Revised: 10/08/03 Contract No. 34461 & 3887-H Page 48 of 85 Pages
same shall affect its obligations on this bond, and it does hereby waive notice of any change,
extension of time, alterations or addition to the terms of the contract or to the work or to the
specifications.
-
In the event that Contractor is an individual, it is agreed that the death of any such Contractor shall
not exonerate the Surety from its obligations under this bond.
Executed by CONTRACTOR this ,?F' Executed by SURETY this 23RD day
CONTRACTOR: SURETY:
CASS CONSTRUCTION, INC. SAFECO INSURANCE COMPANY OF AMERICA
(name of Contractor) (name of Surety)
330 N. BRAND BOULEVARD, SUITE 1000, CLENDALE, CA 91203
d/ (sign he re) (address of Surety)
I($& Pq $3503 81 8-956-4200 , (print name here) (telephone number of Surety)
PbST \IICO pa-. OF P h%s ~~UCTl~4 srrrf/
(title and organization of signatory)
By: m.4 A
I (sign here) JACK C. L UPIEN. ATTORNEY-IN-FACT
(printed name of Attorney-in-Fact)
~qurq fi, /e/Ldn
(attach corporate resolution showing current
power of attorney)
(Proper notarial acknowledge of execution by CONTRACTOR and SURETY must be attached.)
(President or vice-president and secretary or assistant secretary must sign for corporations. If only
one officer signs, the corporation must attach a resolution certified by the secretary or assistant
secretary under corporate seal empowering that officer to bind the corporation.)
APPROVED AS TO FORM:
RONALD R. BALL
General Counsel
By: -
Deputy General coubsel
%#Revised: 10/08/03 Contract No. 34461 & 3887-H Page 49 of 85 Pages
State of California
County of San Diego
On October 1, 2004 before me, Shannon Burke, Notary
Public, personally appeared Kyle P. Nelson,
personally known to me to be the person whose name
is subscribed to the within instrument and
acknowledged to me that he executed the same in his
authorized capacity, and that by his signature on
the instrument the person, or the entity upon
behalf of which the person acted, executed the
instrument.
Witness my hand and official seal.
2
(SIGNATURE)
State of California
County of San Diego
On October 1, 2004 before me, Shannon Burke, Notary
Public, personally appeared Laura M. Nelson,
personally known to me to be the person whose name
is subscribed to the within instrument and
acknowledged to me that she executed the same in
her authorized capacity, and that by her signature
on the instrument the person, or the entity upon
behalf of which the person acted, executed the
instrument.
Witness my hand and official seal.
. (SIGNATURE)
c
”..-
State of California )
County of San Diego - )
On September 23, 2004 before me, Maria Hallmark, Notary Public,
personally appeared Jack G. Lupien, personally known to me to be the person
whose name is subscribed to the within instrument and acknowledged to me
that he executed the same in his authorized capacity, and that by his signature
on the instrument the person(s), or the entity upon behalf of which the person
acted, executed the instrument.
WITNESS my hand and official seal.
POWER
.- A E O" OFATTORNEY
SAFECO INSURANCE CQMPANY OF AMERICA GENERAL INSURANCE COMPANY OF AMERICA HOME OFFICE: SAFECO PLAZA SEATTLE, WASHINGTON wia5
No. 5628
KNOW ALL BY THESE PRESENTS:
That SAFECO INSURANCE COMPANY OF AMERICA and GENERAL INSURANCE COMPANY OF AMERICA, each a Washington corporation, does each
LUPIEN; DALE G HARSHAW; GEOFFREY SHELTON; TARA BACON; CAROLYN M KERL; WILLIAM L POPE San Diego, California* **** * * **
its true and lawful attorney(s)-In-fact, with full authority to execute on its behalf Welity and surely bonds or undertakings and other documents of a similar
character issued in the course of its business, and to bind the respective company thereby.
IN WITNESS WHEREOF, SAFECO INSURANCE COMPANY OF AMERICA and GENERAL INSURANCE COMPANY OF AMERICA have each executed and
attested these presents
this 28th day of July , 2004
C H RlSTl N E MEAD, SECRETARY MIKE MCGAVICK, PRESIDENT
CERTIFICATE
Extract from the By-Laws of SAFECO INSURANCE COMPANY OF AMERICA
and of GENERAL INSURANCE COMPANY OF AMERICA
"Article V, Section 13. - FIDELITY AND SURETY BONDS ... the President, any Vice President, the Secretary, and any Assistant Vice President appointed for that
purpose by the ofiicer in charge of surety operations, shall each have authority to appoint individuals as attorneys-in-fact or under other appropriate titles with
authority to execute on behalf of the company fidelity and surety bonds and other documents of similar character issued by the company In the course of Its
business ... On any instrument making or evidencing such appointment, the signatures may be afiixed by facsimile. On any Instrument conferring such authority
or on any bond or undertaking of the company. the seal, or a facsimile thereof, may be impressed or affixed or in any other manner reproduced: provided,
however, that the seal shall not be necessary to the validity of any such instrument or undertaklng "
Extract from a Resolutlon of the Board of Direclors of SAFECO INSURANCE COMPANY OF AMERICA
and of GENERAL INSURANCE COMPANY OF AMERICA adopted July 28,1970.
I
"On any certificate executed by the Secretary or an assistant secretary of the Company setting out,
(i) The provisions of Article V, Section 13 of the By-Laws, and
(ii) A copy of the power-of-attorney appointment, executed pursuant thereto, and
(iii) Certifying that said power-of-attorney appointment is in full force and effect,
the signature of the certifying officer may be by facsimile, and the seal of the Company may be a facsimile thereof."
I, Christine Mead, Secretary of SAFECO INSURANCE COMPANY OF AMERICA and of GENERAL INSURANCE COMPANY OF AMERICA, do hereby certify
that the foregoing extracts of the By-Laws and of a Resolutlon of the Board of Directors of these corporations, and of a Power of Attorney iSSlJed pursuant thereto,
are true and correct, and that both the By-Laws, the Resolution and the Power of Attorney are still in full force and effect.
IN WITNESS WHEREOF, I have hereunto set my hand and affixed the facsimile seal of said corporation
this 23RD day of SEPTEMBER , 2004 .
CHRISTINE MEAD, SECRETARY
e
S-O974/SAEF 2/01 Q A registered trademark of SAFECO Corporation
07/28/2004 PDF
BOND NO. 6261520
IMPORTANT NOTICE TO SURETY BOND CUSTOMERS REGARDING
THE TERRORISM RISK INSURANCE ACT OF 2002
As a surety bond customer of one of the SAFECO insurance companies (SAFECO Insurance Company of
America, General Insurance Company of America, First National Insurance Company of America, American
States Insurance Company or American Economy Insurance Company), it is our duty to notify you that the
Terrorism Risk Insurance Act of 2002 extends to "surety insurance". This means that under certain circum-
stances we may be eligible for reimbursement of certain surety bond losses by the United States government
under a formula established by this Act.
Under this formula, the United States government pays 90% of losses caused by certified acts of terrorism that
exceed a statutorily established deductible to be paid by the insurance company providing the bond. The Act
also establishes a $100 billion cap for the total of all losses to be paid by all insurers for certified acts of
terrorism. Losses on some or all of your bonds may be subject to this cap.
This notice does not modify any of the existing terms and conditions of this bond, the underlying agreement
guaranteed by this bond, any statutes governing the terms of this bond or any generally applicable rules of law.
At this time there is no premium change resulting from this Act.
56248 3/03
:EXECUTED IN DUPLICATE BOND NO. 6261520
PREMIUM: $24,797.00
FAITHFUL PERFORMANCENVARRANTY BOND
WHEREAS, the Board of Directors of the Carlsbad Municipal Water District of the City of Carlsbad,
State of California, by Resolution No. 1223 , adopted September 14, 2004 , has awarded to
CASS CONSTRUCTION INC. , (hereinafter designated as the
"Principal"), a Contract for:
CONTRACT NO. 34461
EL CAMINO REAL AND CASSIA ROAD
30" AND 24" POTABLE WATER TRANSMISSION MAINS
CONTRACT NO. 3887-H
EL CAMINO REAL AND CASSIA ROAD
18" AND 20" RECYCLED WATER TRANSMISSION MAINS
in the Carlsbad Municipal Water District, in strict conformity with the contract, the drawings and
specifications, and other Contract Documents now on file in the Office of the Secretary of the Board
of Directors (City Clerk of the City of Carlsbad), all of which are incorporated herein by this reference.
WHEREAS, Principal has executed or is about to execute said Contract and the terms thereof
require the furnishing of a bond for the faithful performance and warranty of said Contract;
NOW, THEREFORE, WE, CASS CONSTRUCTION INC., as Principal, (hereinafter designated as the "Contractof), and SAFECO I NSURANCE COMPANY OF AMERICA , as Surety,
are held and firmly bound unto the Carlsbad Municipal Water District, in the sum of THREE
MILLION. THREE HUNDRED NINETY-TWO THOUSAND, SEVEN HUNDRED THREE Dollars
($3,392,703.00), said sum being equal to one hundred percent (100%) of the estimated amount of
the Contract, to be paid to District or its certain attorney, its successors and assigns; for which
payment, well and truly to be made, we bind ourselves, our heirs, executors and administrators,
successors or assigns, jointly and severally, firmly by these presents.
-
THE CONDITION OF THIS OBLIGATION IS SUCH that if the above bounden Contractor, their heirs,
executors, administrators, successors or assigns, shall in all things stand to and abide by, and well
and truly keep and perform the covenants, conditions, and agreements in the Contract and any
alteration thereof made as therein provided on their part, to be kept and performed at the time and in
the manner therein specified, and in all respects according to their true intent and meaning, and shall
indemnify and save harmless the Carlsbad Municipal Water District, its officers, employees and
agents, as therein stipulated, then this obligation shall become null and void; otherwise it shall
remain in full force and effect.
As a part of the obligation secured hereby and in addition to the face amount specified therefore,
there shall be included costs and reasonable expenses and fees, including reasonable attorney's
fees, incurred by the District in successfully enforcing such obligation, all to be taxed as costs and
included in any judgment rendered.
Surety stipulates and agrees that no change, extension of time, alteration or addition to the terms of
the Contract, or to the work to be performed thereunder or the specifications accompanying the
same shall affect its obligations on this bond, and it does hereby waive notice of any change,
extension of time, alterations or addition to the terms of the contract or to the work or to the
specifications.
-
em
%#Revised: 10/08/03 Contract No. 34461 & 3887-H Page 50 of 85 Pages
In the event that Contractor is an individual, it is agreed that the death of any such Contractor shall
not exonerate the Surety from its obligations under this bond.
Executed by CONTRACTOR this ?gg’ Executed by SURETY this 23RD day of -c-- fl
CONTRACTOR: SURETY:
CASS CONSTRUCTION, INC. SAFECO INSURANCE COMPANY OF AMERICA
(name of Contractor) (name of Surety)
330 N. BRAND BOULEVARD, SUITE 1000 By: CLENDALE, CA 91203 d’ (sign here) (address of Surety)
Kylc; P I JL%UtJ 81 8-956-4200
(print name here) (telephone number of Surety)
kx J,c&!s & (1\pu t*hI 5nLuenow *.
(Title and Organization of Signatory)
JACK C.LUPIEN, ATTORNEY-IN-FACT 44- (printed name of Attorney-in-Fact) - (sign he re)
L-QW-Q M , hwkd4 (Attach corporate resolution showing current
(print name here)
(Title and Organization of signkory)
power of attorney.) 070
cas5 C0,n Lfpu cflr3rl, LYI C,
uei e A- es,/Se c P e fyy
Y
(Proper notarial acknowledgment of execution by CONTRACTOR and SURETY must be attached.)
(President or vice-president and secretary or assistant secretary must sign for corporations. If only
one officer signs, the corporation must attach a resolution certified by the secretary or assistant
secretary under corporate seal empowering that officer to bind the corporation.)
APPROVED AS TO FORM:
RONALD R. BALL
General Counsel
By:
Deputy General Counsel
I--
<$ Revised 1OlO8IO3 Contract No. 34461 & 3887-H Page 51 of 85 Pages
State of California
,-
County of San Diego
On October 1, 2004 before me, Shannon Burke, Notary
Public, personally appeared Kyle P. Nelson,
personally known to me to be the person whose name
is subscribed to the within instrument and
acknowledged to me that he executed the same in his
authorized capacity, and that by his signature on
the instrument the person, or the entity upon
behalf of which the person acted, executed the
instrument.
Witness my hand and official seal.
(SIGNATUFU3)
State of California
.-
County of San Diego
On October 1, 2004 before me, Shannon Burke, Notary
Public, personally appeared Laura M. Nelson,
personally known to me to be the person whose name
is subscribed to the within instrument and
acknowledged to me that she executed the same in
her authorized capacity, and that by her signature
on the instrument the person, or the entity upon
behalf of which the person acted, executed the
instrument.
Witness my hand and official seal
(SIGNATURE)
State of California )
County of San Diego )
On September 23, 2004 before me, Maria Hallmark, Notarv Public,
personally appeared Jack G. Lupien, personally known to me to be the person
whose name is subscribed to the within instrument and acknowledged to me
that he executed the same in his authorized capacity, and that by his signature
on the instrument the person(s), or the entity upon behalf of which the person
acted, executed the instrument.
-
WITNESS my hand and official seal.
POWER - A E O" OFATTORNEY
SAFECO INSURANCE COMPANY OF AMERICA
GENERAL INSURANCE COMPANY OF AMERICA
HOME OFFICE: SAFECO PLAZA SEAITLE. WASHINGTON 98185
No. 5628
KNOW ALL BY THESE PRESENTS:
That SAFECO INSURANCE COMPANY OF AMERICA and GENERAL INSURANCE COMPANY OF AMERICA, each a Washington corporation, does each
hereby appoint ********JACK G LUPIEN; DALE G HARSHAW, GEOFFREY SHELTON, TAU BACON; CAROLYN M KERL, WILLIAM L POPE; San Diego, California*********
its true and lawful attomey(s)-In-fad, with full authority to execute on its behalf fdelity and surety bonds or undertakings and other documents of a similar
character issued in the course of its business, and to bind the respective company thereby.
IN WITNESS WHEREOF, SAFECO INSURANCE COMPANY OF AMERICA and GENERAL INSURANCE COMPANY OF AMERICA have each executed and
attested these presents
this 28th day of July , 2004
CHRISTINE MEAD, SECRETARY MIKE MCGAVICK, PRESIDENT
CERTIFICATE
Extract from the By-Laws of SAFECO INSURANCE COMPANY OF AMERICA
and of GENERAL INSURANCE COMPANY OF AMERICA
"Article V, Section 13. - FIDELITY AND SURETY BONDS ... the President, any Vice President, the Secretary, and any Assistant Vice President appointed for that
purpose by the officer in charge of surety operations, shall each have authority to appoint individuals as attorneys-in-fact or under other appropriate titles with
authority to execute on behalf of the company fidelity and surety bonds and other documents of similar character issued by the company in the course of Its
business ... On any instrument making or evidencing such appointment, the signatures may be affixed by facsimile. On any instrument conferring such authority
or on any bond or undertaking of the company, the seal, or a facsimile thereof, may be impressed or affixed or in any other manner reproduced; provided,
however, that the seal shall not be necessary to the validity of any such instrument or undertaking "
Extract from a Resolution of the Board of Directors of SAFECO INSURANCE COMPANY OF AMERICA
and of GENERAL INSURANCE COMPANY OF AMERICA adopted July 28.1970.
I
"On any certificate executed by the Secretary or an assistant secretary of the Company setting out.
(i) The provisions of Article V, Section 13 of the By-Laws, and
(ii) A copy of the power-of-attorney appointment, executed pursuant thereto, and (iii) Certifying that said power-of-attorney appointment is in full force and effect,
the signature of the certifying officer may be by facsimile. and the seal of the Company may be a facsimile thereof."
I, Christine Mead, Secretary of SAFECO INSURANCE COMPANY OF AMERICA and of GENERAL INSURANCE COMPANY OF AMERICA, do hereby certify
that the foregoing extracts of the By-Laws and of a Resolution of the Board of Directors of these corporations, and of a Power of Attorney issued pursuant thereto,
are true and correct, and that both the By-Laws, the Resolution and the Power of Attorney are still in full force and effect.
IN WITNESS WHEREOF, I have hereunto set my hand and affixed the facsimile seal of said corporation
this 23RD day of SEPTEMBER , 2004 .
CHRISTINE MEAD, SECRETARY
-
S-O974/SAEF 2/01 0 A registered irademark of SAFECO Corporation
07/28/2004 PDF
EXECUTED IN WPLICATE
LABOR AND MATERIALS BOND
BOND NO. 6261520
PREMIUM: INCLUDED IN
PERFORMANCE BOND
WHEREAS, the Board of Directors of the City of Carlsbad, State of California, by Resolution No. 1223 , adopted September 14,2004, has awarded to CASS CONSTRUCTION INC.
(hereinafter designated as the “Principal”), a Contract for:
CONTRACT NO. 34461
EL CAMINO REAL AND CASSIA ROAD
30” AND 24” POTABLE WATER TRANSMISSION MAINS
CONTRACT NO. 3887-H
EL CAMINO REAL AND CASSIA ROAD
18” AND 20” RECYCLED WATER TRANSMISSION MAINS
in the City of Carlsbad, in strict conformity with the drawings and specifications, and other Contract
Documents now on file in the Office of the Secretary of the Board of Directors (City Clerk of the City
of Carlsbad) and all of which are incorporated herein by this reference.
WHEREAS, Principal has executed or is about to execute said Contract and the terms thereof
require the furnishing of a bond, providing that if Principal or any of their subcontractors shall fail to
pay for any materials, provisions, provender or other supplies or teams used in, upon or about the
performance of the work agreed to be done, or for any work or labor done thereon of any kind, the
Surety on this bond will pay the same to the extent hereinafter set forth.
NOW, THEREFORE, WE, CASS CONSTRUCTION INC. , as Principal,
(hereinafter designated as the “Contractor“), and SAFECO INSURANCE COMPANY OF AMERICA as Surety,
are held firmly bound unto the Carlsbad Municipal Water District in the sum of THREE MILLION,
THREE HUNDRED NINETY-TWO THOUSAND, SEVEN HUNDRED THREE Dollars
($3,392,703.00). said sum being an amount equal to: One hundred percent (100%) of the total
amount payable under the terms of the contract by the Carlsbad Municipal Water District, and for
which payment well and truly to be made we bind ourselves, our heirs, executors and administrators,
successors, or assigns, jointly and severally, firmly by these presents.
-
THE CONDITION OF THIS OBLIGATION IS SUCH that if the Contractor or hidher subcontractors
fail to pay for any materials, provisions, provender, supplies, or teams used in, upon, for, or about the
performance of the work contracted to be done, or for any other work or labor thereon of any kind,
consistent with California Civil Code section 3181, or for amounts due under the Unemployment
Insurance Code with respect to the work or labor performed under this Contract, or for any amounts
required to be deducted, withheld, and paid over to the Employment Development Department from
the wages of employees of the contractor and subcontractors pursuant to section 13020 of the
Unemployment Insurance Code with respect to the work and labor, that the Surety will pay for the
same, and, also, in case suit is brought upon the bond, reasonable attorney’s fees, to be fixed by the
court consistent with California Civil Code section 3248.
This bond shall inure to the benefit of any of the persons named in California Civil Code section
3181, so as to give a right of action to those persons or their assigns in any suit brought upon the
bond.
Surety stipulates and agrees that no change, extension of time, alteration or addition to the terms of the Contract, or to the work to be performed thereunder or the specifications accompanying the
,-
tpRevised: 10/08/03 Contract No. 34461 & 3887-H Page 48 of 85 Pages
same shall affect its obligations on this bond, and it does hereby waive notice of any change,
extension of time, alterations or addition to the terms of the contract or to the work or to the
-c". specifications.
In the event that Contractor is an individual, it is agreed that the death of any such Contractor shall
not exonerate the Surety from its obligations under this bond.
Executed by CONTRACTOR this ZY rK Executed by SURETY this 23RD day
day of ~~P~,-cs~~.x 819 * of SEPTEMBER ,m 2004. ZUOV
CONTRACTOR: SURETY:
CASS CONSTRUCTION, INC. SAFECO INSURANCE COMPANY OF AMERICA
(name of Contractor) (name of Surety)
330 N. BRAND BOULEVARDy SUITE 1000, CLENDALE, CA 91203
J (address of Surety)
By:
(sign here)
KUE P.Nt%%/J 81 8-956-4200
(print name here) (telephone number of_Surety)
/)
bT* (title &e6 and PAe. organization 06 w> cou4'ipLcAkm,,r9c. of signatory) By: 'I - &pJ 4kPk f-
ByAA
(sign here) JACK C. LUPIEN. ATTORNEY-IN-FACT - (printed name of Attorney-in-Fact)
LsLLm m* A/4dt?
G? ss co /I-SfPuc"l'avl, 44
(print name here)
C.
(title and organization ofsignatory)
(attach corporate resolution showing current
power of attorney) vrie fpes./.secrelLspjy d-f I
(Proper notarial acknowledge of execution by CONTRACTOR and SURETY must be attached.)
(President or vice-president and secretary or assistant secretary must sign for corporations. If only
one officer signs, the corporation must attach a resolution certified by the secretary or assistant
secretary under corporate seal empowering that officer to bind the corporation.)
APPROVED AS TO FORM:
RONALD R. BALL
General Counsel
By:
Depcty General C'ou)(sel -
e-
%SRevised: 10/08/03 Contract No. 34461 & 3887-H Page 49 of 85 Pages
State of California _-
County of San Diego
On October 1, 2004 before me, Shannon Burke, Notary
Public, personally appeared Kyle P. Nelson,
personally known to me to be the person whose name
is subscribed to the within instrument and
acknowledged to me that he executed the same in his
authorized capacity, and that by his signature on
the instrument the person, or the entity upon
behalf of which the person acted, executed the
instrument.
Witness my hand and official seal.
I (SIGNATURE)
State of California
,/-
County of San Diego
On October 1, 2004 before me, Shannon Burke, Notary
Public, personally appeared Laura M. Nelson,
personally known to me to be the person whose name
is subscribed to the within instrument and
acknowledged to me that she executed the same in
her authorized capacity, and that by her signature
on the instrument the person, or the entity upon
behalf of which the person acted, executed the
instrument.
Witness my hand and official seal.
NOTARY PUBLIC-CALIFORNIA
(SIGNATURE)
State of California )
County of San Diego )
On September 23, 2004 before me, Maria Hallmark, Notary Public,
personally appeared Jack G. Lupien, personally known to me to be the person
whose name is subscribed to the within instrument and acknowledged to me
that he executed the same in his authorized capacity, and that by his signature
on the instrument the person(s), or the entity upon behalf of which the person
acted, executed the instrument.
WITNESS my hand and official seal.
POWER A E a OFATTORNEY
SAFECO INSURANCE COMPANY OF AMERICA
GENERAL INSURANCE COMPANY OF AMERICA
HOME OFFICE: SAFECO PLAZA
SEATTLE, WASHINGTON 98185
No. 5628
KNOW ALL BY THESE PRESENTS:
That SAFECO INSURANCE COMPANY OF AMERICA and GENERAL INSURANCE COMPANY OF AMERICA, each a Washington corporation, does each
hereby appoint ********JACK G LUPIEN; DALX G HARSHAW, GEOFFREY SHELTON; TAU BACON; CAROLYN M KERL; WILLIAM L POPE; San Diego, California*********
its true and lawful attorney(s)-in-fact, with full authority to execute on its behalf fidelity and surety bonds or undertakings and other documents of a similar
character issued in the course of its business, and to bind the respective company thereby.
IN WITNESS WHEREOF, SAFECO INSURANCE COMPANY OF AMERICA and GENERAL INSURANCE COMPANY OF AMERICA have each executed and
attested these presents
this 28th day of July , 2004
CHRISTINE MEAD, SECRETARY MIKE MCGAVICK, PRESIDENT
CERTIFICATE
Extract from the By-Laws of SAFECO INSURANCE COMPANY OF AMERICA
and of GENERAL INSURANCE COMPANY OF AMERICA:
"Article V, Section 13. - FIDELITY AND SURETY BONDS ... the President, any Vice President, the Secretary, and any Assistant Vice President appointed for that
purpose by the officer in charge of surety operations, shall each have authority to appoint individuals as attorneys-in-fact or under other appropriate titles with
authority to execute on behalf of the company fidelity and surety bonds and olher documents of similar character issued by the company in the course of its
business ... On any instrument making or evidencing such appointment, the signatures may be affixed by facsimile. On any instrument conferring such authority
or on any bond or undertaking of the company, the seal, or a facsimile thereof, may be impressed or affixed or in any other manner reproduced: provided,
however, that the seal shall not be necessary to the validity of any such instrument or undertaking."
Extract from a Resolution of the Board of Directors of SAFECO INSURANCE COMPANY OF AMERICA
and of GENERAL INSURANCE COMPANY OF AMERICA adopted July 28,1970.
-
"On any certificate executed by the Secretary or an assistant secretary of the Company setting out,
(i) The provisions of Article V, Section 13 of the By-Laws, and
(ii) A copy of the power-of-attorney appointment, executed pursuant thereto, and
(iii) Certifying that said power-of-attorney appointment is in full force and effect,
the signature of the certifying officer may be by facsimile, and the seal of the Company may be a facsimile thereof."
I, Christine Mead, Secretary of SAFECO INSURANCE COMPANY OF AMERICA and of GENERAL INSURANCE COMPANY OF AMERICA, do hereby certify
that the foregoing extracts of the By-Laws and of a Resolution of the Board of Directors of these corporations, and of a Power of Attorney issued pursuant thereto,
are true and correct, and that both the By-Laws, the Resolution and the Power of Attorney are still in full force and effect.
IN WITNESS WHEREOF, I have hereunto set my hand and affixed the facsimile seal of said corporation
this 23RD day of SEPTEMBER , 2004 .
CHRISTINE MEAD, SECRETARY
#-
S-09741SAEF 2/01 Q A registered trademark of SAFECO Corporatlon
07/28/2004 PDF
BOND NO. 6261520
IMPORTANT NOTICE TO SURETY BOND CUSTOMERS REGARDING
THE TERRORISM RISK INSURANCE ACT OF 2002
As a surety bond customer of one of the SAFECO insurance companies (SAFECO Insurance Company of
America, General Insurance Company of America, First National Insurance Company of America, American
States Insurance Company or American Economy Insurance Company), it is our duty to notify you that the
Terrorism Risk Insurance Act of 2002 extends to "surety insurance". This means that under certain circum-
stances we may be eligible for reimbursement of certain surety bond losses by the United States government
under a formula established by this Act.
Under this formula, the United States government pays 90% of losses caused by certified acts of terrorism that
exceed a statutorily established deductible to be paid by the insurance company providing the bond. The Act
also establishes a $100 billion cap for the total of all losses to be paid by all insurers for certified acts of
terrorism. Losses on some or all of your bonds may be subject to this cap.
This notice does not modify any of the existing terms and conditions of this bond, the underlying agreement
guaranteed by this bond, any statutes governing the terms of this bond or any generally applicable rules of law.
At this time there is no premium change resulting from this Act.
5-6248 3/03
OPTIONAL ESCROW AGREEMENT.FOR
SECURITY DEPOSITS IN LIEU OF RETENTION
This Escrow Agreement is made and entered into by and between the City of Carlsbad, Carlsbad Municipal Water District whose address is 5950 El Camino Real, Carlsbad, California, 92008, hereinafter called “District”
whose address is he rein afte r called
“Contractor” and whose address is
hereinafter called “Escrow Agent.”
For the consideration hereinafter set forth, the District, Contractor and Escrow Agent agree as follows:
1. Pursuant to sections 22300 and 10263 of the Public Contract Code of the State of California, the Contractor has the option to deposit securities with the Escrow Agent as a substitute for retention earnings required to be withheld by the City pursuant to the Construction Contract entered into between the City and Contractor for
CONTRACT NO. 34461 EL CAMINO REAL AND CASSIA ROAD
30” AND 24” POTABLE WATER TRANSMISSION MAINS
CONTRACT NO. 3887-H EL CAMINO REAL AND CASSIA ROAD 18” AND 20” RECYCLED WATER TRANSMISSION MAINS
in the amount of dated (hereinafter referred to as the “Contract”). Alternatively, on written request of the Contractor, the District shall make
payments of the retention earnings directly to the Escrow Agent. When the Contractor deposits the securities as a substitute for Contract earnings, the Escrow Agent shall notify the District within 10 days of the deposit. The Escrow Agent shall maintain insurance to cover negligent acts and
omissions of the Escrow Agent in connection with the handling of retentions under these sections in an amount not less than $100,000 per contract. The market value of the securities at the time of the substitution shall be a least equal to the cash amount then required to be withheld as retention under the terms of the contract between the District and Contractor. Securities shall be held in the name of the District and shall designate the Contractor as the beneficial owner.
2. The District shall make progress payments to the Contractor for such funds which otherwise would be withheld from progress payments pursuant to the Contract provisions, provided that the Escrow Agent holds securities in the form and amount specified above.
3. When the District makes payment of retentions earned directly to the Escrow Agent, the Escrow Agent shall hold them for the benefit of the Contractor until such time as the escrow created under this contract is terminated. The Contractor may direct the investment of the payments into securities. All terms and conditions of this agreement and the rights and responsibilities of the parties shall be equally applicable and binding when the District pays the Escrow Agent directly.
4. The Contractor shall be responsible for paying all fees for the expenses incurred by the Escrow
Agent in administering the Escrow Account and all expenses of the District. These expenses and
payment terms shall be determined by the City, District, Contractor and Escrow Agent. -
@ Revised 10/08/03 Contract No. 34461 & 3887-H Page 52 of 85 Pages
5. The interest earned on the securities or the money market accounts held in escrow and all
interest earned on that interest shall be for the sole account of Contractor and shall be subject to withdrawal by Contractor at any time and from time to time without notice to the District.
6. Contractor shall have the right to withdraw all or any part of the principal in the Escrow Account
only by written notice to Escrow Agent accompanied by written authorization from City to the Escrow Agent that City consents to the withdrawal of the amount sought to be withdrawn by Contractor.
-
7. The District shall have a right to draw upon the securities in the event of default by the
Contractor. Upon seven days' written notice to the Escrow Agent from the District of the default, the
Escrow Agent shall immediately convert the securities to cash and shall distribute the cash as
instructed by the City or District.
8. Upon receipt of written notification from the District certifying that the Contract is final and complete and that the Contractor has complied with all requirements and procedures applicable to
the Contract, the Escrow Agent shall release to Contractor all securities and interest on deposit less
escrow fees and charges of the Escrow Account. The escrow shall be closed immediately upon disbursement of all moneys and securities on deposit and payments of fees and charges.
9. The Escrow Agent shall rely on the written notifications from the District, and the Contractor
pursuant to sections (1) to (8), inclusive, of this agreement and the District, and Contractor shall hold
Escrow Agent harmless from Escrow Agent's release, conversion and disbursement of the securities
and interest as set forth above.
10. The names of the persons who are authorized to give written notices or to receive written notice
on behalf of the District, and on behalf of Contractor in connection with the foregoing, and exemplars of their respective signatures are as follows:
For District: Title FINANCE DIRECTOR
I
Name
Signature
Address
For Contractor:
For Escrow Agent:
Title
Name
Signature
Address
Title
Name
Signature
Add res
At the time the Escrow Account is opened, the City and Contractor shall deliver to the Escrow Agent
a fully executed counterpart of this Agreement. -
Revised 10/08/03 Contract No. 34461 & 3887-H Page 53 of 85 Pages
IN WITNESS WHEREOF, the parties have executed this Agreement by their proper officers on the
date first set forth above. -
For District:
For Contractor:
For Escrow Agent:
a Revised 10/08/03
Title PRESIDENT
Name
Signature
Address
Title
Name
Signature
Address
Title
Name
Signature
Address
Contract No. 34461 & 3887-H
- ~~
Page 54 of 85 Pages
SUPPLEMENTAL PROVISIONS
FOR
CONTRACT NO. 34461
EL CAMINO REAL AND CASSIA ROAD
30” AND 24” POTABLE WATER TRANSMISSION MAINS
CONTRACT NO. 3887-H
EL CAMINO REAL AND CASSIA ROAD
18” AND 20” RECYCLED WATER TRANSMISSION MAINS
SUPPLEMENTAL PROVISIONS TO
STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION
PART 1, GENERAL PROVISIONS
SECTION 1 -- TERMS, DEFINITIONS ABBREVIATIONS AND SYMBOLS -
1-1 TERMS
Add the following section:
1-1.1 Reference to Drawings. Where words “shown”, “indicated”, “detailed”, “noted”, “scheduled”, or
words of similar import are used, it shall be understood that reference is made to the plans
accompanying these provisions, unless stated otherwise.
Add the following section:
1-1.2 Directions. Where words “directed”, “designated”, “selected”, or words of similar import are
used, it shall be understood that the direction, designation or selection of the Engineer is intended,
unless stated otherwise. The word “required” and words of similar import shall be understood to
mean “as required to properly complete the work as required and as approved by the Engineer,”
unless stated otherwise.
Add the following section:
1-1.3 Equals and Approvals. Where the words “equal”, “approved equal”, “equivalent”, and such
words of similar import are used, it shall be understood such words are followed by the expression “in
the opinion of the Engineer”, unless otherwise stated. Where the words ”approved”, “approval”,
“acceptance”, or words of similar import are used, it shall be understood that the approval,
acceptance, or similar import of the Engineer is intended.
Add the following section:
1-1.4 Perform. The word “perform” shall be understood to mean that the Contractor, at its expense,
shall perform all operations, labor, tools and equipment, and further, including the furnishing and
installing of materials that are indicated, specified or required to mean that the Contractor, at its
expense, shall furnish and install the work, complete in place and ready to use, including furnishing
of necessary labor, materials, tools, equipment, and transportation.
c
?@ Revised 10/08/03 Contract No. 34461 & 3887-H Page 55 of 85 Pages
1-2 DEFINITIONS. Modify as follows: The following words, or groups of words, shall be exclusively
defined by the definitions assigned to them herein.
-
Agency - the City of Carlsbad, California. and the Carlsbad Municipal Water District.
City Council - the City Council of the City of Carlsbad.
City Manager - the City Manager of the City of Carlsbad or hisher approved representative.
Dispute Board - persons designated by the City Manager to hear and advise the City Manager on
claims submitted by the Contractor. The City Manager is the last appeal level for informal dispute
resolution.
Engineer - the Public Works Director of the City of Carlsbad or his/her approved representative. The
Engineer is the third level of appeal for informal dispute resolution.
Minor Bid Item - a single contract item constituting less than 10 percent (10%) of the original
Contract Price bid.
Own Organization - When used in Section 2-3.1 - Employees of the Contractor who are hired,
directed, supervised and paid by the Contractor to accomplish the completion of the Work. Further,
such employees have their employment taxes, State disability insurance payments, State and
Federal income taxes paid and administered, as applicable, by the Contractor. When used in Section
2-3.1 ”own organization” means construction equipment that the Contractor owns or leases and uses
to accomplish the Work. Equipment that is owner operated or leased equipment with an operator is
not part of the Contractor’s Own Organization and will not be included for the purpose of compliance
with section 2-3.1 of the Standard Specifications and these Supplemental Provisions.
-
Owner Operator/Lessor - Any person who provides equipment or tools with an operator provided
who is employed by neither the Contractor nor a subcontractor and is neither an agent or employee
of the Agency or a public utility.
Principal Inspector - The Senior Inspector’s immediate supervisor and second level of appeal for
informal dispute resolution.
Project Inspector - the Engineer’s designated representative for inspection, contract administration
and first level for informal dispute resolution.
Senior Inspector - the Project Inspector’s immediate supervisor and first level of appeal for informal
dispute resolution.
1-3 ABBREVIATIONS
1-3.2 Common Usage, add the following:
Abbreviation Word or Words
Apts ........................................ Apartment and Apartments
Bldg ........................................ Building band Buildings
CMWD .................................... Carlsbad Municipal Water District
CSSD .................................... Carlsbad Supplemental Standard Drawings
cfs ........................................... Cubic Feet per Second
Comm .................................... .Commercial
DR .......................................... Dimension Ratio
E ............................................. Electric
Revised 10/08/03 Contract No. 34461 & 3887-H Page 56 of 85 Pages
G ............................................. Gas
gal ........................................... Gallon and Gallons
Gar ......................................... Garage and Garages
GNV ........................................ Ground Not Visible
gpm ........................................g allons per minute
IE ............................................ Invert Elevation
LCW D ..................................... Leucadia County Water District
MSL ........................................ Mean Sea Level (see Regional Standard Drawing M-12)
MTBM ................................... ..Microtunneling Boring Machine
NCTD ..................................... North County Transit District
OHE ........................................ Overhead Electric
OMWD ................................... Olivenhain Municipal Water District
ROW ...................................... Right-of-way
S ............................................. Sewer or Slope, as applicable
SDNR ..................................... San Diego Northern Railway
SDRSD ................................... San Diego Regional Standard Drawing
SFM ........................................ Sewer Force Main
T ............................................. Telephone
UE .......................................... Underground Electric
W ............................................ Water, Wider or Width, as applicable
VWD ....................................... Vallecitos Water District
P
SECTION 2 -- SCOPE AND CONTROL OF THE WORK -
2-3 SUBCONTRACTS.
2-3.1 General, add the following: Should the Contractor fail to adhere to the provisions requiring the
Contractor to complete 50 percent of the contract price with its own organization, the Agency may at
its sole discretion elect to cancel the contract or to deduct an amount equal to 10 percent of the value
of the work performed in excess of 50 percent of the contract price by other than the Contractor's
own organization. The City Council shall be the sole body for determination of a violation of these
provisions. In any proceedings under this section, the prime contractor shall be entitled to a public
hearing before the City Council and shall be notified ten (10) days in advance of the time and location
of said hearing. The determination of the City Council shall be final.
2-4 CONTRACT BONDS, modify the second sentence of paragraph one as follows: Delete, "who is
listed in the latest version of U.S. Department of Treasury Circular 570,".
Modify paragraphs three and four to read: The Contractor shall provide a faithful
perforrnance/warranty bond and payment bond (labor and materials bond) for this contract. The
faithful performance/warranty bond shall be in the amount of 100 percent of the contract price. The
Contractor shall provide bonds to secure payment of laborers and materials suppliers, in an amount
equal to:
1) One hundred percent (100%) of the total amount payable by the terms of the contract when the total amount payable does not exceed five million dollars ($5,000,000).
2) Fifty percent (50%) of the total amount payable by the terms of the contract when the total amount payable is not less than five million dollars ($5,000,000) and does not exceed ten million
dollars ($1 0,000,000).
3) Twenty-five percent (25%) of the total amount payable by the terms of the contract if the contract exceeds ten million dollars ($1 0,000,000).
c
a Revised 10/08/03 Contract No. 34461 & 3887-H Page 57 of 85 Pages
Both bonds shall extend in full force and effect and be retained by the Agency during this project until -
they are released according to the provisions of this section. I
The faithful performance/warranty bond will be reduced to 25 percent of the original amount 30 days
after recordation of the Notice of Completion and will remain in full force and effect for the one year
warranty period and until all warranty repairs are completed to the satisfaction of the Engineer. The
bonds to secure payment of laborers and materials suppliers shall be released six months plus 30
days after recordation of the Notice of Completion if all claims have been paid.
Add the following: All bonds are to be placed with a surety insurance carrier admitted and authorized
to transact the business of insurance in California and whose assets exceed their liabilities in an
amount equal to or in excess of the amount of the bond. The bonds are to contain the following
documents:
1) An original, or a certified copy, of the unrevoked appointment, power of attorney, by laws, or other
2) A certified copy of the certificate of authority of the insurer issued by the insurance commissioner.
instrument entitling or authorizing the person who executed the bond to do so.
If the bid is accepted, the Agency may require a financial statement of the assets and liabilities of the
insurer at the end of the quarter calendar year prior to 30 days next preceding the date of the
execution of the bond. The financial statement shall be made by an officer's certificate as defined in
Section 173 of the Corporations Code. In the case of a foreign insurer, the financial statement may
be verified by the oath of the principal officer or manager residing within the United States. I
2-5 PLANS AND SPECIFICATIONS. -
2-5.1 General, add the following: The specifications for the work include the Standard Specifications
for Public Works Construction, (SSPWC), 2003 Edition, hereinafter designated "SSPWC", as written
and promulgated by Joint Cooperative Committee of the Southern California Chapter American
Public Works Association and Southern California Districts Associated General Contractors of
California, and as amended by the Supplemental Provisions section of this contract.
The construction plans consist of two (2) sets.
The first set is designated as City of Carlsbad Drawing No. 394-1 and consists of 20 sheets.
The second set is designated as City of Carlsbad Drawing No. 414-4 and consists of 22 sheets.
The standard drawings used for this project are the latest edition of the San Diego Area Regional
Standard Drawings, hereinafter designated SDRS, as issued by the San Diego County Department
of Public Works, together with the most recent editions of the City of Carlsbad Supplemental
Standard Drawings, hereinafter designated as CSSD, as issued by the City of Carlsbad and the
Carlsbad Municipal Water District Standard Plans hereinafter designated as CMW DSD, as issued iby
the Carlsbad Municipal Water District. Copies of some of the pertinent standard drawings are
enclosed as an appendix to these Supplemental Provisions. I
e Revised 10/08/03 Contract No. 34461 & 3887-H Page 58 of 85 Pages
- 2-5.2 Precedence of Contract Documents, modify as follows: If there is a conflict between
Contract Documents, the document highest in precedence shall control. The precedence shall be the
most recent edition of the following documents listed in order of highest to lowest precedence:
1) 2) Supplemental Provisions.
3) Plans.
4) Standard Plans.
a) City of Carlsbad Supplemental Standard Drawings.
b) Carlsbad Municipal Water District Standard Drawings.
c) City of Carlsbad modifications to the San Diego Area Regional Standard Drawings.
d) San Diego Area Regional Standard Drawings.
e) State of California Department of Transportation Standard Plans.
5) Standard Specifications for Public Works Construction.
6) State Water Resources Control Board Requirements. 7) Reference Specifications.
8) Manufacturer’s Installation Recommendations.
Permits from other agencies as may be required by law.
Change Orders, Supplemental Agreements and approved revisions to Plans and Specifications will
take precedence over items 2) through 7) above. Detailed plans and plan views shall have
precedence over general plans.
2-5.3.3 Submittals, add the following: Each submittal shall be consecutively numbered.
Resubmittals shall be labeled with the number of the original submittal followed by an ascending
alphabetical designation (e.g. The label ‘4-C’ would indicate the third instance that the fourth
submittal had been given to the Engineer). Each sheet of each submittal shall be consecutively
numbered. Each set of shop drawings and submittals shall be accompanied by a letter of transmittal
on the Contractor’s letterhead. The Letter of transmittal shall contain the following:
1 ) Project title and Agency contract number. 2) Number of complete sets.
3) Contractor’s certification statement.
4) Specification section number(s) pertaining to material submitted for review.
5) Submittal number (Submittal numbers shall be consecutive including subsequent submittals for the same materials.)
6) Description of the contents of the submittal.
7) Identification of deviations from the contract documents.
-
When submitted for the Engineer’s review, Shop Drawings shall bear the Contractor‘s certification
that the Contractor has reviewed, checked, and approved the Shop Drawings and that they are in
conformance with the requirements of the Contract Documents. The Contractor shall subscribe to
and shall place the following certification on all submittals:
”I hereby certify that the (equipment, material) shown and marked in this submittal is that proposed to
be incorporated into this Project, is in compliance with the Contract Documents, can be installed in
the allocated spaces, and is submitted for approval.”
By: Title:
Company Name:
a Revised 10/08/03 Contract No. 34461 & 3887-H Page 59 of 85 Pages
Add the following: -
2-5.4 Record Drawings, The Contractor shall provide and keep up-to-date a complete ”as-built”
record set of blue-line prints, which shall be corrected in red daily and show every change from the original drawings and specifications and the exact “as-built” locations, sizes and kinds of equipment, underground piping, valves, and all other work not visible at surface grade. Prints for this purpose may be obtained from the Agency at cost. This set of drawings shall be kept on the job and shall be used only as a record set and shall be delivered to the Engineer within ten (IO) days of completion of the work. Payment for performing the work required by section 2-5.4 shall be included in the various bid items and no additional payment will be made therefor.
2-9 SURVEYING
2-9.1 Permanent Survey Markers, Delete sections 2-9.1 and replace with the following: The Contractor shall not cover or disturb permanent survey monuments or benchmarks without the consent of the Engineer. Where the Engineer concurs, in writing, with the Contractor that protecting an existing monument in place is impractical, the Contractor shall employ a licensed land surveyor or a registered civil engineer authorized to practice land surveying within the State of California, hereinafter Surveyor, to establish the location of the monument before it is disturbed. The Contractor shall have the monument replaced by the Surveyor no later than thirty (30) days after construction at the site of the replacement is completed. The Surveyor shall file corner record(s) as required by 55 8772 and 8773, et seq. of the California Business and Professions Code.
When a change is made in the finished elevation of the pavement of any roadway in which a permanent survey monument is located, the Contractor shall adjust the monument frame and cover to the new grade within 7 days of paving unless the Engineer shall approve otherwise. Monument frames and covers shall be protected during street sealing or painting projects or be cleaned to the
satisfaction of the Engineer.
2-9.2 Survey Service, Delete sections 2-9.2 and replace with the following: The Contractor shall
hire and pay for the services of a Surveyor, hereinafter Surveyor to perform all work necessary for establishing control, construction staking, records research and all other surveying work necessary to construct the work, provide surveying services as required herein and provide surveying, drafting and other professional services required to satisfy the requirements of the Land Surveyors Act. Surveyor shall be resident on the site during all surveying operations and shall personally supervise and certify
the surveying work.
Add the following section:
2-9.2.1 Submittal of Surveying Data, All surveying data submittals shall conform to the requirements of section 2-5.3.3, “Submittals”, herein. The Contractor shall submit grade sheets to the Engineer before commencing work in the area affected by the grade sheets. The Contractor shall submit field notes for all surveying required herein to the Engineer within ten days of performing the survey. All surveying field notes{ grade sheets and survey calculations shall be submitted in bound form on 215mm by 280 mm (8 12)) by 11”) paper. The field notes, calculations and supporting data shall be clear and complete. Supporting data shall include all maps, affidavits, plats, field notes from earlier surveys and all other evidence used by the Surveyor to determine the location of the monuments set. The field notes and calculations will be labeled with name of the Surveyor, the party chief, field crew members and preparer of the field notes or calculations. They shall be annotated with the date of observation or calculation, be numbered with consecutive page numbers and shall be readable without resort to any electronic aid, computer program or documentation for any
computer program. The field notes shall be prepared in conformance with the CALTRANS ‘Surveys Manual”. The Contractor shall have a Record of Survey prepared by the Surveyor and file it in conformance with $5 8700 - 8805 of the State of California Business and Professions Code when the Surveyor performs any surveying that such map is required under 55 8762 of the State of California Business and Professions Code and whenever the Surveyor shall establish, set or construct any permanent survey monument. SDRS drawing M-IO type monuments, bolts, spikes, leaded tacks and nails (when set in concrete), iron pipes, reinforcing steel and all monuments and marks that are at, or accessory to, property corners and street centerlines are permanent survey monuments. The Record of Survey shall show all monuments set, control monuments used, the basis of bearings and all other data needed to determine the procedure of survey and the degree of accuracy attained by the field
-
Revised 10/08/03 Contract No. 34461 & 3887-H Page 60 of 85 Pages
__ surveying including the unadjusted ratio of closure. The unadjusted ratio of closure shall not exceed 1 part in 40,000. The record of survey shall show the location and justification of location of all permanent monuments set and their relation to the street right-of-way. Record(s) of Survey(s) shall be submitted for the Engineer’s review and approval before submittal to the County Surveyor and before submittal to the County Recorder.
Add the following section:
2-9.2.2 Survey Requirements, Stakes shall be set at offsets approved by the Engineer at no
greater intervals than specified in TABLE 2-9.2.2(A) as measured along the project stationing. Stakes shall be set to show the location and grade of future curbs adjacent to traffic signal locations where the curb is not being built as a part of this contract. Staking and marking shall be completed by the Surveyor and inspected and approved by the Engineer before the start of construction in the area marked. Centerline monument shall have the disk stamped with the date the monument was set and the registration number of the Surveyor. Habitat mitigation sites and other areas to be preserved that are shown on the plans shall be staked and flagged prior to the start of any other activities within the limits of the work. When curb and gutter does not exist and is not being installed as a part of the
project the location of adjacent facilities being constructed as a part of the contract the Contractor shall place stakes defining the horizontal and vertical location of such adjacent utility vaults, poles or other facilities that are being installed as parts of, or adjunct to, the project either by the Contractor and/or those noted on the plans as to be installed by others.
TABLE 2-9.2.2(A)
Survey Requirements for Construction Staking
Feature Staked
Conduit 0
x
Minor Structure
Miscellaneous 6 Contour Grading rn - Utilities 0, 0
Channels, Dikes & Ditches 0
Signs 0
Pavement Markers0
0 Staking for feati
Stake Description 0 RP + Marker Stake
RP + Marker Stake + Line Stake
RP + Marker Stake RP + Marker Stake
RP + Marker Stake
RP + Marker Stake + Line ’oint +Guarc Stake RP
3 may be orr
Centerline or Parallel to Centerline Spacing@, 0
I 15 m (50’) on tangents & curves when R2
300m (1000’) & I 7.5m (25’) on curves when
R I 300m (1 000’) or where grade I 0.30%
for catch basins: at centerline of box, ends of box & wings & at each end of the local depression 6
I15 m (50’)
I 15 m (50’) on tangents & curves when R2 300m (1 000’) & I 7.5m (25’) on curves when R I 3bOm (1 000’) or where grade I 0.30%
intervisible & I30 m (loo’), BC & EC of facilities, Grade breaks, Alignment breaks, Junctions, Inlets & similar facilities At sign location
60 m (200’) on tangents, 15m (50’) on curves when R 2 300m (1 000’) &7.5m (25’) on curves when R I300m (1000’) For PCC surfaced streets lane cold joints will suffice
ed when adjacent marker stakes reference tl
Lateral Spacing 0, Q
as appropriate
as appropriate
along contour line
as appropriate
as appropriate
Line point
at pavement marker location(s)
Setting Tolerance (Within)
10 mm (781)) Horizontal & when depth cannot be measured from existinp pnavement 7 mm ( /4 ) Vertical
10 mm Horizontal & 7 mm ( /4”) Vertical (when vertical data needed)
30 mm (0.1’1 Vertical & Horizontal
10 mm Horizontal & 7 mrn ( /4”) Vertical
30 mm (0.1’) Horpontal& 7 mm ( /Z) Vertical
30 mm (0.1’) Vertical & Horizontal
7 mm (’/Z) Horizontal
! offset and elevation of those features and the accuracy requirements of the RP meet the requirements for the feature @
(3 Perpendicular to centerline. 0 Some features are not necessarily parallel to centerline but are referenced thereto 61 Multi-plane surfaced features shall be staked so as to provide line & grade information for each plane of the feature
0 2 means greater than, or equal to, the number following the symbol. 5 means less than, or equal to, the number fol- lowing the symbol. 0 The cut datum for storm drainage & sanitary sewer pipes & similar structures shall be their invert. The cut datum for all
Reference points shall be sufficiently durable and set securely enough to survive with accuracy intact throughout the installation & inspection of the features or adjacent facilities for which they provide control. RP means reference point for the purposes of this table -
other utilities shall be the top of their pipe or conduit. a Revised 10/08/03 Contract No. 34461 & 3887-H Page 61 of 85 Pages
All guard stakes, line stakes and lath shall be flagged. Unless otherwise approved by the Engineer _-
flagging. psint and marking cards shall be the color specified in TABLE 2-9.2.2(6)
-~ ~ Vertical Control Bench marks
Cleaiing Limits of clearing
Gmhg
-I,-
I Slope, intermediate slope, abutment fill, rough grade, contour grading, final
TABLE 2-9.2.2(8)
Survey Stake Color Code for Construction Staking
White/Orange
Yellow/Biack
Yellow
Type of Stake I Description 1 Color*
Ho:izontal Control I Coordinated control points, control lines, control reference points, centerline, 1 W hite/Red
--mr StrttcLrre (11
Drainage, Sewer, Curb I*
grade. etc.
Bridges, sound and retaining walls, box culverts, etc.
Pipe culverts, junction boxes, drop inlets, headwalls, sewer lines, storm
White
Blue
-*- Fi.ght-3f-Way
Miscellaneous -- drains, slope protection, curbs, gutters, etc.
Fences, R/ W lines, easements, property monuments, etc.
Signs, railings, barriers, lighting, etc.
WhiteNellow
Orange
* F1;:Fging and marking cards, if used.
Ado tne foiicwing section:
2-9.2.3 Paknzant for Survey, Payment for work performed to satisfy the requirements of Sections 2-
9 1 through 2-9.3.2 shall be included in the actual bid items requiring the survey work and no
additma! pajment will be made. Extension of unit prices for extra work shall include full
ccmpensation for attendant survey work and no additional payment will be made therefor. Payment
fo; +vie repiacement of disturbed monuments and the filing of records of survey and/or corner
rc :or&, incb ding filing fees therefor, shall be incidental to the work necessitating the disturbance of
sai -! rmrrrimc:?ts and no additional payment will be made therefor.
-
Z-40 &llTt+f,?RITY OF BOARD AND ENGINEER.
Adt1 the fn:iowing section:
2-10.1 Availability of Records, The Contractor shall, at no charge to the Agency, provide copies of
a,! records in the Contractor’s or subcontractor’s possession pertaining to the work that the Engineer
rray roguEst.
Add the following section:
2-’fQ.2 budit And Inspection, Contractor agrees to maintain and/or make available, to the
Encjii.\wr, within San Diego County, accurate books and accounting records relative to all its
shai; P:avs iiw right to monitor, assess, and evaluate Contractor‘s and its subcontractors performance
purs:xmt to tkis Agreement, said monitoring, assessments, and evaluations to include, but not be
limited to, audits, inspection of premises, reports, contracts, subcontracts and interviews of
Contmtar’s staff and the staff of all subcontractors to this contract. At any time during normal
biisiness hmrs and as often as the Engineer may deem necessary, upon reasonable advance
notice, Contractor shall make available to the Engineer for examination, all of its, and all
sc,bcon:ractors to this contract, records with respect to all matters covered by this Contract and will
permit .the Erigineer to audit, examine, copy and make excerpts or transcripts from such data and
records, and !.o make audits of all invoices, materials, payrolls, records of personnel, and other data
relatirg io ali matters covered by this Contract. However, any such activities shall be carried out in a
maii,w so es to not unreasonably interfere with Contractor’s ongoing business operations.
Contractor and all subcontractors to this contract shall maintain such data and records for as long as
may be :cqi:i:ed by applicable laws and regulations.
ac)’ _, L,;i t i G3 (4 =tn? to contractually require all subcontractors to this Contract to do the same. The Engineer
-
?@ Revised 10/08/03 Contract No. 34461 & 3887-H Page 62 of 85 Pages
SECTION 3 -- CHANGES IN WORK
3-2 CHANGES INITIATED BY THE AGENCY.
3-2.2.1 Contract Unit prices, add the following: In the case of an increase or decrease in quantity
of a minor bid item in excess of 25 percent of the original quantity bid the adjustment of contract unit price for such items will be limited to that portion of the change in excess of 25 percent of the original quantity listed in the Contractor’s bid proposal for this contract. Adjustments in excess of 25 percent may, at the option of the Engineer, be paid pursuant to section 3-3, Extra Work.
3-3 EXTRA WORK.
3-3.2.2 ( c ) Tool and Equipment Rental, second paragraph, modify as follows: Regardless of ownership, the rates and right-of-way delay factors to be used in determining rental and delay costs shall be the edition of the, “Labor Surcharge and Equipment Rental Rates” published by CALTRANS, current at the time of the actual use of the tool or equipment. The right-of-way delay factors therein shall be used as multipliers of the rental rates for determining the value of costs for delay to the Contractor and subcontractors, if any. The labor surcharge rates published therein are not a part of this contract.
3-3.2.3 Markup, Delete sections 3-3.2.3 (a) and (b) and replace with the following:
(a) shall constitute the markup for all overhead and profits: 1) Labor ................................... 20 2) Materials ............................. 15 3) Equipment Rental ................... 15
4) Other Items and Expenditures .. 15
To the sum of the costs and markups provided for in this section, 1 percent shall be added as compensation for bonding.
(b) Work by Subcontractor. When all or any part of the extra work is performed by a Subcontractor, the markup established in section 3-3.2.3(a) shall be applied to the Subcontractor’s actual cost of such work. A markup of 10 percent on the first $5,000 of the subcontracted portion of the extra work and a markup of 5 percent on work added in excess of $5,000 of the subcontracted portion of the extra work may be added by the Contractor.
3-3.3 Daily Reports by Contractor, add the following after the second sentence: Payment for extra work will not be made until such time that the Contractor submits completed daily reports and all
supporting documents to the Engineer.
Work by Contractor. The following percentages shall be added to the Contractor’s costs and
c
3-4 CHANGED CONDITIONS.
Delete the second sentence of paragraph three, delete paragraph five (5), and add the following: The Contractor shall not be entitled to the payment of any additional compensation for any act, or failure to act, by the Engineer, including failure or refusal to issue a change order, or for the happening of any event, thing, occurrence, or other cause, unless the Contractor shall have first given the
Engineer due written notice of potential claim as hereinafter specified. Compliance with this section shall not be required as a prerequisite to notice provisions in Section 6-7.3 Contract Time Accounting, nor to any claim that is based on differences in measurement or errors of computation as to contract quantities. The written notice of potential claim for changed conditions shall be submitted by the Contractor to the Engineer upon their discovery and prior to the time that the Contractor performs the work giving rise to the potential claim. The Contractor’s failure to give written notice of potential claim for changed conditions to the agency upon their discovery and before they are disturbed shall constitute a waiver of all claims in connection therewith. _I
a Revised 10/08/03 Contract No. 34461 & 3887-H Page 63 of 85 Pages
The Contractor shall provide the City with a written document containing a description of the particular circumstances giving rise to the potential claim, the reasons for which the Contractor believes additional compensation may be due and nature of any and all costs involved within 20 working days of the date of service of the written notice of potential claim for changed conditions. Verbal notifications are disallowed.
-
The potential claim shall include the following certification relative to the California False Claims Act, Government Code Sections 12650-1 2655.
“The undersigned certifies that the above statements are made in full cognizance of the California False Claims Act, Government Code sections 12650-1 2655. The undersigned further understands and agrees that this potential claim, unless resolved, must be restated as a claim in response to the
City’s proposed final estimate in order for it to be further considered.’’
By: Title:
Company Name:
The Contractor’s estimate of costs may be updated when actual costs are known. The Contractor shall submit substantiation of its actual costs to the Engineer within 20 working days after the affected work is completed. Failure to do so shall be sufficient cause for denial of any claim subsequently filed on the basis of said notice of potential claim.
It is the intention of this section that differences between the parties arising under and by virtue of the contract be brought to the attention of the Engineer at the earliest possible time in order that such
matters be settled, if possible, or other appropriate action promptly taken. -
3-5 DISPUTED WORK.
Add the following: The Contractor shall give the agency written notice of potential claim prior to commencing any disputed work. Failure to give said notice shall constitute a waiver of all claims in
connection therewith.
Delete second sentence of paragraph one and add the following: Prior to proceeding with dispute resolution pursuant to Public Contract Code provisions specified hereinafter, the contractor shall attempt to resolve all disputes informally through the following dispute resolution chain of command:
1. Project Inspector
2. Senior Inspector 3. Principal Inspector 4. Public Works Director 5. City Manager
The Contractor shall submit a complete report within 20 working days after completion of the disputed work stating its position on the claim, the contractual basis for the claim, along with all documentation supporting the costs and all other evidentiary materials. At each level of claim or appeal of claim the City will, within 10 working days of receipt of said claim or appeal of claim, review
the Contractor’s report and respond with a position, request additional information or request that the Contractor meet and present its report. When additional information or a meeting is requested the City will provide its position within 10 working days of receipt of said additional information or Contractor’s presentation of its report. The Contractor may appeal each level’s position up to the City Manager after which the Contractor may proceed under the provisions of the Public Contract Code.
Revised 10/08/03 Contract No. 34461 & 3887-H Page 64 of 85 Pages
~ ~~~
.- The authority within the dispute resolution chain of command is limited to recommending a resolution
to a claim to the City Manager. Actual approval of the claim is subject to the change order provisions
in the contract.
All claims by the contractor for $375,000 or less shall be resolved in accordance with the procedures in the Public Contract Code, Division 2, Part 3, Chapter 1, Article 1.5 (commencing with Section
201 04) which is set forth below:
ARTICLE 1.5 RESOLUTION OF CONSTRUCTION CLAIMS
20104. (a)(l) This article applies to all public works claims of three hundred seventy-five thousand
dollars ($375,000) or less which arise between a contractor and a local agency.
(2) This article shall not apply to any claims resulting from a contract between a contractor and a
public agency when the public agency has elected to resolve any disputes pursuant to Article 7.1
(commencing with Section 10240) of Chapter 1 of Part 2. (b)(l) "Public work" has the same meaning as in Sections 31 00 and 31 06 of the Civil Code, except
that "public work" does not include any work or improvement contracted for by the state or the
Regents of the University of California.
(2) "Claim" means a separate demand by the contractor for (A) a time extension, (6) payment of
money or damages arising from work done by, or on behalf of, the contractor pursuant to the contract
for a public work and payment of which is not otherwise expressly provided for or the claimant is not
otherwise entitled to, or (C) an amount the payment of which is disputed by the local agency.
(c) The provisions of this article or a summary thereof shall be set forth in the plans or specifications
for any work which may give rise to a claim under this article.
(d) This article applies only to contracts entered into on or after January 1, 1991. .-
201 04.2. For any claim subject to this article, the following requirements apply:
(a) The claim shall be in writing and include the documents necessary to substantiate the claim.
Claims must be filed on or before the date of final payment. Nothing in this subdivision is intended to
extend the time limit or supersede notice requirements otherwise provided by contract for the filing of
claims.
(b)(l) For claims of less than fifty thousand dollars ($50,000), the local agency shall respond in
writing to any written claim within 45 days of receipt of the claim, or may request, in writing, within 30
days of receipt of the claim, any additional documentation supporting the claim or relating to
defenses to the claim the local agency may have against the claimant.
(2) If additional information is thereafter required, it shall be requested and provided pursuant to this
subdivision, upon mutual agreement of the local agency and the claimant.
(3) The local agency's written response to the claim, as further documented, shall be submitted to the
claimant within 15 days after receipt of the further documentation or within a period of time no greater
than that taken by the claimant in producing the additional information, whichever is greater.
(c)(l) For claims of over fifty thousand dollars ($50,000) and less than or equal to three hundred
seventy-five thousand dollars ($375,000), the local agency shall respond in writing to all written
claims within 60 days of receipt of the claim, or may request, in writing, within 30 days of receipt of
the claim, any additional documentation supporting the claim or relating to defenses to the claim the
local agency may have against the claimant.
(2) If additional information is thereafter required, it shall be requested and provided pursuant to this
subdivision, upon mutual agreement of the local agency and the claimant.
(3) The local agency's written response to the claim, as further documented, shall be submitted to
the claimant within 30 days after receipt of the further documentation, or within a period of time no
greater than that taken by the claimant in producing the additional information or requested
documentation, whichever is greater.
.-
Revised 10/08/03 Contract No. 34461 & 3887-H Page 65 of 85 Pages
(d) If the claimant disputes the local agency's written response, or the local agency fails to respond
within the time prescribed, the claimant may so notify the local agency, in writing, either within 15
days of receipt of the local agency's response or within 15 days of the local agency's failure to
respond within the time prescribed, respectively, and demand an informal conference to meet and
confer for settlement of the issues in dispute. Upon a demand, the local agency shall schedule a
meet and confer conference within 30 days for settlement of the dispute.
(e) Following the meet and confer conference, if the claim or any portion remains in dispute, the
claimant may file a claim as provided in Chapter 1 (commencing with Section 900) and Chapter 2
(commencing with Section 910) of Part 3 of Division 3.6 of Title 1 of the Government Code. For
purposes of those provisions, the running of the period of time within which a claim must be filed
shall be tolled from the time the claimant submits his or her written claim pursuant to subdivision (a)
until the time that claim is denied as a result of the meet and confer process, including any period of
time utilized by the meet and confer process.
(f) This article does not apply to tort claims and nothing in this article is intended nor shall be
construed to change the time periods for filing tort claims or actions specified by Chapter 1
(commencing with Section 900) and Chapter 2 (commencing with Section 910) of Part 3 of Division
3.6 of Title 1 of the Government Code.
-
20104.4. The following procedures are established for all civil actions filed to resolve claims subject
to this article:
(a) Within 60 days, but no earlier than 30 days, following the filing or responsive pleadings, the court
shall submit the matter to nonbinding mediation unless waived by mutual stipulation of both parties.
The mediation process shall provide for the selection within 15 days by both parties of a disinterested
third person as mediator, shall be commenced within 30 days of the submittal, and shall be
concluded within 15 days from the commencement of the mediation unless a time requirement is
extended upon a good cause showing to the court or by stipulation of both parties. If the parties fail to
select a mediator within the 15-day period, any party may petition the court to appoint the mediator.
(b)(l) If the matter remains in dispute, the case shall be submitted to judicial arbitration pursuant to
Chapter 2.5 (commencing with Section 1141 .lo) of Title 3 of Part 3 of the Code of Civil Procedure,
notwithstanding Section 11 41 .ll of that code. The Civil Discovery Act of 1986 (Article 3 (commencing
with Section 2016) of Chapter 3 of Title 3 of Part 4 of the Code of Civil procedure) shall apply to any
proceeding brought under the subdivision consistent with the rules pertaining to judicial arbitration.
(2) Notwithstanding any other provision of law, upon stipulation of the parties, arbitrators appointed
for purposes of this article shall be experienced in construction law, and, upon stipulation of the
parties, mediators and arbitrators shall be paid necessary and reasonable hourly rates of pay not to
exceed their customary rate, and such fees and expenses shall be paid equally by the parties, except
in the case of arbitration where the arbitrator, for good cause, determines a different division. In no
event shall these fees or expenses be paid by state or county funds.
(3) In addition to Chapter 2.5 (commencing with Section 1141 .lo) Title 3 of Part 3 of the Code of Civil
Procedure, any party who after receiving an arbitration award requests a trial de novo but does not
obtain a more favorable judgment shall, in addition to payment of costs and fees under that chapter,
pay the attorney's fees of the other party arising out of the trial de novo.
(c) The court may, upon request by any party, order any witnesses to participate in the mediation or
-
arbitration process.
20104.6. (a) No local agency shall fail to pay money as to any portion of a claim which is undisputed
except as otherwise provided in the contract.
(b) In any suit filed under Section 201 04.4, the local agency shall pay interest at the legal rate on any
arbitration award or judgment. The interest shall begin to accrue on the date the suit is filed in a court
of law. -
Revised 10/08/03 Contract No. 34461 & 3887-H Page 66 of 85 Pages
SECTION 4 - CONTROL OF MATERIALS
4-1 MATERIALS AND WORKMANSHIP.
4-1.3.1 General, add the following: The Contractor shall provide the Engineer free and safe access
to any and all parts of work at any time. Such free and safe access shall include means of safe
access and egress, ventilation, lighting, shoring, dewatering and all elements pertaining to the safety
of persons as contained in the State of California, California Code of Regulations, Title 8, Industrial
Relations, Chapter 4, Division of Industrial Safety, Subchapter 4, Construction Safety Orders and
such other safety regulations as may apply. Contractor shall furnish Engineer with such information
as may be necessary to keep the Engineer fully informed regarding progress and manner of work
and character of materials. Inspection or testing of the whole or any portion of the work or materials
incorporated in the work shall not relieve Contractor from any obligation to fulfill this Contract.
4-1.4 Test of Materials, delete the phrase, “and a reasonable amount of retesting”, from the third
sentence of the first paragraph.
add the following: Except as specified in these Supplemental Provisions, the Agency will bear the
cost of testing of locally produced materials and/or on-site workmanship where the results of such
tests meet or exceed the requirements indicated in the Standard Specifications and the
Supplemental Provisions. The cost of all other tests shall be borne by the Contractor.
At the option of the Engineer, the source of supply of each of the materials shall be approved by the
Engineer before the delivery is started. All materials proposed for use may be inspected or tested at
any time during their preparation and use. If, after incorporating such materials into the Work, it is
found that sources of supply that have been approved do not furnish a uniform product, or if the
product from any source proves unacceptable at any time, the Contractor shall furnish approved
material from other approved sources. If any product proves unacceptable after improper storage,
handling or for any other reason it shall be rejected, not incorporated into the work and shall be
removed from the project site all at the Contractor’s expense.
_-
Compaction tests may be made by the Engineer and all costs for tests that meet or exceed the
requirements of the specifications shall be borne by the Agency. Said tests may be made at any
place along the work as deemed necessary by the Engineer. The costs of any retests made
necessary by noncompliance with the specifications shall be borne by the Contractor.
4-1.6 Trade names or Equals, add the following: The Contractor is responsible for the satisfactory
performance of substituted items. If, in the sole opinion of the Engineer, the substitution is
determined to be unsatisfactory in performance, appearance, durability, compatibility with associated
items, availability of repair parts and suitability of application the Contractor shall remove the
substituted item and replace it with the originally specified item at no cost to the Agency.
Add the following section:
4-2 MATERIALS TRANSPORTATION, HANDLING AND STORAGE.
The Contractor shall order, purchase, transport, coordinate delivery, accept delivery, confirm the quantity and quality received, prepare storage area(s), store, handle, protect, move, relocate, remove and dispose excess of all materials used to accomplish the Work. Materials shall be delivered to the site of the work only during working hours, as defined in section 6-7.2, and shall be accompanied by bills of lading that shall clearly state for each delivery: the name of the Contractor as consignee, the project name and number, address of delivery and name of consignor and a description of the material(s) shipped. Prior to storage of any materials which have been shipped to or by the Contractor to any location within the Agency’s boundaries the Contractor shall provide the
-
a Revised 10/08/03 Contract No. 34461 & 3887-H Page 67 of 85 Pages
Engineer a copy of lease agreements for each property where such materials are stored. The lease agreement shall clearly state the term of the lease, the description of materials allowed to be stored and shall provide for the removal of the materials and restoration of the storage site within the time allowed for the Work. All such storage shall conform to all laws and ordinances that may pertain to the materials stored and to preparation of the storage site and the location of the site on which the materials are stored. Loss, damage or deterioration of all stored materials shall be the Contractor’s responsibility. Conformance to the requirements of this section, both within and outside the limits of work are a part of the Work. The Engineer shall have the right to verify the suitability of materials and their proper storage at any time during the Work.
-
SECTION 5 -- UTILITIES
5-1 LOCATION.
Delete the first paragraph and substitute the following: The Agency and affected utility companies have, by a search of known records, endeavored to locate and indicate on the Plans, all utilities which exist within the limits of the work. However, the accuracy and/or completeness of the nature, size and/or location of utilities indicated on the Plans is not guaranteed.
5-4 RELOCATION.
Add the following: In conformance with section 5-6 the Contractor shall coordinate the work with utility agencies and companies. Prior to the installation of any and all utility structures within the limits of work by any utility agency or company, or its contractor, the Contractor shall place all curb or curb and gutter that is a part of the work and adjacent to the location where such utility structures are shown on the plans and are noted as being located, relocated or are otherwise shown as installed by others. In order to minimize delays to the Contractor caused by the failure of other parties to relocate utilities that interfere with the construction, the Contractor, upon the Engineer’s approval, may be
permitted to temporarily omit the portion of work affected by the utility. If such temporary omission is approved by the Engineer the Contractor shall place survey or other physical control markers sufficient to locate the curb or curb and gutter to the satisfaction of the utility agency or company. Such temporary omission shall be for the Contractor’s convenience and no additional compensation will be allowed therefor or for additional work, materials or delay associated with the temporary omission. The portion thus omitted shall be constructed by the Contractor immediately following the relocation of the utility involved unless otherwise directed by the Engineer.
-.
SECTION 6 -- PROSECUTION, PROGRESS AND
ACCEPTANCE OF THE WORK
6-1 CONSTRUCTION SCHEDULE AND COMMENCEMENT OF WORK.
Delete section 6-1 and substitute the following: Except as otherwise provided herein and unless otherwise prohibited by permits from other agencies as may be required by law the Contractor shall
begin work within 20 calendar days after receipt of the “Notice to Proceed”.
Add the following section:
6-1.1 Pre-Construction Meeting. After, or upon, notification of contract award, the Engineer will set the time and location for the Preconstruction Meeting. Attendance of the Contractor’s management personnel responsible for the management, administration, and execution of the project is mandatory for the meeting to be convened. Failure of the Contractor to have the Contractor’s responsible project personnel attend the Preconstruction Meeting will be grounds for default by Contractor per section 6-
4. No separate payment will be made for the Contractor’s attendance at the meeting. The notice to proceed will only be issued on or after the completion of the preconstruction meeting.
.-.
@ Revised 10/08/03 Contract No. 34461 8,3887-H Page 68 of 85 Pages
_- Add the following section:
6-1.1.1 Baseline Construction Schedule Submittal. The Contractor shall submit the Baseline
Construction Schedule per the submittal requirements of section 2-5.3. The submittal of the Baseline
Construction Schedule shall include each item and element of sections 6-1.2 through 6-1.2.9 and
shall be on hard (paper) copy and electronic media conforming to section 6-1.3.3 Electronic Media.
Add the following section:
6-1.2 Preparation and Review of the Baseline Construction Schedule. The Contractor shall
prepare the Baseline Construction Schedule as a Critical Path Method (CPM) Schedule in the
precedence diagram method (activity-on-node) format. The Baseline Construction Schedule shall
depict a workable plan showing the sequence, duration, and interdependence of all activities
required to represent the complete performance of all project work as well as periods where work is
precluded. The Baseline Construction Schedule shall begin with the projected date of issuance of the
notice to proceed and conclude with the date of final completion per the contract duration. The
Baseline Construction Schedule shall include detail of all project phasing, staging, and sequencing,
including all milestones necessary to define beginning and ending of each phase or stage.
Add the following section:
6-1.2.1 lime-Scaled Network Diagram. As a part of the Baseline Construction Schedule the
Contractor shall prepare and submit to the Engineer a complete time-scaled network diagram
showing all of the activities, logic relationships, and milestones comprising the schedule.
Add the following section:
6-1.2.2 Tabular Listing. As a part of the Baseline Construction Schedule the Contractor shall
prepare and submit to the Engineer a tabular listing of all of the activities, showing for each activity
the identification number, the description, the duration, the early start, the early finish, the late start,
the late finish, the total float, and all predecessor and successor activities for the activity described.
-
Add the following section:
6-1.2.3 Bar Chart. As a part of the Baseline Construction Schedule the Contractor shall prepare and
submit to the Engineer a chart showing individual tasks and their durations arranged with the tasks
on the vertical axis and duration on the horizontal axis. The bar chart shall use differing texture
patterns or distinctive line types to show the critical path.
Add the following section:
6-1.2.4 Schedule Software. The Contractor shall use commercially available software equal to the
Windows 95 compatible “Suretrak” program by Primavera or “Project” program by Microsoft
Corporation to prepare the Baseline Construction Schedule and all updates thereto. The Contractor
shall submit to the Agency a 89 mm (3.5”) data disk with all network information contained thereon, in
a format readable by a Microsoft Windows 95 system. The Agency will use a “Suretrak”, “Project” or
equal software program for review of the Contractor’s schedule. Should the Contractor elect to use a
scheduling program other than the “Suretrak” program by Primavera or “Project” program by
Microsoft Corporation the Contractor shall provide the Engineer three copies of the substituted
program that are fully licensed to the Agency and 32 class hours of on-site training by the program
publisher for up to eight Agency staff members. The classes shall be presented on Mondays through
Thursdays, inclusive, between the hours of 8:OO a.m. and 5:OO p.m. The on-site training shall be held
at 1635 Faraday Avenue, Carlsbad, California. The dates and times of the on-site training shall be
submitted to the Engineer for approval five working days before the start of the on-site training. The
on-site training shall be completed prior to the submittal of the first Baseline Construction Schedule.
Revised 10/08/03 Contract No. 34461 & 3887-H Page 69 of 85 Pages
Add the following section: h
6-1.2.5 Schedule Activities. Except for submittal activities, activity durations shall not be shorter
than 1 working day nor longer than 15 working days, unless specifically and individually allowed by
the Engineer. The Baseline Construction Schedule shall include between 100 and 500 activities,
including submittals, interfaces between utility companies and other agencies, project milestones and
equipment and material deliveries. The number of activities will be sufficient, in the judgment of the
Engineer, to communicate the Contractor’s plan for project execution, to accurately describe the
project work, and to allow monitoring and evaluation of progress and of time impacts. Each activity’s
description shall accurately define the work planned for the activity and each activity shall have
recognizable beginning and end points.
Add the following section:
6-1.2.6 Float. Float or slack time within the schedule is available without charge or compensation to
whatever party or contingency first exhausts it.
Add the following section:
6-1.2.7 Restraints to Activities. Any submittals, utility interfaces, or any furnishing of Agency
supplied materials, equipment, or services, which may impact any activity’s construction shall be
shown as a restraint to those activities. Time periods to accommodate the review and correction of
submittals shall be included in the schedule.
Add the following section:
6-1.2.8 Late Completion. A Baseline Construction Schedule showing a project duration longer than
the specified contract duration will not be acceptable and will be grounds for determination of default
by Contractor, per section 6-4. -_
Add the following section:
6-1.2.9 Early Completion. The Baseline Construction Schedule will show the Contractor’s plan to
support and maintain the project for the entire contractual time span of the project. Should the
Contractor propose a project duration shorter than contract duration, a complete Baseline
Construction Schedule must be submitted, reflecting the shorter duration, in complete accordance
with all schedule requirements of section 6-1. The Engineer may choose to accept the Contractor’s
proposal of a project duration shorter than the duration specified; provided the Agency is satisfied the
shortened Baseline Construction Schedule is reasonable and the Agency and all other entities, public
and private, which interface with the project are able to support the provisions of the shortened
Baseline Construction Schedule. The Agency’s acceptance of a shortened duration project will be
confirmed through the execution of a contract change order revising the project duration and
implementing all contractual requirements including liquidated damages in accordance with the
revised duration.
Add the following section:
6-1.2.10 Engineer’s Review. The Construction Schedule is subject to the review of the Engineer.
The Engineer’s determination that the Baseline Construction Schedule proposed by the Contractor
complies with the requirements of these supplemental provisions shall be a condition precedent to
issuance of the Notice to Proceed by the Engineer. If the Engineer determines that the Construction
Schedule does not meet the requirements of these specifications the Contractor shall correct the
Construction Schedule to meet these specifications and resubmit it to the Engineer. Failure of the
Contractor to obtain the Engineer’s determination that the initial Construction Schedule proposed by
the Contractor complies with the requirements of these supplemental provisions within thirty (30)
working days after the date of the preconstruction meeting shall be grounds for termination of the
contract per section 6-4. Days used by the Engineer to review the initial Construction Schedule will
not be included in the 30 working days.
-
Revised 10/08/03 Contract No. 34461 & 3887-H Page 70 of 85 Pages
- The Engineer will review and return to the Contractor, with any comments, the Baseline Construction
Schedule within 15 working days of submittal. The Baseline Construction Schedule will be returned
marked as per sections 6-1.2.1 0.1 through 6-1.2.1 0.3.
Add the following section:
6-1.2.10.1 “Accepted.” The Contractor may proceed with the project work upon issuance of the
Notice to Proceed, and will receive payment for the schedule in,accordance with section 6-1.8.1.
Add the following section:
6-1.2.1 0.2 “Accepted with Comments.” The Contractor may proceed with the project work upon
issuance of the Notice to Proceed. The Contractor must resubmit the schedule incorporating the
comments prior to receipt of payment per section 6-1.8.1.
Add the following section:
6-1.2.1 0.3 “Not Accepted.” The Contractor must resubmit the schedule incorporating the
corrections and changes of the comments prior to receipt of payment per section 6-1.8.1. The Notice
to Proceed will not be issued by the Engineer if the changes of the comments are not submitted as
required hereinbefore and marked “Accepted” or “Accepted with Comments” by the Engineer. The
Contractor, at the sole option of the Engineer, may be considered as having defaulted the contract
under the provisions of section 6-4 DEFAULT BY CONTRACTOR if the changes of the comments
are not submitted as required hereinbefore and marked “Accepted” by the Engineer.
Add the following section:
6-1.3 Preparation of Schedule Updates and Revisions. The Contractor shall meet with the
Engineer during the last week of each month to agree upon each activity’s schedule status and shall
submit monthly updates of the Baseline Construction Schedule confirming the agreements no later
than the fifth working day of the following month. The monthly update will be submitted on hard
(paper) copy and electronic media conforming to section 6-1.3.3 Electronic Media per the submittal
requirements of section 2-5.3 and will include each item and element of sections 6-1.2 through
6-1.2.9 and 6-1.3.1 through 6-1.3.7.
_-
Add the following section:
6-1.3.1 Actual Activity Dates. The actual dates each activity was started andlor completed during
the month. After first reporting an actual date, the Contractor shall not change that actual date in later
updates without specific notification to the Engineer with the update.
Add the following section:
6-1.3.2 Activity Percent Complete. For each activity underway at the end of the month, the
Contractor shall report the percentage determined by the Engineer as complete for the activity.
Add the following section:
6-1.3.3 Electronic Media. The schedule data disk shall be a 89 mm (3‘1;) high density diskette,
labelled with the project name and number, the Contractor’s name and the date of preparation of the
schedule data disk. The schedule data disk shall be readable by the software specified in section
6-1.2.4 “Schedule Software” and shall be free of file locking, encryption or any other protocol that
would impede full access of all data stored on it.
Add the following section:
6-1.3.4 List of Changes. A list of all changes made to the activities or to the interconnecting logic,
with an explanation for each change. -
a Revised 10108103 Contract No. 34461 & 3887-H Page 71 of 85 Pages
Add the following section:
6-1.3.5 Change Orders, Each monthly update will include the addition of the network revisions
reflecting the change orders approved in the previous month. The network revisions will be as
agreed upon during the review and acceptance of the Contractor’s change orders.
Add the following section:
6-1.3.6 Bar Chart. Each monthly update will include a chart showing individual tasks and their
durations arranged with the tasks on the vertical axis and duration on the horizontal axis. The bar
chart shall use differing texture patterns or distinctive line types to show the critical path.
Add the following section:
6-1. 4 Engineer’s Review of Updated Construction Schedule. The Engineer will review and
return the Updated Construction Schedule to the Contractor, with any comments, within 5 working
days of submittal. The Updated Construction Schedule will be returned marked as per sections
6-1.4.1 through 6-1.4.3. Any Updated Construction Schedule marked “Accepted with Comments” or
“Not Accepted” by the Engineer will be returned to the Contractor for correction. Upon resubmittal the
Engineer will review and return the resubmitted Updated Construction Schedule to the Contractor,
with any comments, within 5 working days. Failure of the Contractor to submit a monthly updated
construction schedule will invoke the same consequences as the Engineer returning a monthly
updated construction schedule marked “Not Accepted”.
Add the following section:
6-1.4.1 “Accepted.” The Contractor may proceed with the project work, and will receive payment for
the schedule in accordance with section 6-1.8.2.
Add the following section:
6-1.4.2 “Accepted with Comments.” The Contractor may proceed with the project work.
The Contractor must resubmit the Updated Construction Schedule to the Engineer incorporating the
corrections and changes noted in the Engineer’s comments prior to receipt of payment per section
6-1 .a.2.
Add the following section:
6-1.4.3 “Not Accepted.” The Contractor must resubmit the Updated Construction Schedule to the
Engineer incorporating the corrections and changes noted in the Engineer’s comments prior to
receipt of payment per section 6-1.8.2. The Contractor, at the sole option of the Engineer, may be
considered as having defaulted the contract under the provisions of section 6-4 DEFAULT BY
CONTRACTOR if the changes of the comments are not submitted and marked “Accepted” by the
Engineer before the last day of the month in which the Updated Construction Schedule is due. If the
Contractor fails to submit the corrected Updated Construction Schedule as required herein the
Contractor may elect to proceed with the project at its own risk. Should the Contractor elect not to
proceed with the project, any resulting delay, impact, or disruption to the project will be the
Contractor’s responsibility.
Add the following section:
6-1.5 Late Completion or Milestone Dates. Should the Schedule Update indicate a completion or
contractually required milestone date later than the properly adjusted contract or milestone duration,
the Agency may withhold Liquidated Damages for the number of days late. Should a subsequent
“Accepted” Schedule Update remove all or a portion of the delay, all or the allocated portion of the
previously held Liquidated Damages shall be released in the monthly payment to the Contractor immediately following the “Accepted” schedule. --4
Contract No. 34461 & 3887-H
~~
@ Revised 10/08/03
~~
Page 72 of 85 Pages
c. Add the following section:
6-1.6 Interim Revisions. Should the actual or projected progress of the work become substantially
different from that depicted in the Project Schedule, independently of and prior to the next monthly
update, the Contractor will submit a revised Baseline Construction Schedule, with a list and
explanation of each change made to the schedule. The Revised Construction Schedule will be
submitted per the submittal requirements of section 2-5.3 and per the schedule review and
acceptance requirements of section 6-1, including but not limited to the acceptance and payment
provisions. As used in this subsection “substantially different” means a time variance greater than
5 percent of the number of days of duration for the project.
Add the following section:
6-1. 7 Final Schedule Update. The Contractor shall prepare and submit a final schedule update
when one hundred percent of the construction work is completed. The Contractor’s Final Schedule
Update must accurately represent the actual dates for all activities. The final schedule update shall
be prepared and reviewed per sections 6-1.3 Preparation of Schedule Updates and Revisions and
6-1.4 Engineer’s Review of Updated Construction Schedule. Acceptance of the final schedule update
is required for completion of the project and release of any and all funds retained per section 9-3.2.
Add the following section:
6-1.8 Measurement and Payment. Construction Schedule will be paid for at the stipulated lump
sum price. The stipulated lump sum price paid for Construction Schedule shall include full
compensation for furnishing all labor, materials including, but not limited to, the computer hardware
and software, tools, equipment, and incidentals; and for doing all the work involved in attending
meetings, preparing, furnishing, updating, revising the tabular, bar and flow chart Construction
Schedules and narrative reports required by these supplemental provisions and as directed by the
Engineer. The Engineer’s determination that each and any construction schedule proposed by the
Contractor complies with the requirements of these supplemental provisions shall be precedent to
each and any payment for the Construction Schedule. Payments for Construction Schedule will be
made as per sections 6-1.8.1 through 6-1.8.3.
_I
Add the following section:
6-1.8.1 Initial Payment. Twenty Five Percent (25%) of the stipulated lump sum bid for the
Construction Schedule will be made when the Engineer has accepted a Construction Schedule for
this project
Add the following section:
6-1.8.2 Monthly Updated Construction Schedule Payments. Monthly Updated Construction
Schedule Payments of up to Fifty Percent (50%) of the stipulated lump sum bid for the Construction
Schedule divided by the number of months indicated on the approved construction schedule will be
made subsequent to the initial payment for the Construction Schedule for each monthly Construction
Schedule, updated as required herein, that the Engineer has accepted as sufficient within the month
that the monthly progress payment pertains. No payment shall be made, nor shall any payment
accrue, for any monthly updated construction schedule that is not marked “Accepted” by the
Engineer on or before the twentieth working day of the month such monthly updated construction
schedule is due per section 6-1.3 Preparation of Schedule Updates and Revisions. The sum of the
amounts paid for Construction Schedule during the initial and subsequent payment periods, or
extensions to the contract, shall not exceed the stipulated lump sum price for Construction Schedule.
Revised 10/08/03 Contract No. 34461 & 3887-H Page 73 of 85 Pages
Add the following section: -
6-1.8.3 Concluding Payment. A Final payment of Twenty Five Percent (25%) of the stipulated lump sum bid for the Construction Schedule will be made when both one hundred percent of the contract work is completed and the Engineer has accepted a final construction schedule update prepared and submitted by the Contractor as required herein that shows the actual beginning and ending dates and all other data that is required for baseline and update schedules for each activity shown on the baseline construction schedule and updates thereto that the Engineer accepted for this project.
6-2 PROSECUTION OF WORK. Add the following section: 6-2.1 Order of Work. The work to be done shall consist of furnishing all labor, equipment and materials, and performing all operations necessary to complete the Project Work as shown on the Project Plans and as specified in the Specifications. The work includes construction of 24-inch and
30-inch diameter CML tape wrapped and motor coated welded steel potable water transmission mains, 18-inch and 20-inch PVC recycled water transmission mains, 1 2-inch PVC pipe, 8-inch PVC pipe, and appurtenances as shown on the drawings.
The following descriptions outlining the order of work are provided for the Contractor’s review and information. The descriptions are overviews only and shall not relieve the Contractor from its responsibilities to perform the coordination and work in accordance with the plans and specifications. Some phases or portions of phases may overlap each other and/or occur during the same time period for.
0 Pothole existing utilities, existing 12” recycled water lateral, connection points, and provide any conflicting data to the Engineer for review and modification to proposed pipeline. Notify existing utility owners prior to construction.
Submit shop drawings for approval and construct temporary 12 recycled water highline.
Construct and test recycled water pipelines as indicated in the Construction Sequence
provided on the plans.
Construct and test potable water pipelines as indicated in the Construction Sequence provided on the plans.
Notify the City of Carlsbad prior to connecting to existing pipelines.
Remove temporary caps, thrust blocks, and make connections to existing pipelines per plans.
Remove construct temporary 12” recycled water highline.
0
0
0
0
0
0
-
Add the following section: 6-2.3 Project Meetings. The Engineer will establish the time and location of weekly Project Meetings. Each Project Meeting shall be attended by the Contractor’s Representative. The Project Representative shall be the individual determined under section 7-6, ‘The Contractor’s Representative”, SSPWC. No separate payment for attendance of the Contractor, the Contractor’s Representative or any other employee or subcontractor or subcontractor’s employee at these meetings will be made.
6-6 DELAYS AND EXTENSIONS OF TIME.
6-6.4 Written Notice and Report. Modify as follows: The Contractor shall provide written notice to the Engineer within two hours of the beginning of any period that the Contractor has placed any workers or equipment on standby for any reason that the Contractor has determined to be caused by the Agency or by any organization that the Agency may otherwise be obligated by. The Contractor shall provide continuing daily written notice to the Engineer, each working day, throughout the duration of such period of delay. The initial and continuing written notices shall include the classification of each workman and supervisor and the make and model of each piece of equipment placed on standby, the cumulative duration of the standby, the Contractor’s opinion of the cause of the delay and a cogent explanation of why the Contractor could not avoid the delay by reasonable means. Should the Contractor fail to provide the notice(s) required by this section the Contractor
agrees that no delay has occurred and that it will not submit any claim(s) therefor.
a Revised 10/08/03 Contract No. 34461 & 3887-H Page 74 of 85 Pages
.- 6-7 TIME OF COMPLETION. Add the following: The Contractor shall diligently prosecute the work
to completion within 195 working days after the starting date specified in the Notice to Proceed.
6-7.2 Working Day. Add the following: Unless otherwise approved in writing by the Engineer, the
hours of work shall be between the hours of 7:OO a.m. and 4:OO p.m. on Mondays through Fridays,
excluding Agency holidays. The Contractor shall obtain the written approval of the Engineer if the
Contractor desires to work outside said hours or at any time during weekends and/or holidays. This
written permission must be obtained at least 48 hours prior to such work. The Engineer may approve
work outside the hours and/or days stated herein when, in hidher sole opinion, such work conducted
by the Contractor is beneficial to the best interests of the Agency. The Contractor shall pay the
inspection costs of such work.
No work involving Traffic Control shall be performed by the contractor between the hours and/or
dates that are listed on the Traffic Control Plans. The Contractor shall incorporate the dates, areas
and types of work prohibited in this section in the Construction Schedule required by section 6.1.
No additional payment, adjustment of bid prices or adjustment of contract time of completion will be
allowed as a consequence of the prohibition of work being performed within the dates, areas and/or
types of work prohibited in this section.
Contractor is hereby advised that the Engineer will require after hours and weekend work on an
interim basis to accomplish a portion of the Traffic Control Work.
6-8 COMPLETION AND ACCEPTANCE. Delete the second paragraph and add the following:
The Engineer will not accept the Work or any portion of the Work before all of the Work is
completed and all outstanding deficiencies that may exist are corrected by the Contractor and the
Engineer is satisfied that all the materials and workmanship, and all other features of the Work,
meet the requirements of all of the specifications for the Work. Use, temporary, interim or
permanent, of all, or portions of, the Work does not constitute acceptance of the Work. If, in the
Engineer’s judgment, the Work has been completed and is ready for acceptance the Engineer will
so certify to the Board. Upon such certification by the Engineer the Board may accept the completed
Work. Upon the Board’s acceptance of the Work the Engineer will cause a “Notice of Completion’’ to
be filed in the office of the San Diego County Recorder. The date of recordation shall be the date of
completion of the Work.
__
Delete the first sentence of the third paragraph and substitute the following two sentences: All work
shall be warranted for one (1) year after recordation of the “Notice of Completion” and any faulty
work or materials discovered during the warranty period shall be repaired or replaced by the
Contractor, at its expense. Twenty-five percent of the faithful performance bond shall be retained as
a warranty bond for the one year warranty period.
6-9 LIQUIDATED DAMAGES.
Modify the last sentence of the first paragraph and the first sentence of the second paragraph and
add the following: For each consecutive calendar day in excess of the time specified for completion
of Work, as adjusted in accordance with 6-6, the Contractor shall pay the Agency, or have withheld
monies due it, the sum of one thousand dollars ($1,000).
Execution of the Contract shall constitute agreement by the Agency and Contractor that one
thousand dollars ($1,000) per day is the minimum value of costs and actual damages caused by the
Contractor to complete the Work within the allotted time. Any progress payments made after the
specified completion date shall not constitute a waiver of this paragraph or of any damages.
-
e Revised 10/08/03 Contract No. 34461 8,3887-H Page 75 of 85 Pages
SECTION 7 -- RESPONSIBILITIES OF THE CONTRACTOR --
7-3 LIABILITY INSURANCE.
Modify as follows: All insurance is to be placed with insurers that have a rating in Best's Key Rating
Guide of at least A-:V and are admitted and authorized to conduct business in the state of California
and are listed in the official publication of the Department of Insurance of the State of California.
7-4 WORKERS' COMPENSATION INSURANCE.
Add the following: All insurance is to be placed with insurers that are admitted and authorized to
conduct business in the state of California and are listed in the official publication of the Department
of Insurance of the State of California. Policies issued by the State Compensation Fund meet the
requirement for workers' compensation insurance.
7-5 PERMITS.
Delete the first sentence and add the following four sentences: Except as specified herein the
agency will obtain, at no cost to the Contractor, all encroachment, right-of-way, grading, resource
agency and building permits necessary to perform work for this contract on Agency property, in
streets, highways (except State highway right-of-way), railways or other rights-of-way. Contractor
shall not begin work until all permits incidental to the work are obtained. The Contractor shall obtain
and pay for all permits for the disposal of all materials removed from the project. The cost of said
permit(s) shall be included in the price bid for the appropriate bid item and no additional
compensation will be allowed therefor. -
7-7 COOPERATION AND COLLATERAL WORK.
Add the following section:
7-7.1 Coordination. The Contractor shall coordinate and cooperate with all the utility companies
during the relocation or construction of their lines. The Contractor may be granted a time extension if,
in the opinion of the Engineer, a delay is caused by the utility company. No additional compensation
will be made to the Contractor for any such delay.
7-8 PROJECT SITE MAINTENANCE.
7-8.1 Cleanup and Dust Control. Add the following: Cleanup and dust control required herein shall
also be executed on weekends and other non-working days when needed to preserve the health
safety or welfare of the public. The Contractor shall conduct effective cleanup and dust control
throughout the duration of the Contract. The Engineer may require increased levels of cleanup and
dust control that, in hidher sole discretion, are necessary to preserve the health, safety and welfare
of the public. Cleanup and dust control shall be considered incidental to the items of work that they
are associated with and no additional payment will be made therefor.
7-8.5 Temporary Light, Power and Water. Add the following: The Contractor shall obtain a
construction meter for water used for the construction, plant establishment, maintenance, cleanup,
testing and all other work requiring water related to this contract. The Contractor shall contact the
appropriate water agency for requirements. The Contractor shall pay all costs of temporary light,
power and water including hookup, service, meter and any, and all, other charges, deposits and/or
fees therefor. Said costs shall be considered incidental to the items of work that they are associated
with and no additional payment will be made therefor.
--
Contract No. 34461 & 3887-H Page 76 of 85 Pages
~~ ~ ~~~ -
Revised 10/08/03
- 7-8.6 Water Pollution Control. .Add the following The Contractor shall comply with all
requirements of the storm water pollution and monitoring plan that is required to be developed for this
project in accordance with the California State Water Resources Control Board order number 92-08-
DWQ, NPDES General Permit number CAS000002 and the “Water Discharge Requirement for
Discharges of Storm Water Runoff Associated with Construction Activiv
Add the following section:
7-8.8 Noise Control. All internal combustion engines used in the construction shall be equipped
with mufflers in good repair when in use on the project with special attention to the City Noise Control
Ordinance, Carlsbad Municipal Code Chapter 8.48.
7-10 PUBLIC CONVENIENCE AND SAFETY.
7-10.1 Traffic and Access. add the following: The Contractor shall schedule the work so as to
prevent damage by all traffic, including but not limited to mail delivery. The Contractor shall not
schedule work so as to conflict with trash pickup. The trash hauling schedule can be obtained by
calling the City‘s contracted waste disposal company, Coast Waste Management at 929-941 7.
During overlay operations, the Contractors schedule for overlay application shall be designated to
provide residents and business owners whose streets are to be overlaid sufficient paved parking
within an 800 foot distance from their homes or businesses.
Seventy two hours prior to the start of any construction in the public right-of-way that affects vehicular
traffic and/or parking or pedestrian routes, the Contractor shall give written notification of the
impending disruption. For a full street closure, all residences and/or businesses on the affected street
or alley shall be notified. For partial street closures, or curb, sidewalk and driveway repairs, the
residences and/or businesses directly affected by the work shall be notified.
-
The notification shall be hand delivered and shall state the date and time the work will begin and its
anticipated duration. The notification shall list two telephone numbers that may be called to obtain
additional information. One number shall be the Contractor’s permanent office or field office and the
other number shall be a 24 hour number answered by someone who is knowledgeable about the
project. At least one of the phone numbers shall be in the (760) area code. An answering machine
shall not be connected to either number. The notification shall also give a brief description of the
work and simple instructions to the home or business owner on what they need to do to facilitate the
construction. The Contractor shall submit the contents of the notification to the Engineer for approval.
Notices shall not be distributed until approved by the Engineer.
For residences, the notification shall be pre-cut in a manner that enables it to be affixed to a
doorknob without adhesives. It shall be a minimum size of 3-112 inches by 8-1/2 inches and shall be
brightly colored with contrasting printing. The material shall be equivalent in strength and durability to
65 Ib. card stock. The printing on the notice shall be no smaller than 12 point. An example of such
notice is provided in Appendix “A”.
In addition to the notifications, the contractor shall post no parking signs 48 hours in advance of the
work being performed. The no parking signs shall state the date and time of parking restriction for a
duration not to exceed the time necessary to complete the work at that location. Failure of the
contractor to meet the posted date requires re-posting the no parking signs 48 hours in advance of
the rescheduled work. If the work is delayed or rescheduled the no parking signs shall be removed
and re-posted 48 hours in advance of the rescheduled work. c
Revised 10/08/03 Contract No. 34461 & 3887-H
~~ ~~~
Page 77 of 85 Pages
The preparation, materials, printing and distribution of the notifications shall be included in the
contract price bid for traffic control and the Contractor will not be entitled to any additional
compensation for printing and distributing these notices.
-
7-1 0.3 Street Closures, Detours, Barricades. Modify the second paragraph as follows: After
obtaining the Engineers approval and at least 5 working days before closing, detouring, partially
closing or reopening any street, alley or other public thoroughfare the Contractor shall notify the
following :
1) The Engineer ...................................................................................... (760) 438-1161 X-4411
2) Carlsbad Fire Department Dispatch .................................................. (760) 931 -21 97
3) Carlsbad Police Department Dispatch ............................................... (760) 931 -21 97
4) Carlsbad Traffic Signals Maintenance ............................................... (760) 438-2980 X-2937
5) Carlsbad Traffic Signals Operations .................................................. (760) 438-1 161 X4500
6) North County Transit District .............................................................. (760) 743-9346
7) Coast Waste Management ................................................................ (760) 929-9400
The Contractor shall comply with their requirements. The Contractor shall obtain the Engineer’s
written approval prior to deviating from the requirements of 2) through, and including, 7) above.
The Contractor shall obtain the written approval no less than five working days prior to placing any
traffic control that affects bus stops.
7-1 0.3 Street Closures, Detours, Barricades. Add the following: Traffic controls shall be in
accordance with the plans, Chapter 5 of the California Department of Transportation “Manual of
Traffic Controls,” 1996 edition and these Supplemental Provisions. If any component in the traffic
control system is damaged, displaced, or ceases to operate or function as specified, from any cause,
during the progress of the work, the Contractor shall immediately repair said component to its original
condition or replace said component and shall restore the component to its original location. In the
event that the Contractor fails to install and/or maintain barricades or such other traffic signs,
markings, delineation or devices as may be required herein, the Engineer may, at hidher sole option,
install the traffic signs, markings, delineation or devices and charge the Contractor twenty dollars
($25.00) per day per traffic sign or device, or the actual cost of providing such traffic control facility,
whichever is the greater.
-.
Add the following section:
7-10.3.1 Construction Area Signs and Control Devices. All construction traffic signs and control
devices shall be maintained throughout the duration of work in good order and according to the
approved traffic control plan. All construction area signs shall conform to the provisions of section
206-7.2 et seq. All temporary reflective pavement markers shall conform to the provisions of section
214-5.1 .et seq. All temporary reflective channelizers shall conform to the provisions of section
214-5.2 et seq. All paint for temporary traffic striping, pavement marking, and curb marking shall
conform to the provisions of section 21 0-1.6 et seq. except that all temporary paint shall be rapid dry
water borne conforming to section 21 0-1.6for materials and section 31 0-5 et seq. For workmanship.
Warning and advisory signs, lights and devices installed or placed to provide traffic control, direction
and/or warning shall be furnished, installed and maintained by the Contractor. Warning and advisory
signs, lights and devices shall be promptly removed by the Contractor when no longer required.
Warning and advisory signs that remain in place overnight shall be stationary mounted signs.
Stationary signs that warn of non-existent conditions shall be removed from the traveled way and
from the view of motorists in the traveled way or shielded from the view of the travelling public during
such periods that their message does not pertain to existing conditions. Care shall be used in
performing excavation for signs in order to protect underground facilities. All excavation required to
install stationary construction area signs shall be performed by hand methods without the use of
power equipment. Warning and advisory signs that are used only during working hours may be
portable signs. Portable signs shall be removed from the traveled way and shielded from the view of
-’
Revised 10/08/03 Contract No. 34461 & 3887-H Page 78 of 85 Pages
- the travelling public during non-working hours. During the hours of darkness, as defined in Division 1,
Section 280, of the California Vehicle Code, portable signs shall be illuminated or, at the option of the
Contractor, shall be in conformance with the provisions in section 206-7.2 et seq. If illuminated traffic
cones rather than post-type delineators are used during the hours of darkness, they shall be affixed
or covered with reflective cone sleeves as specified in CALTRANS “Standard Specifications”, except
the sleeves shall be 180 mm (7”) long. Personal vehicles of the Contractor’s employees shall not be
parked within the traveled way, including any section closed to public traffic. Whenever the
Contractor’s vehicles or equipment are parked on the shoulder within 1.8 m (6’) of a traffic lane, the
shoulder area shall be closed with fluorescent traffic cones or portable delineators placed on a taper
in advance of the parked vehicles or equipment and along the edge of the pavement at not less than
7.6 m (25’) intervals to a point not less than 7.6 m (25’) past the last vehicle or piece of equipment.
A minimum of nine (9) cones or portable delineators shall be used for the taper. A C23 (Road Work
Ahead) or C24 (Shoulder Work Ahead) sign shall be mounted, as required herein, on a sign post or
telescoping flag tree with flags. The sign post or flag tree shall be placed where directed by the
Engineer.
Add the following section:
7-1 0.3.2 Maintaining Traffic. The Contractor’s personnel shall not work closer than (insert minimum
acceptable lateral safety buffer distance, eg. 1.8 m (6’))’ nor operate equipment within 0.6 m (2’) from
any traffic lane occupied by traffic. For equipment the than (insert minimum acceptable shy distance,
eg. 0.6 m (2’)) shall be measured from the closest approach of any part of the equipment as it is
operated and/or maneuvered in performing the work. This requirement may be waived when the
Engineer has given written authorization to the reduction in clearance that is specific to the time,
duration and location of such waiver, when such reduction is shown on the traffic control plans
included in these contract documents, when such reduction is shown on the traffic control plans
prepared by the Contractor and approved by the Engineer or for the work of installing, maintaining
and removing traffic control devices. As a condition of such waiver the Engineer may require the
Contractor to detour traffic, adjust the width of, or realign the adjacent traffic lane, close the adjacent
traffic lane or provide barriers.
-
During the entire construction, a minimum of (insert appropriate number of lanes) paved traffic lanes,
not less than (insert appropriate minimum lane widths, eg.3.6m (12’)) wide, shall be open for use by
public traffic in each direction of travel.
Add the following section:
7-1 0.3.3 Traffic Control System for Lane Closure. A traffic control system consists of closing traffic
lanes or pedestrian walkways in accordance with the details shown on the plans, CALTRANS
“Manual of Traffic Control”, 1996 edition and provisions under “Maintaining Traffic” elsewhere in
these Supplemental Provisions. The provisions in this section will not relieve the Contractor from its
responsibility to provide such additional devices or take such measures as may be necessary to
maintain public safety.
When lanes are closed for only the duration of work periods, all components of the traffic control
system, except portable delineators placed along open trenches or excavation adjacent to the
traveled way, shall be removed from the traveled way and shoulder at the end work period. If the
Contractor so elects, said components may be stored at selected central locations, approved by the
Engineer, within the limits of the right-of-way.
,---
Revised 10/08/03 Contract No. 34461 & 3887-H Page 79 of 85 Pages
Add the following section:
7-10.3.4 Traffic Control for Permanent and Temporary Traffic Striping. During traffic stripe
operations, traffic shall be controlled with lane closures, as provided for under “Traffic Control System
for Lane Closure” of these Supplemental Provisions or by use of an alternative traffic control plan
proposed by the Contractor and approved by the Engineer. The Contractor shall not start traffic
striping operations using an alternative plan until the Contractor has submitted its plan to the
Engineer and has received the Engineer’s written approval of said plan.
Add the following section:
7-1 0.3.5 Temporary Pavement Delineation. Temporary pavement delineation shall be furnished,
placed, maintained and removed in accordance with the minimum standards specified in Chapter 5
of the “Traffic Manual”, 1996 edition published by CALTRANS. Whenever the work causes
obliteration of pavement delineation, temporary or permanent pavement delineation shall be in place
prior to opening the traveled way to public traffic. Lane line or centerline pavement delineation shall
be provided at all times for traveled ways open to public traffic. All work necessary, including any
required lines or marks, to establish the alignment of temporary pavement delineation shall be
performed by the Contractor. When temporary pavement delineation is removed, all lines and marks
used to establish the alignment of the temporary pavement delineation shall be removed by grinding.
Surfaces to receive temporary pavement delineation shall be dry and free of dirt and loose material.
Temporary pavement delineation shall not be applied over existing pavement delineation or other
temporary pavement delineation. Temporary pavement delineation shall be maintained until
superseded or replaced with permanent pavement delineation.
Temporary pavement delineation shall be removed when, as determined by the Engineer, the
temporary pavement delineation conflicts with the permanent pavement delineation or with a new
traffic pattern for the area and is no longer required for the direction of public traffic. When temporary
pavement delineation is required to be removed, all lines and marks used to establish the alignment
of the temporary pavement delineation shall be removed.
-
Revised 10/08/03 Contract No. 34461 & 3887-H Page 80 of 85 Pages
1 Add the following section:
7-1 0.3.6 Preparation of New, or Modifications and Additions to Existing, Traffic Control Plan
Sheets. If no traffic control plans (TCP) or Traffic Control Staging plans (TCP) are included in the
project plans, or if the Contractor elects to modify TCP included in the project plans, the Contractor
shall have such new or modified TCP prepared and submitted as a part of the Work for any and all
construction activities that are located within the travelled way. The Contractor shall have TCP
prepared and submitted as a part of the Work for any construction activities that are a part of this
project that are not included in the project plans. The Contractor must submit the TCP for the
Engineer's review in conformance with the requirements of section 2-5.3, et seq. and obtain the
Engineer's approval of the TCP prior to implementing them. The minimum 20 day review period
specified in section 2-5.3.1 for shop drawings and submittals shall pertain to each submittal of TCP,
new, modified or added to, for the Engineer's review. New or revised TCP submittals shall include all
TCP needed for the entire duration of the Work. Each phase of the TCP shall be shown in sufficient
scale and detail to show the lane widths, transition lengths, curve radii, stationing of features
affecting the traffic control plan and the methodology proposed to transition to the subsequent TCP
phase. When the vertical alignment of the travelled surface differs from the finished pavement
elevation vertical curves must also be shown. The Contractor may choose to modify, add to or
supplement the TCP shown on sheets of Drawing No. 394-1 and 414-4 of the contract documents or
substitute TCP to further its own interests. Such substitution shall be prepared in type and kind as
sheets of Drawing No. 394-1 and 414-4. The level of detail, format, and graphics shall be of quality
and size no less than shown on sheets of Drawing No. 394-1 and 414-4. Such modification,
addition, supplement, and/or new design of TCP shall be prepared by a registered professional
engineer appropriately registered in the State of California. The Engineer shall be the sole judge of
the suitability and quality of any such modifications, supplements, and/or new designs to TCP. The
Engineer may approve any such modifications, supplements, and/or new designs to the TCP when,
in the Engineer's sole opinion, such modifications, supplements, and/or new designs to the TCP
prepared by the registered professional engineer retained by the Contractor will be beneficial to the
best interests of the Agency. Such modification, addition, supplement, and/or new design shall not be
implemented and no work shall be commenced that is contingent on such approval until the changed
TCP are approved by the Engineer. The preparation of such modification, addition, supplement,
and/or new designs of TCP shall not presuppose their approval or obligate the Agency in any
fashion. Submittal and review requirements for such modifications, supplements, and/or new designs
to TCP shall conform to the requirements of section 2-5.3 Shop Drawings and Submittals.
-
Add the following section:
7-10.3.7 Payment. The Contractor shall provide traffic control at the contract lump sum price bid.
The contract lump sum price paid for "traffic control" shall include full compensation for furnishing all
labor (including flagging costs), materials (including signs), tools, equipment and incidentals, and for
doing all the work involved in preparation, reproduction and changing of traffic control plans, placing,
applying traffic stripes and pavement markers with bituminous adhesive, removing, storing,
maintaining, moving to new locations, replacing, and disposing of the components of the traffic
control system as shown on the plans and approved additions and modifications, as specified in
these supplemental provisions, and as directed by the Engineer. All expenses and time to prepare
and review modifications, additions, supplements and/or new TCP designs shall be included in the
lump sum bid for traffic control and no additional payment will be made therefor. Flagging costs will
be paid for as a part of the Lump Sum Amount for "Traffic Control." The cost of labor and material for
portable concrete barriers will be paid for at the unit price bid. When there is no bid item the cost of
labor and material for portable concrete barriers they will be paid as an incidental to the work being
performed and no additional payment will be made therefor. Progress payments for "Traffic Control"
will be based on the percentage of the improvement work completed. -
@ Revised 10/08/03 Contract No. 34461 & 3887-H Page 81 of 85 Pages
Add the following section: x
7-10.4.4 Safety and Protection of Workers and Public. The Contractor shall take all necessary
precautions for the safety of employees on the work and shall comply with all applicable provisions of
Federal, State and Municipal safety laws and building codes to prevent accidents or injury to persons
on, about, or adjacent to the premises where the work is being performed. The Contractor shall erect
and properly maintain at all times, as required by the conditions and progress of the work, all
necessary safeguards for the protection of workers and public, and shall use danger signs warning
against hazards created by such features of construction as protruding nails, hoists, well holes, and
falling materials.
7-13 LAWS TO BE OBSERVED. Add the following: Municipal ordinances that affect this work
include Chapter 11.06. Excavation and Grading. If this notice specifies locations or possible
materials, such as borrow pits or gravel beds, for use in the proposed construction project which
would be subject to Section 1601 or Section 1603 of the Fish and Game Code, the conditions
established pursuant to Section 1601 et seq. of the Fish and Game Code shall become conditions of
the contract.
SECTION 9 -- MEASUREMENT AND PAYMENT
9-1 MEASUREMENT OF QUANTITIES FOR UNIT PRICE WORK
9-1.4 Units of Measurement, modify as follows: The system of measure for this contract shall be
the U.S. Standard Measures. -
9-3 PAYMENT.
9-3.1 General. Delete the eighth paragraph and substitute the following: Guarantee periods shall
not be affected by any payment but shall commence on the date of recordation of the “Notice of
Completion”
9-3.2 Partial and Final Payment. Delete the second paragraph and substitute the following: Each
month, the Engineer will make an approximate measurement of the work performed to the closure
date as basis for making monthly progress payments. The estimated value will be based on contract
unit prices, completed change order work and as provided for in Section 9-2 of the Standard
Specifications (SSPWC). Progress payments shall be made no later than thirty (30) calendar days
after the closure date. Five (5) working days following the closure date, the Engineer shall complete
the detailed progress pay estimate and submit it to the Contractor for the Contractor’s information.
Should the Contractor assert that additional payment is due, the Contractor shall within ten (10)
days of receipt of the progress estimate, submit a supplemental payment request to the Engineer
with adequate justification supporting the amount of supplemental payment request. Upon receipt of
the supplemental payment request, the Engineer shall, as soon as practicable after receipt,
determine whether the supplemental payment request is a proper payment request. If the Engineer
determines that the supplemental payment request is not proper, then the request shall be returned
to the Contractor as soon as practicable, but not later than seven (7) days after receipt. The
returned request shall be accompanied by a document setting forth in writing the reasons why the
Supplemental payment request was not proper. In conformance with Public Contract Code Section
20104.50, the City shall make payments within thirty (30) days after receipt of an undisputed and
supplemental payment request is not made within thirty (30) days after receipt by the Engineer, then
the City shall pay interest to the Contractor equivalent to the legal rate set forth in subdivision (a) of
Section 685.01 0 of the Code of Civil Procedure.
properly submitted supplemental payment request from the Contractor. If payment of the undisputed 4
Contract No. 34461 & 3887-H
~~
Revised 10/08/03
~
Page 82 of 85 Pages
-c
Add paragraph 6 et seq. as follows: After final inspection, the Engineer will make a Final Payment
Estimate and process a corresponding payment. This estimate will be in writing and shall be for the
total amount owed the Contractor as determined by the Engineer and shall be itemized by the
contract bid item and change order item with quantities and payment amounts and shall show all
deductions made or to be made for prior payments and amounts to be deducted under provisions of
the contract. All prior estimates and progress payments shall be subject to correction in the Final
Payment Estimate.
The Contractor shall have 30 calendar days from receipt of the Final Payment Estimate to make
written statement disputing any bid item or change order item quantity or payment amount. The
Contractor shall provide all documentation at the time of submitting the statement supporting its
position. Should the Contractor fail to submit the statement and supporting documentation within the
time specified, the Contractor acknowledges that full and final payment has been made for all
contract bid items and change order items.
If the Contractor submits a written statement with documentation in the aforementioned time, the
Engineer will review the disputed item within 30 calendar days and make any appropriate
adjustments on the Final Payment. Remaining disputed quantities or amounts not approved by the
Engineer will be subject to resolution as specified in subsection 3-5, Disputed Work.
The written statement filed by the Contractor shall be in sufficient detail to enable the Engineer to
ascertain the basis and amount of said disputed items. The Engineer will consider the merits of the
Contractor’s claims. It will be the responsibility of the Contractor to furnish within a reasonable time
such further information and details as may be required by the Engineer to determine the facts or
contentions involved in its claims. Failure to submit such information and details will be sufficient
cause for denying payment for the disputed items.
.-
9-3.2.1 Payment for Claims. Add the following: Except for those final payment items disputed in the
written statement required in subsection 9-3.2 all claims of any dollar amount shall be submitted in a
written statement by the Contractor no later than the date of receipt of the final payment estimate.
Those final payment items disputed in the written statement required in subsection 9-3.2 shall be
submitted no later than 30 days after receipt of the Final Payment estimate. No claim will be
considered that was not included in this written statement, nor will any claim be allowed for which
written notice or protest is required under any provision of this contract including sections 3-4
Changed Conditions, 3-5 Disputed Work, 6-6.3 Payment for Delays to Contractor, 6-6.4 Written
Notice and Report, or 6-7.3 Contract Time Accounting, unless the Contractor has complied with
notice or protest requirements.
The claims filed by the Contractor shall be in sufficient detail to enable the Engineer to ascertain the
basis and amount of said claims. The Engineer will consider and determine the Contractor’s claims
and it will be the responsibility of the Contractor to furnish within a reasonable time such further
information and details as may be required by the Engineer to determine the facts or contentions
involved in its claims. Failure to submit such information and details will be sufficient cause for denying the claims.
Payment for claims shall be processed within 30 calendar days of their resolution for those claims
approved by the Engineer. The Contractor shall proceed with informal dispute resolution under
subsection 3-5, Disputed Work, for those claims remaining in dispute.
c
Revised 10/08/03 Contract No. 34461 & 3887-H Page 83 of 85 Pages
- Add the following section:
9-3.3.1 Delivered Materials. The cost of materials and equipment delivered but not incorporated
into the will not be included in the progress estimate.
Add the following section:
9-3.4.1 Mobilization and Preparatory Work. Payment for mobilization and preparatory Work will be
made at the stipulated lump-sum price bid therefor in the bid schedule, and includes full
compensation for furnishing all insurance, bonds, licenses, labor, materials, utilities, tools, equipment
and incidentals, and for doing all the work involved in mobilization and preparatory work and
operations, including, but not limited to, those necessary for the movement of personnel, equipment,
supplies, and incidental to preparing to conduct work on and off the project site and other offsite
facilities necessary for work on the project; for all other facilities, sureties, work and operations which
must be performed or costs incurred prior to beginning work on various contract items on or off the
project site, excepting those specifically paid for under separate sections of these specifications.
The Contractor hereby agrees that the stipulated lump sum amount is sufficient for Mobilization and
Preparatory Work, as described in this section, and that the Contractor shall have no right to
additional compensation for Mobilization and Preparatory Work.
Progress payments for Mobilization and Preparatory Work will be made as follows:
For the first progress payment (after the issuance of the Notice to Proceed), forty percent (40%) of
the amount bid for Mobilization And Preparatory Work will be allowed. For the second progress
payment, an additional sixty percent (60%) of the amount bid for mobilization and preparatory work
will be allowed therefor.
Revised 10/08/03 Contract No. 34461 & 3887-H Page 84 of 85 Pages
APPENDIX “A”
RESIDENT NOTIFICATION EXAMPLE
CITY OF CARLSBAD
ROAD WORK
ABC CONTRACTORS
OFFICE # (76O)XXX-XXXX
FIELD # (76O)XXX-XXXX
)ear resident:
4s a part of the City of Carlsbad’s ongoing program to maintain its streets, your street will be resurfaced with a layer of asphalt concrete iver the existing roadway surface. This construction will require the clos- ng of your street to through traffic for one day. Your street, from XYZ St.
:o XYZAve. will be closed to through traffic and resurfaced on:
‘rom 7:OOA.M. to 5:OO P.M.
If you don’t plan to leave your home by 7:OO A.M. on the above date >lease park your car on an adjacent street in your neighborhood that will lot be resurfaced. Streets scheduled for resurfacing can be determined
>y calling either the Contractor or the City of Carlsbad Engineering In- spection Department. When walking to and from your car, remember not
:o walk on the newly overlaid street or you will have black residue on the
3ottom of your shoes. Please do not drive, walk on, walk pets, play, or skate on the newly overlaid asphalt. Also, please refrain from watering pur lawns, washing cars, etc., approximately 6-8 hours after the asphalt s laid as running water will cause damage to the new surface.
ABC is the Contractor that will be performing the resurfacing work for :he city and you may call them at
(76O)XXX-XXXX if you have any questions regarding the project. Resur-
‘acing of your street will not occur on the day your trash is collected. Mail Jelivery may be delayed if the postman cannot reach the mailbox that
Jay. If you have a moving company scheduled for that day please call and inform the Contractor of the date. If you have any concerns which :annot be addressed by the Contractor, you may call the City‘s Engineer- ng Inspection Department at 438-1 161 x4323. Thank you for your cooperation as we work to make a better City of 2arlsbad.
MON. TUE. WED. THU. FRI. DATE:
.-
Revised 10/08/03 Contract No. 34461 & 3887-H Page 85 of 85 Pages
r^- STATE OF CALIFORNIA, WATER RESOURCE CONTROL BOARD
CONTRACT REQUIREMENTS
BOILERPLATE
1 - STATE WAGE RATE CLAUSES (Facilities Plan Approval after June 18, 1998, Federal Wage Rates are
not required)
Pursuant to Sections 1720 et seq., and 1770 et seq., of the California Labor Code, the successful bidder shall pay
not less than the prevailing rate of per diem wages as determined by the Director of the California Department of
Industrial Relations for public works projects of more than one thousand dollars ($1,000). Copies of such prevailing
rate or per diem wage are on file at City of Carlsbad which copies shall be made available to any interested party on
request. The successful bidder shall post a copy of such determinations at each job site.
The successful bidder intending to use a craft or classification not shown on the prevailing rate determinations may
be required to pay the rate of the craft or classification most closely related to it.
2- LABOR CODE SECTION 1776
COMPLETE PAYROLL RECORDS: CERTIFIED AND AVAILABLE
(a) Each contractor and subcontractor shall keep an accurate payroll record, showing the name, address, social security
number, work classification, and straight time and overtime hours worked each day and week, and the actual per diem
wages paid to each journeyman, apprentice, worker, or other employee employed by him or her in connection with the
c public work.
(b) The payroll records enumerated under subdivision (a) shall be certified and shall be available for inspection at all
reasonable hours at the principal office of the contractor on the following basis:
(1) A certified copy of an employee's payroll record shall be made available for inspection or finished to the
employee or his or her authorized representative on request.
(2) A certified copy of all payroll records enumerated in subdivision (a) shall be made available for inspection or
furnished upon request to a representative of the body awarding the contract, the Division of Labor Standards
Enforcement, and the Division of Apprenticeship Standards of the Department of Industrial Relations.
(3) A certified copy of all payroll records enumerated in subdivision (a) shall be made available upon request by the
public for inspection or for copies thereof. However, a request by the public shall be made through either the body
awarding the contract, the Division of Apprenticeship Standards, or the Division of Labor Standards Enforcement. If
the requested payroll records have not been provided pursuant to paragraph (2), the requesting party shall, prior to
being provided the records, reimburse the costs of preparation by the contractor, subcontractors, and the entity through
which the request was made. The public shall not be given access to the records at the principal office of the contractor.
(c) The certified payroll records shall be on forms provided by the Division of Labor Standards Enforcement or shall
contain the same information as the forms provided by the division.
(d) Each contractor shall file a certified copy of the records enumerated in subdivision (a) with the entity that
requested the records within 10 days after receipt of a written request.
(e) Any copy of records made available for inspection as copies and furnished upon request to the public or any public
agency by the awarding body, the Division of Apprenticeship Standards, or the Division of Labor Standards
Enforcement shall be marked or obliterated in a manner so as to prevent disclosure of an individual's name, address,
and social security number. The name and address of the contractor awarded the contract or performing the contract
shall not be marked or obliterated.
-
BP-1
(f) The contractor shall inform the body awarding the contract of the location of the records enumerated under
.---. subdivision (a), including the street address, city and county, and shall, within five working days, provide a notice of a
change of location and address.
(g) The contractor shall have 10 days in which to comply subsequent to receipt of written notice specifjmg in what
respects the contractor must comply with this section. In the event that the contractor fails to comply within the 10-
day period, he or she shall, as a penalty to the state or political subdivision on whose behalf the contract is made or
awarded, forfeit twenty-five dollars ($25) for each calendar day, or portion thereof, for each worker, until strict
compliance is effectuated. Upon the request of the Division of Apprenticeship Standards or the Division of Labor
Standards Enforcement, these penalties shall be withheld from progress payments then due.
(h) The body awarding the contract shall cause to be inserted in the contract stipulations to effectuate this section.
These stipulations shall fix the responsibility for compliance with this section on the prime contractor.
(i) The director shall adopt rules consistent with the California Public Records Act, (Chapter 3.5 (commencing with
Section 6250), Division 7, Title 1, Government Code) and the Information Practices Act of 1977, (Title 1.8
(commencing with Section 1798), Part 4, Division 3, Civil Code) governing the release of these records, including the
establishment of reasonable fees to be charged for reproducing copies of records required by this section.
3- LABOR CODE SECTION 1777.5
EMPLOYMENT OF PROPERLY REGISTERED APPRENTICES
Nothing in this chapter shall prevent the employment of properly registered apprentices upon public works.
Every such apprentice shall be paid the standard wage paid to apprentices under the regulations of the craft or trade at
which he or she is employed, and shall be employed only at the work of the craft or trade to which he or she is
registered.
Only apprentices, as defined in Section 3077, who are in training under apprenticeship standards and written -
apprentice agreements under Chapter 4 (commencing with Section 3070) of Division 3, are eligible to be employed on
public works. The employment and training of each apprentice shall be in accordance with the apprenticeship
standards and apprentice agreements under which he or she is training.
When the contractor to whom the contract is awarded by the state or any political subdivision, or any subcontractor
under him or her, in performing any of the work under the contract or subcontract, employs workers in any
apprenticeable craft or trade, the contractor and subcontractor shall apply to the joint apprenticeship committee
administering the apprenticeship standards of the craft or trade in the area of the site of the public work for a certificate
approving the contractor or subcontractor under the apprenticeship standards for the employment and training of
apprentices in the area or industry affected. However, approval as established by the joint apprenticeship committee or
committees shall be subject to the approval of the Administrator of Apprenticeship. The joint apprenticeship
committee or committees, subsequent to approving the subject contractor or subcontractor, shall arrange for the
dispatch of apprentices to the contractor or subcontractor in order to comply with this section. Every contractor and
subcontractor shall submit contract award information to the applicable joint apprenticeship committee which shall
include an estimate of journeyman hours to be performed under the contract, the number of apprentices to be
employed, and the approximate dates the apprentices will be employed. There shall be an affirmative duty upon the
joint apprenticeship committee or committees administering the apprenticeship standards of the craft or trade in the
area of the site of the public work to ensure equal employment and affirmative action in apprenticeship for women and
minorities. Contractors or subcontractors shall not be required to submit individual applications for approval to local
joint apprenticeship committees provided they are already covered by the local apprenticeship standards. The ratio of
work performed by apprentices to journeymen who shall be employed in the craft or trade on the public work may be
the ratio stipulated in the apprenticeship standards under which the joint apprenticeship committee operates, but, except
as otherwise provided in this section, in no case shall the ratio be less than one hour of apprentices work for every five
hours of labor performed by a journeyman. However, the minimum ratio for the land surveyor classification shall not
be less than one apprentice for each five journeymen . - Any ratio shall apply during any day or potion of a day when any journeyman, or the higher standard stipulated by
the joint apprenticeship committee, is employed at the job site and shall be computed on the basis of the hours worked
BP-2
during the day by journeymen so employed, except for the land surveyor classification. The contractor shall employ
apprentices for the number of hours computed as above before the end of the contract. However, the contractor shall
endeavor, to the greatest extent possible, to employ apprentices during the same time period that the journeymen in the
same craft or trade are employed at the job site. Where an hourly apprenticeship ratio is not feasible for a particular
craft or trade, the Division of Apprenticeship Standards, upon application of a joint apprenticeship committee, may
order a minimum ratio of not less than one apprentice for each five journeymen in a craft or trade classification.
The contractor or subcontractor, if he or she is covered by this section, upon the issuance of the approval certificate, or
if he or she has been previously approved in the craft or trade, shall employ the number of apprentices or the ratio of
apprentices to journeymen stipulated in the apprenticeship standards. Upon proper showing by the contractor that he or
she employs apprentices in the craft or trade in the state on all of his or her contracts on an annual average of not less
than one hour of apprentice work for every five hours of labor performed by a journeyman, or in the land surveyor
classification, one apprentice for each five journeymen, the Division of Apprenticeship Standards may grant a
certificate exempting the contractor from the 1-to-5 hourly ratio as set forth in this section. This section shall not apply
to contracts of general contractors or to contracts of specialty contractors not bidding for work through a general or
prime contractor, when the contracts of general contractors or those specialty contractors involve less than thirty
thousand dollars ($30,000) or 20 working days . Any work performed by a journeyman in excess of eight hours per
day or 40 hours per week, shall not be used to calculate the hourly ratio required by this section.
"Apprenticeable craft or trade," as used in this section, means a craft or trade determined as an apprenticeable
occupation in accordance with rules and regulations prescribed by the Apprenticeship Council. The joint
apprenticeship committee shall have the discretion to grant a certificate, which shall be subject to the approval of the
Administrator of Apprenticeship, exempting a contractor from the 1-to-5 ratio set forth in this section when it finds that
any one of the following conditions is met:
(a) Unemployment for the previous three-month period in the area exceeds an average of 15 percent.
(b) The number of apprentices in training in such area exceeds a ratio of 1 to 5 .
(c) There is a showing that the apprenticeable craft or trade is replacing at least one-thirtieth of its journeymen
annually through apprenticeship training, either on a statewide basis, or on a local basis.
(d) Assignment of an apprentice to any work performed under a public works contract would create a condition
which would jeopardize his or her life or the life, safety, or property of fellow employees or the public at large or if the
specific task to which the apprentice is to be assigned is of such a nature that training cannot be provided by a
journeyman.
When exemptions are granted to an organization which represents contractors in a specific trade from the 1 -to-5 ratio
on a local or statewide basis the member contractors will not be required to submit individual applications for approval
to local joint apprenticeship committees, if they are already covered by the local apprenticeship standards.
A contractor to whom the contract is awarded, or any subcontractor under him or her, who, in performing any of the
work under the contract, employs journeymen or apprentices in any apprenticeable craft or trade and who is not
contributing to a fund or funds to administer and conduct the apprenticeship program in any craft or trade in the area of
the site of the public work, to which fund or funds other contractors in the area of the site of the public work are
contributing, shall contribute to the fund or funds in each craft or trade in which he or she employs journeymen or
apprentices on the public work in the same amount or upon the same basis and in the same manner as the other
contractors do, but where the trust fund administrators are unable to accept the funds, contractors not signatory to the
trust agreement shall pay a like amount to the California Apprenticeship Council. The contractor or subcontractor may
add the amount of the contributions in computing his or her bid for the contract. The Division of Labor Standards
Enforcement is authorized to enforce the payment of the contributions to the fimd or funds as set forth in Section 227.
The body awarding the contract shall cause to be inserted in the contract stipulations to effectuate this section. The
stipulations shall fix the responsibility of compliance with this section for all apprenticeable occupations with the prime
contractor.
All decisions of the joint apprenticeship committee under this section are subject to Section 308 1.
BP-3
4- LABOR CODE SECTION 18 10
DEFINITION: A LEGAL DAY’S WORK
Eight hours labor constitutes a legal day’s work in all cases where the same is performed under the authority of any
law of this State, or under the direction, or control, or by the authority of any officer of this State acting in his official
capacity, or under the direction, or control or by the authority of any municipal corporation, or of any officer thereof A
stipulation to that effect shall be made a part of all contracts to which the State or any municipal corporation therein is a
Party.
5- LABOR CODE SECTION 18 13
PENALTY FOR OVERTIME ON ANY PUBLIC WORK CONTRACT
The contractor shall, as a penalty to the State or political subdivision on whose behalf the contract is made or awarded,
forfeit twenty-five dollars ($25) for each workman employed in the execution of the contract by the contractor or by
any subcontractor for each calendar day during which such workman is required or permitted to work more than 8
hours in any one calendar day and 40 hours in any one calendar week in violation of the provisions of this article. In
awarding any contract for public work, the awarding body shall cause to be inserted therein a stipulation to this effect.
The awarding body shall take cogmzance of all violations of this article committed in the course of the execution of the
contract, and shall report them to the officer of the State or political subdivision who is authorized to pay the contractor
money due him under the contract.
6- LABOR CODE SECTION 18 15
MMMUM OVERTIME PAY
Notwithstanding the provisions of Sections 18 10 to 18 14, inclusive, of this code, and notwithstanding any stipulation
inserted in any contract pursuant to the requirements of said sections, work performed by employees of contractors in
excess of 8 hours per day, and 40 hours during any one week, shall be permitted upon public work upon compensation
for all hours worked in excess of 8 hours per day at not less than one and one-half (1.5) times the basic rate of pay.
7- LABOR CODE SECTION 1860
CONTRACT PROVISION
The awarding body shall cause to be inserted in every public works contract a clause providing that, in accordance
with the provisions of Section 3700 of the Labor Code, every contractor will be required to secure the payment of
compensation to his employees.
8- LABOR CODE SECTION 1861
CONTRACTOR CERTIFICATION TO LABOR CODE SECTION 3700
Each contractor to whom a public works contract is awarded shall sign and file with the awarding body the following
certification prior to performing the work of the contract: “I am aware of the provisions of Section 3700 of the Labor
Code which require every employer to be insured against liability for workers‘ compensation or to undertake
self-insurance in accordance with the provisions of that code, and I will comply with such provisions before
commencing the performance of the work of this contract.”
9- CULTURAL RESOURCES
In accordance with the National Historic Preservation Act of 1966, (16 U.S.C. 470), the following procedures are
implemented to insure historic preservation and fair compensation to the Contractor for delays attendant to cultural
resources investigations.
In the event potential Historical, Architectural, Archeological, or Cultural Resources (herein after cultural
resources) are discovered during subsurface excavations at the site of construction, the following procedures shall be
instituted:
1) at the location of such potential cultural resources find.
The Engineer shall issue a “Stop Work Order” directing the Contractor to cease all construction operations
BP-4
2) Such “Stop Work Order” shall be effective until such time as a qualified archeologist can be called to assess the value of these potential cultural resources and make recommendations to the State Water Resources
Control Board Cultural Resources Officer. Any “Stop Work Order” shall contain the following:
a)
b)
c)
d)
e)
A clear description of the work to be suspended;
Any instructions regarding issuance of further orders by the Contractor for material services;
Guidance as the action to be taken on subcontracts;
Any suggestions to the Contractor as to minimization of his costs;
Estimated duration of the temporary suspension.
If the archeologist determines that the potential find is a bonafide cultural resource, at the direction of the State
Water Resources Control Board Cultural Resources Officer, the Engineer shall extend the duration of the “Stop
Work Order” in writing, and the Contractor shall suspend work at the location of the find.
Equitable adjustment of the construction contract shall be made in the following manner:
1) Time Extension
If the work temporarily suspended is on the “critical path”, the total number of days for which the suspension is in
effect shall be added to the number of allowable contract days.
If a portion of work at the time of such suspension is not on the “critical path”, but subsequently becomes work on
the critical path, the allowable contract time will be computed from the date such work is classified as on the critical
path.
2) Additional ComDensation
If, as a result of a suspension of the work, the Contractor sustains a loss which could not have been avoided by his
judicious handling of forces, and equipment, or redirection of forces or equipment to perform other work on the
contract, there shall be paid to the Contractor an amount as determined by the Engineer to be fair and reasonable
compensation for the Contractor’s actual loss in accordance with the following:
a) Idle Time of Eauipment
Compensation for equipment idle time will be determined on a force account (time and materials) basis, and shall
include the cost of extra moving of equipment and rental loss. The right-of-way delay factor for each classification
of equipment shown in the California Department of Transportation publication entitled, Equipment Rental Rates
and the General Prevailing Wage Rates, will be applied to any equipment rental rates.
b) Idle Time of Labor
Compensation for idle time of workers will be determined by the Engineer as “Labor” less any actual productivity
factor of this portion of the work force.
c) Increased Costs of Labor and Materials
Increased costs of labor and materials will be compensated only to the extent such increase was in fact caused by the
suspension, as determined by the Engineer.
Compensation for actual loss due to idle time of either equipment or labor shall not include markup for profit.
The hours for which compensation will be paid will be the actual normal working time during which such delay
condition exists, but will in no case exceed eight hours in any one day.
The days for which compensation will be paid shall be full or partial calendar days, excluding Saturdays, Sundays,
and legal holidays, during the existence of such delay. .--
BP-5
10 - STATE MBE/WBE PROVISIONS -_
CONTRACT PROVISIONS OF THE
STATE WATER RESOURCES CONTROL BOARD (SWRCB)
DIVISION OF CLEAN WATER PROGRAMS
RELATIVE TO THE UTILIZATION OF
MINORITY BUSINESS ENTERPRISE (MBE) AND
WOMEN BUSINESS ENTERPRISE (WBE)
ON CLEAN WATER PROGRAM CONSTRUCTION CONTRACTS IN CALIFORNIA
This document and attachments shall be included by the owner as a contract provision for all construction contracts
exceeding $10,000.
Compliance with the requirements of this document and attachments satisfies the MBEWBE requirements of the U.
S. Environmental Protection Agency and the SWRCB. This document supersedes any conflicting requirements.
Failure to take the five (5) affirmative steps listed under Requirements, Section A, prior to bid opening and to submit
“Minority Business Enterprisernomen Business Enterprise Information” (Attachment B) with the bid shall cause
the bid to be rejected as a non-responsive bid.
DEFINITIONS
BONA FIDE MINORITY BUSINESS ENTERPRISE fMBE) MEANS:
An MBE that has submitted a ”Minority Business Enterprisernomen Business Enterprise Self Certification“
(Attachment A) to, and been accepted as, a bona fide MBE by the owner. In addition, the following requirements
apply:
1. An independent business concern which is at least 5 1% owned and controlled by minority group
member(s) (see definition of Minority Group Member). Ownership and control can be measured by:
a. Responsibility for performance of contract work.
b. Management responsibility.
c. At least 5 1% share of profits and risk.
d. Other data (such as voting rights) that may be related to ownership andor control.
2. In cases where a firm is owned and controlled by a minority woman or women, the percentage may be
credited towards MBE participation or as WBE participation, or allocated, but may not be credited fully
to both.
BONA FIDE WOMEN BUSINESS ENTERPRISE (WBE) MEANS:
A WBE that has submitted Attachment A to, and been accepted as, a bona fide WBE by the owner. In addition, the
following requirements apply:
1. An independent business which is at least 5 1% owned by a woman or women who also control and
operate it.
a. Ownership. Determination of whether a business is at least 5 1% owned by a woman or women shall
be made without regard to community property laws. For example, an otherwise qualified WBE
which is 5 1 % owned by a married woman in a community property state will not be disqualified
because her husband has a 50% interest in her share.
Similarly, a business which is 51% owned by a married man and 49% by an.unmarried woman will
not become a qualified WBE by virtue of his wife‘s 50% interest in his share of the business.
BP-6
b. Control and operation. "Control" means exercising the power to make policy decisions and "operate"
means being actively involved in the day-to-day management of the business.
JOINT VENTURE (JVl .c
A business enterprise formed by a combination of firms under a JV agreement. To qualify as a bona fide
MBENBE, the minority-owned/woman or women owned and controlled firms in the JV must:
1. Satisfy all requirements for bona fide MBENBE participation in their own rights.
In cases where a minority woman or women-owned firm participates in a JV, the percentage may be
credited towards MBE participation or as WBE participation, or allocated, but may not be credited fully
to both.
2. Share a clearly defined percentage of the ownership, management responsibilities, risks, and profits of
the JV. Only this percentage will be credited towards the MBENBE goal.
MINORITY GROUP MEMBERS
A minority group member is an individual who is a citizen of the United States and one of the following:
1. Native Americans consist of American Indian, Eskimo, Aleut, and native Hawaiian.
2. Black Americans consist of U.S. citizens, other than Hispanic, having origins in any of the black racial
groups of Africa.
.+
,-
3. Asian Pacific Americans consist of U.S. citizens having origins in any of the original peoples of the Far
East, Southeast Asia, and the Indian subcontinent. This area includes, for example, China, Japan,
Korea, the Philippines, Vietnam, Samoa, Guam, the U.S. Trust Temtories of the Pacific, Northern
Marianas, Laos, Cambodia, and Taiwan. The Indian subcontinent takes in the countries of India,
Pakistan, Bangladesh, Sri Lanka, Sikkim. and Bhutan.
4. Hispanic Americans consist of U.S. citizens with origins from Puerto Rico, Mexico, Cuba, or South or
Central America. Only those persons from Central and South American countn'es who are of Spanish
origin, descent, or culture should be included in this category. Persons from Brazil, Guyana, Surinam or
Trinidad, for example, would be classified according to their race and would not necessarily be included
in the Hispanic category. In addition, this category does not include persons from Portugal, who should
be classified according to race.
BROKERAGE MEANS
Buying and selling for others on commission of other fee basis without maintaining a warehouse or other similar
inventory storage facilities (supplier and wholesale arrangements may also fall into this business enterprise
category).
CONSTRUCTION MEANS
Erection, building, alteration, remodeling, improvement or extension of buildings, structures, or other property.
REOUIREMENTS
A. Positive Effort Documentation
The bidder must take affirmative steps prior to bid opening to assure that MBEs and WBEs are used
whenever possible as sources of supplies, construction and services. Failure to take such stem prior to bid
opening and to submit Attachment B with the bid shall cause the bid to be rejected as non-responsive.
Affirmative steps shall be as follows:
1, Including qualified MBEs and WBEs on solicitation lists.
BP-7
2.
3.
4.
5.
The bidder must document that it requested assistance from the Small Business Administration and the
Office of Minority Business Enterprise MBENVBE assistance centers and that this request for assistance
was received by the MBE/WBE assistance centers at least five (5) working days prior to the need for
referrals (see affirmative step no. 5).
Assure that MBEs and WBEs are solicited whenever they are potential sources.
The bidder must document that it has provided invitations to MBENVBE bidders at least seven (7)
working days prior to the need of a bid response.
The bidder must document that invitations were sent to at least three (3) (or all if less than three)
MBENVBE contractors/suppliers for each item of work referred by the MBENBE assistance center(s).
The invitations must adequately specify the item(s) for which sub-bids were requested. The
documentation of the bidder's effort to show positive efforts must indicate a real desire for a positive
response; i.e., certified letter with return receipt requested or telephone call documentation. A regular
letter or an unanswered telephone call is not adequate positive effort.
The bidder must submit to the owner documentation consisting of a list of all sub-bidders for each item
of work that MBEs or WBEs were solicited including dollar amounts for both MBE/WBE and
non-MBENVBE sub-bidders.
Divide total requirements, when economically feasible, into small tasks or quantities to permit maximum
participation of MBEs and WBEs.
A bidder must document that it gave consideration to dividing the contract into small proprietary
portions (paving, electrical, landscaping, etc.). If this was not done, documentation must be submitted
explaining why it could not be done.
Establish delivery schedules, where the requirements of the work permit, which will encourage
participation by MBEs and WBEs.
The bidder must document that it gave consideration to establishing a project schedule which would
allow MBEs and WBEs to bid the work as subcontractors or suppliers. If this is not done, document
reasons why the project schedule, or portions thereof, cannot be modified so as to accommodate
interested MBEs and WBEs.
Use of the services and assistance of the Small Business Administration and the Office of Minority
Business Enterprise of the U. S. Department of Commerce, as appropriate.
The bidder must present documentation that contact was made with both of the offices listed below.
Their services are provided at no cost to the bidder. Do not write. The internet web site contains local
SBA and MBDA centers. The local center may provide the bidder with a listing of MBE/WBE firms. If
a list was not provided, bidder must explain why it was not and describe what MBE/WBE solicitation list
was used.
Small Business Administration:
<http://www.sba.gov>
Office of Minority Business
Enterprise: Regional Office
U.S. Dept. of Commerce
<http://www.mbda.gov>
Government Contracting Office
455 Market Street, Suite 600
San Francisco, CA 94 105
Telephone: (415) 744-8429
Minority Business Development
Agency (MBDA)
San Francisco, CA 941 05
Telephone: (41 5) 744-3001
In addition, the bidder is encouraged to procure supplies and services from labor surplus area firms.
x.
BP-8
B. Other Requirements
1.
2.
3.
4.
5.
6.
7.
The apparent successful low bidder must submit documentation showing that, prior to bid opening, all
required positive efforts were made. This documentation must be received by the owner within ten (IO)
working days following bid opening (except Attachment B which is to be submitted with the bid).
Failure to submit Attachment B with the bid will cause the bid to be rejected as non-rewonsive.
If the apparent successful low bidder has rejected or considered as non-responsible andlor non-
responsive any low MBE or WBE sub-bidder, a complete explanation must be provided to the owner.
Each MBENBE firm to be utilized must complete the Attachment A, which is to be with the
documentation submitted to the owner by the apparent successful low bidder.
If additional MBENBE subcontracts become necessary after the award of the prime contract,
Attachment B must be provided to the owner by the Prime Contractor within ten (10) working days
following the award of each new subcontract.
Any deviation from the information contained in Attachment B shall not result in a reduction of
MBE/WBE participation without prior approval of the owner.
When brokerage type arrangements are utilized, only the amount of commission or fee will be eligible
for MBE/WBE consideration.
Failure of the apparent low bidder to perform the five affirmative steps prior to bid opening andor to
submit Attachment B with its bid will lead to its bid being declared non-responsive by the owner. The
owner may then award the contract to the next low responsive, responsible bidder meeting the
requirements of these contract provisions. The owner also may rebid the contract.
- C. State's "Fair Share" Obiectives
The SWRCB has established the following fair share objectives for this construction contract:
20 % of the total bid dollar amount of this contract for MBE.
10 % of the total bid dollar amount of this contract for WBE.
(The owner may contact the SWRCB, Division of Clean Water Programs, Design Review Unit at
(916) 227-4588 for questions on the state's fair share objectives.)
D. LocaURegional Obiectives
The owner may have established localhegional objectives and those requirements may be attached if appropriate.
c
BP-9
ATTACHMENT A
MINORITY BUSINESS ENTERPRISE/WOMEN'S BUSINESS ENTERPRISE (MBEWBE)'
SELF CERTIFICATION
STATE WATER RESOURCES CONTROL BOARD
DIVISION OF CLEAN WATER PROGRAMS
Firm Name: Phone:
Address:
Principal Service or Product:
- MBE - WBE
I I
~~~~
- Prime Contractor - Supplier of MateriaYService
- Subcontractor - Broker
I I
- Sole Ownership - Corporation
- Partnership - Joint Venture
I
~
Names of Owners Percent MBE-Ethnic WBE
Ownership Identity'
Additional proofs may be required upon written challenge of this certification by any person or agency.
Falsification of this certification by a firm selected to perform Federally funded work may result in a
determination that the firm is non-responsible and ineligible for future contracts.
Certified by: Title:
(Signature)
Name: Date:
~
Refer to definitions on the next page.
BP- 10
-DEFINITIONS-
MINORITY BUSINESS ENTERPRISENOMEN’S BUSINESS ENTERPRISE (MBENBE)
An MBE or WBE is a business which is at least 5 1 percent owned and controlled by minority group members or by
woman or women. Owners must exercise actual day-to-day management.
MINORITY GROUP MEMBERS
_.-
American Indians
Persons having origins in any of the original peoples of North America. To qualify in this group, a person
must be a citizen of the United States and meet one or more of the following:
(1) Be at least one-fourth Indian descent (as evidenced by registration with the Bureau of Indian
Affairs).
(2) Characteristic Indian appearance and features.
(3) Characteristic Indian name.
(4) Recognition in the community as an Indian.
(5) Membership in a tribe, band or group of American Indians (recognized by the Federal
Government), as evidenced by a tribal enrollment number or similar indication.
Black Americans
U.S. citizens, other than Hispanic, having origins in any of the black racial groups of Africa.
Asian Americans
U.S. citizens having origins in any of the original peoples of the Far East, Southern Asia, the Indian
subcontinent or the Pacific Islands. This area includes, for example, China, Japan, Korea, the Philippine
Islands and Samoa. The Indian subcontinent takes in the countries of India, Pakistan, Bangladesh, Sri
Lanka, Nepal, Sikkim, and Bhutan.
Hispanic Americans
U.S. citizens of Mexican, Puerto Rican, Cuban, or other Spanish culture or origin, regardless of race. Only
those persons from Central and South American countries who are of Spanish origin, descent, or culture
should be included in this category. Persons from Brazil, Guyana, Surinam or Trinidad, for example,
would be classified according to their race and would not .necessarily be included in the Hispanic category.
In addition, the category does not include persons from Portugal, who should be classified according to
race.
American Eskimos and American Aleuts
BP-11
ATTACHMENT B
MINORITY BUSINESS ENTERPRISENOMEN BUSINESS ENTERPRISE INFORMATION
SWRCB DIVISION OF CLEAN WATER PROGRAMS r I
NAME AND ADDRESS (Include ZIP Code, DOB, & SSN)
I LOAN RECIPIENTS NAME I CONTRACT NO. OR SPECIFICATION NO.
MBE WE
I MBE WEE NAME AND ADDRESS (Include ZIP Code, DOB, & SSN)
SUBCONTRACTOR
JOINT VENTURE
SUPPLIEWSERVICE
BROKER
AMOUNT OF CONTRACT PHONE
NAME AND ADDRESS (Include ZIP Code, DOB, & SSN)
SUBCONTRACTOR SUPPLIEWSERVICE
JOINT VENTURE
AMOUNT OF CONTRACT PHONE
MBE WEE
SUBCONTRACTOR SUPPLIEWSERVICE
JOINT VENTURE BROKER
WORK TO BE PERFORMED
NAME AND ADDRESS (Include ZIP Code, DOB, & SSN)
TOTAL MBE AMOUNT: $ TOTAL WBE AMOUNT: $
ACTUAL MBE PARTICIPATION: Yo ACTUAL WBE PARTICIPATION: %
MBE GOAL: % WBE GOAL: %
SIGNATURE OF PERSON
COMPLETING FORM:
AMOUNT OF CONTRACT
TITLE: PHONE: DATE:
:ORM 4700-B (rev 2/98)
PHONE
BP- 12
MBE WE NAME AND ADDRESS (Include ZIP Code, DOB, & SSN)
SUBCONTRACTOR
JOINT VENTURE
SUPPLIEWSERVICE
BROKER
AMOUNT OF CONTRACT PHONE
11 - THE SUBLETTING AND SUBCONTRACTING FAIR PRACTICES ACT
Any person making a bid or offer to perform a contract shall, in his or her bid or offer, set forth the following: -
1) The name and the location of the place of business of each subcontractor who will perform work or labor or
render service to the prime contractor in or about the construction of the work or improvement, or a subcontractor
licensed by the State of California who, under subcontract to the prime contractor, specially fabricates and installs a
portion of the work or improvement according to detailed drawings contained in the plans and specifications, in an
amount in excess of one-half of 1 percent of the prime contractor’s total bid or in the case of bids or offers for the
construction of streets or highways, including bridges in excess of one-half or 1 percent of the prime contractor’s
total bid or ten thousand dollars ($1 O,OOO), whichever is greater.
2) The potion of work that will be done by each subcontractor under this act. The prime contractor shall list
only one subcontractor for each portion of work as is defined by the prime contractor in his or her bid or offer.
These requirements apply to the information required relating to subcontractors certified as minority or women
business enterprises. For purposes of this requirement, “subcontractor” and “prime contractor” shall have the same
meaning as those terms are defined in Section 4 1 13 of the Public Contracts Code.
12 - 40 CFR 60-8.4(b) - EQUAL OPPORTUNITY CLAUSE (in relevant part)
During the performance of this contract the contractor agrees as follows:
(1) The contractor will not discriminate against any employee or applicant for employment because of race, color,
religion, sex, or national origin. The contractor will take affirmative action to ensure that applicants are employed
and that employees are treated during employment without regard to their race, color, religion, sex, or national
origin. Such action shall include, but not be limited to the following: Employment, upgrading, demotion or transfer,
recruitment or recruitment advertising, layoff or termination, rates of pay or other forms of compensation, and
selection for training including apprenticeship. The contractor agrees to post, in conspicuous places available to
employees and applicants for employment, notices to be provided setting forth the provisions of this
nondiscrimination clause.
c
(2) The contractor will, in all solicitations or advertisements for employees placed by or on behalf of the contractor,
state that all qualified applicants will receive considerations for employment without regard to race, color, religion,
sex, or national origin.
(3) The contractor will send, to each labor union or representative of workers with which he has a collective
bargaining agreement or other contract or understanding, a notice to be provided advising the said labor union or
workers representatives of the contractor’s commitments under this section, and shall post copies of the notice in
conspicuous places available to employees and applicants for employment.
(4) The contractor will comply with all provisions of Executive Order 11246 of September 24, 1965, and of the
rules, regulations, and relevant orders of the Secretary of Labor.
(5) The contractor will furnish all information and reports required by Executive Order 11246 of September 24,
1965, and by rules, regulations, and orders of the Secretary of Labor, or pursuant thereto, and will permit access to
his books, records, and accounts by the administering agency and the Secretary of Labor for purposes of
investigation to ascertain compliance with such rules, regulations, and orders.
(6) In the event of the contractor’s noncompliance with the nondiscrimination clauses of this contract or with any
of the said rules, regulations, or orders, this contract may be canceled, terminated, or suspended in whole or in part,
and the contractor may be ineligible for further Government contracts or federally assisted construction contracts in
accordance with procedures authorized in Executive Order 1 1246 or September 24, 1965, and such other sanctions
may be imposed and remedies invoked a s provided in Executive Order 1 1246 of September 24, 1965, or by rule,
regulation, or orders of the Secretary of Labor, or as otherwise provided by law.
c
BP-13
(7) The contractor will include the sentence immediately preceding paragraph (1) and the provisions of paragraphs
(1) through (7) in every subcontract or purchase order unless exempted by rules, regulations, or orders of the
Secretary of Labor issued pursuant to section 204 of Executive Order 1 1246 of September 24, 1965, so that such
provisions will be binding upon each subcontractor or vendor. The contractor will take such action with respect to
any subcontract or purchase order as the administering agency may direct as a means of enforcing such provisions
including sanctions for noncompliance: Provided however, That in the event a contractor becomes involved in, or is
threatened with litigation with a subcontractor or vendor, as a result of such direction by the administering agency,
the contractor may request the United States to enter into such litigation to protect the interests of the United States.
-
13 - NONDISCRIMINATION CLAUSE
NONDISCRTMINATION CLAUSE
1. During the performance of this contract, contractor and its subcontractors shall not unlawfully discriminate
against any employee or applicant for employment because of race, religion, color, national origin,
ancestry, physical handicap, medical condition, marital status, age (over 40) or sex. Contractors and
subcontractors shall insure that the evaluation and treatment of their employees and applicants for
employment are free of such discrimination. Contractors and subcontractors shall comply with the
provisions of the Fair Employment and Housing Act (Government Code Section 12900 et seq.) and the
applicable regulations promulgated thereunder (California Administrative Code, Title 2, Section 7285.0 et
seq.). The applicable regulations of the Fair Employment and Housing Commission implementing
Government Code, Section 12900, set forth in Chapter 5 of Division 4 of Title 2 or the California
Administrative Code are incorporated into this contract by reference and made a part hereof as if set forth
in full. Contractor and its subcontractor shall give written notice of their obligations under this clause to
labor organizations with which they have a collective bargaining or other agreement.
2. This contractor shall include the nondiscrimination and compliance provisions of this clause in all
subcontracts to perform work under the contract.
THE UNDERSIGNED CERTIFIES THAT THE CONTRACTOR WILL COMPLY WITH THE ABOVE
REQUIREMENTS.
CONTRACTOR OR
SUBCONTRACTOR NAME:
CERTIFIED BY:
NAME: TITLE:
SIGNATURE: DATE:
BP-14
14 - 41 CFR 60-4.2
CONSTRUCTION CONTRACTORS--AFFIRMATIVE ACTION REQUIREMENTS (in relevant part)
c Notice of requirement for Afirmative Action to ensure Equal Employment Opportunity (EEO) by Executive Order
1 1246, as amended by Executive Order 11375.
1. The Offeror's or Bidder's attention is called to the "Equal Opportunity Clause" and the "Standard Federal Equal
Employment Specifications" set forth herein.
2. The goals and timetables for minority and female participation, expressed in percentage terms for the contractor's
aggregate workforce in each trade on all construction work in the covered area, are as follows:
Time- Goals for minority participation Goals for female participation
tables for each trade for each trade
For duration of the 16.9% 6.9%
Contract with the City
(Contact SWRCB, Division of Clean Water Programs, at (916) 227-4586 for assistance with the minority goal and
timetables. E-mail <musialr@cwp.swrcb.ca.gov>: Office of Federal Contract Compliance Programs' web site for
compliance issues and preaward registry is <http://www.dol.gov/doWesa/public/ofcp-erg>)
These goals are applicable to all the Contractor's construction work (whether or not it is Federal or federally
assisted) performed in the covered area. If the contractor performs construction work in a geographical area located
outside of the covered area, it shall apply the goals established for such geographical area where the work is actually
performed. With regard to this second area, the contractor also is subject to the goals for both its federally involved
and non-federally involved construction. +
The Contractor's compliance with the Executive Order and the regulations in 41 CFR Part 60-4 shall be based on
its implementation of the Equal Opportunity Clause, specific affirmative action obligations required by the
specifications set forth in 41 CFR 60-4.3(a), and its efforts to meet the goals. The hours of minority and female
employment and training must be substantially uniform throughout the length of the contract, and in each trade, and
the contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The
transfer of minority or female employees or trainees from Contractor to Contractor or from project to project for the
sole purpose of meeting the Contractor's goals shall be a violation of the contract, the Executive Order and the
regulations in 41 CFR Part 60-4. Compliance with the goals will be measured against the total work hours
performed.
3. The Contractor shall provide written notification to the Director of the Office of Federal Contract Compliance
Programs within IO working days of award of any construction subcontract in excess of $10,000 at any tier for
construction work under the contract resulting from this solicitation. The notification shall list the name, address
and telephone number of the subcontractor; employer identification number of the subcontractor; estimated dollar
amount of the subcontract; estimated starting and completion dates of the subcontract; and the geographical area in
which the subcontract is to be performed.
4. As used in this Notice, and in the contract resulting from this solicitation, the "covered area" is (insert
description of the geographical areas where the contract is to be performed giving the state, county and city, if any).
Q 60-4.3 Equal opportunity clauses (in relevant part)
Standard Federal Equal Employment Opportunity Construction Contract
Specifications (Executive Order 1 1246)
BP- 15
1. As used in these specifications:
a. Tovered area" means the geographical area described in the solicitation from which this contract resulted;
b. "Director" means Director, Office of Federal Contract Compliance Programs, United States Department of
Labor, or any person to whom the Director delegates authority;
c. "Employer identification number" means the Federal Social Security number used on the Employer's Quarterly
Federal Tax Return, U.S. Treasury Department Form 941.
d. "Minority" includes:
(i) Black (all persons having origins in any of the Black African racial groups not of Hispanic origin);
(ii) Hispanic (all persons of Mexican, Puerto Rican, Cuban, Central or South American or other Spanish Culture
or origin, regardless of race);
(iii) Asian and Pacific Islander (all persons having origins in any of the original peoples of the Far East,
Southeast Asia, the Indian Subcontinent, or the Pacific Islands); and
(iv) American Indian or Alaskan Native (all persons having origins in any of the original peoples of North
America and maintaining identifiable tribal affiliations through membership and participation or community
identification).
2. Whenever the Contractor, or any Subcontractor at any tier, subcontracts a portion of the work involving any
construction trade, it shall physically include in each subcontract in excess of $10,000 the provisions of these
specifications and the Notice which contains the applicable goals for minority and female participation and which is
set forth in the solicitations from which this contract resulted.
3. If the Contractor is participating (pursuant to 41 CFR 60-4.5) in a Hometown Plan approved by the U.S.
Department of Labor in the covered area either individually or through an association, its affirmative action
obligations on all work in the Plan area (including goals and timetables) shall be in accordance with that Plan for
those trades which have unions participating in the Plan. Contractors must be able to demonstrate their participation
in and compliance with the provisions of any such Hometown Plan. Each Contractor or Subcontractor participating
in an approved Plan is individually required to comply with its obligations under the EEO clause, and to make a
good faith effort to achieve each goal under the Plan in each trade in which it has employees. The overall good faith
performance by other Contractors or Subcontractors toward a goal in an approved Plan does not excuse any covered
Contractor's or Subcontractor's failure to take good faith efforts to achieve the Plan goals and timetables.
4. The Contractor shall implement the specific affirmative action standards provided in paragraphs 7 a through p of
these specifications. The goals set forth in the solicitation from which this contract resulted are expressed as
percentages of the total hours of employment and training of minority and female utilization the Contractor should
reasonably be able to achieve in each construction trade in which it has employees in the covered area. Covered
Construction contractors performing construction work in geographical areas where they do not have a Federal or
federally assisted construction contract shall apply the minority and female goals established for the geographical
area where the work is being performed. Goals are published periodically in the Federal Register in notice form,
and such notices may be obtained from any Office of Federal Contract Compliance Programs office or from Federal
procurement contracting officers. The Contractor is expected to make substantially uniform progress in meeting its
goals in each craft during the period specified.
5. Neither the provisions of any collective bargaining agreement, nor the failure by a union with whom the
Contractor has a collective bargaining agreement, to refer either minorities or women shall excuse the Contractor's
obligations under these specifications, Executive Order 1 1246, or the regulations promulgated pursuant thereto.
6. In order for the non-working training hours of apprentices and trainees to be counted in meeting the goals, such
apprentices and trainees must be employed by the Contractor during the training period, and the Contractor must
have made a commitment to employ the apprentices and trainees at the completion of their training, subject to the
availability of employment opportunities. Trainees must be trained pursuant to training programs approved by the
U.S. Department of Labor.
BP-16
c.
7. The Contractor shall take specific aErmative actions to ensure equal employment opportunity. The evaluation
of the Contractor's compliance with these specifications shall be based upon its effort to achieve maximum results
from its actions. The Contractor shall document these efforts fully, and shall implement affirmative action steps at
least as extensive as the following:
a. Ensure and maintain a working environment free of harassment, intimidation, and coercion at all sites, and in all
facilities at which the Contractor's employees are assigned to work. The Contractor, where possible, will assign
two or more women to each construction project. The Contractor shall specifically ensure that all foremen,
superintendents, and other on-site supervisory personnel are aware of and cany out the Contractor's obligation to
maintain such a working environment, with specific attention to minority or female individuals working at such
sites or in such facilities.
b. Establish and maintain a current list of minority and female recruitment sources, provide written notification to
minority and female recruitment sources and to community organizations when the Contractor or its unions have
employment opportunities available, and maintain a record of the organizations' responses.
c. Maintain a current file of the names, addresses and telephone numbers of each minority and female
off-the-street applicant and minority or female referral from a union, a recruitment source or community
organization and of what action was taken with respect to each such individual. If such individual was sent to the
union hiring hall for referral and was not referred back to the Contractor by the union or, if referred, not employed
by the Contractor, this shall be documented in the file with the reason therefor, along with whatever additional
actions the Contractor may have taken.
d. Provide immediate written notification to the Director when the union or unions with which the Contractor has
a collective bargaining agreement has not referred to the Contractor a minority person or woman sent by the
Contractor, or when the Contractor has other information that the union referral process has impeded the
Contractor's efforts to meet its obligations.
e. Develop on-the-job training opportunities and/or participate in training programs for the area which expressly
include minorities and women, including upgrading programs and apprenticeship and trainee programs relevant to
the Contractor's employment needs, especially those programs hded or approved by the Department of Labor.
The Contractor shall provide notice of these programs to the sources compiled under 7b above.
f. Disseminate the Contractor's EEO policy by providing notice of the policy to unions and training programs and
requesting their cooperation in assisting the Contractor in meeting its EEO obligations; by including it in any
policy manual and collective bargaining agreement; by publicizing it in the company newspaper, annual report,
etc.; by specific review of the policy with all management personnel and with all minority and female employees
at least once a year; and by posting the company EEO policy on bulletin boards accessible to all employees at
each location where construction work is performed.
g. Review, at least annually, the company's EEO policy and affirmative action obligations under these
specifications with all employees having any responsibility for hiring, assignment, layoff, termination or other
employment decisions including specific review of these items with onsite supervisory personnel such as
Superintendents, General Foremen, etc., prior to the initiation of construction work at any job site. A written
record shall be made and maintained identifying the time and place of these meetings, persons attending, subject
matter discussed, and disposition of the subject matter.
h. Disseminate the Contractor's EEO policy externally by including it in any advertising in the news media,
specifically including minority and female news media, and providing written notification to and discussing the
Contractor's EEO policy with other Contractors and Subcontractors with whom the Contractor does or anticipates
doing business.
i. Direct its recruitment efforts, both oral and written, to minority, female and community organizations, to
schools with minority and female students and to minority and female recruitment and training organizations
serving the Contractor's recruitment area and employment needs. Not later than one month prior to the date for
the acceptance of applications for apprenticeship or other training by any recruitment source, the Contractor shall
send written notification to organizations such as the above, describing the openings, screening procedures, and
tests to be used in the selection process.
.-
BP- 17
j. Encourage present minority and female employees to recruit other minority persons and women and, where
reasonable, provide after school, summer and vacation employment to minority and female youth both on the site
and in other areas of a Contractor's work force. -.
k. Validate all tests and other selection requirements where there is an obligation to do so under 41 CFR Part 60-3.
1. Conduct, at least annually, an inventory and evaluation at least of all minority and female personnel for
promotional opportunities and encourage these employees to seek or to prepare for, through appropriate training,
etc., such opportunities.
m. Ensure that seniority practices, job classifications, work assignments and other personnel practices, do not have
a discriminatory effect by continually monitoring all personnel and employment related activities to ensure that
the EEO policy and the Contractor's obligations under these specifications are being carried out.
n. Ensure that all facilities and company activities are Non-Segregated except that separate or single-user toilet
and necessary changing facilities shall be provided to assure privacy between the sexes.
0. Document and maintain a record of all solicitations of offers for subcontracts from minority and female
construction contractors and suppliers, including circulation of solicitations to minority and female contractor
associations and other business associations.
p. Conduct a review, at least annually, of all supervisors' adherence to and performance under the Contractor's
EEO policies and affirmative action obligations.
8. Contractors are encouraged to participate in voluntary associations which assist in fidfilling one or more of their
affirmative action obligations (7a through p). The efforts of a contractor association, joint contractor-union,
contractor-community, or other similar group of which the contractor is a member and participant, may be asserted
as fulfilling any one or more of its obligations under 7a through p of these Specifications provided that the
contractor actively participates in the group, makes every effort to assure that the group has a positive impact on the
employment of minorities and women in the industry, ensures that the concrete benefits of the program are reflected
in the Contractor's minority and female workforce participation, makes a good faith effort to meet its individual
goals and timetables, and can provide access to documentation which demonstrates the effectiveness of actions
taken on behalf of the Contractor. The obligation to comply, however, is the Contractor's and failure of such a
group to fulfill an obligation shall not be a defense for the Contractor's noncompliance.
9. A single goal for minorities and a separate single goal for women have been established. The Contractor,
however, is required to provide equal employment opportunity and to take affirmative action for all minority groups,
both male and female, and all women, both minority and non-minority. Consequently, the Contractor may be in
violation of the Executive Order if a particular group is employed in a substantially disparate manner (for example,
even though the Contractor has achieved its goals for women generally, the Contractor may be in violation of the
Executive Order if a specific minority group of women is underutilized).
10. The Contractor shall not use the goals and timetables or affirmative action standards to discriminate against any
person because of race, color, religion, sex, or national origin.
1 1. The Contractor shall not enter into any Subcontract with any person or firm debarred from Government
contracts pursuant to Executive Order 11246.
12. The Contractor shall carry out such sanctions and penalties for violation of these specifications and of the Equal
Opportunity Clause, including suspension, termination and cancellation of existing subcontracts as may be imposed
or ordered pursuant to Executive Order 1 1246, as amended, and its implementing regulations, by the Office of
Federal Contract Compliance Programs. Any Contractor who fails to carry out such sanctions and penalties shall be
in violation of these specifications and Executive Order 1 1246, as amended.
1 3. The Contractor, in fulfilling its obligations under these specifications, shall implement specific affirmative
action steps, at least as extensive as those standards prescribed in paragraph 7 of these specifications, so as to
achieve maximum results from its efforts to ensure equal employment opportunity. If the Contractor fails to comply
with the requirements of the Executive Order, the implementing regulations, or these specifications, the Director
shall proceed in accordance with 41 CFR 60-4.8.
1.
BP- 18
14. The Contractor shall designate a responsible official to monitor all employment related activity to ensure that
the company EEO policy is being carried out, to submit reports relating to the provisions hereof as may be required
by the Government and to keep records. Records shall at least include for each employee the name, address,
telephone numbers, construction trade, union affiliation if any, employee identification number when assigned,
social security number, race, sex, status (e.g., mechanic, apprentice trainee, helper, or laborer), dates of changes in
status, hours worked per week in the indicated trade, rate of pay, and locations at which the work was performed.
Records shall be maintained in an easily understandable and retrievable form; however, to the degree that existing
records satisfy ths requirement, contractors shall not be required to maintain separate records.
-
15. Nothing herein provided shall be construed as a limitation upon the application of other laws which establish
different standards of compliance or upon the application of requirements for the hiring of local or other area
residents (e.g., those under the Public Works Employment Act of 1977 and the Community Development Block
Grant Program).
15 - ELIMINATION OF SEGREGATED FACILITIES
NOTICE TO PROSPECTIVE FEDERALLY-ASSISTED CONSTRUCTION CONTRACTORS
(a) A Certification of Non-Segregated Facilities, as required by the May 9, 1967 Order (32 F.R. 7439,
May 19, 1967) on Elimination of Segregated Facilities, by the Secretary of Labor, must be submitted prior to the
award of a Federally-assisted construction contract exceeding $10,000 which is not exempt from the provisions of
the Equal Opportunity Clause.
(b) Contractors receiving Federally-assisted construction contract awards exceeding $10,000 which,
are not exempt from the provisions of the Equal Opportunity Clause, will be required to provide for the forwarding
of the following notice to prospective subcontractors for supply and construction contracts where the subcontracts
exceed $10,000 and are not exempt from the provisions of the Equal Opportunity Clause.
NOTICE TO PROSPECTIVE SUBCONTRACTORS OF REQUIREMENT
FOR CERTIFICATION OF NON-SEGREGATED FACILITIES
(a) A Certification of Non-Segregated Facilities, as required by the May 9, 1967 Order (32 F.R. 7439,
May 19, 1967) on Elimination of Segregated Facilities, by the Secretary of Labor, must be submitted prior to the
award of a subcontract exceeding $10,000 which is not exempt from the provisions of the Equal Opportunity Clause.
(b) Contractors receiving subcontract awards exceeding $10,000 which are not exempt from the
provisions of the Equal Opportunity Clause will be required to provide for the forwarding of this notice to
prospective subcontractors for supply and construction contracts where the subcontracts exceed $10,000 and are not
exempt from the provisions of the Equal Opportunity Clause.
BP-19
16 - CERTIFICATION OF NON-SEGREGATED FACILITIES
Environmental Protection Agency Region IX
75 Hawthorne Street
San Francisco, California 94 105
.-
CERTIFICATION OF NON-SEGREGATED FACILITIES
(Applicable to federally assisted construction contracts and related subcontracts exceeding $10,000 which are not
exempt from the Equal Opportunity Clause.)
The federally assisted construction contractor certifies that he does not maintain or provide for his
employees any segregated facilities at any of his establishments, and that he does not permit his employees to
perform their services at any location, under his control, where segregated facilities are maintained. The federally
assisted construction contractor certifies further that he will not maintain or provide for his employees any
segregated facilities at any of his establishments, and that he will not permit his employees to perform their services
at any location, under his control, where segregated facilities are maintained. The federally assisted construction
contractor agrees that a breach of this certification is a violation of the Equal Opportunity Clause in this contract. As
used in this certification, the term “segregated facilities” means any waiting rooms, work areas, restrooms and wash
rooms, restaurants and other eating areas, time clocks, locker rooms and other storage or dressing areas,
transportation, and housing facilities provided for employees which are segregated by explicit directive or are in fact
segregated on the basis of race, creed, color, or national origin, because of habit, local custom, or otherwise. The
federally assisted construction contractor agrees that (except where he has obtained identical certifications from
proposed subcontractors for specified time period) he will obtain identical certifications from proposed
subcontractors prior to the award of subcontracts exceeding $10,000 which are not exempt form the provisions of
the Equal Opportunity Clause, and that he will retain such certifications in his files.
Signature Date
Name and Title of Signer (Please Type)
Note: The penalty for making false statements in offers is prescribed in 18 U.S.C. 1001.
BP-20
17 - DRUG-FREE WORKPLACE CERTIFICATION
DRUG-FREE WORKPLACE CERTIFICATION
CONTRACTOWAPPLICANT:
The contractor or applicant named above hereby certifies compliance with Government Code Section 8355 in
matters relating to providing a drug-free workplace. The above named contractor or applicant will:
1. Publish a statement notifying employees that unlawful manufacture, distribution, dispensation, possession, or
use of a controlled substance is prohibited and specifying actions to be taken against employees for violations,
as required by Government Code Section 8355(a).
Establish a Drug-Free Awareness Program as required by Government Code Section 8355(b), to inform
employees about all of the following:
2.
(a) The dangers of drug abuse in the workplace,
(b) The person’s or organization’s policy of maintaining a drug-free workplace,
(c) Any available counseling, rehabilitation and employee assistance programs, and
(d) Penalties that may be imposed upon employees for drug abuse violations.
3. Provide as required by Government Code Section 8355(c), that every employee who works on the proposed
contract or loan:
(a) Will receive a copy of the company’s drug-free policy statement, and
(b) Will agree to abide by the terms of the company’s statement as a condition of employment on the contract
-
or loan.
CERTIFICATION
I, the oficial named below, hereby swear that I am duly authorized legally to bind the contractor or loan recipient to
the above described certification. I am fully aware that this certification, executed on the date and in the county
below, is made under penalty of perjury under the laws of the State of California.
OFFICIAL’S NAME:
DATE EXECUTED: EXECUTED IN COUNTY OF:
CONTRACTOWAPPLICANT SIGNATURE:
TITLE:
BP-2 1
18 - PART 32-GOVERNMENT WIDE DEBARMENT AND SUSPENSION (NONPROCUREMENT) AND
GOVERNMENT WIDE REOUIREMENTS FOR DRUG-FREE WORKPLACE (GRANTS)
Appendix A to Part 32--Certification Regarding Debarment, Suspension, and Other Responsibility Matters--Primary
Covered Transactions
Instructions for Certification
1. By signing and submitting this proposal, the prospective primary participant is providing the certification set out
below.
2. The inability of a person to provide the certification required below will not necessarily result in denial of
participation in this covered transaction. The prospective participant shall submit an explanation of why it cannot
provide the certification set out below. The certification or explanation will be considered in connection with the
department or agency's determination whether to enter into this transaction. However, failure of the prospective
primary participant to furnish a certification or an explanation shall disqualify such person from participation in this
transaction.
3. The certification in this clause is a material representation of fact upon which reliance was placed when the
department or agency determined to enter into this transaction. If it is later determined that the prospective primary
participant knowingly rendered an erroneous certification, in addition to other remedies available to the Federal
Government, the department or agency may terminate this transaction for cause or default.
4. The prospective primary participant shall provide immediate written notice to the department or agency to which
this proposal is submitted if at any time the prospective primary participant learns that its certification was erroneous
when submitted or has become erroneous by reason of changed circumstances.
5. The terms covered transaction, debarred, suspended, ineligible, lower tier covered transaction, participant,
person, primary covered transaction, principal, proposal, and voluntarily excluded, as used in this clause, have the
meanings set out in the Definitions and Coverage sections of the rules implementing Executive Order 12549. You
may contact the department or agency to which this proposal is being submitted for assistance in obtaining a copy of
those regulations.
6. The prospective primary participant agrees by submitting this proposal that, should the proposed covered
transaction be entered into, it shall not knowingly enter into any lower tier covered transaction with a person who is
proposed for debarment under 48 CFR part 9, subpart 9.4, debarred, suspended, declared ineligible, or voluntarily
excluded from participation in this covered transaction, unless authorized by the department or agency entering into
this transaction.
7. The prospective primary participant further agrees by submitting this proposal that it will include the clause
titled "Certification Regarding Debarment, Suspension, Ineligibility and Voluntary Exclusion-Lower Tier Covered
Transaction," provided by the department or agency entering into this covered transaction, without modification, in
all lower tier covered transactions and in all solicitations for lower tier covered transactions.
8. A participant in a covered transaction may rely upon a certification of a prospective participant in a lower tier
covered transaction that it is not proposed for debarment under 48 CFR part 9, subpart 9.4, debarred, suspended,
ineligible, or voluntarily excluded from the covered transaction, unless it knows that the certification is erroneous. A
participant may decide the method and frequency by which it determines the eligibility of its principals. Each
participant may, but is not required to, check the List of Parties Excluded from Federal Procurement and Non-
procurement Programs.
9. Nothing contained in the foregoing shall be construed to require establishment of a system of records in order to
render in good faith the certification required by this clause. The knowledge and information of a participant is not
required to exceed that which is normally possessed by a prudent person in the ordinary course of business dealings.
10. Except for transactions authorized under paragraph 6 of these instructions, if a participant in a covered
transaction knowingly enters into a lower tier covered transaction with a person who is proposed for debarment
under 48 CFR part 9, subpart 9.4, suspended, debarred, ineligible, or voluntarily excluded from participation in this
BP-22
transaction, in addition to other remedies available to the Federal Government, the department or agency may
terminate this transaction for cause or default.
Certification Regarding Debarment, Suspension, and Other Responsibility
Matters--Primary Covered Transactions
-
(1) The prospective primary participant certifies to the best of its knowledge and belief, that it and its principals:
(a) Are not presently debarred, suspended, proposed for debarment, declared ineligible, or voluntarily excluded by
any Federal department or agency;
(b) Have not within a three-year period preceding this proposal been convicted of or had a civil judgment rendered
against them for commission of fraud or a criminal offense in connection with obtaining, attempting to obtain, or
performing a public (Federal, State or local) transaction or contract under a public transaction; violation of Federal
or State antitrust statutes or commission of embezzlement, theft, forgery, bribery, falsification or destruction of
records, making false statements, or receiving stolen property;
(c) Are not presently indicted for or otherwise criminally or civilly charged by a governmental entity (Federal,
State or local) with commission of any of the offenses enumerated in paragraph (l)(b) of this certification; and
(d) Have not within a three-year period preceding this applicatiodproposal had one or more public transactions
(Federal, State or local) terminated for cause or default.
(2) Where the prospective primary participant is unable to certify to any of the statements in this certification, such
prospective participant shall attach an explanation to this proposal.
Appendix B to Part 32--Certification Regarding Debarment, Suspension, Ineligibility and Voluntary
Exclusion--Lower Tier Covered Transactions
Instructions for Certification
1. By signing and submitting this proposal, the prospective lower tier participant is providing the certification set c
out below.
2. The certification in this clause is a material representation of fact upon which reliance was placed when this
transaction was entered into. If it is later determined that the prospective lower tier participant knowingly rendered
an erroneous certification, in addition to other remedies available to the Federal Government the department or
agency with which this transaction originated may pursue available remedies, including suspension and/or
debarment .
3. The prospective lower tier participant shall provide immediate written notice to the person to which this proposal
is submitted if at any time the prospective lower tier participant learns that its certification was erroneous when
submitted or had become erroneous by reason of changed circumstances.
4. The terms covered transaction, debarred, suspended, ineligible, lower tier covered transaction, participant,
person, primary covered transaction, principal, proposal, and voluntarily excluded, as used in this clause, have the
meaning set out in the Definitions and Coverage sections of rules implementing Executive Order 12549. You may
contact the person to which this proposal is submitted for assistance in obtaining a copy of those regulations.
5. The prospective lower tier participant agrees by submitting this proposal that, should the proposed covered
transaction be entered into, it shall not knowingly enter into any lower tier covered transaction with a person who is
proposed for debarment under 48 CFR part 9, subpart 9.4, debarred, suspended, declared ineligible, or voluntarily
excluded from participation in this covered transaction, unless authorized by the department or agency with which
this transaction originated.
6. The prospective lower tier participant further agrees by submitting this proposal that it will include this clause
titled "Certification Regarding Debarment, Suspension, Ineligibility and Voluntary Exclusion-Lower Tier Covered
Transaction," without modification, in all lower tier covered transactions and in all solicitations for lower tier
covered transactions.
-
BP-23
7. A participant in a covered transaction may rely upon a certification of a prospective participant in a lower tier
covered transaction that it is not proposed for debarment under 48 CFR part 9, subpart 9.4, debarred, suspended,
ineligible, or voluntarily excluded from covered transactions, unless it knows that the certification is erroneous. A
participant may decide the method and frequency by which it determines the eligibility of its principals. Each
participant may, but is not required to, check the List of Parties Excluded from Federal Procurement and
Nonprocurement Programs.
-
8. Nothing contained in the foregoing shall be construed to require establishment of a system of records in order to
render in good faith the certification required by this clause. The knowledge and information of a participant is not
required to exceed that which is normally possessed by a prudent person in the ordinary course of business dealings.
9. Except for transactions authorized under paragraph 5 of these instructions, if a participant in a covered
transaction knowingly enters into a lower tier covered transaction with a person who is proposed for debarment
under 48 CFR part 9, subpart 9.4, suspended, debarred, ineligible, or voluntarily excluded from participation in this
transaction, in addition to other remedies available to the Federal Government, the department or agency with which
this transaction originated may pursue available remedies, including suspension andor debarment.
Certification Regarding Debarment, Suspension, Ineligibility and Voluntary
Exclusion--Lower Tier Covered Transactions
(1) The prospective lower tier participant certifies, by submission of this proposal, that neither it nor its principals
is presently debarred, suspended, proposed for debarment, declared ineligible, or voluntarily excluded from
participation in this transaction by any Federal department or agency.
(2) Where the prospective lower tier participant is unable to certify to any of the statements in this certification,
such prospective participant shall attach an explanation to this proposal.
19 - RESPONSIBILITY FOR REMOVAL, RELOCATION, OR PROTECTION OF EXISTING
UTILITIES; CONTRACTS AND PROVISIONS
GOVERNMENT CODE SECTION 42 1 5 (in relevant part)
The contract documents shall include provisions to compensate the contractor for the costs of locating, repairing
damage not due to the failure of the contractor to exercise reasonable care, and removing or relocating such utility
facilities not indicated in the plans and specifications with reasonable accuracy, and for equipment on the project
necessarily idled during such work. The contract documents shall include provisions that the contractor shall not be
assessed liquidated damages for delay in completion ofthe project, when such delay was caused by the failure of the
public agency or the owner of the utility to provide for removal or relocation of such utility facilities. (1974)
20 - SUBMITTING OF BIDS AND AGREEING TO ASSIGN
GOVERNMENT CODE SECTION 4552 (in relevant part)
In submitting a bid to a public purchasing body, the bidder offers and agrees that if the bid is accepted, it will
assign to the purchasing body all rights, title, and interest in and to all causes of action it may have under Section 4
of the Clayton Act (I5 U.S. C. Sec. 15) or under the Cartwright Act (Chapter 2 (commencing with Section 16700) of
Part 2 of Division 7 of the Business and Professions Code), arising from purchases of goods, materials, or services
by the bidder for sale to the purchasing body pursuant to the bid. Such assignment shall be made and become
effective at the time the purchasing body tenders final payment to the bidder. (1978)
BP-24
2 1 - NON-COLLUSION AFFIDAVIT
PUBLIC CONTRACTS CODE SECTION 7106
NON-COLLUSION AFFIDAVIT
TO BE EXECUTED BY BIDDER AND SUBMITTED WITH BID
State of California
County of ss
; being first duly sworn, deposes and says that he or she is
of the party making the
foregoing bid, that the bid is not made in the interest of, or on behalf of, any undisclosed person, partnership,
company, association, organization, or corporation; that the bid is genuine and not collusive or sham; that the bidder
has not directly or indirectly colluded, conspired, connived, or agreed with any bidder or anyone else to put in a
sham bid, or that anyone shall refrain from bidding; that the bidder has not in any manner, directly or indirectly,
sought by agreement, communication, or conference, with anyone to fix the bid price of the bidder or any other
bidder, or to fix any overhead, profit, or cost element of the bid price, or of that of any other bidder, or to secure any
advantage against the public body awarding the contract of anyone interested in the proposed contract; that all
statements contained in the bid are true; and, further, that the bidder has not, directly or indirectly, submitted his or
her bid price or any breakdown thereof, or the contents thereof, or divulged information or data relative thereto, or
paid, and will not pay, any fee to any corporation, partnership, company association, organization, bid depository, or
to any member or agent thereof the effectuate a collusive or sham bid.
personally known to me OR proved to me on the basis of satisfactory evidence to be the person(s) whose name(s)
islare subscribed to the within instrument and acknowledged to me that helshelthey executed the same in
his/her/their authorized capacity(ies), and that by hislherhheir signatures(s) on the instrument the person(s), or entity
upon behalf of which the person(s) acted, executed the instrument.
+-
Subscribed and sworn to before me on
(Notary Public)
BP-25
Minority Participation Goals for California
Affirmative ActiodEqual Employment Opportunity for Construction Contractors Aggregate Work Force
Standard Metropolitan Statistical Area (SMSA) - 41 CFR 960 - 4.6
All areadall trades Female participation goal 6.9%
Area minority participation Goal (YO)
174 Redding:
Non-SMSA 6.8 Lassen; Modoc; Plumas; Shasta;
Siskiyou; Tehema
175 Eureka:
Non-SMSA Counties 6.6 Del Norte; Humboldt; Trinity
176 San Francisco-Oakland-San Jose: SMSA Counties:
7 120 Salinas-Seaside-Monterev 28.9 Monterey
7360 San Francisco-Oakland 26.6 Alameda; Contra Costa; Marin;
San Francisco; San Mateo
7400 SanJose 19.6 Santa Clara
7485 SantaCruz 14.9 Santa Cruz
7500 Santa Rosa 9.1 Sonoma.
8720 Valleio-Fanfield-Naoa 17.1 Napa; Solano
Non-SMSA Counties 23.2 Lake; Mendocino; San Benito
177 Sacramento: SMSA Counties:
6920 Sacramento 16.1
Placer; Sacramento; Yo10
Non-SMSA Conuties 14.3 Butte; Colusa; El Dorado; Glenn; Nevada; Sierra; Sutter; Yuba
178 Stockton-Modesto:
SMSA Counties:
5170 Modesto 12.3
8120 Stockton 24.3
Stanislaus
San Joaquin
Non-SMSA Counties 19.8
Alpine; Amador; Calaveras; Mariposa;
Merced; Tuolumne
Area minority participation Goal (Yd
179 Fresno-Bakersfield: SMSA Counties:
0680 Bakersfield 19.1
2840 Fresno 26.1 Fresno
Non-SMSA Counties 23.6
Kings; Madera; Tulare
Kern
180 Los Angeles:
SMSA Counties:
0360 Anaheim-Santa Ana-Garden Grove 11.9
4480 Los Andes-Lone Beach 26.3
6000 Oxnard-Simi Valley-Ventura 21.5
6780 Riverside-San Bernardino-Ontario 19.0
7480 Santa Barbara-Santa Maria-LomDoc 19.7
Orange
Los Angeles
Ventura.
Riverside; San Bemardino.
Santa Barbara
Non-SMSA Counties 24.6 Inyo; Mono; San Luis Obisbo
181 San Diego:
SMSA Counties:
7320 San Diego 16.9 San Diego
Non-SMSA Counties 16.2 Imperial
BP-26
23 - LABOR CODE SECTION 6500 _c
6500.
injury, the division shall require the issuance of a permit prior to the initiation of any practices, work, method,
operation, or process of employment. The permit requirement of this section is limited to employment or places of
employment that are any of the following:
(a) For those employments or places of employment that by their nature involve a substantial risk of
(1) required to descend.
(2) the equivalent height.
(3) equivalent height.
(4) This subdivision does not apply to motion picture, television, or theater stages or sets, including, but not
(b)
Construction of trenches or excavations that are five feet or deeper and into which a person is
The construction of any building, structure, falsework, or scaffolding more than three stories high or
The demolition of any building, structure, falsework, or scaffold more than three stories hgh or the
The underground use of diesel engines in work in mines and tunnels.
limited to, scenery, props, backdrops, flats, greenbeds, and grids.
stages or sets, if there has occurred within any one prior calendar year in any combination at separate locations three
serious injuries, fatalities, or serious violations related to the construction or demolition of sets more than 36 feet in
height for the motion picture, television, and theatrical production industry.
An annual permit shall be required for employers who construct or dismantle motion picture, television, or
theater stages or sets that are more than three stories or the equivalent height. A single permit shall be required under
this subdivision for each employer, regardless of the number of locations where the stages or sets are located. An
employer with a currently valid annual permit issued under this subdivision shall not be required to provide notice to
the division prior to commencement of any work activity authorized by the permit. The division may adopt
procedures to permit employers to renew by mail the permits issued under this subdivision. For purposes of this
subdivision, "motion picture, television, or theater stages or sets" include, but are not limited to, scenery, props,
backdrops, flats, greenbeds, and grids.
On or after January 1,2000, this subdivision shall apply to motion picture, television, or theater
-
24 - PUBLIC CONTRACT CODE SECTION 7 105
7 105.
cost of repairing or restoring damage to the work, which damage is determined to have been proximately caused by
an act of God, in excess of 5 percent of the contracted amount, provided, that the work damaged is built in
accordance with accepted and applicable building standards and the plans and specifications of the awarding
authority. However, contracts may include provisions for terminating the contract. The requirements of this section
shall not be mandatory as to construction contracts financed by revenue bonds. This section shall not prohibit a
public agency from requiring that a contractor obtain insurance to indemnify the public agency for any damage to
the work caused by an act of God if the insurance premium is a separate bid item. If insurance is required, requests
for bids issued by public agencies shall set forth the amount of the work to be covered and the contract resulting
from the requests for bids shall require that the contractor furnish evidence of satisfactory insurance coverage to the
public agency prior to execution of the contract.
(a) Construction contracts of public agencies shall not require the contractor to be responsible for the
(b)
(1)
For the purposes of this section:
"Public agency" shall include the state, the Regents of the University of California, a city, county,
district, public authority, public agency, municipal utility, and any other political subdivision or public corporation
of the state.
"Acts of God" shall include only the following occurrences or conditions and effects: earthquakes in
excess of a magnitude of 3.5 on the Richter Scale and tidal waves.
Public agencies may make changes in construction contracts for public improvements in the course
of construction to bring the completed improvements into compliance with environmental requirements or standards
established by state and federal statutes entered into. The contractor shall be paid for the changes in accordance with
the provisions of the contract governing payment for changes in the work or, if no provisions are set forth in the
contract, payment shall be as agreed to by the parties.
include the power, by mutual consent of the contracting parties, to terminate, amend, or modify any contract within
the scope of such authority.
(2)
(c)
ZL (d) (1) Where authority to contract is vested in any public agency, excluding the state, the authority shall
BP-27
(2) Paragraph (I) shall not apply to contracts entered into pursuant to any statute expressly requiring that
contracts be let or awarded on the basis of competitive bids. Contracts of public agencies, excluding the state,
required to be let or awarded on the basis of competitive bids pursuant to any statute may be terminated, amended,
or modified only if the termination, amendment, or modification is so provided in the contract or is authorized under
provision of law other than this subdivision. The compensation payable, if any, for amendments and modifications
shall be determined as provided in the contract. The compensation payable, if any, in the event the contract is so
terminated shall be determined as provided in the contract or applicable statutory provision providing for the
termination.
(3) at the discretion of the public agencies.
Contracts of public agencies may include provisions for termination for environmental considerations
25 - PUBLIC CONTRACT CODE SECTION 9203
9203.
improvement of any public structure, building, road, or other improvement, of any kind which will exceed in cost a
total of five thousand dollars ($5,000), shall be made as the legislative body prescribes upon estimates approved by
the legislative body, but progress payments shall not be made in excess of 95 percent of the percentage of actual
work completed plus a like percentage of the value of material delivered on the ground or stored subject to, or under
the control of, the local agency, and unused. The local agency shall withhold not less than 5 percent of the contract
price until final completion and acceptance of the project. However, at any time after 50 percent of the work has
been completed, if the legislative body finds that satisfactory progress is being made, it may make any of the
remaining progress payments in full for actual work completed.
to a twenty-five thousand dollar ($25,000) limit for purposes of subdivision (a).
(a) Payment on any contract with a local agency for the creation, construction, alteration, repair, or
(b) Notwithstanding the dollar limit specified in subdivision (a), a county water authority shall be subject
BP-28
TECHNICAL
S PEC I FI CATIONS
CARLSBAD MUNICIPAL WATER DISTRICT - EL CAMINO REAL (PAR to CASSIA) 24-INCH AND 30-INCH DOMESTIC WATER AND
20-INCH RECYCLED WATER TRANSMISSION MAINS
<
TABLE OF CONTENTS
Section No. Title
DIVISION 1: GENERAL REQUIREMENTS
rc
01 001
01 002
01 005
01 01 0
01011
01 025
01 040
01 047
01 048
01 200
01 300
01 31 0
01 340
01 400
01410
01 500
01 520
01 530
01 550
01 570
01 580
01 590
01 600
01 61 0
01 630
01 700
01710
01 720
01 730
City of Carlsbad
03/04 (DBE)
Standard Drawings, Standard Specifications and Approved Materials List
Contractor’s Insurance Certification
Coordination with Design Engineer and Owner
Summary of Work
General Construction Sequence
Measurement and Payment
Coordination
Connections to Existing Facilities
Special Construction Conditions and Procedures - General
Project Meetings
Shop Drawing Submittals
Progress Schedule, Submittal Schedule, and Schedule of Values
Shop Drawing, Product Data and Samples
Quality Control
Testing and Inspection of Earthwork and Concrete
Construction Facilities and Temporary Controls
Maintenance of Traffic and Detours
Protection of Existing Utilities
Traffic Control and Re-Striping
Maintenance and Protection of Traffic
Project Identification and Signs
Field Offices and Sheds
Material and Equipment
SupplierWManufacturer’s Special Services
Product Options and Substitutions
Contract Closeout
Cleaning and Final Cleaning
Record Drawings
Operating and Maintenance Data and Training
-_
ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
Table of Contents - 1 of 2
Section No. Title
DIVISION 2: SITE WORK
021 30
02223 Trenching, Backfilling and Compacting
02225 Utility Crossings
0251 0 Asphaltic Concrete Pavement
Removal and Resurfacing of Pavement Surfaces
DIVISION 3: CONCRETE
03300 Concrete Construction
DIVISION 9: FINISHES
09870
09900 Painting and Coating
09902 Petrolatum Wax Tape Coating
Tape Wrap and Concrete Mortar Coating
DIVISION 13: CATHODIC PROTECTION
131 20 Cathodic Protection
DIVISION 15: MECHANICAL
15000
15040 Testing, Flushing and Disinfection
15056
15064
15066
15076
15092
151 00 Valves
General Piping System and Appurtenances
Ductile Iron Pipe and Fittings
PVC Pressure Pipe and Fittings (AWWA C900)
PVC Pressure Pipe and Fittings (AWWA C905)
Cement Mortar-Lined and Coated Steel Pipe
Miscellaneous Couplings, Pipe and Appurtenances
City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains Table of Contents - 2 of 2
c
SECTION 01 001
STANDARD DRAWINGS, STANDARD SPECIFICATIONS
AND APPROVED MATERIALS LIST
PART 1 - GENERAL
1 .I Standard Specifications and Standard Drawinas
A. Standard Specifications, Standard Drawings and Approved Materials List shall be
as described in these specifications and the Carlsbad Municipal Water District's
Rules and Regulations for the Construction of Public Potable Water Mains,
current edition and Reclamation Rules and Regulations for Reclaimed Water
Mains, current edition.
1.2 Reference Standards
A. Standards listed as "Reference Standards" in the various sections of these
contract documents are hereby incorporated into this specification by reference.
B. Referenced documents shall include all revisions, amendments, supplements or
addenda issued on or before the date of advertising for bids.
C. The Carlsbad Municipal Water District Standards and Standard Drawings are
incorporated into these contract documents by their reference herein and will be
enforced unless superseded by the project specifications or specific details of the
contract documents.
1.3 Approved Materials List
A. All the material used on this project, including pipe, valves, couplings etc., shall be
in accordance with items listed in these specifications or as indicated in the
Carlsbad Municipal Water District's Rules and Regulations for the Construction of
Public Potable Water Mains, current edition and Reclamation Rules and
Regulations for Reclaimed Water Mains, current edition.
B. Materials not listed in these specifications must be submitted for the District's
approval and must be accepted for use on this project prior to contract award.
PART 2 - PRODUCTS (Not applicable)
PART 3 - EXECUTION (Not applicable)
rc
END OF SECTION
City of Carlsbad
03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01 001 Standard Drawings, Standard Specifications, and Approved Materials List - 1 of 1
SECTION 01 002
1 CONTRACTOR'S INSURANCE CERTl FlCATlON
PART 1 - GENERAL
1.1 Insurance and Indemnification
The Contractor, by entering into a contract with the Carlsbad Municipal Water District for the
El Camino Real 24-Inch and 30-Inch Domestic Water and 20-Inch Recycled Water
Transmission Mains, certifies and guarantees to the District that the insurance which the
Contractor furnishes for the contract will provide for the following:
The Contractor shall hold harmless, indemnify and defend Daniel Boyle
Engineering (DBE), his consultants, and each of their officers, agents and
employees from any and all liability, claims, losses or damage arising out of or
alleged to arise from the Contractor's negligence in the pedormance of the Work
described in the construction contract documents, but not including liability that
may be due to the sole negligence of DBE, his consultants, or his officers, agents
and employees. Furthermore, the Contractor shall provide
comprehensive/commercial general liability insurance, including completed
operations and contractual liability, with the latter coverage sufficient to insure the
Contractor's indemnity, as above required; and, such insurance will include DBE,
his consultants, and each of his officers, agents, and employees as additional
insureds. -
PART 2 - PRODUCTS (Not applicable)
PART 3 - EXECUTION (Not applicable)
END OF SECTION
City of Carlsbad
03/04 (DBE)
ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01 002 - Contractor's Insurance/Certification - 1 of 1
SECTION 01 005
COORDINATION WITH DESIGN ENGINEER AND OWNER
PART 1 - GENERAL
1.1 District / Owner
CARLSBAD MUNICIPAL WATER DISTRICT
1635 FARADAY AVENUE
CARLSBAD, CA 92008
Telephone: (760) 602-2748
Project Manager: Mr. Dave Ahles
1.2 Desiqn Engineer
A. The engineering firm that is responsible for preparation of the Plans and
Specifications is Daniel Boyle Engineering, Inc.
Daniel Boyle Engineering
3142 Vista Way, Suite 303
Oceanside, CA 92056
(760) 433-871 0
(760) 433-9709 (FAX)
Contact: Mr. Daniel G. Smith
Mr. Robert Satchel1
1.3 Lines of Communication
A. The lines of communication between the Contractor, the Design Engineer and the
Owner shall be defined as part of the Pre-Construction Conference. Contractor
shall adhere to the direction regarding this matter that is given to him at that time.
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION (Not Applicable)
City of Carlsbad
03/04 (DBE)
END OF SECTION
ECR (PAR to Cassia) Domestic 8, Recycled Water Transmission Mains
01005 - Coordination with Design Engineer and Owner - 1 of 1
SECTION 01 01 0
SUMMARY OF WORK
PART 1 - GENERAL
1.1 Work Covered by Contract Documents
A. The Work generally includes, but is not limited to, furnishing products, labor, tools,
transportation, and services to construct the following:
1. Pavement removal and replacement, traffic control and coordination with utility
companies for locating their facilities.
2. Construction of 24-inch and 30-inch domestic water transmission mains with
connections and appurtenances as described in the plans.
3. Construction of 30-inch, 20-inch, 12-inch and 8-inch recycled water main stub-
out laterals with connections and appurtenances as described in the plans.
4. Testing disinfection and placing into service of domestic water transmission
mains.
5. Construction of 20-inch and 18-inch recycled water transmission mains with
connections and appurtenances as described in the plans.
6. Installing new recycled water irrigation service laterals.
7. Testing, disinfection and placing into service of recycled water transmission
mains.
8. Connections to existing recycled water pipelines as required to place new
mains in service.
1.2 Proiect Location
A. The Project is located in Carlsbad, California, generally along El Camino Real
between Palomar Airport Road and Cassia Road and along Cassia Road to a
point 450 feet west of El Camino Real.
6. Conditions at the Project site are as follows:
Ground Elevation: 285 - 325 feet MSL
Typical Temperature Range: 31 O - 11 0" F
,---
City of Carlsbad
03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01010 - Summary of Work - 1 of 3
1.3 Related Work
A.
B.
C.
D.
E.
Section 01 01 1 : General Construction Sequence
Section 01 048: Special Construction Conditions and Procedures - General
Section 01 700: Contract Closeout
Section 01710: Cleaning and Final Cleaning
Section 01 730: Operating and Maintenance Data and Training
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION
3.1 Work Sequence
A. The general sequence of Work shall be as follows:
1.
2.
3.
4.
5.
6.
7.
8.
9.
City of Carlsbad
03/04 (DBE)
Before beginning Work, coordinate with servicing electrical utility regarding
electric service to site. Obtain required permits, licenses and construction
easements. Call Underground Service Alert and utilities to obtain staking
and marking of buried utilities. Submit proposed schedule of Work,
insurance and bonds.
Take pre-construction photographs.
Pothole points-of-connection to existing water facilities, existing utilities
crossing the pipeline alignment and those parallel to it within 5 feet (from
outside of pipe).
Submit shop drawings, pipeline lay diagrams and other submittals.
Begin manufacturing and shipping materials and equipment after receiving
submittals marked "No Exception Taken" or "Make Corrections Noted".
Complete Work according to proposed Work schedule.
Perform testing and disinfection.
Finalize clean up and restore construction areas.
Provide warranty as specified.
-
-.
ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01 01 0 - Summary of Work - 2 of 3
3.2 Contractor Use of Premises
rc
A. The following facilities shall remain operational during construction of this project:
1. Existing water facilities. Shut downs only permitted under observation of
Water Department personnel and according to schedule of required
shutdowns.
2. Install approved signs, barricades and lights necessary to ensure public
safety and safety of Owners operators and personnel. Provide plates
across ditches to enable safe access of Owner's personnel to facilities or the
public across excavations within public right-of-way that can not be
backfilled at the end of the day.
END OF SECTION
,-
City of Carlsbad
03/04 (DBE)
ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01 01 0 - Summary of Work - 3 of 3
SECTION 01 01 1
GENERAL CONSTRUCTION SEQUENCE
PART 1 - GENERAL
1.1 Scope
A. This section describes a general sequence of construction that the Contractor
shall follow. The general order for the majority of the work performed shall be
determined by the Contractor and a schedule shall be submitted to the Owner for
approval. The construction sequence described herein has the following goal:
To construct the transmission mains expeditiously, in accordance with the
contract documents, with minimum disruption to traffic flow on El Camino Real
and Cassia Road.
1.2 Requirements Covered in Other Specification Sections
A.
B. Section 01 040: Coordination
C.
Section 01 010: Summary of Work
c Section 01 048: Special Construction Conditions and Procedures - General
1.3 General Construction Sequence
.-
Task 1 :
Task 2:
Task 3:
Task 4:
Task 5:
Task 6:
Task 7:
Task 8:
Task 9:
City of Carlsbad
03/04 (DBE)
Pothole utilities - crossings, connections and potential conflicts for
domestic water transmission mains.
Submit shop drawings for domestic water pipelines including pipeline
lay diagrams for 24-inch and 30-inch steel pipe.
Pothole utilities - crossings, connections and potential conflicts for
recycled water transmission mains.
Construct proposed domestic water main piping.
Complete testing and disinfection of piping of domestic water main.
Complete connection to existing domestic water mains.
Place new domestic water pipeline into service.
Submit shop drawings and pipeline lay diagrams for 18-inch and 20-
inch AWWA C-905 PVC pipe. Shop drawings for any other necessary
submittals specified herein.
Construct proposed recycled water main piping and appurtenances.
ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01 01 1 - General Construction Sequence - 1 of 2
Task 1 0:
Task 11:
Task 12:
Task 13:
Task 14:
Task 15:
Complete flushing, testing, and disinfection of piping of recycled water
mains.
Complete connection to existing recycled water mains.
Place new recycled water pipelines into service.
Complete surface repair for domestic and recycled alignment.
Complete site cleanup.
Submit as-builts to the City Inspector.
_,
1.4 Scheduling
Prior to starting construction, the Contractor shall submit a fully detailed schedule of Work.
This schedule shall conform to the schedule generally described above. It may be necessary
to do certain parts of the construction Work outside normal working hours in order to avoid
undesirable conditions, and it shall be the obligation of the Contractor to do this Work at such
times at no additional cost to the Owner.
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION (Not Applicable)
END OF SECTION
City of Carlsbad
03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01 01 1 - General Construction Sequence - 2 of 2
_- SECTION 01025
MEASUREMENTANDPAYMENT
_-
PART 1 - GENERAL
1.1 Description
Measurement and payment for bid items listed in the proposal shall be based upon use of a
lump sum or unit price method. Extra work or changes in the Work shall be accomplished as
provided in the General Provisions.
1.2 Related Work (Not Applicable)
1.3 Submittals (Not Applicable)
1.4 Payment
A. Payment for Unit Price Items
Payment for a unit price bid item shall be based upon tile amount shown in the bid
schedule multiplied by the total quantity measurement of the item and shall be full
compensation for furnishing all labor, transportation, materials, equipment, tools and
appurtenances required for construction of the item complete in place in accordance
with the Plans and Specifications.
B. Payment for Lump Sum Items
Payment for lump sum bid items shall be based upon the amount shown in the bid
schedule and shall be full compensation for furnishing all labor, transportation,
materials, equipment, tools and appurtenances required for construction of the unit
complete in place in accordance with the Plans and Specifications. The Carlsbad
Municipal Water District reserves the right to adjust any Lump Sum Item if the Total
Bid Amount does not reflect the added value of the individual Bid Items.
C. Work Not Listed in the Bid Schedule
Costs for related work and appurtenances which are required and/or implied by the
General Provisions, Technical Specifications, Special Provisions and Plans and are
not listed as a separate bid item but are necessary to complete the project shall be
included in the appropriate bid item or items within the proposal.
PART 2 - MATERIALS
2.1 General (Measurement)
Measurement for unit price quantities shall be based upon the appropriate bid item in the
proposal. The actual quantity of measurement shall be as constructed by the Contractor in
place in conformance with the Plans and Specifications.
City of Carlsbad
03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01 025 - Measurement and Payment - 1 of 20
2.2 Linear Measurements
Pipelines' and related facilities' measurement shall be made horizontally and/or vertically
along the centerline of the pipeline and related facilities through tees, bends, valves, fittings
and as shown on the Plans for its limits or as otherwise specified in the Special Provisions.
Manholes and vaults shall be measured vertically from the lowest to the highest elevations
and as shown on the Plans or as otherwise specified in the Special Provisions.
2.3 Area Measurements
Measurement for bid items involving area units shall be based upon the surface area
measured in acres, square yards, square feet or as indicated in the bid item.
2.4 Volume Measurements
Measurement for bid items involving volume units shall be based upon the volume measured
in cubic yards, tons or as indicated in the bid item.
2.5 Unit Measurements
Measurement for bid items involving units of the item shall be based upon the number of
units counted as indicated in the bid item.
--r 2.6 Lump Sum Measurement
Measurement for a lump sum bid item shall be considered as a complete project or a portion
of a project constituting a unit. The items to be included in the lump sum bid shall be as
specified in the proposal bid item and/or the Standard or Special Provisions.
PART 3 - EXECUTION
3.1 GENERAL
This section covers methods of measurement and payment for items of Work under this
Contract. The total Bid Price shall cover all Work required by the Contract Documents. All costs
in connection with the proper and successful completion of the work, including furnishing all
materials, equipment, supplies, and appurtenances; providing all construction plant, equipment,
and tools; and performing all necessary labor and supervision to fully complete the Work, shall
be included in the unit and lump sum prices bid, All Work not specifically set forth as a pay item
in the Bid Form shall be considered a subsidiary obligation of Contractor and all costs in
connection therewith shall be included in the prices bid. The descriptions of bid items provided
hereafter apply to Schedules 1 through 3.
3.2 ESTIMATED QUANTITIES
All estimated quantities stipulated in the Bid Form or other Contract Documents are
approximate and are to be used only (a) as a basis for estimating the probable cost of the
City of Carlsbad
63/04 (DBE)
ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01 025 - Measurement and Payment - 2 of 20
Work and (b) for the purpose of comparing the bids submitted for the Work. The actual
amounts of work done and materials furnished under unit price items may differ from the
estimated quantities. The basis of payment for work and materials will be the actual amount of
work done and materials furnished. Contractor agrees that he will make no claim for damages,
anticipated profits, or otherwise on account of any difference between the amounts of work
actually performed and materials actually furnished and the estimated amounts therefore.
--
3.3 BID SCHEDULE NO. 1 - DOMESTIC WATER TRANSMISSION MAIN - CONTRACT
NO. 34461
The drawings associated with Bid Schedule No. 1 are titled “El Camino Real and Cassia
Road 30 and 24” Potable Water Transmission Mains,” sheets 1 through 20, CIP No.
34461.
A. MOBILIZATION, DEMOBILIZATION AND CLEANUP, Bid Item 1.
1.
c
No measurement shall be made for this item. This item covers all the work
necessary for mobilization, demobilization, providing project sign, on-going
compliance with the General Conditions and final clean-up of construction site.
Mobilization includes: (1) Obtaining all permits necessary for performing the
work. (2) Assembly, equipment, material and supplies for the prosecution of
the work but which are not to be incorporated in the work. (3) Construction of
temporary yards, access road, development of disposal areas and other
facilities. (4) Provide project sign and install as directed by the District. (5) Compliance with the General Conditions.
Demobilization includes: (1) removal of all temporary facilities from the site. (2) Clean up of all debris and disposal offsite. (3) Contract closeout.
2. Payment for Bid Item 1, will be based upon the following:
c
a.
b.
C.
d.
City of Carlsbad
03/04 (DBE)
During the course of project construction the amount paid for Mobilization
and Demobilization will be 100 percent of the contract price for Bid Item 1 or
6.5 percent of the original contract amount, whichever is the less.
During the course of project construction, the amount paid for Mobilization
will be 70 percent of the contract price for Bid Item 1 or 70 percent of 6.5
percent of the original contract amount, whichever is the less. The initial
partial payment for Mobilization will not exceed one-third of the amount to be
paid for this item. Payment requests for Mobilization shall be accompanied
by information (invoices, timesheets, etc.) that support the amount being
requested.
During the course of project construction, the amount paid for
Demobilization will be 30 percent of the contract price for Bid Item 1 or 30
percent of 6.5 percent of the original contract amount, whichever is the less.
After completion of the work and acceptance of the contract, the amount, if
any, of the contract item price for Mobilization and Demobilization in excess
ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01025 - Measurement and Payment - 3 of 20
of 6.5 percent of the original contract amount will be included for payment in
accordance with Subsection 7.1 9 Acceptance of Work; Final Payment. -.
B. PERFORM EXPLORATORY EXCAVATIONS FOR UNDERGROUND UTILITIES,
Bid Item 2.
1. Measurement for payment for performing exploratory excavation at all under
ground utility crossings and points of connection to verify location, size and type
of existing facility will be based upon the complete work, all in accordance with
the requirements of the Contract Documents.
2. Payment for performing exploratory excavation at all underground utility
crossings and points of connection to verify location, size and type of existing
facility will be made at the lump sum price named in the Bid Schedule under Item
No. 2, which shall constitute full compensation for completely performing all
exploratory excavations, including but not limited to, pavement removal and
restoration, excavation and backfill, obtaining depths and sizes of utilities, traffic
control and other ancillary work.
C. CONSTRUCT 30-INCH DIAMETER TRANSMISSION MAIN, Bid Item 3.
1. Measurement for payment for construction of 30-inch diameter
CML, tape-wrapped and mortar coated steel pipe transmission main will be
based upon the number of linear feet of such pipe actually placed as determined
by measurement along the centerline of such pipe, all in accordance with the
requirements of the Contract Documents.
-
2. Payment for construction of 30-inch diameter transmission main will be made at
the unit price per linear foot named in the Bid Schedule under Item No. 3, which
price shall constitute full compensation for furnishing and placing such pipe
including excavation, backfill, bedding, compaction, fittings, thrust blocks,
locator tape, disposal of excess excavated material, pavement removal and
replacement, pavement overlay, re-striping, testing, flushing and disinfection
and any appurtenant work as shown on the Plans or called for in the
Specifications, complete in place for the unit price.
D. PROVIDE TRAFFIC CONTROL, Bid Items 4 and 6
1. No measurement shall be made for these items.
2. Payment for traffic control related to construction of the 30-inch and 24-inch
diameter transmission mains will be made at the lump sum price named in the
Bid Schedule under Item Nos. 4 and 6. Partial payments will be made on the
basis of the percentage of construction completion with respect to each waterline
up to a maximum of 50-percent of the lump sum price. The final amount which
completion and acceptance by the jurisdictional agency of the paving repair, final
paving, pavement overlay, and re-striping.
constitutes full compensation for the complete work can be applied for upon -...
City of Carlsbad
03/04 (DBE)
ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01 025 - Measurement and Payment - 4 of 20
E. CONSTRUCT 24-INCH DIAMETER TRANSMISSION MAIN, Bid Item 5.
1. Measurement for payment for construction of 24-inch diameter CML tape
wrapped and mortar coated steel pipe transmission main will be based upon the
number of linear feet of such pipe actually placed as determined by
measurement along the centerline of such pipe, all in accordance with the
requirements of the Contract Documents.
c
2. Payment for construction of 24-inch diameter transmission main will be made at
the unit price per linear foot named in the Bid Schedule under Item No. 5, which
price shall constitute full compensation for furnishing and placing such pipe
including excavation, backfill, bedding, compaction, fittings, thrust blocks,
locator tape, disposal of excess excavated material, pavement removal and
replacement, pavement overlay, re-striping, testing, flushing and disinfection
and any appurtenant work as shown on the Plans or called for in the
Specifications, complete in place for the unit price.
F. CONSTRUCT 12-INCH DIAMETER WATER MAIN, Bid Item 7.
1. Measurement for payment for construction of 12-inch diameter PVC water main
at Station No. 48+78 (Town Garden Road) will be based upon the complete
work, all in accordance with the requirements of the Contract Documents.
.-
2. Payment for construction of 12-inch diameter PVC water main and connections
to existing water main at Station No. 48 +78 (Town Garden Road) will be made
at the lump sum price named in the Bid Schedule under Item No. 7, which price
shall constitute full compensation for furnishing and placing such pipe including
excavation, backfill, bedding, compaction, fittings, temporary blow-off, thrust
blocks, locator tape, removal of existing 8-inch diameter piping and 8-inch
valve, 8-inch blind flange on 8-inch stub from 20-inch diameter water main,
phased construction to comply with City requirements, disposal of excess
excavated material, pavement removal and replacement, pavement overlay, re-
striping, traffic control, testing, flushing and disinfection and any appurtenant
work as shown on the Plans or called for in the Specifications, complete in
place for the unit price.
G. CONSTRUCT 12-INCH DIAMETER WATER MAIN, Bid Item 8.
1. Measurement for payment for construction of 12-inch diameter PVC water main
at Station No. 60+23.92 (Gateway Road) will be based upon the complete work,
all in accordance with the requirements of the Contract Documents.
2. Payment for construction of 12-inch diameter PVC water main and connections
to existing water main at Station No. 60+23.92 (Gateway Road) will be made at
the lump sum price named in the Bid Schedule under Item No. 8, which price
shall constitute full compensation for furnishing and placing such pipe including
excavation, backfill, bedding, compaction, fittings, temporary blow-off , thrust
blocks, locator tape, removal of existing 12-inch diameter pipe (temporary for
Bressi Ranch), 12-inch blind flange on 12-inch outlet on 20-inch diameter water
City of Carlsbad
03/04 (DBE)
ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01 025 - Measurement and Payment - 5 of 20
main, phased construction to comply with City requirements, disposal of excess
excavated material, pavement removal and replacement, pavement overlay, re-
striping, traffic control, testing, flushing and disinfection and any appurtenant
work as shown on the Plans or called for in the Specifications, complete in
place for the unit price.
-.
H. CONSTRUCT CONNECTION AT STATION No. 70+74.70, Bid Item 9.
1. Measurement for payment for construction of the connection to the existing
20-inch diameter steel water main at Station No. 70+74.70 will be based upon the
complete work, all in accordance with the requirements of the Contract
Documents.
2. Payment for construction of the connection to the existing 20-inch diameter
steel water main at Station No. 70+74.70 will be made at the lump sum price
named in the Bid Schedule under Item No. 9, which shall constitute full
compensation for furnishing and placing such pipe including excavation,
backfill, bedding, compaction, fittings, couplings, removal of 24-inch diameter
steel dished head, installation of butt strap for closing section, abandonment of
existing piping, properly plugging abandoned piping, thrust blocks, locator tape,
disposal of excess excavated material, pavement removal and replacement,
pavement overlay, re-striping, traffic control, testing, flushing and disinfection
and any appurtenant work as shown on the Plans or called for in the
Specifications, complete in place for the unit price. -
1. CONSTRUCT INTERCONNECTION AT STATION No. 48+78, Bid Item 10.
1. Measurement for payment for construction of an 8-inch diameter PVC pipe
interconnection to the existing 16-inch diameter distribution line at Station No.
48+78 will be based upon the complete work, all in accordance with the
requirements of the Contract Documents.
2. Payment for construction of the 8-inch diameter PVC pipe interconnection from
Sta. No. 0+66 to Sta. No. 1+00, to the existing 16-inch diameter distribution line
at Station No. 48+78 will be made at the lump sum price named in the Bid
Schedule under Item No. 10, which shall constitute full compensation for
furnishing and placing such pipe including excavation, removal of existing
piping interconnection, backfill, bedding, compaction, fittings, 8-inch gate valve,
removal of existing piping, phased construction to comply with City
requirements, thrust blocks, locator tape, disposal of excess excavated
material, pavement removal and replacement, pavement overlay, re-striping,
traffic control, testing, flushing and disinfection and any appurtenant work as
shown on the Plans or called for in the Specifications, complete in place for the
unit price.
City of Carlsbad
03/04 (DBE)
ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01 025 - Measurement and Payment - 6 of 20
J. CONSTRUCT CONNECTION AT STATION No. 80+09, Bid Item 11.
1. Measurement for payment for construction of the connection to the existing
16-inch diameter, 14-inch diameter and 6-inch diameter distribution lines at
Station No. 80+09 (Cassia Road) will be based upon the complete work, all in
accordance with the requirements of the Contract Documents.
-
2. Payment for construction of the connection to the existing 16-inch diameter, 14-
inch diameter and 6-inch diameter distribution lines at Station No. 80+09 at the
intersection of El Camino Real and Cassia Road will be made at the lump sum
price named in the Bid Schedule under Item No. 11, which shall constitute full
compensation for furnishing and placing such pipe including excavation, backfill,
bedding, compaction, fittings, couplings, removal of existing piping and valving
and appurtenances, thrust blocks, locator tape, disposal of excess excavated
material, pavement removal and replacement , pavement overlay, re-striping,
traffic control, testing, flushing and disinfection and any appurtenant work as
shown on the Plans or called for in the Specifications, complete in place for the
unit price. All removals of existing piping, valves and appurtenances shown on
Detail 1 on Sheet C-8 shall be included in this bid item.
K. CONSTRUCT CONNECTION AT STATION No. 84+29.00, Bid Item 12.
c
c
1. Measurement for payment for construction of the connection to the existing
30-inch diameter transmission main and the abandonment of the existing 18-inch
transmission main at Station No. 84+29.00 along Cassia Road will be based
upon the complete work, all in accordance with the requirements of the Contract
Documents.
2. Payment for construction of the connection to the existing 30-inch diameter
transmission main and the abandonment of the existing 18-inch transmission
main at Station No. 84+29.00 along Cassia Road will be made at the lump sum
price named in the Bid Schedule under Item No. 12, which shall constitute full
compensation for furnishing and placing such pipe including excavation, backfill,
bedding, compaction, fittings, removal of dished head, installation of butt strap
for closing section, abandonment and/or removal of existing piping and valves,
properly plugging abandoned piping as indicated on the plans, thrust blocks,
locator tape, disposal of excess excavated material, pavement removal and
replacement, pavement overlay, re-striping, traffic control, testing, flushing and
disinfection and any appurtenant work as shown on the Plans or called for in
the Specifications, complete in place for the unit price.
L. CONSTRUCT CONNECTION AT STATION No. 83+91 .OO, Bid Item 13.
1. Measurement for payment for construction of the connection to the existing
8-inch diameter steel water main at Station No. 83+91 .OO along Cassia Road will
be based upon the complete work, all in accordance with the requirements of the
Contract Documents.
City of Carlsbad
03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01 025 - Measurement and Payment - 7 of 20
M.
2. Payment for construction of the connection to the existing 8-inch diameter steel
water main at Station No. 83+91.00 along Cassia Road will be made at the lump
sum price named in the Bid Schedule under Item No. 13, which shall constitute
full compensation for furnishing and placing such pipe including excavation,
backfill, bedding, compaction, fittings, couplings, removal of existing piping,
abandonment of existing piping and valves, properly plugging abandoned piping,
thrust blocks, locator tape, disposal of excess excavated material, pavement
removal and replacement, pavement overlay, re-striping, traffic control, testing,
flushing and disinfection and any appurtenant work as shown on the Plans or
called for in the Specifications, complete in place for the unit price
-
CONSTRUCT 2-INCH AIR RELEASE AND VACUUM RELIEF VALVE, Bid Item
1.
2.
Measurement for payment for construction of 2-inch air release and vacuum relief
valve assembly, will be based upon the actual quantity, each, of such 2-inch air
release and vacuum valve assembly furnished and installed per the Carlsbad
Municipal Water District Standard Drawing No. W7, all in accordance with the
requirements of the Contract Documents.
Payment for said 2-inch air release and vacuum relief valve assembly, will be
made at the unit price, each, named in the Bid Schedule under Item No. 14,
which price shall constitute full compensation for the complete 2-inch air release
and vacuum valve assembly. -
N. CONSTRUCT 2-INCH MANUAL AIR RELEASE VALVE, Bid Item 15.
1. Measurement for payment for construction of 2-inch manual air release valve
assembly, will be based upon the actual quantity, each, of such 2-inch manual air
release valve assembly furnished and installed per the Carlsbad Municipal Water
District Standard Drawing No. W6, all in accordance with the requirements of the
Contract Documents.
2. Payment for said 2-inch manual air release valve assembly, will be made at the
unit price, each, named in the Bid Schedule under Item No. 15, which price shall
constitute full compensation for the complete 2-inch manual air release valve
assembly.
0. FURNISH AND CONSTRUCT 4-INCH BLOW OFF ASSEMBLY, Bid Item 16.
1. Measurement for payment for construction of 4-inch blow off assembly, will be
based upon the actual quantity, each, of such 4-inch blow off assembly furnished
and installed per the Carlsbad Municipal Water District Standard Drawing No.
W1 1, all in accordance with the requirements of the Contract Documents.
- 2. Payment for said 4-inch blow off assembly, will be made at the unit price, each,
named in the Bid Schedule under Item No. 16, which price shall constitute full
compensation for the complete 4-inch blow off assembly.
City of Carlsbad
03/04 (DBE)
ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01 025 - Measurement and Payment - 8 of 20
P. FURNISH AND INSTALL 6-INCH FIRE HYDRANT ASSEMBLY, Bid Item 17
1. Measurement for payment for construction of 6-inch fire hydrant assembly, will be
based upon the actual quantity, each, of such 6-inch fire hydrant assembly per
the Carlsbad Municipal Water District Standard Drawing No. W12 and as shown
on the plans, all in accordance with the requirements of the Contract Documents.
c
2. Payment for said 6-inch fire hydrant assembly, will be made at the unit price,
each, named in the Bid Schedule under Item No. 17, which price shall constitute
full compensation for the complete 6-inch fire hydrant assembly.
Q. FURNISH AND INSTALL 30-INCH BUTERFLY VALVE, Bid Item 18
1. Measurement for payment for construction of 30-inch butterfly valve, will be
based upon the actual quantity, each, of such 30-inch butterfly valve and valve
assembly per the Carlsbad Municipal Water District Standard Drawing Nos. W17
and W13, all in accordance with the requirements of the Contract Documents.
2. Payment for said 30-inch butterfly valve and valve box assembly, will be made at
the unit price, each, named in the Bid Schedule under Item No. 18, which price
shall constitute full compensation for the complete installed 30-inch butterfly valve
and valve box assembly.
R. FURNISH AND INSTALL 24-INCH BUTTERFLY VALVE, Bid Item 19
1. Measurement for payment for construction of 24-inch butterfly valve, will be
based upon the actual quantity, each, of such 24-inch butterfly valve and valve
box assembly, per the Carlsbad Municipal Water District Standard Drawing Nos.
W17 and W13, all in accordance with the requirements of the Contract
Documents.
2. Payment for said 24-inch butterfly valve and valve box assembly, will be made at
the unit price, each, named in the Bid Schedule under Item No. 19, which price
shall constitute full compensation for the complete installed 24-inch butterfly valve
and valve box assembly.
S. FURNISH AND INSTALL 14-INCH BUTTERFLY VALVE, Bid Item 20
1. Measurement for payment for construction of 14-inch butterfly valve, will be
based upon the actual quantity, each, of such 14-inch butterfly valve and valve
box assembly per the Carlsbad Municipal Water District Standard Drawing
Nos. W17 and W13, all in accordance with the requirements of the Contract
Documents.
2. Payment for said 14-inch butterfly valve and valve box assembly, will be made at
the unit price, each, named in the Bid Schedule under Item No. 20, which price
shall constitute full compensation for the complete installed 14-inch butterfly valve
and valve box assembly.
City of Carlsbad
03/04 (DBE)
ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01 025 - Measurement and Payment - 9 of 20
T.
U.
V.
W.
FURNISH AND INSTALL 16-INCH BUTTERFLY VALVE, Bid Item 21.
1. Measurement for payment for construction of 16-inch butterfly valve, will be
based upon the actual quantity, each, of such 16-inch butterfly valve and valve
box assembly per the Carlsbad Municipal Water District Standard Drawing
Nos. W17 and W13, all in accordance with the requirements of the Contract
Documents.
2. Payment for said 16-inch butterfly valve and valve box assembly, will be made at
the unit price, each, named in the Bid Schedule under Item No. 21, which price
shall constitute full compensation for the complete installed 16-inch butterfly valve
and valve box assembly.
FURNISH AND INSTALL 12-INCH RESILIENT WEDGE GATE VALVE, Bid
Item 22.
1. Measurement for payment for construction of 12-inch resilient wedge gate valve,
will be based upon the actual quantity, each, of such 12-inch resilient wedge gate
valve and valve box assembly per the Carlsbad Municipal Water District
Standard Drawing Nos. W16 and W13, all in accordance with the requirements of
the Contract Documents.
2. Payment for said 12-inch resilient wedge gate valve and valve box assembly, will
be made at the unit price, each, named in the Bid Schedule under Item No. 22,
which price shall constitute full compensation for the complete installed 12-inch
resilient wedge gate valve and valve box assembly.
FURNISH AND INSTALL 8-INCH RESILIENT WEDGE GATE VALVE, Bid
Item 23.
1.
2.
Measurement for payment for construction of 8-inch resilient wedge gate valve,
will be based upon the actual quantity, each, of such 8-inch resilient wedge gate
valve and valve box assembly per the Carlsbad Municipal Water District
Standard Drawing No. W16 and W13, all in accordance with the requirements of
the Contract Documents.
Payment for said 8-inch resilient wedge gate valve and valve box assembly, will
be made at the unit price, each, named in the Bid Schedule under Item No. 23,
which price shall constitute full compensation for the complete 8-inch resilient
wedge gate valve and valve box assembly.
FURNISH AND INSTALL CATHODIC PROTECTION, Bid Item 24.
1. No measurement will be made for this item.
- 2. Payment for cathodic protection of 30-inch and 24-inch CML, tape wrapped and
mortar coated steel pipe transmission main will be made at the lump sum price
named in the Bid Schedule under Item No. 24, which shall constitute full
compensation for completely furnishing all labor, materials and equipment to
City of Carlsbad
03/04 (DBE)
ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01 025 - Measurement and Payment - 10 of 20
.-
X.
Y.
Z.
install cathodic protection for steel transmission mains including: excavation,
backfill, bedding, compaction, wiring, welding, test stations, testing of system and
documented recordation of initial readings, disposal of excess excavated
materials, removal and replacement of pavement, and any appurtenant work as
shown on the Plans and Specifications.
INSTALL TRAFFIC VIDEO DETECTION SYSTEM, Bid Item 25.
1. Measurement for payment for installation of permanent traffic video detection
equipment, will be based upon the actual quantity, each, of such detection
systems furnished and installed per the City of Carlsbad standard, all in
accordance with the requirements of the traffic control Contract Documents.
2. Payment for said traffic video detection equipment assembly, will be made at the
unit price, each, named in the Bid Schedule under Item No. 25, which price shall
constitute full compensation for the completed and functioning installation.
PROVIDE PROJECT CONSTRUCTION SCHEDULE, Bid Item 26.
1. No measurement shall be made for this item. This item covers all the work
necessary for providing the project construction schedule in accordance with the
requirements of the Contract Documents.
2. Payment for Bid Item 26, will be based upon the following:
a. Upon acceptance by the District Representative, the payment will be made
at the lump sum price named in the Bid Schedule under Item No. 26. Partial
payments will be made on the basis of the percentage of construction
completion with respect to the recycled waterline.
PROVIDE AND PREPARE DRAWINGS FOR SWPPP AND BMP PERMITS AND
FURNISH AND INSTALL EROSION CONTROL AND WATER POLLUTION
CONTROL DEVICES, Bid Item 27
1. No measurement will be made for this item.
2. Payment for providing and preparing drawings for SWPPP and BMP permits
and furnishing and installing erosion control and water pollution control devices,
will be made at the lump sum price named in the Bid Schedule under Item No.
27, which shall constitute full compensation for this item.
AA. PROVIDE EXCAVATION SAFETY MEASURES, Bid Item 28.
1. No measurement will be made for this item.
2. Payment for providing excavation safety measures including sheeting, shoring
and bracing, or equivalent method for the protection of life and limb in trenches
and open excavation in conformance with applicable safety orders, will be made
City of Carlsbad
03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01 025 - Measurement and Payment - 1 1 of 20
at the lump sum price named in the Bid Schedule under Item No. 28, which
shall constitute full compensation for this item. -
3.4 BID SCHEDULE NO. 2 - RECYCLED WATER TRANSMISSION MAIN - CONTRACT
NO. 38871-H
The drawings associated with Bid Schedule No. 2 are titled “El Camino Real and Cassia
Road 18’720” Recycled Water Transmission Mains,” sheets 1 through 22, CIP No.
38871 -H.
A. MOBILIZATION, DEMOBILIZATION AND CLEANUP, Bid Item 1.
1. No measurement shall be made for this item. This item covers all the work
necessary for mobilization, demobilization, providing project sign, on-going
compliance with the General Conditions and final clean-up of construction site.
Mobilization includes: (1) Obtaining all permits necessary for performing the
work. (2) Assembly, equipment, material and supplies for the prosecution of the work but which are not to be incorporated in the work. (3) Construction of
temporary yards, access road, development of disposal areas and other
facilities. (4) Provide project sign and install as directed by the District. (5)
Compliance with the General Conditions. Demobilization includes: (1) removal
of all temporary facilities from the site. (2) Clean up of all debris and disposal
offsite. (3) Contract closeout. -
2. Payment for Bid Item 1, will be based upon the following:
a. During the course of project construction the amount paid for Mobilization
and Demobilization will be 100 percent of the contract price for Bid Item 1 or
3.0 percent of the original contract amount, whichever is the less.
b. During the course of project construction, the amount paid for Mobilization
will be 70 percent of the contract price for Bid Item 1 or 70 percent of 3.0
percent of the original contract amount, whichever is the less. The initial
partial payment for Mobilization will not exceed one-third of the amount paid
to be paid for this item. Payment requests for Mobilization shall be
accompanied by information (invoices, timesheets, etc.) that support the
amount being requested.
c. During the course of project construction, the amount paid for
Demobilization will be 30 percent of the contract price for Bid Item 1 or 30
percent of 3.0 percent of the original contract amount, whichever is the less.
d. After completion of the work and acceptance of the contract, the amount, if
any, of the contract item price for Mobilization and Demobilization in excess
of 3.0 percent of the original contract amount will be included for payment.
--4
City of Carlsbad
03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01 025 - Measurement and Payment - 12 of 20
c
B. PERFORM EXPLORATORY EXCAVATIONS FOR UNDERGROUND UTILITIES,
Bid Item 2.
1. Measurement for payment for performing exploratory excavation at all under
ground utility crossings and points of connection to verify location, size and type of existing facility will be based upon the complete work, all in accordance with
the requirements of the Contract Documents.
2. Payment for performing exploratory excavation at all underground utility
crossings and points of connection to verify location, size and type, of existing
facility will be made at the lump sum price named in the Bid Schedule under Item
No. 2, which shall constitute full compensation for completely performing all
exploratory excavations, including but not limited to, pavement removal and
restoration, excavation and backfill, obtaining depths and sizes of utilities, traffic
control and other ancillary work.
C. CONSTRUCT 20-INCH DIAMETER RECYCLED WATER MAIN, Bid Item 3.
1. Measurement for payment for construction of 20-inch diameter C-905 Class 235
PVC pipe recycled water main (Line A) in El Camino Real from Station No.
100+00 to approximate Station No. 157+85 will be based upon the number of
linear feet of such pipe actually placed as determined by measurement along the
centerline of such pipe, all in accordance with the requirements of the Contract
Documents.
2. Payment for construction of 20-inch diameter C-905 Class 235 PVC pipe recycled water main (Line A) in El Camino Real from Station No. 100+00 to
approximate Station No. 157+85 will be made at the unit price per linear foot
named in the Bid Schedule under Item No. 3, which price shall constitute full
compensation for furnishing and placing such pipe including excavation,
backfill, bedding, compaction, fittings, thrust blocks, disposal of excess
excavated material, pavement removal and replacement, pavement overlay, re-
striping, testing, flushing and disinfection and any appurtenant work as shown
on the Plans or called for in the Specifications, complete in place for the unit
price.
D. PROVIDE TRAFFIC CONTROL, Bid Items 4,12 and 14
1. No measure shall be made for these items.
i--
2. Payment for traffic control related to construction of bid item Nos. 4, 12 and 14
will be made at the lump sum price named in the Bid Schedule. Partial payments
will be made on the basis of the percentage of construction completion with
respect to the recycled waterline up to a maximum of 50-percent of the lump sum
price. The final amount which constitutes full compensation for the complete work
can be applied for upon completion and acceptance by the jurisdictional agency
of the paving repair, final paving, pavement overlay, and re-striping.
City of Carlsbad
03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01 025 - Measurement and Payment - 13 of 20
E. PROVIDE HIGH LINE FOR BY-PASSING 12-INCH RECYCLED WATER MAIN, Bid Item 5 x
1. No measure shall be made for these items.
2. Payment for installation and construction of High Line and appurtenances as
approved by shop drawings to convey flow around the planned abandonment
12-inch recycled water main during construction of the recycled water main as
indicated in Bid Item No. 5 and project documents will be made at the lump sum
price named in the Bid Schedule under Item No. 5. Partial payments will be
made per the following schedule: 1'' 40% of the lump sum indicated in Item No.
6 after completion on installation, disinfection, and initial by-passing is started, 2nd
the next set of payments for Item No. 5 will be issued on the basis of the
percentage of construction completion with respect to the recycled waterline or
duration of high lining operation whichever is longer up to a maximum of 80%,
and 3rd the final payment of the remaining 20% will be made after removal is
completed and accepted by the district. The 1'' payment includes but not limited
to placing such pipe including excavation, backfill, bedding, compaction, fittings,
thrust blocks, disposal of excess excavated material testing, flushing and
disinfection and any appurtenant work as shown on the Plans or called for in
the Specifications, the 2nd pa ment phase includes maintaining the high line in
an operational status and 3 payment includes the removal of the high line
equipment, piping and any restoration required including but not limited to
rK
backfilling, pavement replacement, and re-striping. -_
F. CONSTRUCT 12-INCH DIAMETER RECYCLED WATER MAIN, Bid Item 6.
1. Measurement for payment for construction of 12-inch diameter C-900 Class 150
PVC pipe recycled water main lateral (Line Al) and appurtenances to the east at
approximate Station No. 11 2+90 will be based upon the complete work, all in
accordance with the requirements of the Contract Documents.
2. Payment for construction of 12-inch diameter C-900 Class 150 PVC pipe
recycled water main lateral (Line Al) and appurtenances to the east at
approximate Station No. 112+90 will be made at the lump sum price named in
the Bid Schedule under Item No. 6, which price shall constitute full
compensation for furnishing and placing such pipe including excavation,
removal of existing piping and valves, proper abandonment of existing piping,
backfill, bedding, compaction, fittings, thrust blocks, reconnection to existing
piping, phased construction per City requirements, disposal of excess
excavated material, traffic control, pavement removal and replacement,
pavement overlay, re-striping, testing, flushing and disinfection and any
appurtenant work as shown on the Plans or called for in the Specifications,
complete in place for the unit price.
City of Carlsbad
03/04 (DBE)
ECR (PAR to Cassia) Domestic 84 Recycled Water Transmission Mains
01 025 - Measurement and Payment - 14 of 20
G. - Item 7.
CONSTRUCT 10-INCH DIAMETER RECYCLED WATER MAIN STUB-OUT, Bid
1. Measurement for payment for construction of 1 0-inch diameter C-900 PVC Class
200 pipe recycled water main stub-out (Line A2) and appurtenances to the west
at approximate Station No. 124+77 (Camino Vida Roble) will be based upon the
complete work, all in accordance with the requirements of the Contract
Documents.
2. Payment for construction of 10-inch diameter C-900 PVC Class 200 pipe
recycled water main stub-out (Line A2) and appurtenances to the west at
approximate Station No. 124+77 (Camino Vida Roble) will be made at the lump
sum price named in the Bid Schedule under Item No. 7, which price shall
constitute full compensation for furnishing and placing such pipe including
excavation, backfill, bedding, compaction, fittings, temporary blow-off assembly,
thrust blocks, phased construction per City requirements, connection to existing
recycled water main, disposal of excess excavated material, pavement removal
and replacement, traffic control, pavement overlay, re-striping, testing, flushing
and disinfection and any appurtenant work as shown on the Plans or called for
in the Specifications, complete in place for the unit price.
H. CONSTRUCT 12-INCH DIAMETER RECYCLED WATER MAIN, Bid Item 8.
1. Measurement for payment for construction of 12-inch diameter C-900 Class 150
PVC pipe recycled water main (Line A3) and appurtenances to the east at
approximate Station No. 138+78 (Town Garden Road) will be based upon the
complete work, all in accordance with the requirements of the Contract
Documents.
2. Payment for construction of 12-inch diameter C-900 Class 150 PVC pipe
recycled water main (Line A3) and appurtenances to the east at approximate
Station No. 138+78 (Town Garden Road) will be made at the lump sum price
named in the Bid Schedule under Item No. 8, which price shall constitute full
compensation for furnishing and placing such pipe, including excavation,
backfill, bedding, compaction, fittings, temporary blow-off assembly, thrust
blocks, phased construction per City requirements, connection to the existing
12-inch diameter recycled water main, disposal of excess excavated material,
pavement removal and replacement, traffic control, pavement overlay, re-
striping, testing, flushing and disinfection and any appurtenant work as shown
on the Plans or called for in the Specifications, complete in place for the unit
price.
1. CONSTRUCT 30-INCH DIAMETER RECYCLED WATER MAIN, Bid Item 9.
1. Measurement for payment for construction of 30-inch diameter CML and tape-
wrapped, CMC recycled water main (Line A4) and appurtenances to the east at
approximate Station No. 150+00 will be based upon the complete work, all in
accordance with the requirements of the Contract Documents.
--
City of Carlsbad
03/04 (D B E) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01025 - Measurement and Payment - 15 of 20
2. Payment for construction of 30-inch diameter CML and tape-wrapped, CMC
recycled water main (Line A4) and appurtenances to the east at approximate
Station No. 150+00 will be made at the lump sum price named in the Bid
Schedule under Item No. 9, which price shall constitute full compensation for
furnishing and placing such pipe, including excavation, backfill, bedding,
compaction, fittings, temporary blow-off assembly, thrust blocks, phased
construction per City requirements, connection to existing 30-inch diameter
recycled water main , disposal of excess excavated material, pavement removal
and replacement, traffic control, pavement overlay, re-striping, testing, flushing
and disinfection and any appurtenant work as shown on the Plans or called for
in the Specifications, complete in place for the unit price.
-
J. CONSTRUCT 20-Inch Diameter Recycled Water Main Stub-Out, Bid Item 10.
1. Measurement for payment for construction of 20-inch diameter C-905 Class 235
PVC pipe recycled water main stub-out (Line A5) and appurtenances to the east
at approximate Station No. 157+65 will be based upon the complete work, all in
accordance with the requirements of the Contract Documents.
2. Payment for construction of 20-inch diameter (2-905 Class 235 PVC pipe
recycled water main stub-out (Line A5) and appurtenances to the east at
approximate Station No. 157+65 will be made at the lump sum price named in
the Bid Schedule under Item No. 10, which price shall constitute full
compensation for furnishing and placing such pipe, including excavation, -
backfill, bedding, compaction, fittings, temporary blow-off assembly, thrust
blocks, phased construction per City requirements, disposal of excess
excavated material, pavement removal and replacement, traffic control,
pavement overlay, re-striping, testing, flushing and disinfection and any
appurtenant work as shown on the Plans or called for in the Specifications,
complete in place for the unit price.
K. CONSTRUCT 18-INCH DIAMETER RECYCLED WATER MAIN, Bid Item 11.
1. Measurement for payment for construction of 18-inch diameter C-905 Class 235
PVC pipe recycled water main in El Camino Real from approximate Station No.
157+85 to Station 162+07.79 will be based upon the number of linear feet of
such pipe actually placed as determined by measurement along the centerline of
such pipe, all in accordance with the requirements of the Contract Documents.
2. Payment for construction of 18-inch diameter (3-905 Class 235 PVC pipe
recycled water main in El Camino Real from approximate Station No. 157+85 to
Station 162+07.79 will be made at the unit price per linear foot named in the Bid
Schedule under Item No. 11 , which price shall constitute full compensation for
furnishing and placing such pipe including excavation, backfill, bedding,
compaction, fittings, thrust blocks, disposal of excess excavated material,
flushing and disinfection and any appurtenant work as shown on the Plans or
called for in the Specifications, complete in place for the unit price.
pavement removal and replacement, pavement overlay, re-striping, testing, -.
City of Carlsbad
03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01025 - Measurement and Payment - 16 of 20
L. CONSTRUCT 18-INCH DIAMETER RECYCLED WATER MAIN, Bid Item 13.
1. Measurement for payment for construction of 18-inch diameter C-905 Class 235
PVC and ductile iron pipe recycled water main (Line B) in Cassia Road from
approximate Station No. 170+00 to approximate Station 175+00 will be based
upon the number of linear feet of such pipe actually placed as determined by
measurement along the centerline of such pipe, all in accordance with the
requirements of the Contract Documents.
-
2. Payment for construction of 18-inch diameter C-905 Class 235 PVC and ductile
iron pipe recycled water main (Line B) in Cassia Road from approximate Station
No. 170+00 to approximate Station 175+00 will be made at the unit price per
linear foot named in the Bid Schedule under Item No. 13, which price shall
constitute full compensation for furnishing and placing such pipe including
excavation, backfill, bedding, compaction, fittings, thrust blocks, disposal of
excess excavated material, pavement removal and replacement, pavement
overlay, curb and gutter removal and replacement, re-striping, testing, flushing
and disinfection and any appurtenant work as shown on the Plans or called for
in the Specifications, complete in place for the unit price.
M. CONSTRUCT CONNECTION IN CASSIA ROAD AT STATION NO. 175+00, Bid
Item 15.
.-
1. Measurement for payment for construction of the connection to the existing 18-
inch diameter transmission main at Station No. 175+00 along Cassia Road will
be based upon the complete work, all in accordance with the requirements of the
Contract Documents.
2. Payment for construction of the connection to the existing 18-inch diameter
transmission main at Station No. 175+00 along Cassia Road will be made at the
lump sum price named in the Bid Schedule under Item No. 15, which shall
constitute full compensation for furnishing and placing such pipe including
excavation, backfill, bedding, compaction, fittings, removal of temporary thrust
blocks, installation of closing section, abandonment and/or removal of existing
piping and valves, properly plugging abandoned piping as indicated on the plans,
thrust blocks, locator tape, disposal of excess excavated material, pavement
removal and replacement, pavement overlay, re-striping, traffic control, testing
and flushing and any appurtenant work as shown on the Plans or called for in the
Specifications, complete in place for the unit price.
N. CONSTRUCT 2-INCH AIR RELEASE AND VACUUM RELIEF VALVE, Bid Item - 16.
1. Measurement for payment for construction of 2-inch air release and vacuum relief
valve assembly, will be based upon the actual quantity, each, of such 2-inch air
release and vacuum valve assembly furnished and installed per the Carlsbad
Municipal Water District Standard Drawing No. W7, all in accordance with the
requirements of the Contract Documents.
City of Carlsbad
03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01025 - Measurement and Payment - 17 of 20
2. Payment for said 2-inch air release and vacuum relief valve assembly, will be
made at the unit price, each, named in the Bid Schedule under Item No. 16,
which price shall constitute full compensation for the complete 2-inch air release
and vacuum valve assembly.
.-
0. CONSTRUCT 2-INCH MANUAL AIR RELEASE VALVE, Bid Item 17.
1. Measurement for payment for construction of 2-inch manual air release or blow-
off valve assembly, will be based upon the actual quantity, each, of such 2-inch
manual air release or blow-off valve assembly furnished and installed per the
Carlsbad Municipal Water District Standard Drawing No. W6, all in accordance
with the requirements of the Contract Documents.
2. Payment for said 2-inch manual air release or blow-off valve assembly, will be
made at the unit price, each, named in the Bid Schedule under Item No. 18,
which price shall constitute full compensation for the complete 2-inch manual air
release or blow-off valve assembly.
P. FURNISH AND CONSTRUCT 4-INCH BLOW OFF ASSEMBLY, Bid Item 18.
1. Measurement for payment for construction of 4-inch blow off assembly, will be
based upon the actual quantity, each, of such 4-inch blow off assembly furnished
and installed per the Carlsbad Municipal Water District Standard Drawing No.
W1 1, all in accordance with the requirements of the Contract Documents. I_
2. Payment for said 4-inch blow off assembly, will be made at the unit price, each,
named in the Bid Schedule under Item No. 18, which price shall constitute full
compensation for the complete 4-inch blow off assembly.
Q. FURNISH AND INSTALL 20-INCH BUlTERFLY VALVE, Bid Item 19.
1. Measurement for payment for construction of 20-inch butterfly valve and valve
box assembly, will be based upon the actual quantity, each, of such 20-inch
butterfly valve and valve box assembly, per the Carlsbad Municipal Water District
Standard Drawing Nos. W17 & W13, all in accordance with the requirements of
the Contract Documents.
2. Payment for said 20-inch butterfly valve and valve box assembly, will be made at
the unit price, each, named in the Bid Schedule under Item No. 19, which price
shall constitute full compensation for the complete and installed 20-inch butterfly
valve and valve box assembly.
R. FURNISH AND INSTALL 18-INCH BUTTERFLY VALVE, Bid Item 20.
1. Measurement for payment for construction of 18-inch butterfly valve and valve
box assembly, will be based upon the actual quantity, each, of such 18-inch
butterfly valve and valve box assembly, per the Carlsbad Municipal Water District
Standard Drawing Nos. W17 & W13, all in accordance with the requirements of
the Contract Documents.
-4
City of Carlsbad
03/04 (DBE)
ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01 025 - Measurement and Payment - 18 of 20
I 2. Payment for said 18-inch butterfly valve and valve box assembly, will be made at
the unit price, each, named in the Bid Schedule under Item No. 20, which price
shall constitute full compensation for the complete and installed 18-inch butterfly
valve and valve box assembly.
S. FURNISH AND INSTALL 12-INCH RESILIENT WEDGE GATE VALVE, Bid
Item 21.
1. Measurement for payment for construction of 12-inch resilient wedge gate valve
and valve box assembly, will be based upon the actual quantity, each, of such
12-inch resilient wedge gate valve and valve box assembly, per the Carlsbad
Municipal Water District Standard Drawing Nos. W16 & W13, all in accordance
with the requirements of the Contract Documents.
2. Payment for said 12-inch resilient wedge gate valve and valve box assembly, will
be made at the unit price, each, named in the Bid Schedule under Item No. 21,
which price shall constitute full compensation for the complete and installed. 12-
inch resilient wedge gate valve and valve box assembly.
T. FURNISH AND INSTALL 10-INCH RESILIENT WEDGE GATE VALVE, Bid
Item 22.
1. Measurement for payment for construction of 1 O-inch resilient wedge gate valve
and valve box assembly, will be based upon the actual quantity, each, of such
10-inch resilient wedge gate valve and valve box assembly, per the Carlsbad
Municipal Water District Standard Drawing Nos. W16 & W13, all in accordance
with the requirements of the Contract Documents.
2. Payment for said 1 O-inch resilient wedge gate valve and valve box assembly, will
be made at the unit price, each, named in the Bid Schedule under Item No. 22,
which price shall constitute full compensation for the complete and installed
8-inch resilient wedge gate valve and valve box assembly.
U. FURNISH AND CONSTRUCT A 1-INCH RECYCLED WATER IRRIGATIONAL
METER SERVICE, Bid Item 23.
1. Measurement for payment for a 1 -inch recycled water irrigational meter service,
will be based upon the actual quantity, each, of such a 1-inch recycled water
irrigational meter service, per the Carlsbad Municipal Water District Standard
Drawing No. W4, all in accordance with the requirements of the Contract
Documents.
2. Payment for said a l-inch recycled water irrigational meter service, will be made
at the unit price, each, named in the Bid Schedule under Item No. 23, which price
shall constitute full compensation for the complete and installed a 1 -inch recycled
water irrigational meter service.
City of Carlsbad
03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01 025 - Measurement and Payment - 19 of 20
V. FURNISH AND CONSTRUCT A 2-INCH RECYCLED WATER IRRIGATIONAL
METER SERVICE, Bid Item 24. A
1. Measurement for payment for a 2-inch recycled water irrigational meter service,
will be based upon the actual quantity, each, of such a 2-inch recycled water
irrigational meter service, per the Carlsbad Municipal Water District Standard
Drawing No. W4, all in accordance with the requirements of the Contract
Documents.
2. Payment for said a 2-inch recycled water irrigational meter service, will be made
at the unit price, each, named in the Bid Schedule under Item No. 24, which price
shall constitute full compensation for the complete and installed a 2-inch recycled
water irrigational meter service.
W. PROVIDE EXCAVATION SAFETY MEASURES, Bid Item 25.
1. No measurement will be made for this item.
2. Payment for providing excavation safety measures including sheeting, shoring
and bracing, or equivalent method for the protection of life and limb in trenches
and open excavation in conformance with applicable safety orders, will be made
at the lump sum price named in the Bid Schedule under Item No. 25, which
shall constitute full compensation for this item.
.-
END OF SECTION
City of Carlsbad
03/04 (DBE)
ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01025 - Measurement and Payment - 20 of 20
SECTION 01040
COORDINATION
PART 1 - GENERAL
1.1 Work Included
A. Licenses, permits, sales taxes, coordination with Owner, Federal, State and Local
authorities, utilities, neighboring property owners, special events and other
contractors.
1.2 Related Work
A.
B. Section 02225: Utility Crossings
Section 01 500: Construction Facilities and Temporary Controls
C. Section 01300: Submittals
1.3. Permits
A. Obtain, pay for, and comply with required permits, licenses, work permits and
authorizations from appropriate agencies, including the following:
1. Licenses
a. Before submitting bids, Contractors shall be licensed in accordance
with provisions of Chapter 9, Division 3, of the Business and
professions Code of the State of California.
2. State and federal permits
a. Excavation and Dirt Moving Permit from Cal OSHA
b.
c. NPDES permit for dewatering
Safety Permit from California Division of Industrial Safety
3. Other permits
a. Air Pollution Control District
b. County of San Diego Health Department
4. City Permits
The Contractor will obtain for the Project, the following permits:
City of Carlsbad
03/04 (DBE)
ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01040 Coordination - 1 of 4
a. Encroachment permits for access to City right-of-way (no fee)
b. Haul routes ( no fee)
c. Night time inspection/work after hours
d. Connection/shut down (no fee)
1.4 Coordination with Owner
A. Notify Owner at least 72 hours before start of construction.
B. Submit written details and reasons for proposed deviations from Contract
Documents. Do not deviate from contract documents until written authorization is
received.
C. If Contractor fails to comply with a request of Owner, or is unable to comply with a
request, and it is necessary for Owner's forces to do Work that is Contractor's
responsibility, Owner will bill Contractor. Each incident requiring work by Owner's
forces will be covered by a separate billing.
1.5 Coordination with Carlsbad Municipal Water District
A. Contact City of Carlsbad Public Works Department, 72 hours before start of - construction at the following location:
C/O CITY OF CARLSBAD
Construction Management and Inspection Division
5950 El Camino Real
Carlsbad, CA 92008
(760) 602-2780
(760) 438-4 1 78 (Fax)
B. Do not begin Work until Contractor's schedule, traffic control plans, haul routes,
and permits have been reviewed and approved by District.
C. Submit a written Request for Shutdown to the Agency seven (7) Working Days in
advance of the anticipated shutdown date for any water, sewer, or storm drain
facility. In regard to any water or sewer utility, the Water Utility Department must
confirm that all necessary materials (valves, piping, appurtenances, etc.) have an
approved submittal, have been inventoried and verified by the District Inspector,
and are on the jobsite prior to the written Request for Shutdown being submitted.
Do not assume water or sewer lines can be shut down. Do not shut down utilities
without prior written authorization.
City of Carlsbad
03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01 040 Coordination - 2 of 4
D. Coordinate draining and filling of water lines, and operation of existing valves with
District Engineer or appropriate Utility Owner. ..-
E. Coordinate with Utility Operations of Public Works regarding time of day that
system tie-ins are made.
1.6 Coordination with District, Countv or State Traffic Engineer
A. Coordinate with District, County or State Traffic Engineer as required, to perform
all portions of the Work.
1.7 Coordination with Propertv Owners
A. Coordinate construction with property owners neighboring project limits,
especially with regard to any limitations with access to their property.
B. At a minimum, the contractor shall coordinate with concurrent projects in the area
such as Bressi Ranch Development, El Camino Real Lane Widening, etc.
1.8 Coordination with Utilities
A.
B.
C.
Protect existing underground utilities. The Contractor shall coordinate with all
utilities affected by the project to mark-out their locations for potholing and notify
utilities of progress during construction so utility field personnel are available
when required. SDG&E and Kinder Morgan require a standby inspector(s) be
present for work near their utilities. The contractor shall be responsible for
coordination, payment (if any) and scheduling issues with utilities.
Electrical utility companies may maintain energized aerial electrical power lines in
immediate vicinity of Work. Do not consider these lines to be insulated.
Construction personnel working near these lines are exposed to an extreme
hazard from electrical shock. Contractors, their employees and construction
personnel working on this project must be warned of the danger and instructed to
take adequate protective measures, including maintaining a minimum of 10 feet
clearance between lines and construction equipment and personnel. (See OSHA
Std. 1926.550(A)15). As an additional safety precaution, call electrical utility
company to arrange, if possible, to have these lines de-energized or relocated
when Work reaches their immediate vicinity. Cost of such temporary
arrangements shall be borne by Contractor.
All demolition of existing facilities or portions there of shall be coordinated and
performed by the Contractor. All costs associated with abandonments or
demolition shall be borne by the Contractor.
City of Carlsbad
03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01040 Coordination - 3 of 4,
1.9 Submittals -" A. Supplementary progress schedules shall be submitted after Work is in progress,
when requested by the Engineer. Schedule changes requiring an increase in
Owner's, Servicing Utility's or District's Engineering personnel on project shall not
be put into effect until Owner, Servicing Utility, or District has made arrangements
for additional personnel.
B. The Contractor shall submit a detailed plan and written description of any water
facility tie-in. The plan will include, but is not limited to, all necessary pumps,
standby pump(s), piping, appurtenances, and 24-hour staffing schedule. When
the submittal has been approved, and all necessary testing has been successfully
completed, the Contractor will submit a Request for Shutdown seven (7) working
days in advance of the anticipated shutdown date.
1.10 Unit Prices
A. Payment for obtaining and complying with permits during construction, including
NPDES permits, building permits, encroachment permits, excavation permits,
drilling permits, disposal permits, temporary easements, licenses, inspection fees,
and Federal, State and local taxes will be included in prices bid for Work for which
such costs are appurtenant.
B. Payment for coordinating with agencies, events and persons described will be
included in prices bid for Work to which coordination is appurtenant.
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION (Not Applicable)
END OF SECTION
City of Carlsbad
03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01 040 Coordination - 4 of 4
SECTION 01 047 - CONNECTIONS TO EXISTING FACILITIES
PART 1 - GENERAL
1.1 SCOPE
A. Perform all construction necessary to complete connections and tie-ins to existing
facilities under District Supervision.
B. Keep existing facilities in operation, unless otherwise specifically permitted in these
Specifications or approved by OWNER.
C. CONTRACTOR shall perform all construction activities so as to avoid interference
with operations of the facility and the work of others.
D. CONTRACTOR shall provide potholing for locating and field verifying all existing
piping, structures and equipment affected by the Work. All potholing shall be
performed by the CONTRACTOR at no additional cost to the OWNER. Delays in
the Work, as a result of insufficient potholing, will be solely the CONTRACTORS
responsibility. No time extensions will be allowed for Contract Work that is delayed
as a result of insufficient potholing and field verification. _-
1.2 SEQUENCING AND OPERATIONS
A. All operation of existing valves required for the Work shall be done by the District.
B. Insofar as possible, all equipment shall be tested and in operating condition before
the final tie-ins are made to connect equipment to the existing facility.
C. CONTRACTOR shall carefully coordinate all Work and schedules and shall provide
OWNER written notice before shut-downs or by-passes are required.
1/3 SUBMllTALS
A. Submit detailed schedule of proposed connections, listing sequence and durations
of all activities including shut-downs and tie-ins.
PART 2 - PRODUCTS (Not Applicable)
PART 3 - MATERIALS (Not Applicable)
LI
END OF SECTION
City of Carlsbad
03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01 047 Connections to Existing Facilities - 1 of 1
SECTION 01 048
SPECIAL CONSTRUCTION CONDITIONS AND PROCEDURES - GENERAL I.
PART 1 - GENERAL
1.1 SCOPE
A. This section covers special construction conditions and procedures associated
with this construction contract.
1.2 REQUIREMENTS COVERED IN OTHER SPECIFICATION SECTIONS
A. Section 01 01 1 : General Construction Sequence
B. Section 01 040: Coordination
C. Section 01 047: Connection to Existing Facilities
1.3 SANITARY ARRANGEMENTS
A. The Contractor shall be responsible for providing sanitation facilities for his
employees and shall fully comply with the rules and regulations of the State Board
of Health and/or other bodies having jurisdiction. -_
B. The Contractor shall, at all times, provide for his employees abundant supply of
safe drinking water and shall give orders against the use of, for drinking purposes,
any water in the vicinity of the Work known to be unsafe.
C. The Contractor shall provide suitable and conveniently located temporary toilets
for use by his forces. They shall be left at the site until final inspection has been
made.
1.4 NORMAL WORK SCHEDULE
A. Contractor shall conduct all Work within the following District-approved schedule
however, working hours required by traffic control plans supersede this:
1. Normal Work Hours: 8:30 AM to 3:30 PM
2. Normal Work Days: Monday through Friday
B. Exceptions to this Work schedule shall be only as approved in writing by the
District per Paragraph 1.5 below.
1.5 SATURDAY, SUNDAY, HOLIDAY AND NIGHT WORK
A. No work shall be done between the hours of 4:OO p.m. and 7:OO a.m., nor on
Saturdays, Sundays or legal holidays, except such work as is necessary for the
City of Carlsbad
03/04 (DBE)
ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01 048 - Special Construction Conditions and Procedures - General - 1 of 5
_-
proper care and protection of the Work already performed, or except in case of
emergency, and in any case only with the written notice of the Owner.
B. It is understood, however, that night work may be established as a regular
procedure by the Contractor if he first obtains the written notice of the Owner, and
that such notice may be revoked at any time by the Owner if the Contractor fails
to maintain at night adequate force and equipment for reasonable prosecution
and to justify inspection of the Work.
1.6 MITIGATION MEASURES
A. The Contractor shall not operate noisy or otherwise irritating construction
equipment except during normal working hours, 7:OO a.m. through 4:OO p.m.,
Monday through Friday, except with written notice of work as outlined in
Paragraph 1.5.B.
B. The Contractor shall employ dust control measures to the satisfaction of the
Owner throughout the duration of the project.
1.7 COOPERATION WITH OTHER CONTRACTORS
A. The Owner may have additional work performed in this area by other Contractors.
The Contract requires cooperation with those contractors in the area. Any
difference or conflict which may arise between the Contractor and other
contractors shall be adjusted and determined by the Owner. The Contractor shall
conduct his operations as to interfere to the least possible extent with the work
being done by other contractors. The Contractor shall make good, promptly, any
injury or damage to other contractor's work caused at his hands and at his own
expense, and no additional allowance will be made therefore.
1.8 SITE CLEARANCE
A. The Contractor shall restrict his area of activity to avoid damage of trees and
shrubs and shall not remove trees unless specifically directed by the contract
Plans and Specifications or at the Owner's direction. The Contractor is
responsible for the disposal of all material to be removed. If burning is
anticipated, the Contractor shall obtain all necessary permits and shall give ample
and proper notice to the local fire warden.
B. All fences, walls, shrubs, sprinkler systems, substructures or any other
improvement removed or disturbed by the Contractor during construction shall be
replaced and/or repaired at the Contractor's expense to the satisfaction of the
Owner immediately.
1.9 PUBLIC UTILITIES
.* A. Location of utilities shown on the Plans were obtained from maps furnished by the
various utility companies, but may not be entirely accurate. The Contractor shall
cooperate with the utility companies' representation in the field in order to
City of Carlsbad
03/04 (DB E)
ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01 048 - Special Construction Conditions and Procedures - General - 2 of 5
ascertain the location of the utility lines ahead of potholing and trenching
operations. The Contractor shall excavate and expose all utilities crossing the
alignment or parallel to it, and within 5 feet from the alignment, prior to the
submittal of shop drawings for pipe and fittings, in order that any adjustments to
the alignment and/or grade of the proposed work requires modifications or
redesign.
-
1.1 0 COMPACTION TESTING
A. The Owner will bear the costs of all initial compaction testing as specified in
Section 02200. The costs of further testing, made necessary as the result of
materials failing the initial testing, will be paid by the Owner and such costs will be
deducted from the progress payments to the Contractor.
1.1 1 PRE-CONSTRUCTION CONFERENCE
A. A pre-construction conference shall be held prior to the commencement of
construction of the Work herein defined and all understandings, interpretations
and agreements reached at said conference shall be reduced to writing, by the
Owner and mailed to all parties attending said pre-construction conference. The
understanding, interpretations and agreements set forth herein shall hereinafter
be considered as a part of the Contract Documents.
1.12 STANDARDIZATION AND UNIFORMITY OF EQUIPMENT AND CERTAIN -
MATERIALS
A. To ensure standardization and uniformity in all parts of the Work under this
Contract, like items of new (i.e., non-salvaged) equipment shall be the products of
one manufacturer. Like items of certain materials shall be the products of one
manufacturer. Materials, equipment, and appliances shall be current models now
in production.
B. Uniformity in like equipment items is required in order to provide the Owner with
inter-changeability capabilities, simplified spare parts inventory, and standardized
maintenance programs and manufacturers' services.
C. Standardization requirements shall be as specified in the various technical
sections.
D. Generally, material items exempt from standardization include structural steel,
reinforcing steel, building insulation, roofing materials, sheet metal, materials
specified only by reference to a recognized standard, and items hidden from view
where inter-changeability, color, and texture is not a significant factor for
standardization.
E. The Contractor shall inform his suppliers and subcontractors of these - requirements, and shall provide the necessary coordination to accomplish the
standardization specified.
City of Carlsbad
03/04 (DBE)
ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01 048 - Special Construction Conditions and Procedures - General - 3 of 5
1.13 COMPLIANCE WITH STATE SAFETY CODES
A.
_c
All necessary machinery guards, railings, and other protective devices shall be
provided as specified and/or required by the State of California Division of
Industrial Safety and the Occupational Safety and Health Administration. It is
assumed that all fabricators, electrical and machinery manufacturers and other
equipment suppliers are conversant with such regulations and they shall be
responsible for the industrial safety aspects of such equipment. All equipment
shall comply with all rules and regulations of the Safety Orders of the State of
California Division of Industrial Safety and all local building, plumbing, and
electrical codes and ordinances. Safety guards shall be easily removed to permit
inspection, removal and repair of the moving parts.
1.14 FIELD TESTS, ADJUSTMENTS AND OPERATION
A. All mechanical and electrical equipment installed by the Contractor shall be
operated and tested by the Contractor to the satisfaction of the Owner. Tests
shall be made to determine whether the equipment has been properly assembled,
aligned, adjusted, wired and connected. Any changes, adjustments or
replacements of equipment which are due to errors or omissions on the part of the
Contractor shall be done at his own expense.
B. Equipment shall be tested at rated speeds for required performance, - instrumentation control and automatic operation.
C. Any water used during these tests shall be at the expense of the Contractor.
D. During the testing of equipment, the Contractor shall arrange for the presence, as
necessary, of representatives of the manufacturers of all the various pieces of
equipment furnished, to provide instruction for District personnel appointed by the
Owner in the operation and care thereof. The cost of providing qualified
instruction personnel shall be borne by the Contractor.
1.15 LUBRICANTS
A. All equipment shall be properly lubricated and furnished with a one (1) year
supply of all necessary lubricants.
1.16 SERVICES OF MANUFACTURER'S REPRESENTATIVE
A. The Contractor shall provide the services of a trained, qualified manufacturer's
representative familiar with all the equipment to supervise the installation of the
equipment furnished and its start-up. The cost for this service shall be included in
the price bid.
.I B. All equipment shall be checked for lubrication, alignment, rotation, vibration, and
the representative shall notify the Contractor and the Owner of anything in the
installation which might render the manufacturer's guarantee null and void.
City of Carlsbad
03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01 048 - Special Construction Conditions and Procedures - General - 4 of 5
C. The Equipment Manufacturer's representative shall also provide instruction to the
operating personnel as to the proper method of operation and recommend
lubrication (products and schedule). -
D. Minimum on-site services of manufacturer's representatives shall be as specified
elsewhere herein (reference specific specification sections for the various
equipment), or if not specified, shall be as necessary for proper installation by the
Contractor and proper instruction of the Owner in the use and maintenance of the
Work.
1.17 RESPONSIBILITY FOR JOB SITE CONDITIONS
A. Contractor agrees that he shall assume sole and complete responsibility for job
site conditions during the course of construction of this project, including safety of
all persons and property; that this requirement shall apply continuously and not be
limited to normal working hours; and that the Contractor shall defend, indemnify
and hold the Owner and the design consultant harmless from any and all liability
except for that arising from the sole negligence of the Owner.
It is the Contractor's sole responsibility to protect the safety of employees from
construction-related conditions or activities.
1.1 8 CLIMATE AND SITE CONDITIONS
Equipment manufacturers shall make all necessary changes in the to assure that it is suited
for the climatic conditions at the site. The site conditions are as follows:
Elevation: k285 - 325 feet
Minimum Ambient Design Temperature: 31 O F
Maximum Ambient Design Temperature: 110" F
Climate: Outdoor installation
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION (Not Applicable)
END OF SECTION
City of Carlsbad
03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01 048 - Special Construction Conditions and Procedures - General - 5 of 5
SECTION 01 200
PROJECT MEETINGS
PART 1 - GENERAL
1.1 Scope
A. This section addresses requirements for pre-construction meeting, progress
meetings, specially called meetings and post-construction meeting.
1.2 Administrative Responsibilities
A. Meeting Preparation
The Owner's Construction ManagedProject Manager shall prepare agenda, notify
participants, and make physical arrangements for all meetings.
B. Meeting Minutes
The Owner's Construction ManagedProject Manager shall record minutes,
including significant proceedings and decisions for each meeting. Owner's
Construction ManagedProject Manager shall reproduce and distribute copies of
minutes within 5 days after each meeting. Owner's Construction ManagedProject
Manager shall provide copies to the Engineer, all other participants in the
meeting, and all other parties affected by decisions made at the meeting. c
1.3 Pre-construction Meeting
A. General
Before issuance of notice to proceed, a pre-construction meeting will be held at a
time and location designated by the District's Project Manager.
B. Attendance
The meeting shall be attended by the City's Project Manager, the Inspector, the
City's Construction Manager (if any), the Resident Engineer, District's consultants,
the Contractor and his superintendent, all major subcontractors and other persons
designated by the Owner. Contractor's attendance should be in accordance with
Section 6-1.1 of the Supplemental Provisions.
C. Agenda
The agenda for the meeting shall include the following items as a minimum.
cc
1. Distribution and discussion of the construction schedule including critical
construction sequencing.
2. Designation of persons authorized to represent and sign documents for the
Owner and Contractor, with examples of official signature of each.
City of Carlsbad
03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01200 - Project Meetings - 1 of 3
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
Procedures and forms for processing submittals, field decisions, proposal
requests, change orders, applications for payment, and revised construction
schedules.
Procedures for maintaining record documents.
Contractor's use of premises including location of office, construction and
storage areas.
Temporary barricades, utilities, sanitary facilities, signs and other temporary
facilities required.
Safety and first aid procedures including designation of Contractor's safety
officer.
Security procedures.
Housekeeping procedures.
Communication procedures between parties.
List of names, addresses and telephone numbers of those persons
_-_
authorized to act for the Contractor in emergencies. -_
Construction permit requirements, procedures and posting.
Testing laboratory or agency and testing procedures.
Establishment of a schedule for progress meetings.
Other administrative items as appropriate.
1.4 Prowess Meetings
A.
B.
General
Progress meetings shall be held at the dates and times scheduled at the pre-
construction meeting unless changes are agreed to by all parties and appropriate
notification of such changes has been given.
Attendance
The meetings shall be attended by the Engineer and the Contractor's
representative as states in Section 6-2.3 Project meetings of the Supplemental
Provisions. When requested by the Engineer or the Contractor; subcontractors,
and the District's consultants shall also attend. -4.
City of Carlsbad
03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01 200 - Project Meetings - 2 of 3
C. Agenda
.- The agenda for these meetings shall include the following items:
1. Review progress of construction since the previous meeting.
2. Discuss field observations, problems and conflicts.
3. Identify problems which impede planned progress and develop corrective
measures as required to regain the projected schedule. Revise the
construction schedule if necessary.
4. Plan progress during the next construction period.
5. Coordinate the progress of subcontractors.
6. Review changes proposed by the Owner for their effect on the construction
schedule and completion time.
1.5 Special Meetinns
Upon appropriate notice to other parties, special meetings may be called by the District’s
Project Manager or Contractor, at times agreed to by all parties involved.
?-- 1.6 Post-construction Conference
A post-construction conference shall be held before final inspection of the Work to discuss
and resolve all unsettled matters. Bonds and insurance to remain in force, and other
documents required to be submitted by the Contractor will be reviewed and all deficiencies
determined. Schedules and procedures for the final inspection process and for the correction
of defects and deficiencies shall be discussed and agreed.
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION (Not Applicable)
END OF SECTION
.-
City of Carlsbad
03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01200 - Project Meetings - 3 of 3
SECTION 01 300
SHOP DRAWING SUBMllTALS
PART 1 - GENERAL
1.1 Work Included
General procedures and requirements for submittals, initial submittal, submittals required on
Owner’s request, progress reports, shop drawings, product data and samples, notification of
affected residences and businesses, and submittal forms.
1.2 Related Work
A. Section 01400: Quality Control
B. Section 01 700: Contract Closeout
1.3 Submittals
A.
B.
C.
D.
E.
F.
Submit six copies of submittals unless otherwise stated. Three copies will be
returned to the Contractor.
Number submittals using numbering system as directed by the Engineer.
Shop Drawing Transmittal Form. The form included at the end of this section
shall be used unless otherwise directed by Owner. Submit a separate form for
each submittal number. Submittals without completed Contractor’s Transmittal
Form attached to each copy of each submittal listed in Schedule of Submittals will
be returned without review and stamped “REJECTED-RESUBMIT AS
SPECIFIED”.
Exceptions and departures from Contract Documents shall be clearly noted, along
with justification for each exception or departure. Otherwise, review or approval
of submittals- shall not constitute approval of exceptions or departures.
Stock or standard drawings will not be accepted for review unless full
identification and supplementary information is shown thereon in ink or typewritten
form.
Review of submittals shall proceed as follows:
1. Submit specified quantity of complete submittals together with Contractor’s
submittal forms to the Engineer for review. Fold submittals to approximately
9-inches by 12-inches.
2. Submittals will be stamped “ACCEPTED”, “ACCEPTED AS NOTED,
“REVISE AS NOTED/RESUBMIT”, “REJECTED/RESUBMIT AS
SPECIFIED”, NO ACTION REQUIRED” and/or SUBMITTAL NOT
City of Carlsbad
03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01300 - Shop Drawing Submittals - 1 of 8
REQUESTED/RETURNED WITHOUT REVIEW”. Three copies with letter
of transmittal will be returned to Contractor. -
3. Submittals stamped “ACCEPTED” require no further action and
fabrication or construction may proceed. The Engineer will return to the
Contractor the stamped transparency of Shop Drawings and two
stamped copies of brochures, schedules, materials lists, and other
product data, except where required otherwise.
4. Submittal stamped “ACCEPTED AS NOTED” require no further action
and fabrication or construction may proceed contingent upon all
corrections being made as noted. Quantities returned will be as
specified for “Accepted.”
5. Submittals stamped “REVISE AS NOTED/RESUBMIT” or “REJECTED
/RESUBMIT AS SPECIFIED” require the Contractor to resubmit them
with reasonable promptness and no fabrication or construction may
begin. The Engineer will return to the Contractor; one stamped
transparency and one marked copy of shop drawings and one marked
copy and three unmarked copies, all stamped, of brochures, schedules,
materials lists, and other product data.
6. Submittals stamped “NO ACTION REQUIRED” indicate the submittal
was for informational purposes only and does not require review. The
Engineer will return to the Contractor the submitted materials as outlined
under “Accepted.”
.-
7. Submittals stamped ‘SUBMITTAL NOT REQUESTED/RETURNED
WITHOUT REVIEW” indicate the Contractor has submitted drawings,
etc. that were not required and therefore, were not reviewed or accepted
by the Engineer.
G. Costs incurred by Owner for second and subsequent re-submittals will be
deducted from payment due Contractor.
H. Allow not less than 30 calendar days for review and response to submittals.
Review may be delayed if contingent on receipt of other submittals. Upon timely
written request by Contractor, the Engineer will make reasonable efforts to
shorten review periods which may fall on Contractor’s critical path.
I. Do not begin work described in submittals until such submittals have been
reviewed and returned by Owner stamped “ACCEPTED” or “ACCEPTED AS
NOTED“. Acceptance of delivery of products prior to receipt of the Engineer’s
satisfactory return of applicable submittals shall be at Contractor’s risk.
City of Carlsbad
03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01300 - Shop Drawing Submittals - 2 of 8
1.4 Submittals on Owner's Request Supplemental Information
F
A.
B.
C.
D.
E.
F.
G.
Detailed construction schedule updates shall be submitted, with monthly pay
requests to describe scheduling of elements of construction requiring Owner's or
Contractor's coordination with public, or other private parties or public agencies.
Supplemental information will be requested for "approved equals" and may be
requested when there is a question that a manufacturer's product conforms to
Contract Documents. Owner reserves right to require submittal of supplemental
information as described herein before approval of product.
Certification of compliance with listed reference standards shall be submitted by
manufacturers on owner's request. Failure of Owner to request certification of
compliance shall not serve as waiver of Contractor's duty to comply with reference
standards.
Transcripts of results of acceptance tests performed at point of manufacture of
products furnished shall be submitted by manufacturers on Owner's request.
Samples shall be submitted on Owner's request.
Names and addresses of nearest local service representatives that maintain
technical service personnel and complete inventory of spare parts and
accessories shall be submitted on owner's request.
List of three installations in which products comparable in size, capacity and rating
with those required in Contract Documents are now in regular operation shall be
submitted on Owner's request. Include listing of size capacity or rating of each
installation. Include name and telephone number of at least one reference
responsible for operations at each installation whom the Engineer may contact.
1.5 Progress Reports
A.
B.
C.
Daily log shall be submitted by Contractor's superintendent on a one page form
provided by Owner. These logs shall be detailed with activities that took place
during each day. Submit logs daily to the Resident Engineer.
Schedule updates shall be submitted with monthly pay requests. If Work falls
behind schedule, monthly pay requests shall include revised schedules to
demonstrate how Contractor intends to bring work back on schedule.
Record drawings, consisting of one set of annotated blueline plans and other
drawings forming a part of the contract, showing installed locations of
improvements and all changes made during construction shall be available to the
Owner for inspection throughout project. Record all deviations from Contract
Documents, including approved change orders, using additional sketches or ink
revisions, immediately after installing each portion of Work. Show locations of
underground piping, conduit, sensor lines, valves, capped ends, branch fittings,
pull boxes and Work. Keep one current record copy of Contract Documents,
City of Carlsbad
03/04 (DBE)
ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01 300 - Shop Drawing Submittals - 3 of 8
addenda, supplementary drawings, working drawings, change orders and
clarifications at site and in good order. Report changes and deviations promptly
to Resident Engineer.
-
D. Partial payment requests may be withheld if daily logs, schedule updates or
record drawings are damaged, lost or not kept current to satisfaction of the
Engineer.
1.6 Shop Drawinas and Product Data
A.
B.
C.
D.
E.
Shop drawings shall clearly show dimensions, clearances, slopes, floor space
requirements, tolerances, conduit, anchor bolt sizes and embedments, finishes,
performance characteristics, and weight and type of products. Shop drawings
shall indicate the location at which products are to be installed, how equipment
will be mounted, how it relates to adjacent structures or products, and how
connection will be made between Work under this contract and work under other
contracts. Shop drawings shall show parts lists and details of appurtenances to
be furnished with specified items, along with references to appropriate ASTM,
Federal Specifications and other reference standards and grades. Use of
contract drawing reproductions for shop drawings is subject to rejection.
Catalog data shall clearly indicate applicable items when several products are
covered on one page. Using black ink, indicate on submitted catalog data,
Installation or Application Instructions shall be manufacturer's printed instructions
including warranty requirements, clearances required and proper field procedures
to deliver, handle, install and prepare product for use. In the absence of
manufacturer's published literature, ASTM, AWWA or trade standards for proper
installation will be accepted.
specification section or plan reference being satisfied. -.
Operation and Maintenance Instructions shall be manufacturer's printed
instructions for correct operation and maintenance procedures for product, along
with data which must accompany manual as directed by current regulations of
government agency. Include operating instructions for each piece of equipment.
Describe equipment function, operating characteristics, limiting conditions,
operating instructions, startup procedures, normal and emergency conditions,
regulation and control, and shutdown. Include preventative maintenance
instructions. List warranty requirements. Explain and illustrate preventative
maintenance tasks. Include lubrication charts, lists of acceptable lubricants,
trouble shooting instructions, and lists of required maintenance tools and
equipment. List recommended spare parts, their costs, and ordering information
for 1 manufacturer who can supply these parts. Index instructions for easy
reference. Include information for installed equipment only.
Manufacturer's Statement of Responsibility shall be copy of form attached, signed
by authorized factory representative for manufacturer whose product is being
furnished. -
City of Carlsbad 03/04 (DB E) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01 300 - Shop Drawing Submittals - 4 of 8
F. Certification of Compliance shall certify materials have been sampled, tested and
found to comply with applicable reference standards.
G. Engineering Calculations shall be clearly legible, and shall demonstrate
compliance with state and local codes, applicable standards, and contract
requirements. Calculations shall be sealed by a licensed engineer.
e-
1.7 Samples
A.
B.
C.
D.
,c- E.
F.
G.
Furnish samples, finished as specified, and as intended to be used on or in Work.
Send samples to the Engineer, carriage prepaid.
Submit samples before purchasing, fabricating, applying, or installing products.
Allow at least 30 days for review and return of samples.
Submit two of each sample, except for field samples. Attach completed
Contractor's submittal form to sample. List items being transmitted, stating
proposed use and location, product, color, trade name, lot, style, and model as
appropriate.
Resubmit samples until acceptable. One of each sample will be returned to
Contractor upon acceptance.
Samples of finishes shall be 8%'' x 10". and shall be of minimum thickness
consistent with sample presentation. In lieu thereof, submit actual full-size item.
Samples of value may be returned to Contractor for use in Work after review,
analysis, comparison, and/or testing as may be required by the Engineer.
Furnish one sample of approved products, colors, or textures to the Engineer for
final record. Show identification previously described including, if finish sample,
manufacturer, mix proportion, name of color, building, Contractor, subcontractor,
and surfaces to which applied on back of sample.
1.8 Pre-construction Video
A. Pre-construction video shall be submitted to the Engineer before Work is
performed which has potential to disturb or modify public or private property not
owned by Owner. Video shall be of sufficient quality and thoroughness to fully
document preexisting damage or wear to property for which Contractor or Owner
might be asked to compensate property owner were it not for photographic
evidence of preexisting damage. Failure by Contractor to submit pre-construction
video, may be taken by owner as evidence that subsequent claims by property
owners for damage to their property can be rightfully attributed to Contractor's
act ions.
City of Carlsbad
03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01300 - Shop Drawing Submittals - 5 of 8
1.9 Notification of Affected Residences and Businesses
A
A. Written notification, with Contractor's 24-hour emergency phone number, shall be
provided to residences and businesses fronting the project on either side of street.
Notify these parties 72 hours in advance of construction which will affect these
properties. Door-hangers or other means of notification shall be submitted to and
approved in advance by the Engineer.
1.10 Notification to the Water Utilities Department
The Contractor shall submit a detailed plan and written description of any water line tie-in.
The plan will include, but is not limited to, all necessary pumps, standby pump@), piping,
appurtenances, and 24-hour staffing schedule. When the submittal has been approved, and
all necessary testing has been successfully completed, the Contractor will submit a Request
for Shutdown seven (7) working days in advance of the anticipated shutdown date.
1.1 1 Unit Prices
A. Payment for submittals and re-submittals, will be included in the price bid for
those items of Work for which the submittals are required.
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION (Not Applicable)
END OF SECTION
City of Carlsbad
03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01 300 - Shop Drawing Submittals - 6 of 8
SHOP DRAWING TRANSMllTAL FORM ..--
FROM: DATE:
PROJECT NAME: El Camino ReaVCassia
Road 24" And 30 Domestic Water
Transmission Mains
Phone: FAX:
TO: Daniel Bovle Enqineerincl, Inc. PROJECT NO.:
3142 Vista Wav, Suite 303
Oceanside, CA 92056 OWNER: City of Carlsbad
ATTN: Mr. Daniel G. Smith 5950 El Camino Real
Proiect Manaqer Carlsbad, CA 92008
THIS IS AN ORIGINAL THIS IS A REVISION
SUBMITTAL NO.: SUBMITTAL OF SUBMITTAL NO.:
SUBJECT OF SUBMITTAL:
SPECIFICATION SECTION(S):
PLAN SHEET NUMBER(S):
.c
CONTRACTOR'S CERTIFICATION: Check & Complete either (A) or (B) below:
We have reviewed in detail and certify that the material, equipment or
construction procedure(s) contained in this submittal meet all the
requirements specified in or shown on the Contract Documents,
Construction Specifications and Construction Plans with no exceptions.
(4
We have reviewed in detail and certify that the material, equipment or
construction procedure(s) contained in this submittal meet all the
requirements specified in or shown on the Contract Documents,
Construction Specifications and Construction Plans except for the followinq
deviations:
(B)
- CONTRACTOR'S AUTHORIZED SIGNATURE:
City of Carlsbad
03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains
01 300 - Shop Drawing Submittals - 7 of 8