HomeMy WebLinkAbout1985-04-02; City Council; 8119; Carlsbad Safety and Service Center Update and Construction of FacilitiesCITY'IF CARLSBAD — AGENDA ILL
AB#_
MTG._
DEPT..
4/2/85
CM
TITLE:
CARLSBAD SAFETY AND SERVICE CENTER
UPDATE AND CONSTRUCTION OF FACILITIES
DEPT. HP. N3
CITY ATTV\/fcrj
CITY
RECOMMENDED ACTION:
City Council receive and approve the progress report of the
Carlsbad Safety and Service Center architect and construction
manager.
Adopt Resolution No. 'J^(e>^3 approving plans and specifi-
cations and authorizing City Clerk to advertise for bids on Bid
Packages 3, 4, 5, 6 and 7.
ITEM EXPLANATION;
Koll Construction Co. (Construction Manager) with Ruhnau, McGavin
& Ruhnau Associates will present a summary of progress to date on
the Carlsbad Safety and Service Center. Included in the presen-
tation will
Packages 3
construction
bids to be
budget with
estimate of
be the general overview of the components of Bid
thru 7 which will cover the majority of remaining
bids to be let on the project. The construction
let are believed to be within the constraints of the
variation from item to item based on the best
the Construction Manager.
FISCAL IMPACT
Funds to be used for these construction bids are funded in
Account Nos. 114-820-1810-3006, 330-820-1810-3006, and 332-820-
1810-3006. Additional funding will be required in 1985-86 as
part of the City's Capital Improvement Plan.
§I
O
1j
O
ENVIRONMENTAL IMPACT
EIR and CUP have been approved.
EXHIBITS
1 . Resolution No.approving plans and specifica-
tions and authorizing City Clerk to advertise for bids on Bid
Packages 3 thru 7.
2. Plans and Specifications, in office of record.
3. Koll Progress Report.
4. Summary of Bid Packages 3 thru 7.
Ou
RESOLUTION NO. 7963
1
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CARLSBAD, CALIFORNIA,
2 ACCEPTING THE PROGRESS REPORT OF KOLL CONSTRUCTION AND APPROVING THE
PLANS AND SPECIFICATIONS FOR THE CONSTRUCTION OF THE FACILITIES AT THE
3 CARLSBAD SAFETY AND SERVICE CENTER.
4 WHEREAS, the City of Carlsbad has been authorized by a vote of the people
5 to construct a $15.3 million dollar Safety and Service Center; and
6 WHEREAS, the City Council has approved funds in the Fiscal Year 84-85
7 budget for the construction of Phase I of this project; and
8 WHEREAS, the Construction Manager (Koll Construction Co.) along with the
9 Architect (Ruhnau, McGavin & Ruhnau Associates) have developed the plans,
10 specifications, and estimates;
11 NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of
12 Carlsbad, California, as follows:
13
1. That the above recitations are true and correct.
14
2. The plans, specifications, and estimates for the construction of the
15
facilities at the Carlsbad Safety and Service Center are approved.
16
3. The City Clerk is directed to make appropriate advertisement for such
17
work as is contained in Bid Packages 3 thru 7.
18
PASSED, APPROVED AND ADOPTED at a regular meeting of the Carlsbad City
19 I
Council held on the 2nd day of April » 1985 by the following vote, to
20
wit:
21
AYES: Council Members Casler, Lewis, Kulchin, Chick and Pettine
22
NOES: None
23
ABSENT: None
24
25 ATTEST- MARY H< CA^LER» MaV°r
\ityUL> 0\ • v\ a26.. .
ALETHA L. RAUTENKRANZ, City Clerk!
(SEAL)
28"
PROJECT MANUAL
s
UBLIC SAFETY
D
C
PROGRESS REPORT NO. 5
3-19-85
ROLL CONSTRUCTION COMPANY CARLSBAD SAFETY CENTER
Progress Report Number 5 March 19, 1985
TABLE OF CONTENTS
Section Title
I Design Progress and Review (Preconstruction Phase)
II Purchasing
III Construction Costs and Value Engineering
IV Payments
V Job Progress (Construction Phase)
VI Schedule
VII Quality Control
VIII Safety
IX Miscellaneous
X Progress Photos
KOLL CONSTRUCTION COMPANY CARI5BAD SAFETY CENTER
Progress Report Number 5 March 19, 1985
DESIGN PROGRESS AND REVIEW
SITEWORK
Since our last progress report the major items which were coordinated in
preparation for the first bid package were as follows:
a. Designing full width improvements and final elevations for Impala Drive.
A minimum of three (3) feet of cover was required by SDG&E over their
existing high pressure gas main, as Impala Drive was extended for the
Northern Project Access. If this was not accomplished, the gas main
would have had to be relocated by SDG&E, with substantial cost impact
and time delays to the project.
b. Design of an underground and surface storm drain system from the project
entrance at Faraday Avenue to the eastern boundary of the project.
c. Resolution to install decorative streetlighting for the project, in lieu of
the City's standard light fixture.
The actual bids for the sitework package, including the above items, were within
the project budget as outlined in the Purchasing section of this report.
Negotiations with the serving utilities (SDG&E and Pacific Bell) have been
completed, and we are expecting contract packages and approved construction
documents within a few weeks.
The landscape and irrigation plans are being completed by the City's Parks and
Recreation Department with the assistance of outside consulting firms. A drip
irrigation system for the site trees is being reviewed as a lower maintenance
alternative. Plant types and lighting requirements for the police building atrium
area are also being researched. Your construction manager is investigating whether
an availability problem exists with respect to proposed plants and trees. Provisions
were made within the various site utility contracts to install necessary street
sleeves for future irrigation distribution and metering/power requirements for
controllers.
The City Engineering Department is completing the remaining C.U.P. requirements
as follows:
a. Verification that sewer facilities are available.
b. Industrial waste discharge permit.
c. Written consent to annex site within lighting and landscape District No. 1.
d. Future coordination of signage and striping.
POLICE/FIRE ADMINISTRATION BUILDING
Contract documents were submitted for initial plan check on February 4, 1985.
After a seventeen (17) working day review, the plans were returned for necessary
corrections. The City Plan Check Department should be commended for completing
the initial review in an expedient manner.
ROLL CONSTRUCTION COMPANY CARISBAD SAFETY CENTER
Progress Report Number 5 March 19, 1985
Your Construction Manager has been reviewing the plans and specifications and
responding to the Architect with questions and comments. Construction methods
and finishes which are not consistent with the original estimate are also
documented. We are currently analyzing costs associated with some of the more
expensive items within the project, to determine whether the original budgets may
allow the introduction of some of these desirable, yet costly, finishes and
construction techniques. Some important detailing and coordination still needs to be
completed in order to pull the entire final project estimate together. This process
is being completed now that initial plan cheeking is complete and the consultant
team is coordinating the documents.
During one of our bi-weekly project team meetings, we discussed the necessity of a
"Halon" fire supression system within the dispatch area. Halon is a chemical which
removes the fire supporting oxygen from the air, thus extingushing any fire. The
chemical system is very expensive to install, and is generally used in areas which
contain computers and related equipment which would be severly damaged by water.
The project team considered the fact that the dispatch area would be in operation
around the clock every day of the year. A cost savings alternative was the
utilization of sensitive heat and smoke detectors, and Halon extinguishers if a fire
should occur. Both the Police and Fire Departments agreed that a fully automated
Halon system would not be necessary. This will save approximately $20,000.00,
which was included in the design/development estimate.
There has been some concern whether all the required electrical design information
for the communications system has been resolved since the Richter Group was on
temporary suspension. However, the electrical consultant has proceeded in some
areas and has been advised that this problem is resolved and they should be
contacting and incorporating any necessary additional requirements.
-2-
KOLL CONSTRUCTION COMPANY
Progress Report Number 5
CARLSBAD SAFETY CENTER
March 19, 1985
PURCHASING
SITEWORK
Approval to bid Sitework Grading and Improvements (Bid Package #1), was made by
the City Council on January 21. Notice to Bidders were mailed by your Purchasing
Department on January 23, 1985 to contractors recommended by your Construction
Manager. Calls were made to these potential bidders to stimulate interest and
confidence in the project. A prebid conference was held on February 14, with bids
received on February 26, 1985. The following is a summary of costs with respect
to the bid estimate and authorization to bid. Your construction manager's comments
and recommendations for award of sitework contracts has been prepared as a
separate agenda bill for the Council meeting of March 19, 1985.
SUMMARY OF COSTS
1A Grading
IB Concrete (no bids received/
preliminary estimate used)
1C Gunite
ID Sewer, Water, Storm Drain
IE Electrical, Telephone, Gas,
C.A.T.V.
IF Asphalt
Subtotal
Unit Price Purchase Orders
Soil Testing and Inspection
Engineering and Survey
Sitework Cost
Sitework Bid Estimate
(January 16 1985)
Variance (Decrease)
$ 268,950.00
154,316.00
19,647.00
394,707.00
136,292.00
273.067.00
$ 1,246,979.00
23,300.00
48.000.00
$ 1,318,279.00
$ 1,395,751.00
($ 77,472.00)
As indicated in the Summary, the current construction costs are under the estimated
budget. It should be pointed out that certain assumptions with respect to rock
excavation quantities, and asphalt/base paving thicknesses were included within the
bid documents. Until the project grading is underway, and designed elevations are
constructed, final rock quantities and/or asphalt sections cannot be determined.
Within the framework of the sitework proposals, your construction manager included
certain allowances for these unknown conditions, and received fixed unit prices as a
basis for adjusting the final quantities. The potential exists for credits and/or
additional costs to the sitework contracts as work is completed. Utilizing the
services of the Survey and Soils Engineers, and monitoring equipment load counts,
your construction manager will determine the need for unit price adjustments and
disposition of the rock excavation allowances.
-3-7
ROLL CONSTRUCTION COMPANY CARLSBAD SAFETY CENTER
Progress Report Number 5 March 19, 1985
A preconstruction meeting is scheduled for 11:00 AM on March 20, 1985 at the
project site. Your construction manager, Council approved contractors, surveying
and soils engineers, City representatives, and other governing agencies will be in
attendance to disucss the project construction. In addition, contract, bond and
insurance requirements, scheduling, and payment procedures will be defined.
POLICE/FIRE ADMINISTRATION AND VEHICLE MAINTENANCE BUILDINGS
Approval to bid Structural Steel and Metal Deck (Bid Package #2) was made by the
City Council on February 19, 1985. Notice to Bidders were mailed by your
purchasing department on February 21, 1985 to contractors recommended by your
Construction Manager. Contacts are being made with these potential bidders to
stimulate interest in the project. A prebid conference was held on March 13 to
answer questions end address problems and concerns of the bidders.
Since structural steel is such a long lead item, prebidding allows a more economical
mill order to be placed, and to receive steel in the appropriate construction
sequence. We have issued a major addendum which clarifies requirements for
Seismic Zone No. 4 as a result of the required plan check/building permit review
process. Based on the time frame to issue the first addendum, and potential
clarifications after the pre-bid conference, the bid date may be extended. We still
need to meet a council contract approval date of April 2, 1985, in order to place a
mill order by April 10th, allowing the contractor sufficient engineering, approval
and fabrication time to meet our scheduled start of erection of August 1, 1985.
Based on current projections, we are expecting the plan corrections, coordination
and permit process to be complete by April 8, 1985, so that the remaining bid
packages may be issued with approved plans. A list of proposed bid packages, and
a bidding and award schedule is included within this report. On March 19, 1985,
the City Council is being asked to approve the proposed plans and specifications,
and authorize the construction manager to proceed with bidding the remaining
packages based on the attached schedule. In addition to outlining the bidding
sequence, the schedule indicates the dates the City Council would be requested to
approve contract awards.
The bid packages have been developed based on construction scheduling
requirements, and organization of trades which tend to complement each other.
Packages No. 3 and 4 involve substantial underground work which must be
completed so that the onsite asphalt may be installed in a timely manner, and
foundations will be completed for structural steel erection. Some long lead items
such as finish hardware, and steel doors and frames are also included in the early
bid packages.
The next series of packages, Numbers 5, 6, and 7, complete the exterior cladding of
the buildings, and develop the interior framework, finishes, fixtures and
miscellaneous specialities. The intent of developing a series of packages allows us
to better coordinate the work as it relates to scheduling, and also resolve and
clarify possible problems which may effect future bid parameters before all prices
are committed. The packages have also been arranged such that the trades are to
some extent interrelated. The various bidders may see an advantage of bidding
-4-
ROLL CONSTRUCTION COMPANY CARU5BAD SAFETY CENTER
Progress Report Number 5 March 1*, 1985
combinations of work that hopefully offer cost savings for the project. Solicitation
of bidders is enhanced when bid requests are grouped into relatively small packages
allowing your construction manager additional time to attract interest in the project
and address questions.
-5-
CARLSBAD SAFETY CENTER
BIDDING SCHEDULE
Bid Description Council
Package of Approval
Number Work To Bid
Mail Notice
to Documents Prebid.
Bidders Available Conf.Bid Due
Council
Contact
Award
1 Sitework
2 Structural Steel
Metal Deck
3 See Attached
4 See Attached
5 See Attached
6 See Attached
7 See Attached
01-22-85 01-23-85 01-28-85 02-14-85 02-26-85 03-19-85
02-18-85 02-20-85 02-21-85 03-13-85 03-21-85 04-02-85
04-08-85 04-23-85 05-02-85 05-14-85
04-22-85 05-16-85 05-27-85 05-27-85
05-06-85 05-21-85 05-30-85 06-11-85
05-20-85 06-04-85 06-13-85 06-25-85
06-03-85 06-18-85 06-27-85 07-09-85
03-iS-85
tf.03-J«-85
03-18-85
03-1^-85
OS-lt-85
04-04-85
04-18-85
05-02-85
05-16-85
05-30-85
-5a-
ROLL CONSTRUCTION COMPANY CARLSBAD SAFETY CENTER
Progress Report Number 5 March 19, 1985
PROJECT BID PACKAGES
BID PACKAGE #2
a. Structural Steel
b. Metal Deck
BID PACKAGE #3
a. Elevators
b. Plumbing
c. Fire Sprinklers
d. H.V.A.C.
e. Electrical
f. Service Station Equipment and Vehicle Wash
g. Finish Hardware and Gate Operators
BID PACKAGE #4
a. Concrete
b. Reinforcing Steel
c. Architectural Pre-Cast
d. Masonry
e. Miscellaneous Iron
f. Landscape and Irrigation
g. Steel Doors and Frames
BID PACKAGE #5
a. Rough and Finish Carpentry
b. Wood, Doors and Cabinets
c. Lath, Plaster and Drywall
d. Roofing, Waterproofing and Insulation
e. Flashing, Sheet Metal, Roof Accessories and Louvers
f. Canopy and Sunscreens
g. Building Insulation
H. Recessed Floor Mats
BID PACKAGE #6
a. Aluminum Entrances and Storefronts, Aluminum Windows and Glazing
b. Coiling Doors and Grills, and Sectional Doors
c. Pneumatic Tube System
d. Acoustical and Metal Ceilings
e. Ceramic Tile and Brick Pavers
f. Painting, Waterproofing, Vinyl Wallcoverings and Fabric Panels
g. Flagpoles
BID PACKAGE #7
a. Computer Access Flooring
b. Resilient Flooring and Carpet
-6-
KOLL CONSTRUCTION COMPANY CARUSBAD SAFETY CENTER
Progress Report Number 5 March 19, 1985
c. Toilet Partitions and Accessories
d. Folding Partitions
e. Metal Lockers
f. Mesh Partitions
g. Miscellaneous Specialties—Fire Extinguishers and Cabinets, Projection
Screen, Vacuum System, etc.
-7-
ROLL CONSTRUCTION COMPANY CARUSBAD SAFETY CENTER
Progress Report Number 5 March 19, 1985
CONSTRUCTION COSTS AND VALUE ENGINEERING
The sitework cost is under the original budgets prepared by Koll Construction
Company. Conversations with the low bidder of record for the underground
utilities, Item ID, indicate there may be a potential for additional value engineering
cost savings, with respect to the storm drain system. This matter will need to be
researched with the city engineer once the contract awards are approved by the
City Council.
We have directed the architect to change the construction of the vehicle wash from
concrete tilt-up to masonry. The design of this facility utilizing concrete tilt-up
does not lend itself to economical or time saving construction. We have always felt
and previously recommended that masonry was the best design parameter for this
facility—both cost and scheduling wise. Masonry is also being used for the
mechanical equipment enclosure adjacent to the Police/Fire building. A decorative
block will add a nice contrast to the other facilities, and is a more traditional
construction method for these type of enclosures.
The elimination of an automatic Halon fire supression system will generate
additional budget funds towards offsetting potential cost problems. Your
construction manager believes that the project budget will allow completion of the
new facilities utilizing quality construction techniques and finishes. In an effort to
accomplish these goals, we will be developing a series of alternates within certain
bid packages so that areas of cost compromise may be available at time of bid.
Some of the major structural trades such as concrete and steel may be a little
more difficult to modify since their designs are based on fixed criterias, i.e.,
building code, soil conditions, project location, etc.
We realize that the primary goal is to construct functional, durable, yet cost
conscious facilities. We do not feel that the entire approved budget should be
spent just because these funds have been approved.
-8-
ROLL CONSTRUCTION COMPANY CARLSBAD SAFETY CENTER
Progress Report Number 5 March 19, 1985
PAYMENTS
The following payments have been approved:
Professional Services
a. Ruhnau McGavin Ruhnau/Associates -
Complete Contract Through Design Development $ 119,870.00
80% of Construction Document Phase
eluding approved changes 237.377.00
Total to Date $ 357,247.00
b. GeoCon, Incorporated -
Completion of Geotechnical Report, dated
September 12, 1984 $ 4,398.00
Additional Consultation Services for Bidding
Clarifications 450.00
Total to Date $ 4,848.00
c. Koll Construction Company -
Schematic Design $ 30,000.00
Design Development 30,000.00
Construction Documents 36,000.00
Bidding 4.000.00
Total to Date $ 100,000.00
Construction Services
None
-9- /if
KOLL CONSTRUCTION COMPANY CARLSBAD SAFETY CENTER
Progress Report Number 5 March 19, 1985
JOB PROGRESS
A ceremonial ground breaking was held on February 27, 1985, with actual
construction anticipated to start on March 25, 1985.
-10-
ROLL CONSTRUCTION COMPANY CARLSBAD SAFETY CENTER
Progress Report Number 5 March 19, 1985
SCHEDULE
We have currently lost approximately four (4) weeks in starting the grading
operation for the project. This is primarily due to two (2) weeks lost during the
holiday season, and two (2) weeks in March preparing sitework contract
recommendations and scheduling City Council approval. This time delay may not be
as critical as indicated on the originally projected schedule dated August 15, 1984.
Now that sitework plans have been completed and bid, we have a more realistic
idea of construction time frames. As long as major rock problems are not
encountered during the grading operation, we should be able to have building pads
ready for construction per the original schedule. The scheduling of the next series
of bid packages which commences April 8, 1985 is critical to maintaining the
project continuity. The plan corrections, coordination and permits must be complete
by this date. We feel the bidding and award schedules will compliment our original
projections. It's also important to know that the City staff and Council will
acknowledge and complete the necessary action and approvals per this schedule.
(See Purchasing Section of this report and Manual schedule section.)
Included within the next report will be a new construction schedule for the
sitework grading and improvements. Some of the onsite concrete and asphalt work
will not be totally resolved, since some of the next bid packages greatly affect
that scheduling. Once the majority of bid packages have been awarded, a new
detailed schedule will be developed. Until this time, smaller realistic schedules and
job progress will be included within these reports.
-11-
KOLL CONSTRUCTION COMPANY CARLSBAD SAFETY CENTER
Progress Report Number 5 March 19, 1985
QUALITY CONTROL
We are currently reviewing proposals for professional testing and inspections
services. We plan on meeting with these firms, visiting actual facilities, and
recommending to the City the firm which will best fulfill the needs of the project,
both economically and professionally. The scope of work involves concrete,
masonry, steel, welding, roofing and waterproofing testing; sampling; and inspecting
for compliance with building codes and the contract documents.
-12- / 7
ROLL CONSTRUCTION COMPANY
Progress Report Number 5
CARLSBAD SAFETY CENTER
March 19, 1985
SAFETY
Nothing to report.
-13-
KOLL CONSTRUCTION COMPANY CARLSBAD SAFETY CENTER
Progress Report Number 5 March 19, 1985
MISCELLANEOUS
Nothing to report.
-14-n
ROLL CONSTRUCTION COMPANY CARLSBAD SAFETY CENTER
Progress Report Number 5 March 19, 1985
PROGRESS PHOTOS
Nothing to report.
-15-
r:& i r
i
01
Iff <u
!*!NX
(A
c*
^S
HA!
$ IjfiS
*t Iff
1
3
I
i
-o3>
O
rnO
f^
!
DO
O
*o
>1
(0
>13D oog
(/) z
S5m -T3
o|c. C <
m
TJ D3J >m -t
J ™
m a
-*
(O«n