Work under the above contract has been satisfactorily completed.
amount of $45,499.44 is less than the ariginally bid price of $46,337.
The final contract
F I SCAL IMPACT
There are sufficient budgeted funds to cover the balance of this contract.
of the final contract amount ($4,549.94) will be withheld until 35 days after the
Notice of Completion records.
Ten percent
ENVIRONMENTAL IMPACT
Environmental assessments were completed prior to start of construction.
RECOMMENDATION
Accept the work; direct the City Clerk to have the Notice of Completion recorded
and release the bonds 35 days after recordation.
EXHIBIT
Notice of Completion
NOTICE OF CONPLETION
ENGINEERISG
To All Laborers and Materia'l Men and to Every Other Person Interested:
YOU WILL PLEASE TAKE NOTICE that on May 19, 1981
the Engineering project consisting of Curb, Gutter and Sidewalk
Re-
' on which Jim McNulty contracting Co.
was the contractor, and The Ohio Casualty Insurance Co.
was the surety, was completed.
CITY OF CARLSBAD
VERIFICATION OF CITY CLERK
I, the undersigned, say:
I am the City Clerk of the City of Carlsbad; the City Council of
said' City on
completed and ordered that a Notice of Completion be filed.
accepted the above described work as
I declare under penalty of perjury that the foregoing is true and
correct .
Executed on at Carlsbad, California,
CITY OF CARLSBAD