AGENDA BILL NO. 3�. /j=1�1ds(oolV Deptial:
ept.Hd.
DATE: July 15, 1975 C. Atty.kC�_
DEPARTMENT: City Manager C. Mgr.
Sub--e—
FIRE STATION NO. 3 SITE
Statement of the Matter
Negotiations have been continuing with the owner of the
property at the southwest corner of E1 Camino and Chestnut
for Fire Station No. 3 site. A memo is attached which
outlines the costs of the location at E1 Camino and Chestnut
and our presently owned location at Catalina and Chestnut.
Exhibit'
Memo to City Council from City Manager dated 7-7-75.
Recommendation
If Council concurs, instruct staff to discontinue negotiations
on the El Camino and Chestnut site and authorize them to
hold neighborhood meetings with the residents on Catalina and
the surrounding area to explain the need for a fire station.
Staff should be further instructed to make application for
a Conditional Use Permit on the City's behalf.
Council action
7-17-75 The Council instructed staff to discontinue negotiations for
Fire Station site on the E1 Camino and Chestnut Site and
apt horizr,d neighborhood meetings with residents.on Catalina
and surrounding area to explain need for fire station.
DATE: JULY 7, 1975
TO: CITY COUNCIL
FROM: City Manager
SUBJECT: FIRE STATION NO. 3 SITE
Several meetings have been concluded with Mr. Marvin
Humphreys concerning the purchase of his property at
the southwest corner of E1 Camino and Chestnut. The
City appraisal of the property indicates a value of
$76,000.00. Although no firm offer has been tendered
or accepted, it appears that a negotiated settlement
could be reached for between $100,000.00 and $120,000.00.
A recapitulation of the cost of the southwest corner of
E1 Camino and Chestnut with the southwest corner of
Catalina and Chestnut is as follows:
Catalina and
E1 Camino and
Chestnut
Chestnut
Site
-0-
$100,000
Building
$80,000
80,000
Architect Fees
-0-
10,000
Curb, Gutter and
-0-
2,700
Sidewalks
Sewer
-0-
8,500
Water
-0-
1,000
Grading
-0-
2,000
Total
$80,000
$204,000
If the actual site at El Camino Real and Chestnut were
purchased as a future park site, a portion of the $75,000.00
in Park District Four could be utilized. This would, of
course, deplete that fund, restricting other park develop-
ment in the area.
It is my recommendation that negotiations for the site be
discontinued. The staff should be authorized to hold a
neighborhood meeting with the residents on Catalina Street
and the surrounding area to explain the need and operation
of a station in the area.
Additionally, the staff should be authorized to apply for a
Conditional Use Permit for the construction of the fire
station. At the time of the Conditional Use Permit hearing,
any neighbors who have questions or wish to protest the
facility can be heard.
PAUL D. BUSSF.Y
City Manager
PDB:Idg