HomeMy WebLinkAbout1984-02-07; City Council; N/A; Sand Bypassp� h
�n
FEBRUARY 7, 1984
TO: CITY MANAGER
FROM: Assistant City Manager/Developmental Services
SAND BYPASS
The project to be discussed at the public hearing scheduled
by the Corps of Engineers is, in all of its elements, the
same project discussed in the January 13, 1983 report to
you from Roy Kackley. That report, which was analyzing the
SANDAG Agenda Report No. R-7,concluded that sand being re-
distributed from the Oceanside beaches southward would
have benefit to the Carlsbad beaches and recommended that
Carlsbad concur with the SANDAG resolution approving the
project. A copy of that report is attached for your
information.
This project has been followed up by city staff since 1981
and the various alternatives supported by us in the past
have always included the sand bypass system.
In conclusion, I would recommend that after council
discussion the city adopt a position supporting the con-
cept of a sand bypass and put ouselves on record with the
Corps of Engineers as encouraging its prompt installation.
r/F �a'
.O
RAB:pab
Attachment
COUNCIL, 2-7-84 Council reiterated their position of support for the
ACTION: a f�'
sand bypass and directed that a letter conveying R v
that support be sent to the Corps of Engineers40
J
r Of
�� Cq is
q
JANUARY 13, 1983
TO: CITY MANAGER
FROM: City Engineer
SANDAG AGENDA REPORT R-7
PURPOSE
The purpose of this memo is to provide comments on SANDAG's Agenda Report
R-7 relating to the experimental sand bypass system program for the City
of Oceanside and to offer some general comments on beach erosion based
upon a report on the bypass program, information from Scripps institution
of Oceanography, and on Dr. Pilkey's book "The Beaches are Moving."
BACKGROUND
The program for installing, monitoring, and evaluating an experimental
sand bypass system at Oceanside beaches was proposed pursuant to House
Appropriations Committee report and authorized by Public Law 97-88.
Nine systems were developed and evaluated by the Corps of Engineers on
the basis of (a) the potential to provide nourishment to Oceanside beaches,
(b) the potential to reduce harbor maintenance costs, (c) the impact on
the operation of Camp Pendleton, and (d) on public acceptance. The
selected system as proposed is a hybrid of several of the alternatives
incorporating the favorable features of each into a single system.
The proposed system will have these components:
a. An entrance channel sand removal system;
b. An accretion fillet removal system to transport sand from
the north beach to the south beaches, and;
c. A pipeline discharge system for distributing sand along
Oceanside beach.
The system will (a) prevent sortie of the sand in the littoral zone
(natural southerly movement of sand) from being moved around the northern
breakwater into the harbor entrance and (b) remove sand from the harbor
channel and transport it to the Oceanside beach.
The cost of the system plus operation over a five -,year experimental
period is estimated at $11 477,000 (design and construction $5,097,000;
operation and maintenance J3,590,000; and monitoring $2,760,000). Pro-
curement and construction (if authorized by Congress and funds appropriated)
could be completed by March 1984.
SANDAG AGENDA REPORT R-7
January 13, 1983
Page -2-
The District Engineer for the Corps of Engineers, in carrying out the
will of the Congress as instructed by the Secretary of Army, concludes
as follows:
a. The experimental system will reduce the amount of maintenance
dredging required at Oceanside harbor.
b. The system will provide the manner of evaluating the perfor-
mance of a jet pump system in maintaining navigation channels.
c. The effects of operating such a system on adjacent beaches
can be evaluated.
d. The economics of the proposed system versus conventional
dredging can be compared.
e. Local groups have been favorable to the proposed sand bypass
system.
SANDAG, in response to public notice from the Corps of.Engineers
inviting comment, proposes to reaffirm support of the program and agree
that such a system when installed would have no significant adverse effect
on human environment.
DPSrIP;';MN
Oceanographers at Scripps Institution indicates that historically the
presence of sand on the beaches of southern California is the result of
the natural erosion of the sea bluffs and the sediment transport of rivers
and streams.
The extensive urbanization of the coast line and severe modifcation of the
natural sediment (sand) generation sources and distribution due to con-
struction of flood control and irrigation structure on inland streams and
marine structures to protect harbors along the coast, have reduced the
sand supply and prevents replenishment. Climatic conditons have also
modified the amount of sand reaching the beaches, less being generated
during the dry periods and more during wet cycles. The period of 1945 to
1977 ►vas a dry period and a reduced sand supply was the result. In general,
conditions such as are experienced at Carlsbad are the result of inadequate
sand supply and not a problem of sand retention. This is true all along
the coast.
Sand in this region moves generally from north to south ending in the
La Jolla trench, a deep depression in the sea bed running perpendicular
to the beach near La Jolla. The sand supply at any given point along the
beach also moves in and out with the seasonal storms. In the winter the
storm waves move the sand out to sea forming bars off shore against which
waves can break which dissipate their energy before they break on the beach.
SANDAL AGENDA REPORT R-7
January 13, 1983
Page -3-
In the summer, or weather moderation, wave action moves the sand back
onto the beach, thus providing longer slopes on which wave energy is
dissipated. These phenomena are beyond the control of man and must be
recognized and accepted. Man cannot manufacture sand but can only try
to redistribute it by artificial measures.
Erosion control of beach areas is of national concern as evidenced by
the authorization and funds provided by Congress for various beach
erosion projects. The Corps of Engineers (under the direction of the
Secretary of Army and controlled by Congress) is the nation's leading
expert on beach erosion. The two specialty agencies of the Corps for
these matters are the Beach Erosion Board and the Waterways Experiment
Station. It should be recognized that the Corps of Engineers is not an
autonomous agency with discretionary funds and authority, but an agency
of execution carrying out the will of Congress and spending federal tax
dollars as authorized. It is not reasonable to ask the federal government
or the Corps of Engineers to be responsible for beach restoration at
Oceanside. In view of the natural erosion that is constantly occurring,
the beach at any point can never be "restored". Technical assistance is
always available to local interests and it is poss;ble.to obtain financial
support within the exercises of national policy.
The project as proposed by the Corps of Engineers, if successful, will
have an ancillary benefit in that some of the sand redistributed to Ocean -
side's south beach will find izs way to Carlsbad beaches. Even with the
groins, as now proposed by local authorities in Oceanside, sand will move
littorally from north to south and provide a source of replenishment.
Carlsbad's Longard project is designed to trap some of that sand and to
build a "perched" beach.
CONCLUSION
The current proposal of SANDAL to reaffirm support of the sand bypass
system and agreement that no adverse environmental impact will occur is
supportable. A demand that the federal government accept full responsi-
bility for beach restoration is naive and should be modified to a more
reasonable demand or statement.
RECOMMENDATION
The City of Carlsbad should concur with Resolution 83-51 as proposed
in Agenda Report No. R-7.
(2Af-_____
ROY KACKLEY
RL K: mmt
C: Assistant City Manager/Developmental Services
PUBLIC NOTICE
OCEANSIDE, CALIFORNIA
DATE OF NOTICE: 2 `am �r?
!r;.
COMMENT DEADLINE: FEB 1984
YOUR COMMENTS ARE INVITED ON THIS PROPOSED EXPERIMENTAL SAND BYPASS PROJECT
INTRODUCTION: The U.S. Army Corps of Engineers, Los Angeles District, has
been authorized to proceed with engineering and design of a sand bypass system
as an alternative to the periodic maintenance dredging of the approach and
entrance channels at Oceanside Harbor, and place the bypass material along the
Oceanside beach (see enclosed map).
LOCATION: Oceanside Harbor, near the city of Oceanside, San Diego County,
California.
PROPOSED ACTIVITY: The following installations are proposed:
--Ten jet pumps at the South Jetty at a depth of minus 45 feet mean lower
low water (MLLW).
--Two jet pumps and three fluidizer pipes at a depth of minus 50 feet MLLW
at the North Breakwater.
--One jet pump at depth of minus 26 feet MLLW at the north fillet area.
--A discharge line about 4,200 feet long across the existing harbor buried
about 7 feet below the harbor bottom.
--A discharge line about 10,800 feet buried from 5 to 10 feet along the
Oceanside beach terminating at Wisconsin Avenue.
--An electrical booster station adjacent to the existing restroom just
downcoast from the South Jetty.
The Experimental Sand Bypass System is designed to intercept the littoral
material at the harbor entrance and the north fillet area and discharge the
material on the downcoa.st beach of Oceanside.
PROJECT AUTHORIZATION: The Experimental Sand Bypass System project at
Oceanside Harbor, Oceanside, California, is pursuant to House Appropriations
Committee Report 97-177 on the Energy and Water Development Appropriation Act
for 1982, Public Law 97-88, which reads as follows:
"The Committee has heard testimony that the City of
Oceanside has suffered severe economic losses as a result
of beach erosion much of which has been attributed to the
construction of the jetty on Camp Pendleton during World
War II. (The City of Oceanside has documented over $34
million in losses last year.)
All of the sand dredged from the common channel to
Oceanside Harbor and Del Mar Boat Basin on Camp Pendleton
Marine Corps Base must be used to nourish Oceanside's
badly eroded beaches in accordance with House Document
456, 86th Congress and House Document 76, 89th Congress.
Dredging cost have continued to increase
dramatically. Last year, $1.6 million in Federal funds
were expended to dredge the channel. Funds have been
appropriated for dredging the channel approximately every
other year since 1962. $5.3 million in dredging funds
have been appropriated to the Corps in the last ten
years, in addition to matching funds provided by the
Navy.
The Committee understands that the Corps of Engineers
has been considering a sand bypass alternative to the
dredging with a view toward reducing channel maintenance
costs over the long .term. The Corps is directed to
proceed with engineering and design of a sand bypass
system in consultation with representatives of the local
and State governments and report to the Committee no
later than March 31, 1982, on a program for installing,
monitoring and evaluating the effectiveness of a sand
bypass system as a means of maintenance of the harbor
channel.
Accordingly, the Committee has appropriated $700,000
for the detailed design, and to undertake procurement and
installation of a sand bypass system at Oceanside Harbor,
California."
STATUTORY AUTHORITY: Section 404 of the Clean Water Act (CWA) (33 USC 1344)
applies to the discharge of dredged or fill material into waters of the United
States.
OTHER REQUIRED AUTHORIZATIONS: A Federal agency is not ordinarily required to
obtain authorization from a state or local entity. Section 404(t) of the CWA
however, allows any state to regulate the discbarge of dredged material into
navigable waters within its jurisdiction, including any such activity by a
Federal agency. I will, therefore, comply with the substantive and procedural
requirements of the State of California (California State and Regional Water
Quality Control Boards) for this discharge.
COASTAL PROGRAM CONSISTENCY DETERMINATION: In accordance with Section 307(c)
of the Coastal Zone Management Act (CZMA) of 1972, as amended (16 USC
1456(c)), I hereby find that the discharges described in this public notice
will be undertaken in a manner consistent, to the maximum extent practicable,
with the State of California Coastal Management Program. The effects of the
discharges on the coastal zone are included in the Revised Draft Environmental
Assessment. By copy of this public notice, I am notifying the California
2
Coastal Commission and the Regional Commissions of my determination. If I
receive an objection which states that these discharges are not consistent
with state programs, I shall not proceed until we. have had an opportunity to
resolve the matter utilizing the procedures provided by the CZMA. A Revised
Draft Determination of Consistency with the California Coastal Act has been
prepared and submitted to the California Coastal Commission.
EQUIPMENT AND/OR TEMPORARY STRUCTURES TO BE USED: The following equipment,
the type of which depends on the contractor and the contract terms and
specifications, that would be used are as follows:
--A crane operating from a barge to install the jet pumps to the designed
depth at the South Jetty and the North Breakwater.
--A crane or a boom constructed on top of the existing Borth Breakwater to
install the jet pump to the designed depth at the north fillet area.
--A dragline to excavate a trench at the North Breakwater to install the
three fluidizer pipes.
--A dragline to excavate a trench across the existing harbor for placement
of the subsea discharge line.
--Backhoes, bulldozers, and a front-end'loader to excavate a trench for
the discharge line along the beach. The trench would then be backfilled and
compacted by bulldozers or front-end loaders.
The contractor may install temporary fencing or barriers to confine the
construction area along the beach in order to allow safe year-round
recreational usage of the remaining existing beach.
ALTERNATIVE TO TH2 PROPOSED ACTION: An alternative to the experimental sand
bypass system would be the present method of periodically dredging the
approach and entrance channels of the existing harbor. The maintenance of the
approach and the entrance channels of Oceanside harbor was authorized by
Public Law 89-298, 89th Congress, 1st Session, approved October 27, 1965. The
material dredged from the harbor has been placed on the beach at Oceanside
(south of the harbor) as a by-product of the maintenance dredging
operations. From 1965 to 1981, an estimated 5 million cubic yards of material
have been dredged from the existing harbor.
SUMMARY OF POTENTIAL ADVERSE ENVIRONMENTAL IMPACTS: About 54 acres within
Oceanside Harbor, the north fillet, and downcoast Oceanside beaches will be
disturbed by construction and/or operation of the proposed sand bypass
system. Potential adverse impacts of the proposed system on the ecology of
Oceanside include: Lons of significant number of small aquatic organisms into
clearwater intakes; avoidance of project areas by fish populations; adverse
effects on benthic invertebrates at discharge points and downcoast; and,
disruption of grunion. Diesel -powered engines used for the system may
contribute to air pollution problems during periods of general reduced air
quality. With appropriate mitigation and monitoring of environmental effects
3
during operation, however, the sand bypass system should reduce adverse
environmental impacts below those caused by existing maintenance dredging.
APPLICABLE ENVIRONMENTAL STATUTES: This proposed project will be reviewed
under the following Federal legislation.
a. National Environmental Policy Act of 1969 (NEPA) as amended (42 USC
4321 et seg.). Environmental information on the project area has been
compiled and a revised draft environmental assessment has been prepared in
accordance with NEPA (PL 91-190) and US Army Corps of Engineers Policy and
Procedures for Implementing NEPA, ER 200-2-2, Section 6(d). Some components
of the previosuly selected Experimental Sand Bypass System for which a draft
environmental assessment was prepared and circulated for public review in
December 1982 have been modified. Since then, the design of the Experimental
Sand Bypass System has been revised to exclude the pump house and rehandling
basin at the South Jetty and include a booster station on the beach. In
addition, implementation of project features will be in stages. Due to the
exclusion of the rehandling area at the south jetty, the overall environmental
impacts for the revised plan are anticipated to be less damaging.
A biological monitoring program will assess the system's actual effects on the
marine environment during operation and provide both qualitative and
quantitative information. This information will be used to adjust the
operation of the system to minimize environmental impacts while still
achieving the system's engineering objectives.
Some aew environmental concerns of the experimental sand bypass system are
discussed below:
(1) The engines that will be used for the sand bypass system on the
mobile trailer unit will be diesel -powered, instead of electrically -powered.
Best available technology will be used since No (oxides of oxygen) emissions
will exceed 100 lb/day. An air quality analysis and analysis of hydrocarbons
will be made because No emissions also exceed 250 lb/day.
(2) The diesel engines on the mubile trailer unit will generate noise
approximately 100 decibels (dBA) at a distance of 1 meter. Noise will be
attenuated by existing sound barriers (e.g. the breakwaters) and/or absorption
structures. Ambient noise levels near the South Jetty are currently about
55-70 dBA. (Source: Noise measurements taken at Oceanside Harbor -South
Jetty, June 16, 1983, city of Oceanside.) A new element of the sand bypass
system is the installation of an electrically -powered booster station on the
beach adjacent to the existing substation. The booster station will consist
of an electric motor enclosed in a masonry house and will be designed to
minimize noise levels until they are similar to background noise levels.
Coordination of public planning and public briefings includes: Three meetings
(November 5, 1981, December 8, 1981, and January 13, 1982) held between
representatives of the Corps of Engineers, the city of Oceanside, a coastal
engineering working group and others; a public briefing (February 17, 1982);
and, a meeting between representatives of Federal and State agencies
(March 26, 1982). All these meetings were based on the previously selected
sand bypass system. Comments from these meetings were incorporated into plan
design.
b. National Historic Preservation Act of 1966, as amended (16 USC 470 et
sec.). No known cultural or archeological resources will be affected by the
proposed action.
c. Clean Air Act (42 USC 7401 et se ). The Corps of Engineers will
coordinate the air quality aspects of the project with the Environmental
Protection Agency (EPA) and the San Diego Regional Air Pollution Control
District. Comments and recommendations from these agencies and others
received during the public ,,;:rice period of the revised draft environmental
assessment will be carefully reviewed and incorporated into final design plans
for this project where applicable and practical. All stationary and mobile
sources of emissions required by the project will co:iply with State and
Federal emission control standards. Special permits, if required for the
diesel -powered engines, will be obtained from the San Diego Regional Air
Pollution Control District.
d. Clean Water Act (PL 92-500 as amended). No toxic materials are known
to occur in the sediment in the dredge area. Sediments in the project area
are substantially the same as those on the receiving beach. No toxic
substances which will adversely affect human health and welfare, or the
biological resources of the area, such as a Befouling agent for pipelines
which carry clear feedwater, will be introduced into the sand bypass system.
A revised draft 404 (b)(1) water quality evaluation has been submitted to the
California Regional Water Quality Control Board, San Diego Region.
e. Endangered Species Act of 1973 as amended (16 USC 1531 et seg.). Two
endangered species, the California least tern (Sterna antillarum (=albifrons)
browni), and the California brown pelican (Pelicanus occidentalis
californicus) are known to occur in the project area. Neither species will be
adversely affected by the proposed action.
f. ,Kish and Wildlife Coordination Act (16 USC 661 et seq.). An
accelerated project schedule has prevented full compliance with the responding
requirements of the Act; however, substantive compliance has occurred. The
U.S. Fish and Wildlife Service (FWS) has reviewed the November 1982 Draft
Environmental Assessment and has determined that no significant fish and
wildlife issues have been overlooked, The FWS considers the biological
monitoring program to be an essentirl and potentially significant component of
the overall sand bypass system, and recommends close evaluation of the chronic
degradation of the benthic community within the fluidizer bed and at the
dredge intake points (source: Letter of Comments, FWS, 1983). The monitoring
of the system's effects upon the benthic community at the dredge, as well as
at the three beach disposal sites, is an integral part of the biological
monitoring program. Funding will be provided to the U.S. Fish and Wildlife
Service to review and comment on the biological monitoring program.
DESCRIPTION OF DREDGE AND FILL MATERIALS: Material which will be removed by
dredging consists primarily of fine sand with about 5% medium sand and 10%
silts. Materials sampled within the harbor in 1980 and 1982 contained a
larger fraction of fines than material in the harbor entrance channel and the
north fillet area. A compatibility analysis conducted in September 1980 by
the Corps of Engineers determined that the dredged material and the receiving
beach were compatible at that time.
FEDERAL, STATE, AND LOCAL AGENCIES CONSULTED DURING DESIGN STAGE: The.
following agencies were contacted during project design: Environmental
Protection Agency; California Coastal Commission; U.S. Fish and Wildlife
Service; National Marine Fisheries Service; California Department of Fish and
Game; San Diego Regional Air Pollution Control District; San Diego Regional
Water Quality Control Board; U.S. Marine Corps Base Camp Pendleton; U.S. Coast
Guard; City of Oceanside; and City of Carlsbad.
A revised draft environmental assessment has been prepared and is available
for review at the Los Angeles District, US Army Corps of Engineers
(Environmental Planning Section, Room 6640, 300 North Los Angeles Street, Los
Angeles, California).
The revised draft environmental assessment has been distributed to Federal,
State, and other concerned agencies, groups, and individuals. Comments
received.during the public review process will be addressed in the final
environmental assessment.
SUPPLEMENTAL ASSESSMENT: Should significant additional information be
developed concerning the proposed activity or the affected environment, or
should the project be significantly modified, the effects of the activity will
be reevaluated and a supplemental assessment will be prepared.
CONCLUSIONS AND RECOMMENDATIONS: The environmental assessment concludes that
no major impacts upon known significant resources are anticipated. The
biological monitoring program is designed to (1) measure the effects of the
sand bypass system and (2) make operational recommendations, if needed and as
feasible, to lessen or avoid adverse effects should any unanticipated,
significant impacts occur.
PUBLIC HEARING: Any person who has an interest which may be affected by the
construction of the Experimental Sand Bypass System may request a public
hearing. The request including the Public Notice must be submitted in writing
to me on or before the Comment Deadline, and must clearly set forth the
interest and the manner in which it may be affected by this activity.
COMMENTS: Your written comments or objections (including this Public Notice)
must reach this office on or before the Comment Deadline.
6
FOR ADDITIONAL INFORMATION CONTACT: Mr. Donald G. Spencer (213) 688-5407 or
Mr. Claude Wong, (213) 688-65AO Coastal Resources Branch.
Paul W. Taylor
Colonel, Carps of Engineers
District Engineer.
a
w I
� w
z
z
J
w
Q:
W UJ
pet.
w
0
Lt:
W -�
n
li
0
C) J L-1
Q
�o
II nl con w
Nys
i'
o a. N
w o
cr w
= o -J
w
z
w
tal
0
t ,a
i
F
CC
/w
z
tV/'
cr
/•
J
�
w
<C
[]
O
m
w
ao
F- a
co
�z
— 0-
F-- 0
Z,
J
g
x
w 10101,9
en
0
z
X
w
WI
69 W
Q Z
vw
cn n.
o a.
W
x
BUJ
Z
0
U W
�,
—
6xx9
co
Lo W
Q
�
W
a
m m
cn
cc o
ui
z ®
_J
<i
_J
^�
U) z
C.�
J <
W
C!.
W co
z 0
l
LLJ
g
a
C
cc W
�z
w
2
X
= 0
w
J
w
z
e
W
d Q„
z E-
0 W
CJ C1s
La �
c
C.a
raw' 0'
1200 ELM AVENUE
CARLSBAD, CALIFORNIA 032008
Office of the Mayor
February 8, 1984
Department of the Army
Los Angeles District
Corps of Engineers
P.O.. Box 2711
Los Angeles, California 90053
Attention: Paul W. Taylor, Colonel C.E.
District Engineer
OCEANSIDE EXPERIMENTAL SAND BYPASS PROJECT
The City Council of the City of Carlsbad, at its February
7, 1984 meeting, unanimously supported the proposed sand
bypass project.
Carlsbad has watched the evolution of this project for a
number of years and is pleased that progress is being
made.
Carlsbad, like our neighbor, Oceanside, has suffered
significant loss of beach due to the disruption of the
natural southerly sand migration. The proposed project
appears to be a significant step in reestablishing the
natural sand flow. We urge prompt installation.
Very.truly yours,
MARY CASs R
Mayor
MC:pab
TELEPHONE:
(714) 438.5561