HomeMy WebLinkAboutEncina Wastewater Authority; 1992-11-06;m 0 T
i
-*
ENCINA WASTEWATER AUTBORITY CONSTRUCTION AGREEMENT
ENCINA COMPOSTINB PROJECT .. FOR TEE
Ref: 34'
This Agreement (hereinafter the Construction Agreement)
19' by and among the CITY OF CARLSBAD (hereafter Carlsbad) , the CITY t VISTA (hereafter Vista), the VALLECITOS WATER DISTRICT, (hereaftc Vallecitos) , the LEUCADIA COUNTY WATER DISTRICT (hereaftc
Leucadia) , the BUENA SANITATION DISTRICT (hereafter Buena) , and tl
ENCINITAS SANITARY DISTRICT (hereafter Endnitas) , herein call1
the "member agencies" for the construction of their jointly own1
composting facility.
made and entered into this 6th day of NOVEMBER
RECITALS
WHEREAS, the member agencies own and operate the Encina Joi
Sewer System pursuant to the Revised Basic Agreement,
WHEREAS, the member agencies have adopted a Revis
Establishment Document, establishing the Encina Wastewat
Authority (EWA), a separate but subordinate public agency,
operator and administrator of the Encina Joint Sewer System,
WHEREAS, the member agencies are planning to construct a operate a biosolids composting facility (Unit K) as part of t
Encina Joint System to provide a reliable, long-term manageme
option for the biosolids generated at the Encina Water Polluti
Control Facility (Unit I), hereafter referred to as "Encinal8; a
WHEREAS, the member agencies desire the EWA to administer t construction of the composting facility;
NOW THEREFORE, TEE PARTIES HERETO AGREE AS FOLLOWS:
Section 1. Definitions
For the purposes of this agreement, the following terns sha have the meanings listed below:
1.1
produced by wastewater treatment processes, that can
beneficially recycled.
Section 2. Cornposting Project (Unit K) Phasing
2.1 Phase I Project Description and Capacity: The Pha I Cornposting Facility shall be as described in the May 13, 1991
Biosolids - Primarily organic solid material
EXHIBIT #1
e 0 “U ‘
*
*I
Conceptual Cost Estimate Report by John Carollo Engineers. Th project shall incorporate an in-vessel composting system sized t
accomodate up to approximately 6 dry tons of biosolids per da
with storage facilities oversized to accommodate ultimat
expansion.
The size of the Phase I facility may be modified at the discretio
of the Operator/ Administrator. Any such modification must b within the approved capital budget. Budget procedures shall be a
set forth in the Revised Basic Agreement.
Capacity rights shall be in the same percentage as the membe
Joint System upon as described in Section 9.2 of the Revised Basi
Agreement.
Assuming the facility will process 4 to 6 dry tons of biosolids pe day, the capacity per agency shall be as follows:
. agency‘s percentage of solids capacity rights in Unit ((It1 of th
PHASE I CAPACITY (DRY TONS PER DAY) * OWNERSHIP (%)
VISTA: 0.85 to 1.27 21.18
0.97 to 1.46 24.32
BUENA: 0.37 to 0.55 9.24
VALLECITOS : 0.79 to 1.19 19.84
LEUCADIA : 0.83 to 1.24 20.68
ENCINITAS : 0.19 to 0.29 4.74
TOTAL 4 to 6 100.00
*The actual ownership capacity will be determined by multiplyir
the percent ownership per agency by the actual rated capacity c
the facility following final design and facility construction a1
start-up.
2.2 Land Use Permits for the Phase I Facility: The Compostix
Facility site is presently located in an unincorporated area of tl County of San Diego, and within the sphere of influence of the Cil of San Marcos. The Operator/Administrator shall pursue a:
necessary approvals from the agency(s) responsible fc
jurisdictional control, in order to obtain land use permits for tl
facility on behalf of the member agencies.
In order to facilitate future expansion, the Operator/Administrat(
may pursue permits for a facility sized to accommodate tl
estimated biosolids production in the year 2010 (ultimate facilii
capacity)
The permitting of a facility of any certain size shall not bind tl
Member Agencies to any greater financial commitment than thi
identified in the approved capital budget.
CARLSBAD:
2.3 Future Expansion of Phase 1 Cornposting Facility:
2.3 Future Ex db nsion of Phase 1 Composti @ Facility:
- y* \
*< Increased capacity resulting from any future enlargement of thc Phase I facility shall belong to those member agencies paying thc
cost and expense thereof. Pending the availability of capacity, a:
described in Section 9 of the Revised Basic Agreement, no membe:
agency shall unreasonably withhold consent to such enlargement
Any such enlargement shall be constructed in accordance with plan:
and specifications approved by the Operator/Administrator.
section 30 Phase I Cost Allocations
The estimated total cost of Phase I, including design, sit
acquisition, construction and other attendant costs, is no
expected to exceed $17,800,000. If this amount is expected to b
exceeded, the Operator/Administrator shall so note in presentin(
the capital budget proposal under the RBA. The costs shall b
apportioned to the member agencies based on the Unit K ownershi
percentages set forth in Section 9.2 of the Revised Basic Agreemen
and as identified in Section 2.1 herein. The estimated Phase
costs shall be as follows (ownership percentages are listed i
Section 2.1) :
Aaency Estimated Phase I Cost
Vista $3,769,000 Carlsbad 4,333,000 Buena 1,643,000 Vallecitos 3,532,000 Leucadia 3,680,000 Encinitas 843,000 Total $17,800,000
Section 4. Payment of Phase I Capital Expenses
Phase I contract expenses approved by the Operator/Administrato
shall be paid in accordance with the provisions established in it
agreements with associated consultants, engineers, contractors
construction manager, and others. The payments will vary overth duration of the project implementation, construction, and start-up The Operator/Administrator shall notify the member agencies of th
amounts needed following receipt of invoices.
8ection so Counterparts
This Agreement may be executed in counterparts and up0
execution thereof by all of the member agencies, each SUC
counterpart shall be deemed to be an original.
CONSTRUCTION AGREEMENT to b resentative
officials duly authorized by the
IN WITNESS WHEREOF, eac
0 0 >-*
REVISED BASIC AGREEMENT
AND MAINTENANCE OF A JOINT SEWAGE SYSTEM
FOR OWNERSHIP, OPERATION
SEPTEMBER 25, 1992 Ref: 432E
8
0
EXHIBIT #2
e e ,.
TABLE OF CONTENTS
Paqe
RECITALS . 0 Section 1 DEFINITIONS .................
1.1 Joint Advisory Committee (JAC) ........
1.2 Joint System .................
1.3 Member Auencies ............... 1.4 Operator/Administrator ............
Section 2 JOINT PARTICIPATION .............
Section 3 AREA TO BE SERVED BY THE JOINT SYSTEM .... 3.1 Existins Sewice Area ............
3.2 Revisions to the Service Area ........
3.3 Prohibition on Discharues from Outside the Exhibit A Sewice Area ............
Section 4 ENLARGEMENT OF THE JOINT SYSTEM ....... Section 5 PROTECTION OF THE JOINT SYSTEM/SOURCE CONTROL ...................
5.1 Protection of the Joint System ........
5.2 Prohibitions .................
Section 6 CAPACITY AND USE OF CAPACITY (CAPACITY INFRINGEMENT) ................
Section 7 CAPACITY MONITORING .............
Section 8 ACQUISITION/SALE OF EXCESS CAPACITY ..... Section 9 CAPACITY RIGHTS IN UNITS ........... ..............
.....
9.31 Pest TT ' Unit I and Unit J
CaDacitv. ..................
4.1 x-*; Iz&+KFme& ........
9.43 - Unit 1 Capacity Infrinsement. . a. Flow Calculation .............
b. Monitorins of CaDacitv Demand ...... c. Excess Use a Trespass ..........
d. Indemnitv and Hold Harmless ....... e. License Payments .............
Resenre. ................
g. Reserve CaDacitv .............
f. Restrictions on Use Over 40% of
h. Sole Method of Allocation .......
Section 10 DEFINITION OF PHASE IV COMPUETION
Section 11 CAPACITY RIGHTS FOR RECLAMZ4TION 11.1 Future Reclamation ............
Section 12 JOINT ADVISORY COMMITTEE 0
11.2 Existinu Reclamation ...........
12.1 Powers ..................
12.2 Representation on JAC ........... 12.3 Officers of JAC ..............
12.4 Meetinas of the JAC . . . . . . 12.5 Rules ...................
12.6 Payment for Attendance ..........
12.7 Assistance from the Operator/Administrator Section 13 OPERATOR/ADMINISTRATOR 13.1 General Duties ..............
13.2 Desiunation and Specific Powers ......
0 e 3, . '"
Section 14 BUDGETING AND ACCOUNTING . . . . . . . 3 14.1 Annual Budqets . . . . . . . . . . . . . . 3 Section 15 ASSISTANCE TO OPERATOR/ADMINISTRATOR - 3 Section 16 RIGHTS OF WAY AND LAND ACQUISITIONS . 3
EXPENSES 0 0 . . 3 17.1 Allocation of Emenses . . . . . . . . 3 17.2 Pavment Schedule . . . . . . . . . . 3 Section 18 PAYMENT OF CAPITAL EXPENSES 3 18.1 Allocation of Emenses . . . . . . 3
18.2 Pavment Schedule . . . . . . . . . . . . 3 Section 19 SETTLEMENT OF DISPUTE OR CONTROVERSY . 3
19.1 Rishtto Arbitration . . . . . . . . . 1
19.2 Riaht of Observation . . . . . . . . . . 1
19.3 Riqht to Emert Arbitration . . . . . . . . 1
Section 20 APPORTIONMENT OF LIABILITY . . . . . . 1
Section 21 NOTICES. ............... 1
Section 22 SEVERABILITY . . . . . . . . . . . . 1
Section 23 MODIFICATION OF AGREEMENT . . . . . . 1
Section 24 SUCCESSION . . . . . . . . . . . . 1
Section 25 APPROVAL . . . . . . . . . . . . . . 1
Section 17 PAYMENT OF OPERATION AND MAINTENANCE
-