DEPARTMENT : Pub I ic Works C. Mgr. u&&
Subject :
SEWER LATERAL I NSTALLAT I ON 'CHARGES
Statement of the Matter
New applicants for sewer service are required to pay a lateral installation
charge which covers the cost for installing the lateral in the City right-of-
way to the main sewer line. Lateral installation charges are levied in ac-
cordance with Resolution No. 1863 which was adopted in June, 1971. These
charges are based on 1971 co'nstruction costs and have not been escalated for
inflation si'nce that time.
4" pi pe
Current Charqes Recommended Charqes
$215 $460
6" pi pe 255 540
8" pi pe 352 Per cost agreement
Plug existing lateral I50 250
These charges are based on Brown & Caldwel I 's-report, "Financial Plan and
Revenue Program for City of Carlsbad Sewerage System" of March, 1978.
have been reviewed by the Utilities/Maintenance Director and he concurs that
these recommended charges more accurately reflect current costs.
They
Exhi bits
Resolution No. 6701estabI ishing new charges for instal lation of sewer laterals
"Financial Plan and Revenue Program for City of Carlsbad Sewerage System" of
March, 1978 (avai table in Engineering Department)
Recommendation
If Council concurs, adopt Resolution No.\+-70/ establishing new charges for
installation of sewer laterals.
Council Action:
3-6-79 Council adopted Resolution 5701, establishing new charges for
installation of sewer laterals.
- J
1
2
3
4
5
6
7
a
9
10
11
12
13
14
3.5
16
3.7
18
19
20
21
22
23
24
25
26
27
28
RESOLUTION NO. 5701
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CARLSBAD,
CALIFORNIA, ESTABLISHING CHARGES FOR
I NSTALLAT ION OF SEWER LATERALS
WHEREAS, present charges for the installation of sewer laterals are based
upon a schedule which was adopted by the City Council in June of 1971; and
WHEREAS, costs of labor and materials have risen substantially since 1971;
NOW, THEREFORE, BE IT RESOLVED that the attached schedule, titled “Sewer
Lateral Charge Summary,” shal I hereafter be used as the basis for such charges
by the City of Carlsbad.
PASSED, APPROVED AND ADOPTED by the City Council of the City of Carlsbad
at a regular meeting held the 6th day of March , 1979, by the fol-
lowing vote, to wit:
AYES : Councilmen Packard, Skotnicki, Anear, Lewis and
NOES : None Councilwoman Casler
ABSENT : None
@dzfK&:J
RONALD C. PACKARD, MAYOR
ATTEST :
(SEAL)
. -
Attachment to Res. 85701
SEWER LATERAL CHARGE SUMMARY
A. FOUR-INCH (4") VITRIFIED CLAY PIPE SEWER (PLASTISOL JOINT):
1. Unsurfaced street with a maximum depth of ten feet (IO') at main and maximum horizontal run of thirty feet (30') -- $460.00.
2. $7.00 per foot over and above ten feet (10') deep at the main
for unsurfaced street.
3. $11.75 per foot over and above thirty feet (30') in horizontal length for unsurfaced street.
4. In computing the installation charge for a surfaced street, add thirty-five percent (35%) for resurfacing to the total charge.
B. SIX-INCH (6") VITRIFIED CLAY PIPE SEWER (PLASTISOL JOINT):
1. Unsurfaced street with a maximum depth of ten feet (10') at main and maximum horizontal run of thirty feet (30') -- $540.00.
2. $7.00 per foot over and above ten feet (10') deep at the main for unsurfaced street.
3. $77.75 per foot over and above thirty feet (30') in horizontal length for unsurfaced street.
4. In computing the installation charge for a surfaced street, add thirty-five percent (35%) for resurfacing to the total charge. -..
C. ALL OTHER
1. Applicant will pay the actual total cost of the installation in- cluding an assessment for administration overhead which shall be set at fifteen percent (15%) of cost as per current practices.
D. CHARGE TO PLUG EXISTING LATERAL -- $250.00
March, 1979