HomeMy WebLinkAboutLeckey Consulting Inc; 2007-07-25;AGREEMENT FOR PROJECT MANAGEMENT SERVICES LECKEY CONSULTING, INC. THIS AGREEMENT is made and entered into as of the c^23 day of 2007, by and between the CITY OF CARLSBAD, a municipal_ corporation, ("City"), and Leckey Consulting, Inc., a corporation, ("Contractor"). RECITALS A. City requires the professional services of a project manager that is experienced in system upgrades and implementations. B. Contractor has the necessary experience in providing professional services and advice related to system upgrades and implementations. C. Selection of Contractor is expected to achieve the desired results in an expedited fashion. D. Contractor has submitted a proposal to City and has affirmed its willingness and ability to perform such work. NOW, THEREFORE, in consideration of these recitals and the mutual covenants contained herein, City and Contractor agree as follows: 1. SCOPE OF WORK City retains Contractor to perform, and Contractor agrees to render, that portion of the services (the "Services") that are defined in Section 1.1.2 (Phase 2 Scope of Services) of the contractor's proposal and listed in the contractor's work plan for completion between September 10, 2007 and December 28, 2007, both attached as Exhibit "A", which is incorporated by this reference in accordance with this Agreement's terms and conditions. 2. STANDARD OF PERFORMANCE While performing the Services, Contractor will exercise the reasonable professional care and skill customarily exercised by reputable members of Contractor's profession practicing in the Metropolitan Southern California Area, and will use reasonable diligence and best judgment while exercising its professional skill and expertise. 3. TERM The term of this Agreement will be effective for a period of one year from the date first above written. 4. TIME IS OF THE ESSENCE Time is of the essence for each and every provision of this Agreement. 5. COMPENSATION The total fee payable for the Services outlined in the Scope of Services described in Section 1 will not exceed fifty eight thousand, four hundred dollars ($58,400). Fees shall City Attorney Approved Version #11.28.06 be paid on an hourly basis per the hourly rate schedule outlined in Exhibit "B", with the Not-to-Exceed Contract Amount for this portion of Phase 2 set at $58,400 to include both consulting and travel costs. Incremental payments, if applicable, should be made as outlined in attached Exhibit "B". No other compensation for the Services will be allowed except for items covered by subsequent amendments to this Agreement. The City reserves the right to withhold a ten percent (10%) retention until City has accepted the work and/or Services specified in Exhibit "A". 6. STATUS OF CONTRACTOR Contractor will perform the Services in Contractor's own way as an independent contractor and in pursuit of Contractor's independent calling, and not as an employee of City. Contractor will be under control of City only as to the result to be accomplished, but will consult with City as necessary. The persons used by Contractor to provide services under this Agreement will not be considered employees of City for any purposes. The payment made to Contractor pursuant to the Agreement will be the full and complete compensation to which Contractor is entitled. City will not make any federal or state tax withholdings on behalf of Contractor or its agents, employees or subcontractors. City will not be required to pay any workers' compensation insurance or unemployment contributions on behalf of Contractor or its employees or subcontractors. Contractor agrees to indemnify City within thirty (30) days for any tax, retirement contribution, social security, overtime payment, unemployment payment or workers' compensation payment which City may be required to make on behalf of Contractor or any agent, employee, or subcontractor of Contractor for work done under this Agreement. At the City's election, City may deduct the indemnification amount from any balance owing to Contractor. 7. SUBCONTRACTING Contractor will not subcontract any portion of the Services without prior written approval of City. If Contractor subcontracts any of the Services, Contractor will be fully responsible to City for the acts and omissions of Contractor's subcontractor and of the persons either directly or indirectly employed by the subcontractor, as Contractor is for the acts and omissions of persons directly employed by Contractor. Nothing contained in this Agreement will create any contractual relationship between any subcontractor of Contractor and City. Contractor will be responsible for payment of subcontractors. Contractor will bind every subcontractor and every subcontractor of a subcontractor by the terms of this Agreement applicable to Contractor's work unless specifically noted to the contrary in the subcontract and approved in writing by City. 8. OTHER CONTRACTORS The City reserves the right to employ other Contractors in connection with the Services. 9. INDEMNIFICATION Contractor agrees to indemnify and hold harmless the City and its officers, officials, employees and volunteers from and against all claims, damages, losses and expenses City Attorney Approved Version #11.28.06 including attorneys fees arising out of the performance of the work described herein caused by any negligence, recklessness, or willful misconduct of the Contractor, any subcontractor, anyone directly or indirectly employed by any of them or anyone for whose acts any of them may be liable. The parties expressly agree that any payment, attorney's fee, costs or expense City incurs or makes to or on behalf of an injured employee under the City's self- administered workers' compensation is included as a loss, expense or cost for the purposes of this section, and that this section will survive the expiration or early termination of this Agreement. 10. INSURANCE Contractor will obtain and maintain for the duration of the Agreement and any and all amendments, insurance against claims for injuries to persons or damage to property which may arise out of or in connection with performance of the services by Contractor or Contractor's agents, representatives, employees or subcontractors. The insurance will be obtained from an insurance carrier admitted and authorized to do business in the State of California. The insurance carrier is required to have a current Best's Key Rating of not less than "A-:V". 10.1 Coverages and Limits. Contractor will maintain the types of coverages and minimum limits indicated below, unless City Attorney or City Manager approves a lower amount. These minimum amounts of coverage will not constitute any limitations or cap on Contractor's indemnification obligations under this Agreement. City, its officers, agents and employees make no representation that the limits of the insurance specified to be carried by Contractor pursuant to this Agreement are adequate to protect Contractor. If Contractor believes that any required insurance coverage is inadequate, Contractor will obtain such additional insurance coverage, as Contractor deems adequate, at Contractor's sole expense. 10.1.1 Commercial General Liability Insurance. $1,000,000 combined single-limit per occurrence for bodily injury, personal injury and property damage. If the submitted policies contain aggregate limits, general aggregate limits will apply separately to the work under this Agreement or the general aggregate will be twice the required per occurrence limit. 10.1.2 Automobile Liability, (if the use of an automobile is involved for Contractor's work for City). $1,000,000 combined single-limit per accident for bodily injury and property damage. 10.1.3 Workers' Compensation and Employer's Liability. Workers' Compensation limits as required by the California Labor Code and Employer's Liability limits of $1,000,000 per accident for bodily injury. Workers' Compensation and Employer's Liability insurance will not be required if Contractor has no employees and provides, to City's satisfaction, a declaration stating this. City Attorney Approved Version #11.28.06 10.1.4 Professional Liability. Errors and omissions liability appropriate to Contractor's profession with limits of not less than $1,000,000 per claim. Coverage must be maintained for a period of five years following the date of completion of the work. 10.2. Additional Provisions. Contractor will ensure that the policies of insurance required under this Agreement contain, or are endorsed to contain, the following provisions: 10.2.1 The City will be named as an additional insured on General Liability. 10.2.2 Contractor will obtain occurrence coverage, excluding Professional Liability, which will be written as claims-made coverage. 10.2.3 This insurance will be in force during the life of the Agreement and any extensions of it and will not be canceled without thirty (30) days prior written notice to City sent by certified mail pursuant to the Notice provisions of this Agreement. 10.3 Providing Certificates of Insurance and Endorsements. Prior to City's execution of this Agreement, Contractor will furnish certificates of insurance and endorsements to City. 10.4 Failure to Maintain Coverage. If Contractor fails to maintain any of these insurance coverages, then City will have the option to declare Contractor in breach, or may purchase replacement insurance or pay the premiums that are due on existing policies in order to maintain the required coverages. Contractor is responsible for any payments made by City to obtain or maintain insurance and City may collect these payments from Contractor or deduct the amount paid from any sums due Contractor under this Agreement. 10.5 Submission of Insurance Policies. City reserves the right to require, at anytime, complete and certified copies of any or all required insurance policies and endorsements. 11. BUSINESS LICENSE Contractor will obtain and maintain a City of Carlsbad Business License for the term of the Agreement, as may be amended from time-to-time. 12. ACCOUNTING RECORDS Contractor will maintain complete and accurate records with respect to costs incurred under this Agreement. All records will be clearly identifiable. Contractor will allow a representative of City during normal business hours to examine, audit, and make transcripts or copies of records and any other documents created pursuant to this Agreement. Contractor will allow inspection of all work, data, documents, proceedings, City Attorney Approved Version #11.28.06 and activities related to the Agreement for a period of three (3) years from the date of final payment under this Agreement. 13. OWNERSHIP OF DOCUMENTS All work product produced by Contractor or its agents, employees, and subcontractors pursuant to this Agreement is the property of City. In the event this Agreement is terminated, all work product produced by Contractor or its agents, employees and subcontractors pursuant to this Agreement will be delivered at once to City. Contractor will have the right to make one (1) copy of the work product for Contractor's records. 14. COPYRIGHTS Contractor agrees that all copyrights that arise from the services will be vested in City and Contractor relinquishes all claims to the copyrights in favor of City. 15. NOTICES The name of the persons who are authorized to give written notices or to receive written notice on behalf of City and on behalf of Contractor under this Agreement. For City: Name: Kevin Branca Title: Assistant Finance Director Department: Finance City of Carlsbad Address: 1635 Faraday Avenue Carlsbad, CA 92008 Phone No.: (760)602-2418 For Contractor: Name: Steve Leckey Leckey Consulting, Inc. Title: President Address: 4927 Runway Drive Fair Oaks, CA 95628 Phone No.: (916)802-9500 Each party will notify the other immediately of any changes of address that would require any notice or delivery to be directed to another address. 16. CONFLICT OF INTEREST City will evaluate Contractor's duties pursuant to this Agreement to determine whether disclosure under the Political Reform Act and City's Conflict of Interest Code is required of Contractor or any of Contractor's employees, agents, or subcontractors. Should it be determined that disclosure is required, Contractor or Contractor's affected employees, agents, or subcontractors will complete and file with the City Clerk those schedules specified by City and contained in the Statement of Economic Interests Form 700. Contractor, for Contractor and on behalf of Contractor's agents, employees, subcontractors and consultants warrants that by execution of this Agreement, that they have no interest, present or contemplated, in the projects affected by this Agreement. City Attorney Approved Version #11.28.06 Contractor further warrants that neither Contractor, nor Contractor's agents, employees, subcontractors and consultants have any ancillary real property, business interests or income that will be affected by this Agreement or, alternatively, that Contractor will file with the City an affidavit disclosing this interest. 17. GENERAL COMPLIANCE WITH LAWS Contractor will keep fully informed of federal, state and local laws and ordinances and regulations which in any manner affect those employed by Contractor, or in any way affect the performance of the Services by Contractor. Contractor will at all times observe and comply with these laws, ordinances, and regulations and will be responsible for the compliance of Contractor's services with all applicable laws, ordinances and regulations. Contractor will be aware of the requirements of the Immigration Reform and Control Act of 1986 and will comply with those requirements, including, but not limited to, verifying the eligibility for employment of all agents, employees, subcontractors and consultants that the services required by this Agreement. 18. DISCRIMINATION AND HARASSMENT PROHIBITED Contractor will comply with all applicable local, state and federal laws and regulations prohibiting discrimination and harassment. 19. DISPUTE RESOLUTION If a dispute should arise regarding the performance of the Services the following procedure will be used to resolve any questions of fact or interpretation not otherwise settled by agreement between the parties. Representatives of Contractor or City will reduce such questions, and their respective views, to writing. A copy of such documented dispute will be forwarded to both parties involved along with recommended methods of resolution, which would be of benefit to both parties. The representative receiving the letter will reply to the letter along with a recommended method of resolution within ten (10) business days. If the resolution thus obtained is unsatisfactory to the aggrieved party, a letter outlining the disputes will be forwarded to the City Manager. The City Manager will consider the facts and solutions recommended by each party and may then opt to direct a solution to the problem. In such cases, the action of the City Manager will be binding upon the parties involved, although nothing in this procedure will prohibit the parties from seeking remedies available to them at law. City Attorney Approved Version #11.28.06 20. TERMINATION In the event of the Contractor's failure to prosecute, deliver, or perform the Services, City may terminate this Agreement for nonperformance by notifying Contractor by certified mail of the termination. If City decides to abandon or indefinitely postpone the work or services contemplated by this Agreement, City may terminate this Agreement upon written notice to Contractor. Upon notification of termination, Contractor has five (5) business days to deliver any documents owned by City and all work in progress to City address contained in this Agreement. City will make a determination of fact based upon the work product delivered to City and of the percentage of work that Contractor has performed which is usable and of worth to City in having the Agreement completed. Based upon that finding City will determine the final payment of the Agreement. Either party upon tendering thirty (30) days written notice to the other party may terminate this Agreement. In this event and upon request of City, Contractor will assemble the work product and put it in order for proper filing and closing and deliver it to City. Contractor will be paid for work performed to the termination date; however, the total will not exceed the lump sum fee payable under this Agreement. City will make the final determination as to the portions of tasks completed and the compensation to be made. 21. COVENANTS AGAINST CONTINGENT FEES Contractor warrants that Contractor has not employed or retained any company or person, other than a bona fide employee working for Contractor, to solicit or secure this Agreement, and that Contractor has not paid or agreed to pay any company or person, other than a bona fide employee, any fee, commission, percentage, brokerage fee, gift, or any other consideration contingent upon, or resulting from, the award or making of this Agreement. For breach or violation of this warranty, City will have the right to annul this Agreement without liability, or, in its discretion, to deduct from the Agreement price or consideration, or otherwise recover, the full amount of the fee, commission, percentage, brokerage fees, gift, or contingent fee. 22. CLAIMS AND LAWSUITS By signing this Agreement, Contractor agrees that any Agreement claim submitted to City must be asserted as part of the Agreement process as set forth in this Agreement and not in anticipation of litigation or in conjunction with litigation. Contractor acknowledges that if a false claim is submitted to City, it may be considered fraud and Contractor may be subject to criminal prosecution. Contractor acknowledges that California Government Code sections 12650 et seq.. the False Claims Act applies to this Agreement and, provides for civil penalties where a person knowingly submits a false claim to a public entity. These provisions include false claims made with deliberate ignorance of the false information or in reckless disregard of the truth or falsity of information. If City seeks to recover penalties pursuant to the False Claims Act, it is entitled to recover its litigation costs, including attorney's fees. Contractor acknowledges that the filing of a false claim may subject Contractor to an administrative debarment proceeding as the result of which Contractor may be prevented to act as a Contractor on any public work or improvement for a period of up to five (5) years. Contractor City Attorney Approved Version #11.28.06 acknowledges debarment by another jurisdiction is grounds for City to terminate this Agreement. 23. JURISDICTIONS AND VENUE Any action at law or in equity brought by either of the parties for the purpose of enforcing a right or rights provided for by this Agreement will be tried in a court of competent jurisdiction in the County of San Diego, State of California, and the parties waive all provisions of law providing for a change of venue in these proceedings to any other county. 24. SUCCESSORS AND ASSIGNS It is mutually understood and agreed that this Agreement will be binding upon City and Contractor and their respective successors. Neither this Agreement or any part of it nor any monies due or to become due under it may be assigned by Contractor without the prior consent of City, which shall not be unreasonably withheld. 25. ENTIRE AGREEMENT This Agreement, together with any other written document referred to or contemplated by it, along with the purchase order for this Agreement and its provisions, embody the entire Agreement and understanding between the parties relating to the subject matter of it. In case of conflict, the terms of the Agreement supersede the purchase order. Neither this Agreement nor any of its provisions may be amended, modified, waived or discharged except in a writing signed by both parties. 26. AUTHORITY The individuals executing this Agreement and the instruments referenced in it on behalf of Contractor each represent and warrant that they have the legal power, right and actual authority to bind Contractor to the terms and conditions of this Agreement. CONTRACTOR *By: CITY OF CARLSBAD, a municipal corporation of the State of California (sign here) (print name/title) _ _ City Manager or Mayor / /T/Vi < ,~ ATTEST: (print name/title) W (j <aJ Itc fctu (e-mail address) J f (pi^ J 8 City Attorney Approved Version #1 1 .28.06 If required by City, proper notarial acknowledgment of execution by contractor must be attached. If a Corporation. Agreement must be signed by one corporate officer from each of the following two groups. "Group A. **Group B. Chairman, Secretary, President, or Assistant Secretary, Vice-President CFO or Assistant Treasurer Otherwise, the corporation must attach a resolution certified by the secretary or assistant secretary under corporate seal empowering the officer(s) signing to bind the corporation. APPROVED AS TO FORM: RONALD/ Deputy City Attorney City Attorney Approved Version #04.01.02 9 CALIFORNIA ALL-PURPOSE ACKNOWLEDGEMENT STATE OF CALIFORNIA ) COUNTY OF SACRAMENTO ) On (J l/\ \ U | (g ( ~Lnr> ") before me, Robert A. Williams, Notary Public personally appeared, t *personally known to-jne -or- proved to me on the satisfactory evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that-be/she/toey executed the same in .bis/he r/tJ^etr authorized capacity(ies), and that byjois/her/tbetts-signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument. ^WILLIAMS? WITNESS my hand and official seal. * ""^ -— • • -— * v,_^..,. (SEAL)7NOTARY PUBLIC SIGNATURE OPTIONAL INFORMATION This optional information section is not required by law but may be beneficial to persons relying on this document. TITLE OR TYPE OF DOCUMENT DATE OF DOCUMENT NUMBER OF PAGE; SIGNER(S) OTHER THAN NAMED ABOVE CALIFORNIA ALL-PURPOSE ACKNOWLEDGEMENT STATE OF CALIFORNIA ) COUNTY OF SACRAMENTO ) On OIA\^ }Li , ^QO") before me, Robert A. Williams, Notary Public personally appeared, W me -or- proved to me on the satisfactory evidence to be the person(s) whose name(s) is/ate subscribed to the within instrument and acknowledged to me that he/sbo/thcy executed the same in his/h-ef&beir authorized capacity(ies), and that by his/hsi/Uieii signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument. WITNESS my hand and official seal.fROBERT A. WILLIAMS COMM. #1696901 «NOTARY PUBLIC-CALIFORNIA W SACRAMENTO COUNTY U COMM. EXPIRES OCT. 28, jOIOj (SEAL) NOTARY PUBLIC SIGNATURE OPTIONAL INFORMATION This optional information section is not required by law but may be beneficial lo persons relying on this document. TITLE OR TYPE OF DOCUMENT DATE OF DOCUMENT NUMBER OF PAGES SIGNER(S) OTHER THAN NAMED ABOVE_ Exhibit A Leckey Consulting Management Institute (PMI). As I will explain later in my proposal, I do make every effort to adhere to these principles in managing projects. More importantly, I have found that preparing a Scope Statement in the planning phase of a project is an excellent opportunity to validate that the all stakeholders are.aligned as to what needs to be accomplished, how it will be accomplished, who/when tasks will be completed, the project budget and other important constraints. This will translate into a meaningful deliverable that can be presented to both the ITGC and City Council to form the basis of the business case to proceed with the IFAS 7i upgrade project. Not completing a Scope Statement (or similar analysis) can result in a misleading implementation plan and the true cost to achieve the goals of the project. Appendix B provides a reference to my website where an excerpt of a sample Scope Statement that I prepared for another project can be reviewed. Since I am very experienced with IFAS 7i and have sample deliveries from other 7i projects (including detailed work plans) I will be able to complete the Scope Statement deliverable within a competitive cost range and, more importantly, present a professional business case to the ITGC and City Council for the need and value of upgrading to IFAS 7i. If, after reviewing my proposal, the City believes that a Scope Statement is not necessary given the information presented to the ITGC or the City Council to date then I will gladly prepare the minimum analysis and documentation described in the RFP. I will also reduce my fees accordingly. 1.1.2 Phase 2 Scope of Services For Phase 2 (IFAS 7i Upgrade) of the project, my project management services will include the following areas: Q Traditional Project Management • Provide day-to-day project management. • Provide hands-on assistance with detailed tasks as needed. For example, provide assistance with overall business process review where new IFAS 7i functions have changed, business and functionality requirements, application configuration, front-end workflow optimization for the purchasing module and development and implementation of dashboard functionality. • Ensure that the City's responsibilities of the project are satisfactorily met. • Review all major deliverables produced by the City. • Monitor the project plan and schedule and make course corrections as necessary. • Manage issues and ensure that resolutions are finalized in a timely manner. • Enforce project scope from start to finish. Final Page 3 January 23,2007 Leckey Consulting • Ensure change management, training and communication are effective (and adjusted accordingly if goals are not met). • Proactively manage risk. • Review and approve staffing changes. • Foster a learning environment. • Re-direct resources as capabilities and/or needs change. • Track and communicate project budget/costs. " ' Identify data integration requirements to support required functionality with other ' systems. • Report and present biweekly status reports to the project stakeholders. • | Provide a post implementation review. Q Contract Management • Ensure that Bi-Tech's responsibilities (and other vendors/contractors) of the project are satisfactorily met. • Act as a liaison between the project team and Bi-Tech from the beginning of project through project completion; coordinate problem identification and resolution activities. • Review all major deliverables produced by Bi-Tech (and other vendors/contractors). • Review and approve all Bi-Tech invoices (and other vendors/contractors). • Review and approve Bi-Tech staffing changes. • Manage proposed scope changes. For end user procedures and training, scope will include training for the key users of the City (approximately 20 people). The City will be responsible for delivering the training to the remaining users of the City. My assumptions for procedures development and training delivery include: Q A City subject matter expert (SME) will exist for each IFAS 7i module and will be able to contribute his or her time to work with me in creating the procedures and training materials where I might have gaps in knowledge. It is acceptable for there to be more than one SME for multiple modules in certain areas. Although I can actually create the Final Page 4 January 23.2007 Leckey Consulting procedures and training material documentation, I may need the SME to walk me through certain screens to make sure I understand the process. If an adequate SME does not exist for an area, I am assuming that a Bi-Tech consultant could fill that role. Procedures documentation is confined to step-by-step instructions for using IFAS 7i screens and not integrated operational procedures or policies. Procedures and training will be limited to end user transaction creation only (except for basic end user navigation training) and not for centrally ran batch processes, workflow administration, year-end close processes, running of payroll, system administration and the like. Specifically, it will include the following areas: • IFAS 7i Navigation (including the Dashboard) • Journal Entries • Direct Budget Update Entry • Budget Adjustment Entry • Invoice Entry • Accounts Receivable Billing Entry • Requisition Entry (including Workflow approvals) • Cash Receipt Entry • Fixed Asset Entry • Timecard Entry • Employee Creation Entry • BK Check Status Changes • Running CDD Reports User procedures will be created using MS Word with traditional screen prints and step- by-step instructions for using an IFAS 7i screen. In addition to being used in training classes, they will also be converted to PDF files and be used to replace the IFAS 7i online generic procedures (wherever an online help facility is offered). They just need to be copied to the help directory on the server. I have done this on two projects without any problems. Final Page 5 January 23.2007 Leckey Consulting Training materials will be a combination of the user procedures (see above), a basic PowerPoint presentation of the changes in the module and a few exercises to reinforce learning. 1.2 Approach and Work Plan In this section, I provide a work approach for three areas: Phase 1 project management services, Phase 2 project management services and an outline of the overall project phases and major tasks, including roles and responsibility for my services, Bi-Tech and the City. Where applicable, the project management methodology employed for these services (and future services) are based on principles embodied in the Project Management Body of Knowledge (PMBOK), which are promulgated by the PMI. There are nine bodies of knowledge described by the PMBOK. They are: 1. Project Integration Management 2. Project Scope Management 3. Project Time Management 4. Project Cost Management 5. Project Quality Management 6. Project Human Resource Management 7. Project Communications Management 8. Project Risk management 9. Project Procurement Management As with any methodology, expert judgment must be used in determining what aspects of the methodology should be employed. Most methodologies (including PMBOK) have a bias towards very large projects and, thus, have an inherent assumption that the project owner has the business justification (and the financial wherewithal) to invest significant resources in project management and control. That is not the case for the City. Therefore, I have tailored an approach for project management based on my understanding of the IF AS 7i initiative and my past system implementation experience. Although I have included descriptions of all tasks in this section, I expect to work closely with the City in revising and finalizing (as necessary) the work plan for these services. Below is a description of the work approach for project management services and end user procedures and training materials. For each task, I provide a brief description of its purpose, the major points of the approach, the work product(s) produced and responsibilities for completing the task. Although the tasks are numbered sequentially (for ease of reference), many of them are Final Page 6 January 23,2007 Microsoft Office Project Exported Information Page 1 of26 City of Carlsbad - 7i Upgrade Project Project Start Date: Mon 09/10/07 Project Finish Date: Mon 06/30/08 Work Plan ID 1 2 3 4 5 I 8 f ~~ I 9 10 11 ! 12 S13 Task Name 7i Upgrade Project Planning Phase Dummy Task for Phase Estimation Project Management Track Project Management Plan (PMP) Validate Content of Scope Statement (i.e., any changes) Refine MS Project Work Plan Contained in the Scope Statement Project Organization & Staffing Identify Project Positions & Time Commitment Define Focus Groups Determine Positions to be Filled by Central Depts Document Org Chart & Roles and Responsibilities Document Standard PM Processes Duration Start Finish Dependency Resource_N i 2 1 1 days (Mon 09/1 0/07 jMon 06/30/08 | j 14 15 Communication Plan 16 days |Mon 09/10/07 JMon 10/01/07 j 1 day JMon 09/10/07 Mon 09/10/07 1 day |Mon 09/10/07 |Mon 09/10/07 I Mon 09/10/07 iMon 09/10/071 day 1 day JMon 09/10/07 Mon 09/10/07 1 day Mon 09/10/07 Mon 09/10/07 1 day [Mon 09/10/07 Mon 09/10/07 1 day Mon 09/10/07 jMon 09/10/07 1 day iMon 09/10/07 JMon 09/10/07 1 1 day !Mon 09/10/07 JMon 09/10/07 j 1 day IMon 09/10/07 Mon 09/10/07 1 day JMon 09/10/07 (Mon 09/10/07 | ;Leckey JLeckey jLeckey jLeckey IBranca jLeckey Risk Management Plan 1 day !Mon 09/10/07 JMon 09/10/07 iLeckey ILeckey file://C:\Documents and Settings\Kbran\Local Settings\Temporary Internet Files\Content.... 07/11/2007 Microsoft Office Project Exported Information Page 2 of26 16 i 18 19 20 122i [: 23 124 | | 25 I i; J26 \ 27 ^28 ! I 30 ,31 !"32~ '33 34 35 Issue Management Status Meetings & Reporting Deliverable Review & Acceptance Process Project Project Financials Change Control Procedures Project Library Procedures & Organization Prepare Remaining Sections of the PMP Bi-Tech Review of PMP Core Team Review of PMP Project Sponsor/Owner Review OF PMP 1 day Mon 09/10/07 Mon 09/10/07 \ 1 day Mon 09/10/07 JMon 09/10/07 ! 1 day :Mon 09/10/07 'Mon 09/10/07 \ 1 day Mon 09/10/07 .Mon 09/10/07 | 1 day IMon 09/10/07 (Mon 09/10/07 j 1 day Mon 09/10/07 Mon 09/10/07 Mon 09/10/07Iday Mon 09/10/07 1 day IMon 09/10/07 IMon 09/10/07 Update PMP with Review Comments Present PMP to ITGC for Feedback Update PMP with Feedback Review and Approve Deliverable Schedule Bi-Tech Consultants for Onsite Training/Setup Schedule City SMEs to Attend Configuration/Training Kick-Off Meeting Schedule Kick-Off Meeting Prepare PowerPoint Presentation Summarize Key Points of Scope Statement 1 day Mon 09/10/07 Mon 09/10/07 j " ''"" .................. )' ...... "———••"••••'••"""••" ....... --- s,™..,, ....... ..,,,,,„„.,... ..... „„ i \ I 1 day JMon 09/10/07 |Mon 09/10/07 ! I i 1 day iMon 09/10/07 |Mon 09/10/07 ! 1 day Mon 09/10/07 Mon 09/10/07 1 day Mon 09/10/07 ;Mon 09/10/07 1 day |Mon 09/10/07 JMon 09/10/07 ............................... i" ...................................................................... > ....................................................................... : 1 day jMon 09/10/07 JMon 09/10/07j j 1 day Mon 09/10/07 Mon 09/10/07 Iday MonlOMon 09/10/07 1 day Mon 09/10/07 |Mon 09/10/07 1 day IMon 09/10/07 (Mon 09/10/07! 1 day (Mon 09/10/07 IMon 09/10/07, [Leckey (Leckey Leckey i Leckey iLeckey i |Leckey (Leckey Bi-Tech |Core Team |Irvine,Branc Leckey Leckey I Leckey I Irvine I Leckey ; Leckey iBranca :Leckey file://C:\Documents and Settings\Kbran\Local Settings\Temporary Internet Files\Content.... 07/11/2007 Microsoft Office Project Exported Information Page 3 of26 36 1 37 ' 38 39 40 41 42 43 44 45 i 46 j 47 ' 48 49 50 : 51 52 53 54 55 56 57 \ Summarize Key Points of PMP I Review Presentation \ by Project Sponser \ and Project Owner \ HoldKick-Off Meeting ; Review and Approve i Deliverable i Ongoing PM Activities Execute Communication Plan Maintain Project ! Work Plan | Maintain Issue Log Maintain Risk Mgmt \ Plan \ Weekly Team \ Meetings/Status Report Prepare Monthly \ Project Financials ; MonthlylTGC Meetings/Status Report Maintain Project Library Phase Close-out Verify Phase : Objectives Being Met Update Project Schedule as Needed \ Release Staff as \ Appropriate \ Review/Assess Scope Approval by Sponsor to Complete Phase (via eMail) Technical Track Procure New Web Servers Network & PC Assessment 1 day Mon 09/10/07 Mon 09/10/07 ! 1 day Mon 09/10/07 Mon 09/10/07 j 1 day Mon 09/10/07 Mon 09/10/07 1 day Mon 09/10/07 'Mon 09/10/07 \ 1 day Mon 09/1 0/07 Mon 09/1 0/07 1 1 day Mon 09/10/07 Mon 09/10/07 1 day Mon 09/10/07 Mon 09/10/07 i 1 day Mon 09/10/07 JMon 09/10/07 | 1 day Mon 09/10/07 Mon 09/10/07 1 day Mon 09/10/07 Mon 09/10/07 1 day Mon 09/10/07 |Mon 09/10/07 1 1 day jMon 09/10/07 Mon 09/10/07 1 day Mon 09/10/07 Mon 09/10/07 !___ j J 1 day Mon 09/10/07 Mon 09/10/07 | 1 day |Mon 09/10/07 Mon 09/10/07 | 1 day Mon 09/10/07 Mon 09/10/07 1 day Mon 09/10/07 |Mon 09/10/07 j 1 day 'Mon 09/10/07 Mon 09/10/07 | 1 day ;Mon 09/10/07 |Mon 09/10/07 i 1 day Mon 09/10/07 Mon 09/10/07 1 day Mon 09/10/07 Mon 09/10/07 < i 1 day Mon 09/10/07 Mon 09/10/07 Leckey I Irvine,Branc All Jrvine Leckey Leckey Leckey | Leckey ILeckey Leckey Leckey Leckey Leckey iLeckey IBranca iLeckey Hrvine IPeterson file://C:\Documents and Settings\Kbran\Local Settings\Temporary Internet Files\Content.... 07/11/2007 Microsoft Office Project Exported Information Page 4 of26 158 59 60 61 62 163 (64 65 I 66 67 69 70 | 71 72 ;73 ^74 75 76 Perform Initial Network Bandwidth Analysis Perform End User PC Analysis Review and Approve Deliverable Blueprint Phase Dummy Task for Phase Estimation 1 day IMon 09/10/07 Mon 09/10/07 Project Management Track Scheduie~CKtoBK conversion with Bi- Tech Schedule development of 3 bank interfaces with Bi-Tech Phase Planning Identify Materials/Decisions Required for Planning Update Blueprint Phase Workplan w/ Detailed Tasks and Dates Review with Sponsor, Project Owner and Core Team Refine Project Schedule as needed Approval by Sponsor to Start Phase (via eMail) Ongoing PM Activities Execute Communication Plan Maintain Project Work Plan Maintain Issue Log Maintain Risk Mgmt Plan Hold Weekly Team Meetings/Status 1 day Mon 09/10/07 (Mon 09/10/07 1 day Mon 09/10/07 Mon 09/10/07 74 days j Tue 10/02/071 Fri 01/11/08 J2 " ~~r """"""" ' r "~~~ ~r~74 days Tue 10/02/07! Fri 01/11/08 | ' "I """"""" "| "" ' ! 1 day \ Tue 10/02/07j Tue 10/02/07 | 1 day'' Tue 10/02/07' Tue 10/02/07l 1 day , Tue 10/02/07 ( Tue 10/02/07 , 1day! Tue""io/02/07 fue~io"/02/071 1 day i Tue 10/02/071 Tue 10/02/07 j 1 day I Tue 10/02/071 Tue 10/02/07 j I ^ 1 day j Tue 10/02/071 Tue 10/02/07 1 day Tue 10/02/07 Tue 10/02/07 1 day! Tue 10/02/07 j Tue 10/02/07 I ! 1 day i Tue 10/02/07 Tue 10/02/07 1 day I Tue 10/02/07, Tue 10/02/07 1 day, Tue 10/02/071 Tue 10/02/07 1 day Tue 10/02/07 Tue 10/02/07 1 day Tue 10/02/07 Tue 10/02/07 1 day I Tue 10/02/07 Tue 10/02/07 jPeterson I Peterson llrvine Leckey (Leckey l iLeckey j Leckey Leckey j Leckey Irvine Leckey Leckey Leckey Leckey Leckey file://C:\Documents and Settings\Kbran\Local Settings\Temporary Internet Files\Content.... 07/11/2007 Microsoft Office Project Exported Information Page 5 of26 78 79 80 i 81 82 83 = 84 •85 ;86 87 88 190 ! 9l 93 94 I 95 96 Report Prepare Monthly Project Financials i Monthly ITGC j Meetings/Status | Report Maintain Project j Library i Phase Close-Out Verify Phase : Objectives Being Met \ Update Project ; Schedule as Needed I Release Staff as | Appropriate | Review/Assess Scope | Approval by Sponsor I to Complete Phase | (via eMail) ' Technical Track Prepare Project Team | Training Room | Identify Project Team I Training Room | Facility | Procure a Dedicated I LCD Projector (if not | available) | Procure a Dual I Whiteboard/Projection | Screen for LCD Install 7.9 PC ! Products on Training | Room PC Test Training Room PC Connections Review and Approve : Deliverable i Install 7.9 Dev | Account on UNIX I Server Create Dev Account i on UNIX Server i Run HFS for IFAS 7.9 i 1 day! Tue 10/02/07! Tue 10/02/071 1 day j Tue 10/02/071 Tue 10/02/07 | 1 day Tue 10/02/07 j Tue 10/02/07 i 7 day Tue 10/02/07 f Tue 10/02/07 | 1 day Tue 10/02/071 Tue 10/02/07' """""" — f 1 day' Tue 10/02/07; Tue 10/02/071 1 day j Tue 10/02/071 Tue 10/02/07! 1 day j Tue 10/02/07 j Tue10/02/071 1 day i Tue 10/02/071 Tue 10/02/07 i 1 day Tue 10/02/07 Tue 10/02/07 1 day I Tue 10/02/07 Tue 10/02/07 Tue 10/02/07: Tue 10/02/071 1 day j Tue 10/02/07 1 day I Tue 10/02/07 1 day j Tue 10/02/07, Tue 10/02/07 j 1 day | Tue 10/02/071 Tue 10/02/07 | 1 day Tue 10/02/07' Tue 10/02/07 1 day I Tue 10/02/07 Tue 10/02/071 1 day | Tue 10/02/071 Tue 10/02/071 1 day Tue 10/02/07: Tue 10/02/07 | Leckey ILeckey Leckey ILeckey ILeckey (Branca iLeckey Irvine Branca iBranca Branca (Peterson (Peterson Irvine Bi-Tech file://C:\Documents and Settings\Kbran\Local Settings\Temporary Internet Files\Content.... 07/11/2007 Microsoft Office Project Exported Information Page 6 of26 97 98 99 100 101 \'"" " T™ |l02 I i •: !103| J104J 105 !106| 107 108 109 110 111 ,112- 113 on the UNIX Server/Dev_____ Products on Team Members PCs Install 7.9 PC Products on Selective Training Room PCs Schedule Bi-Tech for Practice Data Roll to Dev Perform Production Data Roll to Dev Spot Check New Dev for Completeness of Data Roll Implement Backup & Restore Process for UNIX Dev Test UNIX Server Restore Process Review and Approve Deliverable Install 7i on Web Servers (Dev Environment) Procure XXX New Web Servers Complete Si-Tech's Pre-installation Checklist Install OS and Connect to Network Install 3rd Party Software Install IFAS 7.9 on XXX Web Servers (as a web farm) Install Workflow 7.9 Install Other IFAS Producsts Perform High-Level System Testing by Bi- Tech (remote) 1 day' Tue 10/02/071 Tue 10/02/07 1 day I Tue 10/02/071 Tue 10/02/07 1 day; Tue 10/02/07, Tue 10/02/07, 1 day \ Tue 10/02/071 Tue 10/02/07 \ Iday Tue 10/02/07 Tue 10/02/07 [ 1 day , Tue 10/02/07 Tue 10/02/07 1 day j Tue 10/02/071 Tue 10/02/071 1 day | Tue 10/02/071 Tue 10/02/07 j Iday Tue 10/02/07 Tue 10/02/07: j i 1 day | Tue 10/02/07! Tue 10/02/07 j 1 day, Tue 10/02/07; Tue 10/02/07 | 1 day Tue 10/02/07' Tue 10/02/07 | 1 day ' Tue 10/02/071 Tue 10/02/07 1 day Tue 10/02/07 ; Tue 10/02/07 ; 1 day | Tue 10/02/07 ' Tue 10/02/07! j : T day nfueTo/O^O? Tue"T5/02/07 i Iday Tue 10/02/07 Tue 10/02/071 1 day! Tue 10/02/071 Tue 10/02/07 \ |Bi-Tech ;Bi-Tech iPeterson iLeckey [Bi-Tech ;SMEs IPeterson [Peterson i Irvine ^Peterson Peterson [Peterson IPeterson (Bi-Tech |Bi-Tech JBi-Tech !Bi-Tech file://C:\Documents and Settings\Kbran\Local Settings\Temporary Internet Files\Content... 07/11/2007 Microsoft Office Project Exported Information Page 7 of26 I115J 116, 117 118 119 120 122 \24\ 125; I J126J ,127; 128! 129! 130 J131J m Perform High-Level System Testing by City Review and Approve Deliverable Functional Track Current Process Analysis Document Current Processes for All Areas (flowchart) Validate with Users Blueprint Strategy Review Schedule Bi-Tech Consultants for Blueprint Strategy Review Schedule City Participants to Attend Prepare Agenda & Detailed Known Questions Email Bi-Tech Final Scope Statement (for background) Email Bi-Tech Draft Current Process Analysis Hold Strategy Sessions #1 at City (Financials) Hold Strategy Sessions #2 at City (HR/Payroll) Bi-Tech Write-Up of Strategy Session Results Future Process Analysis Complete Reports Gap Analysis (Use- Files, Ad Hoc, etc.) Finalize Blueprint Strategy/Decisions 1 day j Tue 10/02/07 Tue 10/02/07 \ I day Tue 10/02/07 Tue 10/02/07! 1 day Tue 10/02/07 Tue 10/02/07 [ Iday Tue 10/02/07 Tue 10/02/071 1 day \ Tue 10/02/07 Tue 10/02/071 1 day I Tue 10/02/07: Tue 10/02/071 1 day j Tue 10/02/07, Tue 10/02/071 ! | 1 day 1 Tue 10/02/071 Tue 10/02/071 1 day Tue 10/02/07l Tue 10/02/07 | 1 day | Tue 10/02/071 Tue 10/02/07 \ 1 day j Tue 10/02/07, Tue 10/02/07 1 day | Tue 10/02/071 Tue 10/02/07 j 1 day \ Tue 10/02/07 \ Tue 10/02/07 | } I '' 1 day | Tue 10/02/071 Tue 10/02/07j 1 day; Tue 10/02/07 Tue 10/02/07 jSMEs I Irvine 1 day 1 Tue 10/02/07 i Tue 10/02/07 1 day I Tue 10/02/07 \ Tue 10/02/07 i 1 day; Tue 10/02/071 Tue 10/02/07 | ISMES •SMEs iLeckey iLeckey iLeckey iLeckey iLeckey Bi-Tech,All Bi-Tech,All I iBi-Tech JSMEs |Leckey,Bran file://C:\Documents and Settings\Kbran\Local SettingsYTemporary Internet Files\Content.... 07/11/2007 Microsoft Office Project Exported Information Page 8 of26 ;133j 134. !135! 136, 11371 138 139 i 140 141 142 143 ;144- |145; ;i46j J147J '148 i 149 Document Future Processes for All Areas Determine Magnitude of New CDD Reports Needed Develop Blueprint Deliverable Draft Remaining Sections of Blueprint Core Team Review of Blueprint Bi-Tech Review of Blueprint Project Sponsor/Owner Review OF Blueprint Update Blueprint with Review Comments Present Blueprint to ITGC for Feedback 1 day I Tue 10/02/07 1 day |Tue 10/02/07 Update Blueprint with Feedback Review and Approve Deliverable Configuration Training/Setup for Existing Modules Email Bi-Tech Consultant Scope Statement Email Bi-Tech Consultant Draft Current Process Analysis GL/JL Training/Setup (visit 1) Core Financials Configuration Training/Setup (visit 1) Core Financials Configuration Training/Setup (visit 2) Tue 10/02/07! Tue 10/02/07 i ILeckey IPeterson 1 day Tue 10/02/07l Tue 10/02/07 1 day: Tue 10/02/07, Tue 10/02/07 1 day Tue 10/02/07 \ Tue 10/02/07 j 1 day, Tue 10/02/07' Tue 10/02/071 1 day j Tue 10/02/07 | Tue 10/02/07 ; 1 day . Tue 10/02/07: Tue 10/02/071 i ! ! 1 day | Tue 10/02/071 Tue 10/02/071 1 day Tue 10/02/071 Tue 10/02/07 | 1 day \ Tue 10/02/07 j Tue 10/02/071 1 day; Tue 10/02/07 Tue 10/02/07 | 1 day j Tue 10/02/07 Tue 10/02/07 1 day j Tue 10/02/07 j Tue 10/02/07 j 1 day 1 Tue 10/02/071 Tue 10/02/07 1 day i Tue 10/02/071 Tue 10/02/07 1 day | Tue 10/02/071 Tue 10/02/07 j Leckey (Core Team [Bi-Tech iIrvine,Branc ILeckey !Leckey ILeckey I Irvine Leckey Leckey Bi-Tech,Lec ;Leckey,Bi-T |Leckey,Bi-T file://C:\Documents and Settings\Kbran\Local SettingsYTemporary Internet Files\Content... 07/11/2007 Microsoft Office Project Exported Information Page 9 of26 150 i 153 ,154] 155 156 = :157| 158 159 jieo! 161 1162 1164: 165 > HR/Payroll Configuration Training/Setup (visit __1) _ _ _ _ _ HR/Payroll Configuration Training/Setup (visit 2) Document Configuration Design (via DSD) Develop Detailed Design Deliverable (DSD) Summarize all DSD subcomponents (from other tasks) Core Team Review of DSD Bi-Tech Review of DSD Project Sponsor/Owner Review of DSD Update DSD with Review Comments Review and Approve Deliverable Schedule PO Focus Group to Present Workflow Model Development Track Configuration Training/Setup for PO Workflow Email Bi-Tech Consultant Scope Statement Email Bi-Tech Consultant Draft Current Process Analysis PO Workflow Configuration Training/Setup (visit 1 day i Tue 10/02/07 j Tue 10/02/07 \ 1 day ' Tue 10/02/07 j Tue 10/02/07 | 1 day j Tue 10/02/071 Tue 10/02/071 1 day | Tue 10/02/07 j Tue 10/02/07 l 1 day j Tue 10/02/07 Tue 10/02/07 1 day Tue 10/02/07 Tue 10/02/07 1 day ' Tue 10/02/07; Tue 10/02/07 | 1 day I Tue 10/02/07s Tue 10/02/07 1 day Tue 10/02/071 Tue 10/02/07 1 day 1 Tue 10/02/07 | Tue 10/02/07! 1 day i Tue 10/02/07 \ Tue 10/02/07 1 day Tue 10/02/07 Tue 10/02/07 1 day j Tue 10/02/07 j Tue 10/02/07 | 1 day! Tue 10/02/07 i Tue 10/02/07 ; 1 day i Tue 10/02/07 i Tue 10/02/07 I Leckey,Bi-T Leckey,Bi-T ILeckey Leckey Core Team ;Bi-Tech |Irvine,Branc ^Leckey ! Irvine Leckey 1 day | Tue 10/02/071 Tue 10/02/07 i Leckey i Leckey ;Leckey,Bi-T file://C:\Documents and Settings\Kbran\Local Settings\Temporary Internet Files\Content.... 07/11/2007 Microsoft Office Project Exported Information Page 10 of 26 166 ,167 168 169 470 171 172 173, Il74; !l75i 11761"" J177I 178 179 180 181 J182J I ; !l83l I \ 1184: __ 1) _ _ PO Workflow Configuration Training/Setup (visit 2> Document PO Workflow Model Design (via DSD) Create CDD Report Specs (via DSD) Batch Interface Specs Create Cancelled Checks Specs Create AP Positive Pay Specs Create Payroll Positive Pay Specs Conversion Specs Determine Candidates for Conversions (if any) Create Conversion Specs (if any) Training Track Schedule Training Room for User Training Build Phase Dummy Task for Phase Estimation Project Management Track Phase Planning Identify Materials/Decisions Required for Planning Update Build Phase Workplan w/ Detailed Tasks and Dates Review with Sponsor, Project Owner and Core Team 1 day 1 Tue 10/02/07 \ Tue 10/02/07 | ) 1 day ] Tue 10/02/071 Tue 10/02/071 1 day i Tue 10/02/07 ; Tue 10/02/07 I I day |Tuel 0/02/07 j Tue10/02/071 1 day 1 Tue 10/02/071 Tue 10/02/07! 1 day Tue 10/02/07 Tue 10/02/07 \ 1 day Tue 10/02/07 Tue 10/02/07 | fday Tue 10/02/07 Tu7l6/02/077 1 day | Tue 10/02/071 Tue 10/02/071 1 day ( Tue 10/02/071 Tue 10/02/07 | 1 day rfueT6/02/07' Tue10/02/07 ! 1 day, Tue 10/02/07, Tue 10/02/07 50 days Mon 01/14/08 Fri 03/21/08 61 50 days Mon 01/14/08 Fri 03/21/08 1 day Mon 01/14/08 Mon 01/14/08 ! 1 day Mon 01/14/08 Mon 01/14/08'! 1 day jMon 01/14/08 |Mon 01/14/08 ! j i | j 1 day |Mon 01/14/08 |Mon 01/14/08 i ! j 1 1 day Mon 01/14/08 JMon 01/14/08 | |Leckey,Bi-T IBi-Tech iPeterson |Bi-Tech iBi-Tech Bi-Tech IPeterson IPeterson ;Leckey Refine Project Schedule as needed 1 day !Mon 01/14/08 !Mon 01/14/08 ; Leckey • (Leckey ILeckey I Leckey file://C:\Documents and Settings\Kbran\Local SettingsYTemporary Internet Files\Content.... 07/11/2007 Microsoft Office Project Exported Information Page 11 of 26 |186 J187 :188 189 190 191 192 193 194 j 195 196 !l97J 198; 199; 200 S201J 202 203 |2041 J205' 206 Approval by Sponsor to Start Phase (via eMail) Ongoing PM Activities Execute Communication Plan Maintain Project Work Plan Maintain Issue Log Maintain Risk Mgmt Plan Review/Assess Scope Approval by Sponsor to Complete Phase (via eMail) Technical Track Determine Data that Can be Ported from Dev to Prod Send eMail to Depts for Minimum IF AS 7i PC Requirements Copy PDF Procedures Written by Team Leads to Fl Location Functional Track 1 day |Mon 01/14/08 |Mon 01/14/08 1 day Mon 01/14/08 iMon 01/14/08 1 day Mon 01/14/08 Mon 01/14/08 1 day §Mon 01/14/08 JMon 01/14/08 I 7 day Mon 01/14/08 !Mon"o 1/14/08 j 1 day Mon 01/14/08 [Mon 01/14/08 Hold Weekly Team Meetings/Status Report Prepare Monthly Project Financials Monthly ITGC Meetings/Status Report Maintain Project Library Phase Close-Out Verify Phase Objectives Being Met Update Project Schedule as Needed Release Staff as Appropriate 1 day 'Mon 01/14/08 Mon 01/14/08 1 day Mon 01/14/08 Mon 01/14/08 1 day iMon 01/14/08 |Mon 01/14/08 1 day :Mon 01/14/08 Mon 01/14/08 i 1day |MonOi/14/08 Mon01/14/08 1 day Mon 01/14/08 Mon 01/14/08 1 day Mon 01/14/08 iMon 01/14/08 1 day Mon 01/14/08 Mon 01/14/08 Tday Mon 01/14/08 Mon 01/14/08 1 day iMon 01/14/08 |Mon 01/14/08 i 1 day Mon 01/14/08 [Mon 01/14/08 ; 1 day Mon 01/14/08 JMon 01/14/08 I; 1 day iMon 01/14/08 |Mon 01/14/08 1 day Mon 01/14/08 Mon 01/14/08 1 day Mon 01/14/08 Mon 01/14/08 I Irvine Leckey Leckey Leckey Leckey ^Leckey [Leckey [Leckey ILeckey ! Leckey Leckey Branca Leckey Irvine iPeterson [Peterson [Peterson file://C:\Documents and Settings\Kbran\Local SettingsYTemporary Internet Files\Content... 07/11/2007 Microsoft Office Project Exported Information Page 12 of 26 !207i 1208 ;209; 210 211 212: 213- ,214, 215 216 217 218 2191 • i | !220 1221; Module Configuration & Build General Ledger & Job Ledger Update configuration based on DSD Build other coded field values (if any) Update DSD with any configuration changes Unit test module Purchasing/EN Update configuration based on DSD Build coded field values (if any) Update DSD with configuration changes (if any) Unit test module (including workflow) Accounts Payable Update configuration based on DSD Build coded field values (if any) Update DSD with configuration changes (if any) 1 day )MonO 1/14/08 Mon 01/14/08 1 day jMon 01/14/08 [Mon 01/14/08 I 1 day iMon 01/14/08 JMon 01/14/08 | 1 day *Mon 01/14/08 Mon 01/14/08 j 1 day !Mon 01/14/08 (Mon 01/14/08 [ 1 day Mon 01/14/08 [Mon"01/14768 ' 1 day Mon 01/14/08 Mon 01/14/08 1 day Mon 01/14/08 JMon 01/14/08 1 day 'Mon 01/14/08 'Mon 01/14/08 1 day 'Mon 01/14/08 'Mon 01/14/08 1 day Mon 01/14/08 {Mon 01/14/08 I 1 1 day Mon"01/14/08 |Mon~61/14/08 ' """] T 1 day JMon 01/14/08 ^Mon 01/14/08 222 :223 |224 225 J226 Unit test module j Person Entity j Update \ configuration based | on DSD Build coded field i values (if any) ; Update DSD with configuration changes (if any) 1 day Mon 01/14/08 JMon 01/14/08 1 day JMon 01/14/08 iMon 01/14/08 1 day JMon 01 /14/08 |Mon 01/14/08 1day (Mon 01/14/08 ]Mon 01/14/08 1 day IMon 01/14/08 |Mon 01/14/08 1 day Mon 01/14/08 JMon 01/14/08 1 day jMon 01/14/08 (Mon 01/14/08 !Bi-Tech,SM: [SMEs iSMEs iSMEs !SMEs,Bi-Te iSMEs iSMEs iSMEs SMEs,Bi-Te SMEs ISMEs ISMEs |SMEs,Bi-Te ISMEs JSMEs file://C:\Documents and Settings\Kbran\Local Settings\Temporary Internet Files\Content.... 07/11/2007 Microsoft Office Project Exported Information Page 13 of 26 227 228 229; 230 1231 ; 232 233 J234J ! I (235; 236 237 238 ;239! J240 241 242' 243 J244J 245- Unit test module 1 day |Mon 01/14/08 |Mon 01/14/08 j Bank Reconciliation 247 248 Update configuration based on DSD Build coded field values (if any) Update DSD with configuration changes (if any) Unit test module Accounts Receivable Update configuration based on DSD Build coded field values (if any) Update DSD with configuration changes (if any) Unit test module Cash Receipts Update configuration based on DSD Build coded field values (if any) Update DSD with configuration changes (if any) Unit test module Fixed Assets Update configuration based on DSD Build coded field values (if any) Update DSD with configuration changes (if any) Unit test module Budget Preparation Update 1 day jMon 01/14/08 Mon 01/14/08 l 1 day Mon 01/14/08 Mon 01/14/08 1 day Mon 01/14/08 Mon 01/14/08 1 day Mon 01/14/08 [Mon 01/14/08 | 1 day Mon01/14/08]Mon01/r4/08 1 day JMon 01/14/08 JMon 01/14/08 1 day JMon 01/14/08 |Mon 01/14/08 1 day iMon 01/14/08 jMon 01/14/08 7day Mon 01/14/08"[Mon oT/14/08 I day Mon~01/14/08 Mon 01/T4/08 1 day JMon 01/14/08 |Mon 01/14/08 1 day |Mon 01/14/08 |Mon 01/14/08 1 day (Mon 01/14/08 Mon 01/14/08 1 day Mon 01/14/08 [Mon 01/14/08 Tday Mon"oi7i4/08|Mon~Ol7l4y08' 1 day Mon 01/14/08 Mon 01/14/08 1 day Mon 01/14/08 jMon 01/14/08 1 day iMonO 1/14/08 Mon 01/14/08 I | Tday jMon 01/14/08 fMon 01/14/08 T day jMon 01/14/08 Mon 01/14/08 iSMEs |SMEs,Bi-Te iSMEs ISMEs SMEs iSMEs,Bi-Te ISMEs :SMEs I 'ISMEs |SMEs,Bi-Te ISMEs ISMEs i iSMEs |SMEs,Bi-Te ISMEs ISMES TSMEs file://C:\Documents and Settings\Kbran\Local Settings\Temporary Internet Files\Content.... 07/11 /2007 Microsoft Office Project Exported Information Page 14 of 26 1249 250 |251 252 253 (254 255 256 257 258 ;259 260 :261 262 263 i264 :265 |266 267 268 269 270 271 configuration based I on DSD | Build coded field values (if any) Update DSD with configuration i changes (if any) Unit test module Human Resources Update configuration based ! on DSD Build coded field values (if any) Update DSD with 1 configuration changes (if any) \ Unit test module \ Payroll Update configuration based 1 on DSD i Build coded field ; values (if any) | Update DSD with | configuration ; changes (if any) ; Unit test module i Review and Approve j Deliverable Standard Reports I (Standard, CDD, Ad 1 Hoc, etc.) Create List of "Usable" Reports | for Each Module General Ledger Project Ledger Purchasing/EN Accounts Payable Person Entity Bank Reconiliation | Accounts i 1 day MonO 1/1 4/08 1 day jMon 01/14/08 1 day |Mon 01/14/08 Iday MonO 1/14/08 1 day MonO 1/1 4/08 Iday Mon 01/14/08 1 1 day ]MonO 1/1 4/08 1 day ^MonO 1/1 4/08 Iday Mon 01 /1 4/08 Iday Mon 01 /1 4/08 1 day IMonO 1/1 4/08 1 day (Mon 01/14/08 1 day Mon 01/14/08 Iday Mon 01 /1 4/08 1 day Mon 01/14/08 ! 1 day |Mon 01/14/08 ;i 1 1 day Mon 01 /1 4/08 Iday Mon 01/1 4/08 Iday Mon 01 /1 4/08 Iday Mon 01/1 4/08 Iday Mon 01/14/08 1 day sMonO 1/1 4/08 Tday Mon Ol/l 4/08 i Mon 01 /1 4/08 Mon 01/1 4/08 = Mon 01 /1 4/08 Mon 01/14/08 | Mon 01 /1 4/08; \ Mon 01 /1 4/08 i Mon 01 /1 4/08 Mon 01/14/OSi Mon 01 /1 4/08 Mon 01 7l 4/08 I Mon 01 /1 4/08i Mon 01 /1 4/08 | Mon 01 /1 4/08 1 Mon 01 /1 4/08 Mon 01 /1 4/08 Mon 01 /1 4/08 Mon 01 /1 4/08] Mon 01 /1 4/08) Mon 01 /1 4/08 Mon 01/14/08 Mon 01 /1 4/08 Mon 01/14/08) Mon~6I7l4/oT| SMEs,Bi-Te iSMEs !SMEs SMEs SMEs,Bi-Te iSMEs ISMEs SMEs iSMEs,Bi-Te SMEs SMEs SMEs Irvine SMEs ISMEs ISMEs ISMEs SMEs ,SMEs file://C:\Documents and Settings\Kbran\Local Settings\Temporary Internet Files\Content.... 07/11/2007 Microsoft Office Project Exported Information Page 15 of 26 272 273 274 275 276 277 278 j 279 280 281 282 283 284 :285; 286 287 288 289 290 9Q1 Receivable Cash Receipts | Fixed Assets Budget Preparation | Human Resources Payroll | Unit Test the "Useable" Standard j Rpts Identified General Ledger Project Ledger Purchasing/EN Accounts Payable Person Entity Bank Reconiliation Receivable Cash Receipts Fixed Assets \ Budget Preparation i Human Resources i Payroll Use Report | 1 day IMon 01/14/08 [Mon 01/14/08 j 1 day |Monl)i7F4/08 Mon 01/14/08 \__ !_____ |_____ 1 day Mon 01/14/08 |Mon "oi/HAJS "1 Fday Mon 01/14/08 (MonO 1/1 4/08 1 day JMon 01/14/08 |Mon 01/14/08 "! 1 day Mon 01/14/08 jMon 01/14/08 1 \ 1 day Mon 01/14/08 Mon 01/14/08 j Fday MonOl/14/08 Mon 01/14/08 ( Fday Mon 01/14/08 Mon 01/147o8: Fday Mon 01 /1 4/08 Mon 01/1 4/08 1 day Mon 01/14/08 [Mon 01/14/08 1 day JMon 0 1/14708 JMon 01/1 4/08 | 1 day IMon 01/14/08 Mon 01/14/08 ! Fday Mon 01/14/08 Mon 01/14/08 | Fday [Mon 0 1/14/08 Mon 0 I/I 4/08 [ 1 day !Mon 01/14/08 'Mon 01/1 4/08 1 day Mon 01/14/08 Mon 01/14/08 1 1 day Mon 01/14/08 [MonO 1/14/08 ! 1 Hai/sMnn 01/14/08 tMrm 01/14/08 \ SMEs SMEs SMEs [SMEs ISMEs ISMEs SMEs SMEs SMEs SMEs SMEs ~ SMEs :SMEs SMEs [SMEs ISMEs I SMEs JSMEs |292? 293 294 ;295j 296' i297! Conversion Complete Gap Analysis for Use- Files and Ad Hoc Rpts Identify Existing Use Reports Convert Use Reports to Public Favorites (where practical) Create Individual Peronal Favorvites by User Profile (where practical) Unit test each new Favorite Review and Approve Deliverable 1 day IMon 01/14/08 (Mon 01/14/08 ,' 1 day JMon 01/14/08 JMon 01/14/08 1 day Mon 01/14/08 JMon 01/14/08 1 day JMon 01/14/08 JMon 01/14/08 1 day ,Mon 01/14/08 Mon 01/14/08 1 day sMon 01/14/08 !Mon 01/14/08 SMEs ^SMEs iSMEs ISMEs iSMEs Irvine file://C:\Documents and Settings\Kbran\Local SettingsYTemporary Internet Files\Content.... 07/11/2007 Microsoft Office Project Exported Information Page 16 of 26 298; 299 300 301 J302 303 304 '306 307 308 309 ;310 312 j313 1314 J315 J316; bni PO Security & Workflow Approval Hierarchy Build Create Security & WF approval hierarchy templates for work shops Complete work shops with depts Meet with depts post work shop (as needed) Review WF templates completed by depts Finalize WF templates Build new WF structure Unit Test PO WF Models (sample a few depts) Review and Approve Deliverable System Test Plan Create Rough Draft Test Plan (including workflow) Refine Rough Draft Test Plan (including workflow) Project Sponsor/Owner/IT Review of Test Plan Update Draft Test Plan with Review Comments Review and Approve Deliverable Development Track BK to CK Conversion Run Conversion Program Validate Conversion Results Review and Approve Deliverable 1 day |Mon 01/14/08 JMon 01/14/08 1 day [Mon 01/14/08 (Mon 01/14/08 1 day JMon 01/14/08 IMon 01/14/08 1 day Mon 01/14/08 Mon 01/14/08 1 day |Mon 01/14/08 ,Mon 01/14/08 Tday |Mon 01/14/08 JMonO 1714/08"""""r" '"""" ' """I """ ~" 1 day JMon 01/14/08 (Mon 01/14/08 1 day Mon 01/14/08 |Mon 01/14/08 | I 1 day JMon 01/14/08 Mon 01/14/08 1 day Mon oT/14/08 Mon 01/14/68: 1 day JMon 01/14/08 |Mon 01/14/08 1 day |Mon 01/14/08 (Mon 01/14/08 1 day. JMon 01/14/08 Mon 01/14/08 1 day IMon 01/14/08 (Mon 01/14/08 1 day ;Mon 01/14/08 Mon 01/14/08 1 day |Mon 01/14/08 |Mon 01/14/08_.„... ^_.__ _____ ^ 1 day Mon 01/14/08 JMon 01/14/08 1 day Mon 01/14/08 Mon 01/14/08 1 day JMon 01/14/08 |Mon 01/14/08 [Peterson •[- |Leckey,Petei |Leckey,Petei [SMEs SMEs SMEs,Peters |SMEs | Irvine ;Leckey jSMEs [Irvine,Branc Leckey Irvine Bi-Tech iSMEs ilrvine file://C:\Documents and Settings\Kbran\Local Settings\Temporary Internet Files\Content.... 07/11/2007 Microsoft Office Project Exported Information Page 17 of 26 318 319 320 321 322 323 324 325 326 's '327' 328 329 330, 331 ;332 1333! 334 •335 336 337 338 339 340 341 342 343 344 345 PO Workflow Model Build PO Model Unit test PO Model Review and Approve Deliverable Custom CDD Reports Build CDD reports Unit test each CDD report Review and Approve Deliverable Standard Dashboard Template Agree to portlet design Build Homepage, Tabs and Portlets Unit test Dashboard Review and Approve Deliverable Batch Interface Programs Create Cancelled Checks Specs Develop interface Unit test interface Create AP Positive Pay Specs Develop interface Unit test interface Create Payroll Positive Pay Specs Develop interface Unit test interface Review and Approve Deliverable Training Track User Training Plan Develop User Training Plan (TP) Core Team Review of 1 day iMon 01/14/08 Mon 01/14/08 1 day |Mon 1 day 1 day Mon Mon T day Mon I day Mon 01/14/08 01/14/08 01/14/08 01/14/08 |Mon 01/14/08 Mon 01/14/08 Mon 01/14/08 Mon oT/14/08 1 day Mon 01/14/08 Mon 01/14/08 1 day Mon 01/14/08 |Mon 01/14/08 1 day Mon 01/14/08 Mon 01/14/08 1 day Mon 01/14/08 Mon 01/14/08 1 day Mon 01/14/08 ,Mon 01/14/08 I day Mon 01/147o^|Monl) 1/14/08 Mon 01/14/081 day Mon 01/14/08 1 day Mon 01/14/08 (Mon 01/14/08 1 day Mon 01/14/08 [Mon 01/14/08 T day Mon 01/14/08 Mon 01/14/08 1 day Mon 01/14/08 JMon 01/14/08 1 day Mon 01/14/08 JMon 01/14/08 T day Mon 01/14/61 [Mon 01/14/08 T day Mon 01/14/08 |Mon 01/14/08 1 day Mon 01/14/08 !Mon 01/14/08 1day Mon 01/14/08 Mon 01/14/08 1 day Mon 01/14/08 (Mon 01/14/08 1 day |Mon 01/14/08 Mon 01/14/08 s | 1 day -Mon 01/14/08 JMon 01/14/08 1 1 day Mon 01/14/08]Mon 01/14/08] 1 day ;Mon 01/14/08 |Mon 01/14/08 : Mon 01/14/08 Mon 01/14/08 Bi-Tech SMEs I Irvine Peterson ! Peterson Irvine !Branca,Leck Peterson SMEs""" Jrvine |Bi-Tech (Peterson Bi-Tech Peterson !Bi-Tech Peterson I Irvine iLeckey I Core Team file://C:\Documents and Settings\Kbran\Local SettingsYTemporary Internet Files\Content... 07/11/2007 Microsoft Office Project Exported Information Page 18 of 26 346 347 348' 349 ,350 351 352 353 1354 368 369 TP Project Sponsor/Owner Review OF TP Update TP with Review Comments Present TP to ITGC for Feedback Update TP with Feedback Review and Approve Deliverable User Training Facility Determine Training Room Needs Based on Training Plan Book Training Room for All Classes Training Materials & User Guides 1 day |Mon 01/14/08 |Mon 01/14/08 1 day Mon 01/14/08 |Mon 01/14/08 1 day jMonO 1/14/08 Mon 01/14/08 1 day !MonO 1/14/08 Mon 01/14/08 1 day Mon 01/14/08 Mon 01/14/08 1 day Mon 01/14/08 Mon 01/14/08 1 day Mon 01/14/08 iMon 01/14/08 1 day |Mon 01/14/08 Mon 01/14/08 1 day -Mon 01/14/08 sMon 01/14/08 Update Training Materials & User Guides with Review Comments 1 day iMon 01/14/08 JMon 01/14/08 Irvine,Branc ILeckey Leckey Leckey [Irvine Leckey | Leckey 355 356 357 358 359 360 361 362 363 364 365 [366 367 j Dashboard General Ledger & Job \ Ledger Purchasing/EN Accounts Payable Person Entity Bank Reconciliation 1 Accounts Receivable Cash Receipts Fixed Assets | Budget Preparation 1 Human Resources Payroll \ Project Owner Review of Training Materials | & User Guides 1 day Mon 01/14/08 Mon 01/14/08! 1 day Mon 01/14/08 (Mon 01/14/08 j 1 day Mon 0 1/1 4/08 |Mon 01/1 4/08 [ 1 day Mon 01/14/08 Mon 01/14/08 j I day Mon 01/1 4/08 Mon 01 71 4/08 1 day Mon 01/14/08 Mon 01/14/08 ______ .^ Mo~~6I7f4/08 1 day MonTi?14^|MonOl7T4/08 Tday MonOl/14/08 Mon "01/14/08 [ Tday Mon 01/1 4/08 Mon ol/l 4/08 1 day Mon 01/14/08 Mon 6" 1/14/08 j 1 day Mon 0 1/1 4/08 iMonO 1/14/08 \ 1 day JMon 01/14/08 [Mon 01/14/08 | Leckey ! Leckey Leckey Leckey Leckey Leckey Leckey Leckey Leckey Leckey iLeckey |Leckey Branca Review and Approve Deliverable 1 day !Mon 01/14/08 jMon 01/14/08 iSMEs Irvine file://C:\Documents and SettingsVKbranVLocal Settings\Temporary Internet Files\Content... 07/11/2007 Microsoft Office Project Exported Information Page 19 of 26 370 j 371 372 373 374 375; 376 377 : 378 j 379 380 Testing & Training Phase Dummy Task for Phase Estimation 382 '383 385 i386J (387! £ 388 389 390 Project Management Track Phase Planning Identify Materials/Decisions Required for Planning Update T&f Phase Workplan w/ Detailed Tasks and Dates Review with Sponsor, Project Owner and Core Team Refine Project Schedule as needed Approval by Sponsor to Start Phase (via eMail) Ongoing PM Activities Execute Communication Plan Maintain Project Work Plan Maintain Issue Log Maintain Risk Mgmt Plan Hold Weekly Team Meetings/Status Report Prepare Monthly Project Financials Meetings/Status Report Maintain Project Library Phase Close-Out Verify Phase Objectives Being Met Update Project Schedule as Needed 40 days JMon 03/24/08 j Fri 05/16/08 1178 40 days JMon 03/24/08 | Fri 05/16/08 ! 1 day Mon 03/24/08 Mon 03/24/08 1 day Mon 03/24/08 Mon 03/24/08 1 day Mon 03/24/08 ,Mon 03/24/08 1 day JMon 03/24/08 )Mon 03/24/08 1 day sMon 03/24/08 Mon 03/24/08 1 day *Mon 03/24/08 !Mon 03/24/08 1 day |Mon 03/24/08 Mon 03/24/08 1 day IMon 03/24/08 Mon 03/24/08 1 day JMon 03/24/08 JMon 03/24/08 1 day JMon 03/24/08 Mon 03/24/08 „„ l____-_^_____^8 1 day Mon 03/24/08 [Mon 03/24/08 1 day jMon 03/24/08 Mon 03/24/08 1 day |Mon 03/24/08 (Mon 03/24/08 1 day iMon 03/24/08 |Mon 03/24/08 1 day |Mon 03/24/08 |Mon 03/24/08 1day Mon 03/24/08 |M^3/24/68: 1 day Mon 03/24/08 Mon 03/24/08 1 day Mon 03/24/08 [Mon 03/24/08 Leckey jLeckey [Leckey [Leckey [Irvine Leckey Leckey Leckey [Leckey [Leckey |Leckey ;Leckey [Leckey [Leckey Leckey file://C:\Documents and Settings\Kbran\Local SettingsYTemporary Internet Files\Content... 07/11/2007 Microsoft Office Project Exported Information Page 20 of 26 391 392 ,393 394 ,395 i396i !397 398 399 1400 i 401 402 403 J404; 405 i406 ;407 409 :410| kill 412 Release Staff as Appropriate Review/Assess Scope Approval by Sponsor to Complete Phase (via eMail) Technical Track Performance Testing Stress Test the UNIX and Web Servers Stress Test the Network Bandwidth Review and Approve Deliverable Development Track No f&T Tasks are Defined for the Development Track (at this point) Functional Track Cutover Plan Prepare Cutover Plan Project Owner, Core Team and Bi-Tech Review Cutover Plan Update Cutover Plan with Review Comments Review and Approve Deliverable Integration Testing Conduct Integration Testing Using the Test Plan Document Testing Results Communicate Failed Tests to Bi-Tech Rerun Tests for Bug Fixes Project Owner and Core Team Review 1 day (Mon 03/24/08 |Mon 03/24/08 1 day Mon 03/24/08 Mon 03/24/08 1 day sMon 03/24/08 jMon 03/24/08 I I> I I day Mon"'03/24/08 |Mon 03/24/08 1day Mon 03/24/08 |Mon 03/24/08 1 day Mon 03/24/08 IMon 03/24/08 Mon 03/24/081 day Mon 03/24/08 1 day !Mon 03/24/08 JMon 03/24/08 1 day [Mon 03/24/08 Mon 03/24/08 1 day Mon 03/24/08 iMon 03/24/08 1 day Mon 03/24/08 [Mon 03/24/08 1 day Mon 03/24/08 Mon 03/24/08 1 day |Mon 03/24/08 JMon 03/24/08 1 day |Mon 03/24/08 JMon 03/24/08 1 day iMon 03/24/08 JMon 03/24/08 1 day Mon 03/24/08 Mon 03/24/08 1 day Mon 03/24/08 |Mon 03/24/08 1 day Mon 03/24/08 Mon 03/24/08 1 day Mon 03/24/08 [Mon 03/24/08 1 day iMon 03/24/08 Mon 03/24/08 1 1 day iMon 03/24/08 JMon 03/24/08 Branca Leckey i Irvine IPeterson i jPeterson i Irvine ILeckey,Petei Tech Branca,Core Tech ;Leckey Irvine |SMEs jSMEs i Leckey i |SMEs Branca,Core file://C:\Documents and Settings\Kbran\Local SettingsYTemporary Internet Files\Content.... 07/11/2007 Microsoft Office Project Exported Information Page 21 of 26 ,413 414 415 416 417 418 J419 420; 421 422 423 S424, 425 426 j 427 j 428' 429! 430 43 P 432: Testing Results Review and Approve Deliverable User Acceptance Testing Train Users on UAT Methodology Conduct UAT testing Document Testing Results Communicate Failed Tests to Bi-Tech Rerun Tests for Bug Fixes Project Owner and Core Team Review Testing Results Review and Approve Deliverable Updated DSD Update DSD Based on Testing Results Review and Approve Deliverable Training Track User Support Structure (labs, swat teams, etc.) Design User Support Structures and Timeframes Determine How to Staff Support Structures Review and Approve Deliverable End User Training ~Test"7TPC Connections in City's Training Room Register Users for Training 1 day |Mon 03/24/08 Mon 03/24/08 1 day Mon 03/24/08 Mon 03/24/08 1 day Mon 03/24/08 Mon 03/24/08 Tday ,Mon 03/24/08 JMon 03/24/08 1 day JMon 03/24/08 |Mon 03/24/08 I i 1 day iMon 03/24/08 jMon 03/24/08 Irvine 1 day Mon 03/24/08 (Mon 03/24/08 1 day Mon 03/24/08 Mon 03/24/08 | 1 day |Mon 03/24/08 !Mon 03/24/08 1 day jMon 03/24/08 JMon 03/24/08 I 1 day |Mon 03/24/08 ,Mon 03/24/08 1 day Mon 03/24/08 Mon 03/24/08 1 day |Mon 03/24/08 |Mon 03/24/08i j 1 day |Mon 03/24/08 |Mon 03/24/08 1 day 'Mon 03/24/08 [Mon 03/24/08 1 day jMon 03/24/08 iMon 03/24/08 1 day Mon 03/24/08 |Mon 03/24/08 Leckey ;UAT Testers UAT Testers Leckey UAT Testers !Branca,Core • Irvine Leckey Irvine i Leckey Branca Irvine 1 day IMon 03/24/08 (Mon 03/24/08 1 day |Mon 03/24/08 (Mon 03/24/08 Peterson Training Lea file://C:\Documents and Settings\Kbran\Local Settings\Temporary Internet Files\Content... 07/11/2007 Microsoft Office Project Exported Information Page 22 of 26 433 434 '435! 436' \ !437,\ i 438 439 '440! 441 442; 443 444 445, 446, J447' 448 i 449 j \ I I I 450! Create Training | Data on System Produce Copies of Training Material Hand-Outs Conduct Training | for Central Power \ Users (20 total) | Conduct Train-the- j Trainer Course for j New Instructors | Conduct Training \ Classes for | Remaining End | Users | Schedule Makeup | Training Classes Conduct Makeup Training Classes Review and Approve Deliverable j Go-Live Phase I Dummy Task for Phase j Estimation ) Project Management Track Phase Planning I Identify [ Materials/Decisions | Required for Planning ] Update Go-Live Phase Workplan w/ Detailed i Tasks and Dates Confirm Functional j Consultants for \ Cutover Support | Send eMail | Communication to i Departments Review with Sponsor, Project Owner and Core Team Refine Project Schedule as needed 1 day |Mon 03/24/08 (Mon 03/24/08 1 day )Mon 03/24/08 [Mon 03/24/08 1 day IMon 03/24/08 Mon 03/24/08 1 day Mon 03/24/08 jMon 03/24/08 1 day Mon 03/24/08 Mon 03/24/08 1 day IMon 03/24/08 Mon 03/24/08 1 day Mon 03/24/08 Mon 03/24/08 1 day JMon 03/24/08 [Mon 03/24/08 11 days IMon 05/19/08 ]Mon 06/02/08 1370 11 days Mon 05/19/08 IMon 06/02/08 1 day |Mon 05/19/08 Mon 05/19/08 7'day JMaal)57l9/08 Mon"05/19/08" i i 1 day Mon 05/19/08 Mon 05/19/08 1 day JMon 05/19/08 !Mon 05/19/08 1 day JMon 05/19/08 [Mon 05/19/08 1 day |Mon 05/19/08 |Mon 05/19/08 1 day jMon 05/19/08 [Mon 05/19/08 1 day JMon 05/19/08 |Mon 05/19/08 Training Lea [Training Lea Leckey [Leckey |SMEs [Training Lea SMEs [Irvine Leckey Leckey [Leckey Leckey [Irvine,Branc [Team [Leckey file://C:\Documents and Settings\Kbran\Local SettingsYTemporary Internet Files\Content... 07/11/2007 Microsoft Office Project Exported Information Page 23 of 26 451 452 453 454 455 ,456; 457 458 A59\ 460 461 462 463 ; 464 465 466 467, 468 469 (4701 1471 Approval by Sponsor to Start Phase (via eMail) Ongoing PM Activities Execute Communication Plan Maintain Project Work Plan 1 day |Mon 05/19/08 Mon 05/19/08 Maintain Issue Log Maintain Risk Mgmt Plan Hold Weekly Team Meetings/Status Report Prepare Monthly Project Financials Monthly ITGC Meetings/Status Report Maintain Project Library Phase Close-Out Verify Phase Objectives Being Met Update Project Schedule as Needed Release Staff as Appropriate Review/Assess Scope Approval by Sponsor to Complete Phase (via eMail) Technical Track Execute Cutover Plan Validate Cutover Results (spot check) Go-No-Go Decision for IFAS 7i Production Move IFAS 7i to Production for System Go-live eMail Departments that System is in Production 1 day Mon 05/19/08 iMon 05/19/08 1 day iMon 05/19/08 JMon 05/19/08 1 dayjMon 05/19/08 Mon 05/19/08 1 day IMon 05/19/08 ;Mon 05/19/08 1 day |Mon 05/19/08 (Mon 05/19/08 \ " ( " 1 day !Mon 05/19/08 JMon 05/19/08 1 day JMon 05/19/08 !Mon 05/19/08 1 day |Mon 05/19/08 (Mon 05/19/08 I I T day |Mon 05/19/08 JMon"05/19/08 1 day |Mon 05/19/08 IMon 05/19/08 1 day Mon 05/19/08 !Mon 05/19/08 1 day -Mon 05/19/08 Mon 05/19/08 1 day Mon 05/19/08 Mon 05/19/08 1 day jMon 05/19/08 JMon 05/19/08 1 day fMon 05/19/08 Mon 05/19/08 1 day Mon 05/19/08 |Mon 05/19/08 ! 1 day Mon 05/19/08 Mon 05/19/08 Mon 05/19/081 day IMon 05/19/08 1 day Mon 05/19/08 [Mon 05/19/08 1 day IMon 05/19/08 Mon 05/19/08 Irvine Leckey Leckey Leckey i Leckey iLeckey I Leckey ILeckey Leckey ^Leckey ILeckey Branca Leckey Irvine !SMEs,Peters (SMEs Irvine I Peterson iLeckey file://C:\Documents and Settings\Kbran\Local SettingsYTemporary Internet Files\Content.... 07/11/2007 Microsoft Office Project Exported Information Page 24 of 26 1473 474 475 476 477 478 479 480 481 J482; (483 i i484 485 i 486 (487! ;488i 1489 ! 490 491 j492i '493 ' 494 Deliverable Functional Track | Assist with Executing Cutover Plan Go-Live for IFAS 7i Financials Post Implementation Support Phase Dummy Task for Phase Estimation Project Management \ Track Ongoing PM Activities Execute Communication Plan ; Maintain Project Work Plan Maintain Issue Log Maintain Risk Mgmt i Plan j Hold Weekly Team | Meetings/Status | Report \ Prepare Monthly Project Financials Monthly ITGC Meetings/Status Report I Maintain Project | Library Post Implementation Review Interview Project Sponsor Interview Project \ Owner Interview Core Team | Members Identify Departments i to Interview | Conduct Departmental i Interviews 1 day 1 day 1 day 1 day 20 days 20 days 1 day 1 day 1 day 1 day 1 day 1 day 1 day 1 day 1 day 1 day 1 day 1 day 1 day 1 day 1 day 1 day Mon 05/1 9/08 Mon 05/1 9/08 Mon 05/1 9/08 Mon 05/1 9/08 Tue 06/03/08 Tue 06/03/08 Tue 06/03/08 Tue 06/03/08 Tue 06/03/08 Tue 06/03/08 Tue 06/03/08 Tue 06/03/08 Tue 06/03/08 Tue 06/03/08 Tue 06/03/08 Tue 06/03/08 Tue 06/03/08 Tue 06/03/08 Tue 06/03/08 Tue 06/03/08 Tue 06/03/08 Tue 06/03/08 Mon 05/1 9/08) Mon 05/1 9/08 | Mon 05/1 9/08 Mon 05/1 9/08 Mon 06/30/08 1441 Mon 06/30/08 Tue 06/03/08 1 Tue 06/03/08 ; Tue 06/03/08 Tue 06/03/08 Tue 06/03/08 { Tue 06/03/08 Tue 06/03/08 1 Tue 06/03/08 Tue 06/03/08 i Tue 06/03/08 I Tue 06/03/08 | Tue 06/03/08 Tue 06/03/08 ! Tue 06/03/08 : Tue 06/03/08 Tue 06/03/08 [Irvine SMEs Leckey [Leckey [Leckey [Leckey Leckey Leckey iLeckey Leckey iLeckey i Leckey Leckey |Irvine,Branc [Leckey file://C:\Documents and Settings\Kbran\Local SettingsYTemporary Internet Files\Content... 07/11/2007 Microsoft Office Project Exported Information Page 25 of 26 495! 496 497! 498 !499| isoo! 501 502 503 i504 ;505 [ r 506^ |508 509 J510. 511 513 Investigate System and/or Policy Issues (time permitting) Recommend Improvements/Action Items Develop Post Implementation Review Report Core Team Review of Report Project Sponsor/Owner Review of Report Update Report with Review Comments Present Report to ITGC for Feedback Update Report with Feedback Review and Approve Deliverable Publish Results of Review to Users Functional Track Bi-Tech Onsite Consulting Support for Module X Bi-Tech Onsite Consulting Support for Module Y Bi-Tech Onsite Consulting Support for Module Z Training Track Implement User Support Structures eMail Departments of User Support Options Monitor Effectiveness of User Support Structures Make Course Corrections as 1 day ] Tue 06/03/08 j Tue 06/03/08 1 day Tue 06/03/08 i Tue 06/03/08 1 day \ Tue 06/03/08 I Tue 06/03/08 1 day Tue 06/03/08 Tue 06/03/08 1 day 1 Tue 06/03/08 | Tue 06/03/08 1 day: Tue 06/03/08 ; Tue 06/03/08 1 day, Tue 06/03/08 , Tue 06/03/08 1 day Tue 06/03/08 Tue 06/03/08 : 1 day! Tue 06/03/08 Tue 06/03/08 1 day | Tue 06/03/08 Tue 06/03/08 T day |Tue 06/03/08 pfueO'e/OS/OS \ 1 day Tue 06/03/08 | Tue 06/03/08 1 day, Tue 06/03/08 ] Tue 06/03/08 1 day j Tue 06/03/08 I Tue 06/03/08 day 1 day Tue 06/03/08 \ Tue 06/03/08 \ 1 day Tue 06/03/08 Tue 06/03/08 j 1 day Tue 06/03/08 \ Tue 06/03/08 i Leckey Leckey Leckey I Core Team iIrvine,Branc | Leckey Leckey Leckey Irvine Branca iBi-Tech Bi-Tech Bi-Tech 1 day | Tue 06/03/08 I Tue 06/03/08 | i Leckey jBranca,Peter Branca,Peter file://C:\Documents and Settings\Kbran\Local Settings\Temporary Internet Files\Content.... 07/11/2007 Microsoft Office Project Exported Information Page 26 of 26 '•:•• i i. i ; iNecessary | ! I I file://C:\Documents and Settings\Kbran\Local Settings\Temporary Internet Files\Content.... 07/11/2007 nun Exhibit B Leckey Consulting 5 Cost My cost proposal is as follows: Q Hourly Rate: $160 a Fixed Daily Amount for Travel: $250 Q Daily Rate: $1,850, which consist of $1,600 in fees and a $250 daily per diem. This assumes a 10 hour day. I am proposing a 4-10 hour day work week. Q Phase 1 Not-to-Exceed Contract Amount: $10,000 Q Phase 2 Not-to-Exceed Contract Amount: $260,000 Assumptions for my cost proposal include the following: 1. For Phase 1,1 will make two two-day trips to the City to work with the project team in developing the Scope Statement. Given my current project commitment at Shasta County, it will have to be the first two days of the week or the last two days of the week. All other work will be completed remotely and will require a few conference calls with key individuals of the project team. If requested by the City, I can also be present during the City Council meeting to discuss the Scope Statement and the requesting of funds for Phase 2. I anticipate this Phase starting in February 2007 and being completed by the end of March 2007. 2. For Phase 2, the following assumptions are applicable: a. Given my current client commitment at Shasta County, I will be half-time on the IF AS 7i project starting approximately the beginning of September 2007 through December 2007. I will be full-time starting January 2008 through May 2008. Then half-time for June 2008 which will be my last month on the project. b. Chargeable time will not exceed 50 hours a week and billing will occur biweekly. Onsite services will be rendered on a four-day work week schedule (normally 10- hour days, Monday through Thursday), except when needed I will be present on Fridays. c. I will be bill the City for weekly travel time exceeding four hours a week, not-to- exceed three billable hours per week. d. If the project schedule is extended for any reason, my contract ceiling will be increased accordingly. Final Page 26 January 23,2007 Leckey Consulting 3. For all Phases, the following assumptions are applicable: a. The go-live date for both IFAS 7i Financials and HR/Payroll will be at the beginning of June 2008. It will not be a phased implementation. b. The City will have a project sponsor for the IAFS 7i upgrade project who will ensure that timely decisions are made, adequate City resources are assigned to the project and that they produce quality work and other issues that might arise. c. Adequate resources will be assigned to the project from the City. d. A subject matter expert (knowledgeable of the current version of IFAS) will be assigned part-time to assist with each EFAS 7i module in scope of the project. In general, the hourly commitment for each SME will be approximately 12 to 16 hours per person per month. e. The City will agree to a reasonable amount of technical and functional consulting assistance from Bi-Tech. This will be further refined during Phase 1 activities. f. All project documents and deliverables will be stored electronically in the Project Library maintained on the City's network and it will be the City's responsibility to ensure that there are daily server backups during the working week. Deliverables or documents will not be replicated in paper or bound form solely for the purpose of having a paper copy maintained in the Project Library. g. End user procedures exist at the City for the current version of IFAS. Therefore, I will only have to update them for changes in IFAS 7i. h. The current database server is sufficient to address IFAS 7i requirements. Therefore, it will not be necessary to complete a database migration to a new server. Only new web servers and the related IFAS 7i will need installed. i. Steve Leckey will be available if Leckey Consulting is awarded the contract (i.e., he will not have signed another client contract during the County's evaluation of my proposal). 6 Insurance My company currently carries all applicable business insurance coverage and licenses required per the RFP (except a City of Carlsbad Business License) and would be able to comply with the indemnity provisions. I would like to add one point of clarification regarding automobile liability. I carry automobile liability insurance with a coverage of $250,000/$500,000, and then I have umbrella liability coverage for $1,000,000 that also covers my automobile. I am proposing that this combined coverage be adequate in meeting the City's automobile liability insurance requirements. Final Page 27 January 23,2007