TITLE: STORM DRAINS AT OCEAN STREET AND
CEDAR AVENUE - CONTRACT NO. 1086
CITY MGR
Accept the construction of storm drains at Ocean Street and Cedar Avenue as complete;
direct the City Clerk to have the "Notice of Completion" recorded; and release the
bonds 35 days after recordation.
ITEM EXPLANATION:
This project was the construction of storm drains on Ocean Street at Cedar Avenue.
-inalizingof the project was delayed pending completion of the adjacent development
by Tony Howard-Jones. The construction work under this project has now been satis-
factorily completed, and the final contract amount of $12,607 does not exceed the
bid price.
FISCAL IMPACT:
Sufficient budgeted funds are available to pay final contract costs. Ten percent
of the final contract will be withheld until 35 days after the "Notice of Completion''
records .
EXH I B I T :
Notice of Completion