Loading...
HomeMy WebLinkAbout1985-08-27; City Council; 8119-13; Change Order No 2 Central Business Storm Drain Project No. 3085AB# p//9-+/3 MTG. 8/27/85 I DEPT. ENG CITY Am%& CHANGE ORDER NO. 2 TITLE: CENTRAL BUSINESS STORM DRAIN PROJECT NO. 3085 ICITYMGR. a*" RECOMMENDED ACTION: Adopt Resolution No. f& I amending Contract No. 3085 - the Central Business Storm Drain - by approving Change Order No. 2, approving Supplement No. 2 to the Agreement with Fraser d( Associates and appropriating additional funds in the mount of $307,606.00. ITEM EXPLANATION: Council approved the construction of the Central Business Storm Drain and appropriated $800,000.00 in the 1984-85 Capital Improvement Program. On August 7, 1984, Council awarded the contract for construction to the low bidder, Peter C. David Co. for $693,480.20. During construction, many situations occurred here existing utilities shown on the plans were not in the locations indicated by existing records. In some instances there were no records of the underground utilities and they were a complete surprise when encountered. Council may be aware that State Street was once a state highway (hence the name). The numerous underground utilities and poor accuracy of records are not unusual circumstances in older urban areas such as this. Unfortunately, on this project nearly every inaccuracy resulted in another conflict with the storm drain due to the very tight circumstances. The work involved in Change Order No. 2 primarily due to utility conflicts encountered due to utilities being at different locations than shown on records includes: A. B. C. D. E. F. G. H. Field revisions of the pipeline alignment. Reconstruction of an additional 80-feet of sewer line. Reconstruct portion of 15 inch storm drain. Reconstruction of sewer force main. Construct air relief valve on force main. Adjustment of alley grade to resolve drainage problem. Relocation of 8-inch sewer in State Street. Install temporary sewer by-pass in State Street. A complete list of the required changes and reasons is contained in Change Order No. 2 attached as Exhibit 02", In addition to the specific items of additional work identified, the con- tractor is claiming that the changes in State Street constitute a "change in the character of the work". As a result, the contractor states that his construction time will be three weeks longer than anticipated and is claiming an extra for all equipment and labor for this extra time. This mounts to $123,000.00 and has been listed separately in Change Order No. 2 as Part B. Page No. 2 of Agenda Bill No. .- . Because of the extension of time of the contract and the extremely difficult negotiations with the contractor, Fraser & Associates - who are performing the contract management, redesign and inspection services for the City - is requesting an increase in their contract limit. Their fee will continue to be on an hourly basis and they are requesting a second supplement to their agreement not to exceed an additional $1 8,000.00. The contractor, after a long absence, has resumed work and is currently installing the storm drain in State Street. Work has started at the hena Vista Lagoon and is moving south. The contractor has been urged by staff and Fraser and Associates to submit a construction schedule and a completion date, but has yet to do so. Staff is withholding further progress payments to the contractor until the schedule is received. FISCAL.IMPACT: Funds in the amount of $800,000.00 have been appropriated and are available in Account No. 881-820-3410-3085. Total actual and estimated expenses for this project are as follows: Contractor (original contract and Change Order NO. 1) $ 713,795.20 Change Order No. 2 $ 282,706.30 Fraser (Agreement and Supplement No. 1) $ 60,000.00 Supplement No. 2 $ 18,000.00 Design and Miscellaneous expenses (FY 83-84 & FY 84-85) $ 17,104.50 Staff time (FY 84-85 & FY 85-86) $ 16,000.00 TOTAL PROJECT COST: Budgeted Amount $1,107,606.00 -$ 800,000.00 ADDITIONAL FUNDS REQUIRED: $ 307,606.00 The addition of $307,606.00 to this project constitutes a loan to the Redevelopment Agency from the General Capital Construct ion fund. If Council approves Change Order No. 2 and Supplement No. 2, an additional appropriation is required from the General Capital Fund No. to the project Account No. 881-820-3410-3085. Because this project will be paid for the the Redevelopment Agency and not the City, it is exempt from Proposition H requirements. EXHIBITS: 1. Location Map. 2. Change Order No. 2. 3. Supplement No. 2 to Agreement dated March 5, 1985. 4. Resolution No. 81 b 1 amending Contract No. 3085 - the Central Business Storm Drain - by approving Change Order No. 2, approving Supplement No. 2 to the Agreement with- Fraser & Associates and appropriating additional funds in the mount of $307,606.00. .. ! LOCATION MAP %' .\ I. *. .. CITY OF CARLSBAD PUBLIC WORKS PROJECT CHANGE ORDER CHANGE ORDER NO: 2, Part A DATE: August 15, 1985 CONTRACT NO: 3085 PURCHASE ORDER NO: 12601 BUDGET NO: 30-1 8-30-3085 CONTRACTOR'S NAME: Peter C. David Co. PROJECT NAME AND NO: Central Business Storm Drain - No. 3085 REASON/PURPOSE FOR CHANGE: a. b. C. d. e. f. The utilities encountered in Grand Avenue are in locations different than that shown on the contract plans. These differences necessitated field revisions in the pipeline alignment which in turn required the construction of sixteen concrete collars southerly of Grand Avenue. The existing 8-inch diameter force main crossing at station 10+20 is different from that depicted on the contract plans. This resulted in the reconstruction of approximately 120 feet of 8-inch PVC pipe in lieu of 40 feet as would normally be anticipated. The utilities encountered in Grand Avenue are in locations different from that shown on the contract plans. These differences necessitated field revisions in the pipeline alignment which in turn required the construction of five concrete collars northerly of Grand Avenue. The contract plans required the abandonment of an existing 15-inch diameter storm drain. Had this been accomplished, the existing catch basins at the intersection of State Street and Grand Avenue would have had no outlet. The contract documents stipulate that a Type B Cleanout be constructed at station 20+00. However, the 66-inch diameter RCP is too shallow to allow the construction of that type of structure. An 8linch diameter sewer force main crosses the storm drain alignment near station 22+75. The force main is depicted in the plan view but it is not identified in the profile view. A physical conflict existed between the sewer force main and the storm drain pipe requiring the reconstruction of the sewer force main. *. ”-- Change Order No. 2, Part A August 15, 1985 Page two .. q. h. i, j. k. 1. m. n. 0. P. 9. An existing buried telephone conduit, a water line and an existing 8-inch diameter sewer within State Street are located in the field differently than that depicted on the contract plans. The City Maintenance and Utility Department has requested that an air relief valve be installed on the 8-inch sewer force main upstream of the reconstruction described in item f herein above. This has been the cause for several major revisions, The contract drawings stipulate a finished grade for the alley which would not properly serve the adjacent property owners. The stipulated alley grade would also have impeded the exist- ing drainage from adjacent parcels. The contract documents do not include any provisions for ultimate disposal of the storm water tributary to the improved alley or adjacent properties. The contract documents, utility improvement drawings and utility field markings denoted several of the utilities in State Street incorrectly, The accurate field location of these facilities is necessary prior to the construction of the storm d’rain in the immediate vicinity. The trench backfill in the deeper portions of the project are greater than can be safely sustained by the pipe specified, An existing 30-inch diameter lateral was encountered conveying storm water to an existing catch basin in Elm Avenue. This lateral required reconstruction and reconnection to the new catch basin, A local depression exists in the alley between Grand Avenue and Cedar Avenue. This depression was previously served by a catch basin which was removed during the construction of this project. A new inlet structure is required to serve this local depression, During a meeting, February 6, 1985, the City Engineer requested that the existing 8-inch sewer in State Street be excavated and located. A house lateral interferred with the location of the 66-inch RCP and had to be remodeled. An existing house lateral interferred with the location of the 66-inch RCP and had to be remodeled. 5- -. z Change Order No. , Part A I. August 15, 1985 Page three r. The plans and specifications did not include provisions for the adequate protection of a 36-inch vcp trunk sewer in Grand Avenue. The weight of the storm drain pipes cannot be sustained by the 36-inch vcp. s. The resiting of the junction structure in Grand Avenue necessitated resurveying of the area and also additional concrete curb and gutter work. DESCRIPTION OF CHANGE: a. b. C. d. e. f. 9. Construct sixteen concrete collars around 48-inch diameter RCP along curvilinear alignment between approximate stations 26+00 and 27+15, all in accordance with Change Order Proposal Number 2. Reconstruct 120 feet of 8-inch PVC pipe with two 45 degree elbows and thrust blocks all in accordance with Change Order Proposal Number 3. Construct five concrete collars around 66-inch diameter RCP along curvilinear alignment between approximate stations 25+46 and 25+81 all in accordance with Change Order Proposal Number 7. Provide outlet connection for existing 15-inch RCP along southerly side of Grand Avenue by constructing 8 feet of 15- inch RCP and lug connection to 66-inch RCP at station 26+55 in accordance with Change Order Proposal Number 10. Construct Type A Cleanout with flat slab top in accordance with S.D.R.S Drawing No. D-9 at station 20+OO in lieu of cone type access shaft. Reference Change Order Proposal Number 15. Construct temporary force main sewer by-pass and reconstruct interfering portion of existing 8-inch diameter ACP force main in accordance with Sketch C.O. 3085-4. Reference Change Order Proposal Number 4 dated April 4, 1985. Construct 66-inch RCP in State Street and right-of-way between State Street and alley westerly of State Street in accordance with Change Order Proposal 13 and accompanying sketches 13B and 13C all dated May 21, 1985. Alignment of 66-inch RCP is revised as follows: 1. In order to avoid physical conflict with existing 48- inch storm drain, the horizontal curve with EC at approximately 1+95 shall be located northwesterly so as r” f. Change Order No. 2, Part A August 15, 1985 Page four to provide approximately 5 feet of clearance between the two storm drains. Alignment in State Street shall be approximately 27 feet easterly of west curb in lieu of 22 feet as shown on the contract plans. shall be located two pipe lengths (16 feet) southerly of that shown on ’the contract plans. 2. 3. Alignment between approximate stations 8+00 and 9+20 This work and costs thereof are as follows: 1. Relocate 66-inch RCP storage area $ 2,400.00 2. Temporary sewer by-pass 31 ,400.00 3. Reconstruct 8-inch VCP sewer 32,800.00 Total Amount $ 66,600.00 Contractors responsibility includes the following: 1. Relocate stock piling of 66-inch RCP as requested by representative of Carlsbad Police Department. 2. Installation, operation, maintenance and removal of approved sewer by-pass. Facility to include duty pump, stand-by pump, emergency stand-by generator and all labor and equipment required. 3. Reconstruction of existing 8-inch diameter sanitary sewer , City’s responsibility includes the following: 1, Existing 24-inch diameter storm drain, location unknown. 2. Concrete curb and gutter along easterly side of State Street. 3, Cost of electric energy required to operate sewer by- pass pumps. 4. Increased amounts included herein are additive to the amounts included in the bid proposal. 7 a. - .. Change Order No. -, Part A August 15, 1985 Page five h. Construct sewage air relief structure with air relief valve all in accordance with Sketch CO 3085-12 dated 5-1-85 attached hereto . i. Construct alley grade, cross-section and drive entrances in accordance with Sketch F.0.-2 dated May 10, 1985 in lieu of profile identified on contract plans. Payment thereof shall be in accordance with Bid Proposal and contract documents. j. Construct one Catch Basin Type,l, one Catch Basin Type F and 24-inch RCP at low point in alley, Station 16+85 in accordance with Sketch PCO 16-B dated June 18, 1985 attached hereto. Relocate existing ditch outside of proposed fence and pavement area in accordance with Sketch PCO 16-A dated June 18, 1985 attached hereto, k. Provide equipment and labor to excavate the existing utilities in State Street at five specified lcoations. Work is to be performed and compensated for in accordance with Subsection 3- 3.2 of the Standard Specifications (Time and Materials). 1. Where the depth of pipe, as shown on the construction grade sheets, exceeds 15 feet provide crushed rock bedding. Rock pipe bedding shall be in accordance with SDRSD S 5.1. Payment shall be based upon certified weigh bills and include materials, delivery, taxes and all labor and materials necessary for the placement thereof. The agreed unit price is $21.00 per ton. The estimated quantity of rock required is 600 tons. Total estimated price is $12,600.00. m. Reconnect existing 30-inch diameter lateral to new catch basin in Elm Avenue and repair damaged drive entrance adjacent thereto. n. Construct inlet structure Type 1 per drawing D-29.1 on the existing 66-inch RCP at the local depression near Station 24+00, 0. Excavate and locate 8-inch sanitary sewer in State Street southerly of Laguna Drive. Excavation shall be located near the suspected point of interference with proposed 66-inch RCP strom drain as directed by City staff. p. Reconstruct 4-inch diameter house lateral at Station 28+60 so as to permit construction of 66-inch RCP. Change Order No. 2, Part A August 15, 1985 Page six -. q. Reconstruct 4-inch diameter house later at Station 10+35 so as to permit construction of the two 48-inch RCPs. r, Construct- concrete supports under the storm drain pipes, as directed in the field, in manner that no load is added to the existing 36-inch vcp. esu ve &anif AJenue an8 also southerly of Grand Avenue. curb and gutter on northerly side of Grand Avenue at junction of alley. the pi e alignment northerly of Grand Avenue, in Also replace INCREASE IN CONTRACT PRICE INCREASE IN CONTRACT TIME a, b. d. e. f. 9. h. i. C. j. k. 1. m. n. P. 9- r. 0. S. Part A Totals $ 8,000.00 5,675 -60 4,000.00 1,511 .60 206.84 23,193 -92 66,600.00 2,700.00 no change 8,634.00 4,062.91 863.19 2,700.00 1,898.71 1,330.00 2,660 .OO 10,345 .OO 2,724.53 $159,706.30 12,600.00 (estimated) 6 days 2 days 2 days 2 days 2 days 6 days 10 days 3 days no change 5 days 2 days 5 days 1 day 2 days 2 days 1 day 1 day 1 day 2 days 55 days 4 CITY OF CARLSBAD PUBLIC WORKS PROJECT CHANGE ORDER CHANGE ORDER NO: 2, Part B DATE: August 15, 1985 CONTRACT NO: 3085 PURCHASE ORDER NO: 12601 BUDGET NO: 30-18-30-3085 CONTRACTOR'S NAME: Peter C. David Co. PROJECT NAME AND NO: Central Business Storm Drain - No. 3085 REASON/PURPOSE FOR CHANGE: An existing buried telephone conduit, a water line and an existing . 8-inch diameter sewer within State Street are located in the field differently than that depicted on the contract plans. This has been the cause for several major revisions. This is a companion to item g of Part A, but is being presented separately for clarity. ENGINEER'S RECITAL: a. b. C. d. e. In the process of comple-ing the storm drain projec , 23 instances of what the Contractor contends are changed conditions have been encountered to date. The reach of construction between the downstream outlet and upstream thereof to Station 10+16 include the deepest construction and the greatest utility interferences. This reach is the most difficult and should be the slowest to construct. The Contractor requested that because of these alleged changed conditions, this work should proceed in accordance with Section 303 EXTRA WORK of the contract. This section is commonly referred to as Time and Materials. The Engineer has agreed that this method of proceeding is equitable providing the City could be assured of a maximum authorized amount. A review of the Contractors payroll records as well as known equipment rental rates indicate that the Contractors costs for each working day are approximately $8,400.00. -- Change Order 2, P;ut B - August 15, 1985 . -’ Page two --.. f. It is estimated that these conditions will require approximately 15 working days in excess of the time to construct this reach of the project, had the conditions been as represented by the contract drawings. ADDITIONAL WORK: 1. 2, 3. 4. 5, 6. 7. Remove and replace existing asphalt berm. Resurvey of pipline and furnish revised cut sheets. Added support of existing 48-inch diameter RCP storm drain. Added support of existing 8-inch diameter ACP water main. Additional excavation, haul away, back-haul and compaction of trench backfill by virtue of previous 48-inch storm drain trench as well as existing 8-inch VCP sewer pipeline trench. Breaking, removal and disposal of existing concrete pavement that is not identified in the contract documents. The additional risk of constructing facilities that already include 23 instances that are the proper subject of a change order . PART B SUMMARY: PART A PART B TOTAL I~CBEASE-I~-68~TRA~T-PBIGE IW€REASE-IW-€Q~TRA€T-TTWE $123,000.00 15 days INCREASE IN CONTRACT PRICE INCREASE IN CONTRACT TIME $1 59,706.30 123,000 .OO 55 days 15 days $282,706.30 70 days .e Change Order 2, PF-t B Page three ' August 15, 1985 .. RECOMMENDED: .-- FRASER & ASSOCIATES APPROVAL : CONTRACTOR: Peter C. David co . By: City Project Manager DATE : DATE : City Engineer DATE : la .. SUPPLEMENT NO. 2 TO AGREEMENT FOR CONTRACT ADMINISTRATION AND INSPECTION SERVICES FOR THE CENTRAL BUSINESS STORM DRAIN DATED MARCH 5, 1985 THIS SUPPLEMENT NO. 2 to the above,described agreement, hereunder referred to as "Orginal Agreement", entered into as of the 3rd day of June, 1985, by and between CITY OF CARLSBAD, a municipal corporation, hereinafter referred to as "City" and FRASER & ASSOCIATES, hereinafter referred to as ttConsultant". City and Consultant mutually agree to supplement the above referenced agreement as follows: 1. PROGRESS AND COMPLETION The work under this contract shall continue as required until completion of the construction of the Central Business Storm Drain Project by about October 31, 1985. Extensions of time may be granted if requested by Consultant and agreed to in writing by the City Engineer. 2. FEES TO BE PAID TO CONSULTANT The total amount of fees to be paid to Consultant under the Original Agreement dated March 5, 1985 Supplement No. 1 and this Supplement No. 2 shall not exceed the sum of $78,000.00 3. PAYMENT OF FEES Payment of fees shall be on a monthly basis. Those fees shall be based on the hourly rates and direct costs contained in Section 5 of the Original Agreement. 4. EFFECTIVE DATE This Supplement No. 2 shall be effective on and from the day and year first above written. IN WITNESS WHEREOF, we have hereunto set our hands and seals. FRASER & ASSOCIATES CITY OF CARLSBAD By : MARY H. CASLER, Mayor TITLE: President APPROVED AS TO FORM: Ass i st an t City At t o rn e y ATTESTED : ALETHA L. RAUTEN"Z City Clerk SUPPLEMENT NO. 2 TO AGREEMENT FOR CONTRACT ADMINISTRATION AND INSPECTION SERVICES FOR THE CENTRAL BUSINESS STORM DRAIN DATED MARCH 5, 1985 THIS SUPPLEMENT NO. 2 to the above described agreement, hereunder referred to as "Original Agreement"; entered into as of the 3rd day of June, 1985, by and between CITY OF CARLSBAD, a municipal corporation, hereinafter referred to as "City" and FRASER & ASSOCIATES, hereinafter referred to as "'Consultant". City and Consultant mutually agree to supplement the above referenced agreement as follows: 1. PROGRESS AND COMPLETION The work under this contract shall continue as required until completion of the construction of the Central Business Storm Drain Project by about October 31, 1985. Extensions of time may be granted if requested by Consultant and agreed to in writing by the City Engineer. 2. FEES TO BE PAID TO CONSULTANT The total amount of fees to be paid t.=, Consultant under the Original Agreement dated March 5, 1985, Supplenent No. 1 and this Supplement No. 2 shall not exceed the sum of $78,000.00. 3. PAYMENT OF FEES Payment of fees shall be on a monthly basis. Those fees shall be based on the hourly rates and direct costs contained in Section 5 of the Original Agreement. 4. EFFECTIVE DATE and year first written. This Supplement No. 2 shall be effective on and from the day IN WITNESS WHEREOF, we have hereunto set our hands and seals. FRASER & ASSOCIATES CITY OF CARLSBAD TITLE: President APPROVED (1 \ AhiXstant' City Attorney I I MARY H. / CASLER , Mayor ATTESTED: 0 City Clerk EXHIBIT 3 I. .. CITY OF CARLSBAD PUBLIC WORKS PROJECT CHANGE ORDER CHANGE ORDER NO: 2, Part A DATE: August 15, 1985 CONTRACT NO: 3085 PURCHASE ORDER NO: 12601 BUDGET NO: 30-18-30-3085 CONTRACTOR'S NAME: Peter C. David Co. PROJECT NAME AND NO: Central Business Storm Drain - No. 3085 REASON/PURPOSE FOR CHANGE: a. The utilities encountered in Grand Avenue are in locations different than that shown on the contract plans. These differences necessitated field revisions in the pipeline alignment which in turn required the construction of sixteen concrete collars southerly of Grand Avenue. b. The existing 8-inch diameter force main crossing at station 10+20 is different from that depicted on the contract plans. This resulted in the reconstruction of approximately 120 feet of 8-inch PVC pipe in' lieu of 40 feet as would normally be anticipated. c. The utilities encountered in Grand Avenue are in locations different from that shown on the contract plans. These differences necessitated field revisions in the pipeline alignment which in turn required the construction of five concrete collars northerly of Grand Avenue. d. The contract plans required the abandonment of an existing 15-inch diameter storm drain. Had this been accomplished, the existing catch basins at the intersection of State Street and Grand Avenue would have had no outlet. e. The contract documents stipulate that a Type B Cleanout be constructed at station 20+00. However, the 66-inch diameter RCP is too shallow to allow the construction of that type of structure. f. An 8-inch diameter sewer force main crosses the storm drain alignment near station 22+75. The force main is depicted in the plan view but it is not identified in the profile view. A physical conflict existed between the sewer force main and the storm drain pipe requiring the reconstruction of the sewer force main. .. Change Order No. -., Part A August 15, 1985 Page two g. An existing buried telephone conduit, a water line and an existing 8-inch diameter sewer within State Street are located in the field differently than that depicted on the contract plans. h. The City Maintenance and Utility Department has requested that an air relief valve be installed on the 8-inch sewer force main upstream of the reconstruction described in item f herein above. i. The contract drawings stipulate a finished grade for the alley This has been the cause for several major revisions. which would not properly serve the adjacent property owners. The stipulated alley grade would also have impeded the exist- ing drainage from adjacent parcels. j. The contract documents do not include any provisions for ultimate disposal of the storm water tributary to the improved alley or adjacent properties. k. The contract documents, utility improvement drawings and utility field markings denoted several of the utilities.in State Street incorrectly. The accurate field location of these facilities is necessary prior to the construction of the storm d'rain in the immediate vicinity. 1. The trench backfill in the deeper portions of the project are greater than can be safely sustained by the pipe specified. m. An existing 30-inch diameter lateral was encountered conveying storm water to an existing catch basin in Elm Avenue. This lateral required reconstruction and reconnection to the new catch basin. n. A local depression exists in the alley between Grand Avenue and Cedar Aver' e. This depression was previously served by a catch basin which was removed during the construction of this project. A new inlet structure is required to serve this local depression. 0. During a meeting, February 6, 1985, the City Engineer requested that the existing 8-inch sewer in State Street be excavated and located. p. A house lateral interferred with the location of the 66-inch RCP and had to be remodeled. q. An existing house lateral interferred with the location of the 66-inch RCP and had to be remodeled. c ’ Change Order No. , Part A August 15, 1985 Page three r, The plans and specifications did not include provisions for the adequate protection of a 36-inch vcp trunk sewer in Grand Avenue. The weight of the storm drain pipes cannot be sustained by the 36-inch vcp. s. The resiting of the junction structure in Grand Avenue necessitated resurveying of the area and also additional concrete curb and gutter work. DESCRIPTION OF CHANGE: a. Construct sixteen concrete collars around 48-inch diameter RCP along curvilinear alignment between approximate stations 26+00 and 27+15, all in accordance with Change Order Proposal Number 2. b. Reconstruct 120 feet of 8-inch PVC pipe with two 45 degree elbows and thrust blocks all in accordance with Change Order Proposal Number 3. c. Construct five concrete collars around 66-inch diameter RCP along curvilinear alignment between approximate stations 25+46 and 25+81 all in accordance with Change Order Proposal Number 7. d. Provide outlet connection for existing 15-inch RCP along southerly side of Grand Avenue by constructing 8 feet of 15- inch RCP and lug connection to 66-inch RCP at station 26+55 in accordance with Change Order Proposal Number 10. e. Construct Type A Cleanout with flat slab top in accordance with S.D.R.S Drawing No. D-9 at station 20+00 in lieu of cone type access shaft. Reference Change Order Proposal Number 15. f. Construct temporary force main sewer by-pass and reconstruct interfering portion of existing 8-inch diameter ACP force mair, in accordance with Sketch C.O. 3085-4. Reference Change Order Proposal Number 4 dated April 4, 1985. g. Construct 66-inch RCP in State Street and right-of-way between State Street and alley westerly of State Street in accordance with Change Order Proposal 13 and accompanying sketches 13B and 13C all dated May 21, 1985. Alignment of 66-inch RCP is revised as follows: 1. In order to avoid physical conflict with existing 48- inch storm drain, the horizontal curve with EC at approximately 1+95 shall be located northwesterly so as '1 I . . Change Order No. L, Part A August 15, 1985 Page four to provide approximately 5 feet of clearance between the two storm drains. Alignment in State Street shall be approximately 27 feet easterly of west curb in lieu of 22 feet as snown on the contract plans. Alignment between approximate stations 8+00 and 9+20 shall be located two pipe lengths (16 feet) southerly of that shown on the contract plans. 2. 3. This work and costs thereof are as follows: I. Relocate 66-inch RCP storage area $ 2,400.00 2. Temporary sewer by-pass 31 ,400.00 3. Reconstruct 8-inch VCP sewer 32,800.00 Total Amount $ 66,600.00 Contractors responsibility includes the following: I. Relocate stock piling of 66-inch RCP as requested by representative of Carlsbad Police Department. 2. Installation, operation, maintenance and removal of approved sewer by-pass. Facility to include duty pump, stand-by pump, emergency stand-by generator and all labor and equipment required. 3. Reconstruction of existing 8-inch diameter sanitary sewer. City's responsibility includes the following: 1. Existing 24-inch diameter storm drain, location unknown. 2. Concrete curb and gutter along easterly side of State Street. 3. Cost of electric energy required to operate sewer by- pass pumps. 4. Increased amounts included herein are additive to the amounts included in the bid proposal. . . Change Order No. -, Part A August 15, 1985 Page five h. Construct sewage air relief structure with air relief valve all in accordance with Sketch CO 3085-12 dated 5-1-85 attached hereto. i. Construct alley grade, cross-section and drive entrances in accordance with Sketch F.0.-2 dated May 10, 1985 in lieu of profile identified on contract plans. Payment thereof shall be in accordance with Bid Proposal and contract documents. j. Construct one Catch Basin Type.1, one Catch Basin Type F and 24-inch RCP at low point in alley, Station 16+85 in accordance with Sketch PCO 16-B dated June 18, 1985 attached hereto. Relocate existing ditch outside of proposed fence and pavement area in accordance with Sketch PCO 16-A dated June 18, 1985 attached hereto. k. Provide equipment and labor to excavate the existing utilities in State Street at five specified lcoations. Work is.to be performed and compensated for in accordance with Subsection 3- 3.2 of the Standard Specifications (Time and Materials). 1. Where the depth of pipe, as shown on the construction grade sheets, exceeds 15 feet provide crushed rock bedding. Rock pipe bedding shall be in accordance with SDRSD S 5.1. Payment shall be based upon certified weigh bills and include materials, delivery, taxes and all labor and materials necessary for the placement thereof. The agreed unit price is $21.00 per ton. The estimated quantity of rock required is 600 tons. Total estimated price is $12,600.00. m. Reconnect existing 30-inch diameter lateral to new catch basin in Elm Avenue and repair damaged drive entrance adjacent thereto. n. Construct inlet structure Type 1 per drawing D-29.1 on the existing 66-inch RCP at the local depression near Station 24+00. 0. Excavate and locate 8-inch sanitary sewer in State Street southerly of Laguna Drive, Excavation shall be located near the suspected point of interference with proposed 66-inch RCP strom drain as directed by City staff. p. Reconstruct 4-inch diameter house lateral at Station 28+60 so as to permit construction of 66-inch RCP. .. c Change Order No. 2, Part A August 15, 1985 Page six 9. Reconstruct 4-inch diameter house later at Station 10+35 so as to permit construction of the two 48-inch RCPs. Construct. concrete supports under the storm drain pipes, as existing 36-inch vcp. r. directed in the field, in manner that no load is added to the esu ve ?rand AJenue an8 also southerly of Grand Avenue. curb and gutter on northerly side of Grand Avenue at junction of alley. the pi e alignment northerly of Grand Avenue, in Also replace INCREASE IN CONTRACT TIME - INCREASE IN CONTRACT PRICE a. b. d. e. f. 9- h. i. j. k. 1. m. C. n. P. 9. r. 0. S. Part A Totals $ 8,000.00 5,675.60 4 , 000 .OO 1 ,511 .60 206.84 23,193.92 66,600.00 . 2,700 .OO no change 8,634.00 4,062.91 863.19 2,700 .OO 1,898.71 1,330.00 2,660.00 10,345.00 2,724.53 $159,706.30 12,600.00 (estimated) 6 days 2 days 2 days 2 days 2 days 6 days 10 days 3 days no change 5 days 2 days 5 days 1 day 2 days 2 days 1 day 1 day 1 day 2 days 55 days CITY OF CARLSBAD PUBLIC WORKS PROJECT CHANGE ORDER CHANGE ORDER NO: 2, Part B DATE: August 15, 1985 CONTRACT NO: 3085 PURCHASE ORDER NO: 12601 BUDGET NO: 30-18-30-3085 CONTRACTOR'S NAME: Peter C. David Co. PROJECT NAME AND NO: Central Business Storm Drain - NO. 3085 REASON/PURPOSE FOR CHANGE: An existing buried telephone conduit, a water line and an existing 8-inch diameter sewer within State Street are located in the field differently than that depicted on the contract plans. This has been the cause for several major revisions. This is a companion to item g of Part A, but is being presented separately for clarity, ENGINEER'S RECITAL: a. In the process of completing the storm drain project, 23 instances of what the Contractor contends are changed conditions have been encountered to date. b. The reach of construction between the downstream outlet and upstream thereof to Station 10+16 include the deepest construction and the greatest utility interferences. This reach is the most difficult and should be the slowest to construct. c. The Contractor requested that because of these alleged changed conditions, this work should proceed in accordance with Section 303 EXTRA WORK of the contract. This section is commonly referred to as Time and Materials. d. The Engineer has agreed that this method of proceeding is equitable providing the City could be assured of a maximum authorized amount. e. A review of the Contractors payroll records as well as known equipment rental rates indicate that the Contractors costs for each working day are approximately $8,400,00. -. Change Order 2, P-t B Page two .. August 15, 1985 f. It is estimated that these conditions will require approximately 15 working days in excess of the time to construct this reach of the project, had the conditions been as represented by the contract drawings. ADDITIONAL WORK: 1. 2. 3. 4. 5. 6. 7. Remove and replace existing asphalt berm. Resurvey of pipline and furnish revised cut sheets. Added support of existing 48-inch diameter RCP storm drain. Added support of existing 8-inch diameter ACP water main. Additional excavation, haul away, back-haul and compaction of trench backfill by virtue of previous 48-inch storm drain trench as well as existing 8-inch VCP sewer pipeline trench. Breaking, removal and disposal of existing concrete pavement that is not identified in the contract documents. The additional risk of constructing facilities that already include 23 instances that are the proper subject of a change order. PART B SUMMARY: PART A PART B TOTAL $1 23,000 .OO 15 days INCREASE IN CONTRACT PRICE INCREASE IN CONTRACT TIME $159,706 -30 123,000.00 55 days 15 days $282,706.30 70 days -0 Change Order 2, F-t B Page three . * August 15, 1985 RECOMMENDED : APPROVAL : OR: Peter QILhd / ?fl”[&iL L,, Cilty Pfoj ect Manager fI 1 2 3 4 5 6 7 e 9 IC 11 12 13 14 15 IE 17 I€ 1s 2c 21 2: 2: 24 2E 26 27 2E --- RESOLUTION NO. 8161 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CARLSBAD, CALIFORNIA, AMENDING CONTRACT NO. 3085, CENTRAL BUSINESS STORM DRAIN, BY APPROVING CHANGE ORDER NO. 2, APPROVING SUPPLEMENT NO. 2 TO THE AGREEMENT WITH FRASER & ASSOCIATES AND APPROPRIATING ADDITIONAL FUNDS. WHEREAS, funds in the amount of $800,000.00 are available for the Central Business Storm Drain in Account No. 881-820-3410-3085; and WHEREAS, Contract No. 3085 was awarded by the City Council to the Peter C. David Company on August 7, 1984 in the amount of $693,480.20 and Change Order No. 1 was approved by Council on June 4, 1985; and WHEREAS, an Agreement between the City of Carlsbad and Fraser & Associates was approved by the City Council on April 9, 1985 in the mount of $35,000.00 Supplement No. 1 to said agreement was approved by Council on June 18, 1985; and NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Carlsbad, California, as follows: 1. That the above recitations are true and correct. 2. Change Order No. 2 in the amount of $282,706.30 on file in the Engineering Department is hereby approved. 3. Supplement No. 2 to the Agreement between the City of Carlsbad and Fraser & Associates, on file in the Engineering Department and made a part hereof, is hereby approved. 4. Funds in the amount of $307,606.00 are hereby loaned to the Redevelopment Agency from the General Capital Construction fund at an annual interest rate of 10% per annum to be repaid to the General Capital Construction fund from tax increment revenues received by the Agency. These funds are hereby appropriated to Account No. 810-820-3410-3085. /// /// 4. 1- 1 2 1 c 4 F E 'i € 5 1c 11 li 12 14 15 1C 17 le 19 20 21 22 23 24 25 26 27 28 -- PASSED, APPROVED AND ADOPTED at a regular meeting of the Carlsbad City 1985 by the following vote, to Council held on the wit: 27aday of mn+ - AYES: Council Members Casler, Lewis, Kulchin, Chick and Pettine NOES: None ABSENT: None MARY H. CASLER, Mayor ATTEST : ------ ALETHA L. RAUTENKRANZ, City Cle (SEAL)