Statement of the Matter T
The modification of'the traffic signals on Carlsbad Boulevard at Elm and
Grand Av9nues has been satisfactoriLy complgted-by the Traffic Signal
Maintenance Company, Inc .
The contrack price for the project '($9,816.71) was a maximum, subject to
actual costs, which amounted to $9,266.71, as billed, .
The original designtanticipated an existing interconnect conduit between
.the Elm and Grand Avenue controllers. - It was found in the field that
175 feet of conduit had never been installed. Change Order No. 1 in the
amouht of $746.33 is required to cover the cost of installation 6f this
conduit and the attendant wiring. - Total cost of the project including Change Order No. 1 is $10,013.04;
funds bidgeted are in amount of $11,000.00. in the Gas Tax Fund for other projects, .. Exhibit
The excess will be retained
1) Change Order No, 1
I
..
Staff Recommendations
Adopt a mot ion : ..
. 1) 'App;oving-.Chang.e Order No, 1. -.
.-
' 2). Accepting-the work on behalf..of the City. .
3)
4) ... Instructing the City Clerk to'relrease the .bonds 35. days after
Instrqcting .the City- Clerk to .file .a-Notice .. .' .of Compl-etion on
- b.ehalf of the City, : 1.
filing Notice of Completion.
A3 No. Date: January 5, 1970
City Manager's Recommendation
Concur'with City Engineer's recommendation.
Council 'Action
. 1-5-71 Change Order #1 was approved, the work was accepted, and City Clerk instructed to file Notice-of Completion and release bond
35 days after notice of completion is filed. '
.'.
-. .
-2-
1-
CXTY OF CARLSBAD
ENGINEERING DEPARTMENT
CHANGE ORDER
Date: December 10, 1970
Change Order No. 1 Budget No: 2-2107-4
. Contract NO. 1002
Cont5actor: Traffic S,ignal Maintenance Company, Inc.
-i
Project,??arne:, Trdffic Signa.1 Modification, Carlsbad Boulevard,
Elm and Grand Avenues
Action:
The plans for Contract #lo02 call for interconnection of the
signals for synchronization. It was believed that a conduit for
this purpose existed between' the controllers. Actual conditions
disclosed that the installation of an additional 175 feet of
1%'' conduit with wiring was required to complete the installation.
The work has been accomplished.
cost:
The cost of this change order is an additional $746.33 on a time
and materials basis .
Contractor: Traffic Signal Maintenance '
By: See TSM Invoice NO. 10182
Date: 11-30-70
Approval:
City Engineer
EXHIBIT I
. -9 . k' /-
NOTICE OF COMPLETION
ENGINEERING
To All Laborers and.Materia1 Men and to Every Other Person Interested:
YOU WILL PLEASE TAKE NOTICE that on December 1,,1970 I
the Engineering project consisting of modifv ina the traffic si 'gnals on
Carlsbad Boulevard at Elm and Grand Avenues,'
on which Traffic Signal Maintenance Company, Inc.
was the contractor, and United States Fidelity and Guaranty Company
was the surety, was completed.
3 -. CITY OF CARLSBAD
City Engineer
VERIFICATION
I, the undersigned, say:
I am the City Engineer of the City of Carlsbad; the foregoing
Notice of Completion is true of my own knowledge.
I declare under penalty of perjury that the foregoing is true and
Executed on December 15, 1970 at Carlsbad, California.
correct. ' t
VERIFICATION OF CITY CLERK
I, the undersigned, say:
I am the City Clerk of the City of Carlsbad; the City Council of
said City on accepted the above described work
as completed and ordered that a Notice of Completion be filed.
I declare under penalty of perjury that the foregoing is true and
Executed on at Carlsbad, California.
correct .
_-., . __.
I