HomeMy WebLinkAboutDe Lise and Associates Inc; 1987-01-30;January 19, 1987
Mr. Thomas L. Brammell
Costa Real Municipal Water District
5950 El Camino Real
Carlsbad, California 92008
Dear Mr. Brammell:
c
c
-_
De Lise and Associates, Inc. appreciates the opportunity to submit
this agreement for a facility utilization study and preliminary
schematic design for your existing property in Carlsbad, Califor-
nia. Immediately following your approval, we shall proceed with
the following scope of work:
Phase I - Proeram Analvsis
1-1 Establish Program Objectives (Goals, Concepts, Needs)
Includes site visitations and consultation between general
manager, architect, space planner.
1.2 Review surveys, soil tests, reports, codes, ordinances, and
drawings for site. Surveys, test reports, and drawings to
be provided by Costa Real Water District. De Lise and
Associates to research codes and ordenances.
1.3 Prepare Schedule
A time schedule will be prepared outlining areas of respon-
sibility, dates, and tasks to be performed. Schedule will
be revised during project as required and updated version
sent to general manager,
1.4 Site Analysis Study for access, view, and appropriateness
for construction.
1.5 Establish Requirements and Priorities Including:
A. Study and document interdepartmental adjacency matrix.
B. Establish Contact Patterns within departments.
c
Costa Real Municipal Water District
January 19, 1987
Page Two
1.6 Determine Existine and Proiected Space Requirements.
Note: 1.5 and 1.6 will be determined by on-site study of individ-
ual departments and interviews with department managers.
Findings will be organized and reviewed for modification by
space planner and general manager. Findings will be doc-
umented graphically. (See exhibit "A" and "B" attached.)
Phase I1 - Schematic Desien
2.1 Architect and Space Planner will create schematic drawings
to depict their concepts for site plan, building plan, mat-
erial selections, interior blockouts by departments and of-
fices. Projected growth will be indicated within the phased
Master Plan. We will provide conceptual sketches of exterior
elevation (one), interior reception area, and details to depict
overall image.
2.2 Space Planner will establish furniture and equipment layouts
for all departments and private offices. Optional layouts
will be reviewed in a preliminary form by space planner and
general manager. One or two final layouts for each area will
be provided in plan view in utilization study. All furniture
and equipment will be noted by symbol and legend.
2.3 Establish preliminary building standard specifications for
construction to include: -- . Exterior shell materials and construction.
e
Recommended mechanical system.
Interior construction standards for walls, ceilings,
lighting, doors, frames, hardware, ceiling heights,
finishes, and window coverings.
Note: Building Standard Specifications will be written for the
purpose of obtaining preliminary design concepts and
preliminary cost estimate only. Detailed specifications
will be included in design development and construction
documents which are not included.
Phase 111 - Construction Schedule and Budnet
Architect, space planner, general contractor to review program
analysis and schematic design. General contractor to provide
preliminary cost analysis and preliminary construction schedule.
Professional fees for remainder of work: design development, con-
struction documents, and specifications shall be included as a
budget item in preliminary cost analysis.
c
L
c
c
Costa Real Municipal Water District
January 19, 1987
Page Three
Phase IV - PreDaration of Documents Into Presentation Form
De Lise and Associates, Inc. will collect and prepare all infor-
mation covered in Phases I through I11 into presentation report.
Report will include analysis of entire program, conceptual
design sketches, interior blockouts, furniture layouts, value
engineering recommendations, preliminary cost estimate, and
preliminary construction schedule.
Professional Fees
Based upon the scope of work as outlined in this agreement, we
value our services as follows:
Lump Sum: $29,500.00
Basic compensation shall consist of a retainer of $6,250.00 payable
along with the receipt of this signed agreement and an additional
lump sum of twenty-three thousand two hundred fifty dollars shall
be paid as the services are rendered and upon submission of a
statement of services performed for that period of work. The amount
of each statement will be calculated out at standard billing rates
(attached). The retainer shall be applied to the final billing.
Reimbursable Expenses and Additional Services
Certain expenses, when incurred as a necessary part of project
development are reimbursable. These expenses include: Services
defined as direct expenses (see attached Standard Billing Rates).
The following items are not included in the above contract, and
are deemed additional services and, after written approval by the
general manager or the board, will be billed at the hourly rate
schedule. (see attached).
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
General construction.
Professional renderings or models.
Permit and plan check fees.
Any changes made by client after plan approval which requires
additional work or rework.
Services not covered in contract.
Graphics, interior foliage.
Design development, construction documents, and specifications.
Structural, civil other consultants not covered in contract.
Landscape design.
Soil reports, hydrologic drainage report.
Costa Real Municipal Water District
January 19, 1987
Page Four
c
c
L-
General Terms and Conditions
Drawings, schedules and specifications as instruments of service
are and shall remain the property of the Designer whether the
project for which they are prepared is executed or not. The
Owner shall be permitted to retain copies, including reproducible
copies, of drawings, schedules, and specifications for information
and reference in connection with the Owner's use and occupancy of
the project. The drawings, schedules and specifications shall not
be used by the Owner on other projects oe for completion of this
contract by others, provided the Designer is not in default under
this Agreement, except by Agreement in writing and with appropriate
compensation to the Designer.
De Lise and Associates, Inc., shall receive full and appropriate
credit on all publicity releases, reproductions and site signage.
In the event of substantial failure to perform in accordance with
the terms of this agreement, this contract may be terminated by
either party upon 30 days written notice. In the event of termin-
ation client shall pay De Lise and Associates, Inc., for services
rendered up to the date of termination.
All claims, disputes, and other matters in question between the
parties to the Agreement arising out of or relating to this
Agreement or the breach thereof, shall be decided by arbitration
in accordance with the Construction Industry Arbitration Rules
of the American Arbitration Association then existing unless the
parties mutually agree otherwise. Owner, Designer, and consultant
are bound, each to the other by this arbitration clause, provided
such party signed this contract or has signed another contract
which incorporates this contract by reference, or signs any other
agreement to be bound by this arbitration clause. Arbitration
shall be had in accordance with the applicable Rules of the
American Arbitration Association which are in effect at the time
the demand for arbitration is filed. Should any party refuse or
neglect to appear or participate in arbitration proceedings, the
arbitrator is empowered to decide the controversy in accordance
with whatever evidence is presented. The arbitrator is authorized
to award any party or parties such sums as he shall deem proper for
the time, expense and trouble or arbitration. The Owner agrees to
limit the Design Professional's liabilities to the Owner, due to
the Design Professional's negligent acts, errors, or omissions, such
that the total aggregate liability of each Design Professional to
all those named shall not exceed the total fee for services rendered
on this project.
Costa Real Municipal Water District
January 19, 1987
Page Five
Billings will be prepared and invoiced every two weeks in pro-
portion to service performed. Payment is due net ten days of
invoice date. A service charge of one and one half percent
(18 percent per annual rate) will be charged on all invoices
past due.
If the foregoing meets with your approval, please indicate by
signing the original. A copy of this contract is included
for your records.
Submit ed : Accepted and Approved: A 1 L
c
c Director of Design General Manager
De Lise and Associates, Inc. Costa Real Municipal Water District
Date: Date:
c
I
L
--
-.9-
STANDARD BILLING RATES
PRINCIPAL $80.00/HOUR
I
I-- DIRECTOR OF DESIGN $65.00/HOUR
ARCHITECT $65.00/HOUR
SENIOR DESIGNER $45.00/HOUR
DESIGNER $35.00/HOUR
JUNIOR DESIGNER $25.00/HOUR
r-
DRAFTSPERSON $25.00/HOUR
NON-TECHNICAL SUPPORT PERSONNEL $22.60/HOUR
Direct expenses are reimbursable on a cost plus 15%.
These expenses are defined as follows:
Consultant's Services
Reproduction Services
Long Distance Telephone Calls
Travel Expenses
Overnight Lodging
Meals Away From Home City
Messenger Service
Parking
Photographic Documentation
Computer Service