Dyno Construction Co., contractor for subject project, has
satisfactorily completed the work. The original contract price was in the amount of $8,913,and Change2Order No. 1 in
the amount of $640.65 was approved by the City Engineer.
The final contract cost is in the amount of $9,553.65. Ten (10)
percent of the final contract amount will be retained until
35 davs after the Notice of Comcletion is recorded. This yroject
is being.financed by a Housing and Community Development Block
Grant.
EXHIBITS :
1. Change Order No. 1
2. Notice of ComFletion
RECOMMENDATION:
1. APFrove Change Order No. 1, and - 2. Adopt a motion acceFting work and instructing the City Clerk
to record the Notice of Completion and release the bonds
thirty-five (35) days after the recording date.
Counci 1 action
10-26-76 Change Order No. 1 was appt-oved and the Council.accepted the work and instructed .the City Clerk to record the Notice of Completion and release the bonds thirty-five days after the recording date.
. .%_
4
CITY OF CARLSRAD -
PUBLd WORKS PROJECT CHANGE ORL. :
CHANGE ORDER NO. 1 DATE October 1, 1975
CONTRACT NO. 1035 PU~CHASE ORDER NO. BUDGET NO. ,
DYNO CONSTRUCTION CONTRACTOR ' S ISAME
PROJECT NAME AND NO. Wheelchair Ramps
ACTION :
c.3 Unit Addition/ Bid Deletion Item Article Quantity Unit Price Amount
Dele 1 Remove existing P.C.C. - (25) L.F. $3.00 -(75.00)
3.00 30.00 Add 2 Remove existing A.C. 10 L.F.
Add 3 Remove existing P.C.C. 387 S.F. .70 270.90
Add 4 Remove existing A.C.
Curb *.
Curb
Sidewalk
Sidewalk 33 S.F. 3.00 99.00
Dele 5 P.C.C. Curb & Gutter - (15) L.F. 5.00 -(75.00)
Dele 6 4" P.C.C. Wheelchair . -(117) S.F. 1.25 -(146.25)
Ramp
Add 7 4" P.C.C. Sidewalk 537 S.F. 1.00 537.00
APPROVAL : ,
Field Engineer (1 Date
Department Head Date
3?&?
Date
$ 640.65
c
NOTICE OF COMPLETION
ENG I NEE RI NG
To All Laborers and Material Men and to Every other Person Interested:
YOU WILL PLEASE TAKE NOTICE that on October 1, 1976 8
the Engineering project consisting of
constructing wheelchair ramps, Contract No. 1035
on which Dyno Construction Co. of Nest Covina-California
was the contractor, and American Fidelity Fire Insurance Co., Woodbury, N.Y.
was the surety, was completed.
CITY OF CARLSBAD
City eineer
VERIFICATION
I, the undersigned, say:
I am the City Engineer of the City of Carlsbad; fhe foregoing
Notice of Completion is true of my own knowledge.
I declare under penalty of perjury that the foregoing is true and
correct.
Executed on o& c7 1976 at Carlsbad, California.
VERIFICATION OF CITY CLERK
I, the undersigned, say:
lerk of the City of Carlsbad; the City Council of
said City on ZL. /476 accepted the above described work
as completed and ordered that a ISotice,of Completion be filed.