HomeMy WebLinkAbout1977-05-03; City Council; 3240-8; Fire Station No. 3 Contract 1029CITY OF CARLSBAD
AGENDA BILL NO. 3A''�% — P f Lf Initial:
DATE: Mav 3 1977
De t.Hd`��
C.pAtty.
DEPARTMENT:_ Engineerincr C. Mgr.
Subs ect
FIRE STATION NO. 3 - CONTRACT No. 1029
Statement of the Matter
Armstrong -McHugh, the contractor on the sc,bject project., has
completed the work on Contract No. 1029.
The Fire Department has occupied the building since September,
1976 and has indicated that all defective work has been
corrected by the contractor.
The final contract price of this project is $91,490.00 of which
10% is being retained until 35 days after the Notice of Completion
is recorded.
EXHIBIT:
1. Notice Of Completion
2. Memorandum dated April 15, 1977 from Fire Department
Council action
RECOMMENDATION:
Approve a motion accepting the work and instructing the City
Clerk to record the Notice of Completion and release the bonds
.35 days after the recording date. .
Council action
5-3-77 The work was accepted and the Clerk instructed to record the
Notice of Completion and release the bonds 35 days after
recordation date.
NOTICE OF COMPLETION
ENGINEERING
To All Laborers and Material Men and to Every Other Person Interested:
YOU WILL PLEASE TAKE NOTICE that on April 15, 1977
the Engineering project consisting of Construction of Fire Station No. 3
on which Armstronq-McHugh, Inc. of Del Mar, California _
was the contractor, and Fidelity and Deposit.Company of Maryland ---—
was the surety, was completed.
CITY OF CARLSBAD
City Engineer
VERIFICATION
I, the undersigned, say:
I am the City Engineer of the City of Carlsbad the foregoing
Notice of Completion is true of my own knowledge
I declare under penalty of perjury that the foregoing is true and
correct.
Executed on at Carlsbad, California.
VERIFICATION OF CITY CLERK
I, the undersigned, say:
I am the City Clerk of the City of Carlsbad; the City Council of
said City on accepted the above described work
as. completed and ordered, that a Notice of Completion be filed.
I declare under penalty of perjury that the foregoing is true and
Correct.
Executed on at Carlsbad, California.
CARLSBAD FIRE DEPARTMENT
MEMORANDUM
10-11 16 C
�F,C ,IV E 9
f%P R 15 1977
CITY OF UARiLSBAD
Planning Departmm.
TO: PUBLIC WORKS DIRECTOR DATE: 4-15-77
FROM: BATTALION CHIEF/FIRE
SUBJECT: STATION #3 - FINAL INSPECTION
This is to inform you that an inspection was made on
our pick-up list to the contractor of Station #3 and
find that everything was accomplished to the department's
sa tisfaction.
A. Wo enchu <, B/C (,o.
AVR1g77
00
UTILITIES
AINTENANCE
EPARTMENT
RECEIVED
APR 1 81977
CITY OF CARLSBAD
Engineering Department