HomeMy WebLinkAbout1970-12-01; City Council; 300; Request for Transfer of Appropriations,-- ,. u .. T. IT E CITY OF C A R L S B'A D, CALI F'O R NfA
Agenda Bill No. Jo& . Date: Dec. 1, 1970
Ref erred To :
Subject:
Request for Transfer. of Appropriations to
Professional ServicFs Account
~- ~ ~
Submi t ted By:
Hunter T. Cook
City Engineer
-Statement of the. lYatter
See attached Exhibit 1
'
- Exhibit ..
I - Request for Transfe-r of Appropriations to Departmental Professional
Services Funds.
Staff Recommendations
1, Adopt a motion,:
a)
b)
Approving the transfer of appropriations as outlined ih Exhibit I.
Authorizing the Mayor and City Clerk to execute a-contract with
Shuirman-Simpson, Consulting Civil Engineers, for the preparation
of Phase I of the City Master Drainage Plan at a fee not to exceed
$7 , 000 ,
-
h c ..
City Hanager's Recommendation
If financing preparation of project is feasible, we suggest Council
hear from City Engineer on the need for a study and decision for
recommending Engineering Consultants prior to reaching a decision.
r
Council Action
12-1-70 . Authorization was given for transfer of funds in,,tbe amount o.f
$9,500 for preparation .of plans, and the Mayor and City Clerk
authorized to execute agreement with Shuiqrman-Simpson not to
-exceed $7,0.00 for preparation of drainage plan.
..
.. ..
-2-
- -. CZW- OF C'WC.'L 3
REQUEST F9R TRANSFER OF APPROPRIATIONS-
Referred to City
Dept.: .Engineerinq -
Approved as Action of
Dept. No. :
Planager for: Action Requested
Revised 0
City Manager
Department of Finance
BY
Dept. of Finance No.
Date: I
,
Ty) : FINANCE DEPARTMENT
[,Transfer From:
i
City
Council:
_- $ 9500.00
(General Fund Surplus)
Acct.- $
Acct * $ I
Ds",: November 24, 197 o
Transfer to :
ACst. 1-.110 - 15 2 $ 9,500.00
(Professional Services)
Acct . $
Acct. $
Acct . $
Explanation: For preparation of a portion of the City Master Drainage
'PEan, to provide for miscellaneous testing and con-
sulting services and to correct an error in the original - Fiscal Year 1970-71 Budget. .
Name
City Engineer
Title
.City Manager's Report:
City Manager.
Explanat ion
Item 1)
The current budget includes $1,000 for professional services. This
provided amounts for testing and miscellaneous consulting services.
No provision was made to carry over obligations incurred during
the previous fiscal year but which had not been actually expended.
These obligations have been paid from current appropriations with
the result that the professional services fund is in a deficit
posit ion.
The following breakdown shows the funding in this account which
is necessary to complete the fiscal year. Amounts should include
expenditures to date.
1. Testing $ 500
2. Miscellaneous con-
3. Master Drainage Plan 7,000
sulting services 2 , 000
Recommended Appropriation $9,500
1.
2.
3.
Testing - This provides for laboratory testing in con-
nection with project design or construction for which
costs cannot be allocated to a particular project or
subdivision.
This item covers minor consulting services in connection
with specialized engineering matters, i.e., soil
mechancis, traffic engineering, etc., and for obtaining
minor surveying services.
Master Drainage Plan - Phase I
The need for development of a Master Drainage Plan for
the City is becoming critical. Developers are approach-
ing the City staff with questions regarding required
improvements in many areas within the ultimate anti-
cipated City boundaries. No Master Drainage Plan is
available for use in analyzing their requirements.
This transfer will allow preparation of a Master Drainage
Plan for several of the most critical drainage areas
within the City. It will be formulated in such a way
that a study of the remainder of the City can be ob-
tained at a later date utilizing the basic background.
The areas to be studied immediately are depicted on
Attachment "A".
The foreseeable staff work load is such that the study
cannot be performed "in house". The work will be per-
formed by a private engineer experienced in drainage
matters.
A proposal has been received from Shuirman-Simpson,
Consulting Civil Engineers, to provide the required
services for a fee not to exceed $7,000. The final
cost would be based on the actual time spent on the
project. The method of calculating the fee is in
accordance with recommendations of the American Society
of Civil Engineers. The firm is well qualified to per-
form work of this type.
The proposed study has been discussed with the County
Flood Control District. It will not duplicate any work
which they are now doing.
General Fund Balance anticipated on Pg. 2 of 1970-71 Fiscal Budget
indicates $107,116. The actual figure after audit was $121,453.
Thus, sufficient unanticipated reserves are available to cover the
requested transfer.