Loading...
HomeMy WebLinkAbout1980-05-20; City Council; 6007-2; Palomar Airport Rd. and Paseo Del Norte Rd.Initial : DATE : May 20, 1980 C. Atty Engineering C. Mgr. DEPARTMENT: IU Dept. Head * AGENDA BILL NO. ,$ob 7 -AB-&& dz SUBJECT: PALOMAR AIRPORT ROAD AND PASEO DEL NORTE ROAD - CONTRACT NO. 1072 STATEMENT OF THE MATTER . Construction under the above contract has been satisfactorily compl eted. final contract amount was $236,703.60 which is $1,000 over the contract amount of $235,703.60. The $1,000 increase was due to the issuance of a change order for extra base material and fiber reinforcing mat. The (See attached change order.) The original project funding was $370,000 and, therefore, sufficient funds are available to cover the cost of the change order. Ten percent of the final amount will be withheld until 35 days after the Notice of Completion is recorded. EXHIBIT Notice of Completion -- Change Order No. 1 .. RECOMMENDATION' Accept the work including the work under the Change Order, and direct the City Clerk to record the Notice of Completion and.release the bonds 35 days after recordation. Council Action: 5-20-80 - Council approved staff recommendation. -. CITY OF CARTASBAD I f i' ,.1 L * -5 'I+.* A . PUBLIC WORKS PROJECT CHANGE ORDER .- - -- CHANGE ORDER NO. 1 CONTRACT PURCHASE - NO. 1072 DATE April 11, 1980 ORDER NO. BUDGET NO. Palomar Grading and Paving - CONTRACTOR ' S NAME Palomar Airport Toad 6 Paseo del Norte PROJECT NAME AND NO. ACTION: 1. Add D.G. Fill onmedian island (to replace existing damaged pave- ment removed) to form base for median cTirb at lump sum of $500. 2. Add - 750 S.F. of Fermarnat fiber reinforcing mat as test case on applicability at (0.67/S.F. apFroximate'cost) lump sum €or labor, materials and installation at $500. 3. Item 8 - Substitute 414 L.F. of 14" F-curb in lieu of 6" B-1 curb to match grades at no extra cost to City. i PALOMAR GRADING E PAVING, INC. BY DATE 4/11/80 .. . Date Department Head ' Date ..