HomeMy WebLinkAbout1985-12-17; City Council; 8449; La Costa AV improvementsCITY*-IF CARLSBAD - AGENDA -ILL
4B# fv'f 9 TITLE:
IIITG. 12/17/85 IMPROVEMENTS TO LA COSTA AVENUE
IEPT. WEST OF EL CAMINO REAL TO 1-5
DEPT. HD.
CITY All'Y
CITY MGR.L~P/
RECOMMENDED ACTION:
I request the City Council to direct the City Manager to
bring a report to Council within 30 days estimating the
costs of improvements to La Costa Avenue west of El Camino
Real to Interstate 5.
ITEM EXPLANATION:
Estimate should include:
1. Modernizing and widening the intersection and signal
at La Costa Avenue and El Cawino Real.
2. Widening the roadway to 4 lanes.
3. Widening the bridge over 1-5 and improving the on and off-ramps.
This report should also include:
1. Methods and costs of financing
2. Estimate of time until completion
FISCAL IMPACT:
1985-86 CIP appropriates $320,000 for design and construction
of La Costa Avenue and El Camino Real intersection improvements.
Wildan Engineering has contract to do preliminary design
and cost estimates.
DECEMBER 17, 1985
TO: CITY MANAGER
FROM: City Engineer
LA COSTA AVENUE IMPROVEMENTS
The City Council is considering improvement of La Costa Avenue between El Camino Real and 1-5.
Wi 11 dan Associates , consul ting ci vi 1 engineers , have prepared cost estimates for four projects for improving La Costa Avenue. They are:
Phase I - Interim Improvements
a. La Costa Avenue Q El Camino Real $990,000 b. La Costa Avenue 0 1-5 $575 , 000 Total Estimated Interim Project Cost $1,565,000
Phase I1 - Major Improvements
a. Widen Bridge @ 1-5 $2,100,000 b. Widen La Costa Avenue $4,300,000 Total Estimated Major Improvements $6,400,000
TOTAL ESTIMATED PROJECT COST $7,965,000
It is estimated that construction could commence on the interim El Camino Real/La Costa Avenue Project on or about April 15, 1986, rain permitting; and on the interim I-5/La Costa Avenue Project about July, 1986. We have also estimated construction could commence on or about May, 1987 on the Phase I1 major improvements.
Attached is Wi 11 dan Associates ' 1 etter dated December 16, 1985 depicting the above in more detail.
DED: cl e
Attachments
cc: Principal Civil Engineer, Municipal Projects
December 16, 1985
Mr. Donald E. Donovan
CITY OF CARLSBAD
1200 Elm Avenue
Carlsbad, CA. 92008
Dear Gene:
The Carlsbad City Council has grown increasingly concerned about the
current and future traffic congestion along La Costa Avenue. Over the past
few months, they have awarded contracts to prepare an alignment study for
the ultimate improvement of La Costa Avenue, as well as for the final design
for intersection improvements and widening of La Costa Avenue immediately
west of El Camino Real.
Despite these ongoing efforts, based on the estimated 6,000 approved, but
unconstructed, dwelling units in La Costa, the City Council is considering a
plan to complete the widening of La Costa Avenue for the entire length from
El Camino Real to Interstate 5, including the reconstruction of the freeway
interchange. This is based, in part, on the current "F" level of service at
the intersection of El Camino Real and La Costa Avenue during the evening
peak hours, in which it is not uncommon for vehicles to wait through three
or more signal cycles before they are able to clear the intersection. Addi-
tionally, traffic waiting at the freeway off-ramps, at times, backs up to'the
through lanes, which is an extremely undesirable situation. It is clear from
these conditions that improvements must be made in the near future to either
La Costa Avenue and its interchange with Interstate 5, or provisions must
be made for an alternative east/west connection to the freeway, such as the
extension of Olivenhain Road to Leucadia Boulevard. This latter connection,
however, is outside of the City of Carlsbad's jurisdiction, and due to the
current agricultural operations along that alignment, it is unlikely that that
extension will be completed in the near future. You have, therefore, re-
quested this letter to identify the costs for a complete reconstruction of La
Costa Avenue from El Camino Real to Interstate 5, as well as, available
alternatives and their cost implications.
Travel forecasts for this portion of La Costa Avenue, made in connection
with Hunt Property Incorporated's (HPI) proposed Pacific Rim Master Plan,
indicate that La Costa Avenue should be widened to six lanes, plus dual left
turn lanes, at El Camino Real. This six lane configuration should be carried
westerly, approximately 1,500 to 2,000 feet along the Green Valley portion of
HPl's property. At that point, due to the lack of future access, it will be
possible to reduce the width of the roadway to four lanes, with a reduced
c
3633 CAMINO DEL RIO SOUTH SUITE 207 SAN DIEGO CALIFORNIA 92108 (619) 281-9211
December 16, 1985
Letter to Mr. Gene Donovan
CITY OF CARLSBAD
Page Two
median. This narrowed four lane configuration could
erly to a point approximately 1,000 to 1,500 feet from
Doint, the road should widen to six lanes to carry
then be carried west-
Interstate 5. At that
traffic to the freeway
interchange. The interchange needs to be reconstructed to accommodate a
minimum of two through lanes in each direction, plus two left turn lanes and
re la ted bicycle and pedestrian faci lit ie s .
Since La Costa Avenue currently runs along the south shore of Batiquitos
Lagoon and abuts steep slopes south of the roadway, construction of the
widened roadway will result in substantial amounts of cutting into the
hillside. This area is clearly extremely sensitive from an environmental
standpoint, therefore, it is recommended that the roadway be constructed to
minimum design standards, reducing the right-of-way as much as practical to
accommodate the traffic while still minimizing the potential impacts onto the
environment. Based on the preliminary information from the ongoing align-
ment study, a reduced right-of-way width is proposed in this area. The
street cross-sections for the various lane configurations are shown on the
attached figures.
A construction project of this magnitude will involve not only a considerable
design period, but also require permits from various agencies, including
CALTRANS for the freeway interchange, and the State Department of Fish
and Game, and U.S. Corps of Engineers for any encroachments into the wet-
lands area of Batiquitos Lagoon. Additionally, right-of-way will need to be
acquired along the entire length of La Costa Avenue. This process, if
started immediately, is anticipated to take approximately 12 to 15 months,
indicating the complete widening project could be under construction during
the Spring of 1987. Detailed time schedules are included for your review.
As noted, there is currently considerable congestion at both the freeway
interchange and at El Camino Real. The City Council has previously author-
ized a design project to widen La Costa Avenue immediately west of El
Camino Real. If this project were expanded to include the widening of El
Camino Real immediately north and south of the intersection to prime arterial
standards, the current level of service IIF" o peration could be dramatically
improved to level of service 'IB". Since this project is substantially smaller
than the overall widening project, the design and permitting process can be
accomplished much sooner. It is anticipated that it could be under con-
struction as soon as weather permits this Spring, approximately mid-April.
A similar interim project is also possible at the freeway interchange, which
could help to alleviate some of the current congestion. By signalizing the
two freeway ramps and widening La Costa Avenue from two to four lanes for
approximately 1,000 feet east of 1-5, substantial congestion relief could be
realized. Again, due to the reduced scope of this project, it is likely that
this interim project could be accomplished during the Spring of 1986 as well.
This second interim project, however, will involve CALTRANS approvals,
December 16, 1985
Letter to Mr. Gene Donovan
CITY OF CARLSBAD
Page Three
which might extend the design phase into the Spring with construction to
occur during the Summer of 1986. We are attempting to resolve the extent
of CALTRANSI involvement and will advise you as soon as possible.
Both interim projects could be designed and constructed so that they would
be integrated readily into the overall widening project. It should also be
clear that these interim projects will provide only temporary relief, that once
the approved dwelling units are occupied, it will certainly be necessary for
La Costa Avenue and the freeway interchange to be widened as proposed.
We have completed preliminary construction cost estimates for each of these
projects in today's dollars. These costs, including design, construction and
construction management, are summarized below with a detailed cost breakf
down to be submitted under separate cover.
Interim La Costa/El Camino
Intersection Improvements - $ 991,000
Interim Freeway Interchange
I m proveme nt s - $ 575,000
Reconstruction La Costa - El Camino Real to 1-5 - $4,334,000
Widen Freeway Interchange - $2,055,000
No specific sources of funding have been identified for the projects. The
interim projects could possibly be funded by City Gas Tax or general funds
in order to expedite their construction. The two larger projects, however,
will probably require other funding sources. Some of the other sources
might include an Assessment District, Developer Exactions, Certificates of
Participation combined with benefit fees or some combination of the above.
It is our understanding that the ongoing La Costa Area Traffic Fee Study is
reviewing similar options and should provide needed input into this area.
December 16, 1985
Letter to Mr. Gene Donovan
CITY OF CARLSBAD
Page Four
Willdan Associates is available to provide whatever assistance you need in
realizing the completion of these projects. Our staff is rapidly completing
the alignment study, which is expected to be available the first week of
January.
Yours truly,
WI LLDAN ASSOCIATES
Division Manager
RMS: SI
Attachments
P 85-170
JN 6841
- .J IO
IO
17
12 I 15
12
15 "I 110 r- IO I
15
4
I
I
l5 I It I
I'
12
-1
If 't I I
jll
LANE CONFIGURATION
LA COSTA 81 El CAMINO
io L - 17
FIGURE I
LA COSTA AVE.
c ...... -. - .. e-*-: .- :- - . _. . :.. ........... .... .. .. .. . - ..
- 5 BIKE
12
12
64/80* 8
12
- --
12
.... .c
5 BIKE ..... ... .... .. .5* ..... ........... .. *. . % ;' *.. .... .. .* .
I - - --
#k EXPANDS TO 70186 W/ 4 FT. MEDIAN AND
10 FOOT LEK TURN LANE AT SAXONY RD.
I
LANE CONFIGURATION I FIGURE 2
LA COSTA BETWEEN 1-5 8 ELCAMINOIW ~~~~
1. 1 - 12 - I2
' I
I k- I5
LANE CONFIGURATION
LA COSTA AVE/L-5 INTERCHANGE
VI'----- 5 .. .... : ' .:. . '. ;.:. 'r . . .. .> * y , , . :.
e I5
FIGURE 3
7mc
0 cis p;.
-7 13-
JC
CD co
c
0 ucl I
....
VI > C 0 0 < u
C 0 U
'5m>
I-
nau
zo>
0 ucr
0 uc,
I
In L 01 $5
$%
II
L + 0 c
C 0 cr u m
.-
t m .-
E n
c, C Q: C .- E W
In al
53 v)
E
2
'c
E