Loading...
HomeMy WebLinkAbout1986-07-08; City Council; 8119-14; Central Business Storm Drain Change Order No 3 and Notice of CompletionOF CARLSBAD - AGENF BILL 4s/if(& AB« Fin-'*/y MTG 7/08/86 DEPT MP TITLE: CENTRAL BUSINESS CHANGE ORDER NO. OF COMPLETION RECOMMENDED ACTION: STORM DRAIN 3 AND NOTICE DEPT. HD.J^H^L r,TY ATTY\J ^5 CITY MGR._2JMr V amending Contract No. 3085, CentralAdopt Resolution No. Business Storm Drain, by approving Change Order No. 3 and appropriat- ing additional funds in the amount of $67,301.57. Accept the construction of Contract No. 3085, Central Business Storm Drain, as complete. Direct the City Clerk to have the Notice of Completion recorded. Qui OCEQ_ a. ITEM EXPLANATION On August 27, 1985 Council approved Change Order No. 2 on this project. At that time, Council was told some additional changes were likely due to unforseen problems. Some additional problems did occur. A large oil dump had to be removed; large amounts of debris (including abandoned steel pipe, 55 gallon drums and old car bodies) were uncovered and had to be removed and hauled to the dump and some existing sewer laterals conflicted with the storm drain and had to be rebuilt. Also, the plans were revised to lower the grade of the alley in order to properly drain adjacent properties. This resulted in extra excavation and rebuilding of five driveways. The Central Business Storm Drain was essentially completed in November, 1985. The City Inspector prepared a punch list of corrections required on November19, 1985. The contractor finally returned in March, 1986 and satisfactorily completed all corrections, The City Inspector verified that the job was completed on-March 24, 1986. Staff therefore recommends approval of the Notice of Completion. During construction the contractor refused to negotiate change orders for required additional work. Due to the history of this project, staff permitted the work to continue in order to keep the contractor on the job. The contractor did not submit a claim for payment for additional work until January, 1986. The claim was lengthy, complex and much of it was unacceptable. A change order was sent to the contractor on February 25, 1986 which the contractor refused to discuss or sign. Finally in May, 1986, the contractor indicated he wished to settle the matter and met with staff on May 7, 1986. Negotiations were completed and full settlement reached on June 5, 1986. Following is a summary of the claim and recommended settlement: OO Page 2 of Agenda Bill No. <?\ ft - Contractor Claim Settlement 1. List of work for Change Order $ 95,196.12 $ 67,301.57 2. Additional asphalt pavement and base $ 40,752.22 $ -D- TOTALS: $135.948.34 $ 67.301.57 Staff maintained that the claim for additional asphalt and base must be rejected because, according to the contract, payment for those items was included in other items of work. A significant part of the above settlement is that the contractor has dropped this claim and agrees not to pursue the matter further. Staff recommends approval of Change Order No. 3 in the amount of $67,301.57 as full settlement of all claims by the contractor for this project. FISCAL IMPACT The original contract amount for this project was $693,480.20. Two previously approved change orders increased the contract amount to $995,235.80. This Change Order of $67,301.57 brings the final contract amount to $1,062,537.37. An additional appropriation of $67,301.57 is required. The funds will be loaned from the General Capital Construction fund to the Redevelopment Agency. This project will be repaid to the City from Redevelopment funds. EXHIBITS 1 . Location Map 2. Change Order No. 3 with Release and Settlement of Claim attached 3. Resolution No. f(o ££~~ amending Contract No. 3085, Central Business Storm Drain, by approving Change Order No. 3 and appropriating additional funds in the amount of $67,301.57. 4. Notice of Completion LOCATION MAP CITY MAP BOOK PAGE / PROJECT NAME CENTRAL BUSINESS STURM OKAIN PROJ. NO.EXHIBIT! / CITY OF CARLSBAD PUBLIC WORKS PROJECT CHANGE ORDER (More than $5,000) CONTRACT NO. 3085 PURCHASE ORDER NO. 12601 BUDGET NO. CONTRACTOR'S NAME PETER C. DAVID COMPANY PROJECT NAME AND NO. CENTRAL BUSINESS STORM DRAIN, NO. 3085 CITY ENGINEER CHANGE ORDER NO. THREE (3) The contractor is directed to make the following changes. Changes shall include labor, materials and equipment; payment stated on this change order includes all charges, direct or indirect, arising out of this additional work. The requirements of the specifications, where pertinent and not in conflict with this order, shall apply to these changes. Payment under this change order is in full satisfaction of all claims for extra work arising from this contract. The Release and Settlement, attached hereto, is made a part of this change order. CHANGE; 1. Remove unstable ground at Dragmaster. Remove debris and unclassified material at Bauer Lumber. $15,795.93 2. Lower alley grade; regrade Bauer and Mission Electric yards; reconstruct five (5) drive entrances. 36,064.91 3. Perform survey to establish new alley grades. 4,310.62 4. Relocate and rebuild five (5) sewer laterals and one water service. 6,008.34 5. Lower five (5) manholes; install steel plate on clean- out structure. 4,687.75 6. Install additional fence at Bauer Lumber. 434.02 TOTAL $67,301.57 REASON FOR CHANGE; 1. Unforeseen circumstances. Ground saturated with oil wastes was unstable and required removal. Also uncovered was debris, including abandoned steeL pipe drains, old car bodies and 55 gallon drums. - 2 - 2. The alley grades, as originally designed, did not provide adequate drainage for adjacent properties. The grade was lowered requiring additional excavation work. Two properties also required additional grading to drain. Five drive entrances required regrading and repaving to match the new alley. 3. Extra survey work required due to the revision of the alley grade. 4. Existing sewer laterals and one water service were in conflict with the storm drain and had to be relocated. 5. Steel plate required due to reduced clearance. Five existing manholes had to be lowered to match the new alley surface. 6. Actual measured quantity of fence installed was slightly greater than estimated quantity in contract. COST: Total this extra $67,301.57 Previous net changes $ 301,755.60 Original contract amount ?693,480..20 New contract total $1,062,537.37 TIME CHANGE; Previous add/deduct days Original contract days New contract time Approved by City Council on; CITY OF CARLSBAD Mayor Date CONTRACTOR (This change order is not effective unless signed by the Mayor.) RECEIVED RELEASE AND SETTLEMENT OF CLAIM Sixty-seven JULO^ISSG CITY OF CARLS3AEFOR THE SOLE CONSIDERATION of one and'57/100 __^_ Xawful money of the United States, to me/us in hand paid by the City of Carlsbad the receipt of which is hereby acknowledged,I/we Peter C. David Company residing at 13831 Newhojpe Aveftue, Garden Grove, California 92643 of lawful age, DO HEREBY RELEASE, ACQUIT AND FOREVER DISCHARGE City of Carlsbad from any and all actions, causes of being the action^claimsand demands,damages, costs, loss of services, expenses and compensation on account of or in any way growing out of any and all known and unknown costs resulting or to result from performance of the contract for the construction of the Central Business Storm Drain (Contract No. 3D85)and do hereby covenant with - the City of Carlsbad to indemnify and save harmless from all claims and demands,costs,loss of services, expenses and compensation on account of or in any way growing out of said performance of the contract . It is expressly understood and agreed that all rights under Section 1542 of the Civil Code of the State of California are hereby waived, which section reads as follows: "A general release does not extend to claims which the creditor does not know or suspect to exist in his favor at the time of executing the release, which if known by him must have materially affected his settlement with the debtor." It is expressly understood and agreed that the acceptance of the said amount of sixty-seven thousand, three hundred one and 57/100 dollars ($ 67,301.57 1is in full accord and satisfaction of a disputed claim, and" that the payment of the said sum of sixty-seven thousand, three hundred one and 57/100 dollars ( ? 6*7,301.57""]| is not an admission o£ ^liability. Date: STATE OF CALIFORNIA COUNTY OF ORANGE On this appeared //^ ss. /Mf _, 1986, before me personally to me known to be the pers,onl described herein, and who executed the foregoing instrument, and / / ilLk ' acknowledged that UOAUdMK*c-oorLonmiCCOUNTY executed -the same. Notary Public 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 RESOLUTION NO.8655 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CARLSBAD, CALIFORNIA, AMENDING CONTRACT NO. 3085, CENTRAL BUSINESS STORM DRAIN BY APPROVING CHANGE ORDER NO. 3 AND APPROPRIATING ADDITIONAL FUNDS. WHEREAS, Contract No. 3085 was awarded by the City Council to the Peter C. David Company on August 7, 1984 in the amount of $693,480.20, Change Order No. 1 was approved by Council on June 4, 1985, and Change Order No. 2 was approved by Council on August 27, 1985. NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Carlsbad, California, as follows: 1. That the above recitations are true and correct. 2. Change Order No. 3 in the amount of $67,301.57 on file in the Engineering Department is hereby approved. 3. Funds in the amount of $67,301.57 are hereby loaned to the Redevelopment Agency from the General Capital Construction fund at an annual interest rate of 10% per annum to be repaid to the General Capital Construction fund from tax increment revenues received by the Agency. These funds ar hereby appropriated to Account No. 810-820-3410-3085. PASSED, APPROVED AND ADOPTED at a regular meeting of the Carlsbad City Council held on the 8th day of July , 1986 by the following vote, to wit: AYES: Council Members Casler, Lewis, Kulchin, Chick and Pettine NOES: None ABSENT: None > / - ATTEST.MARY H. C^SLER, Mayor ALETHA L. RAUTENKRANZ, City Clerk (SEAL) Recording Requested By and Return To: City Clerk City of Carlsbad 1200 Elm Avenue Carlsbad, CA 92008 NOTICE OF COMPLETION ENGINEERING To All Laborers and Material Men and to Every Other Person Interested: YOU WILL PLEASE TAKE NOTICE that on March 24, 1986, the Engineering project consisting of the construction of the Central Business Storm Drain (Project No. 3085) on which Peter C. David Company was the Contractor, and The Ohio Casualty Insurance Company was the surety, was completed. CITY OF CARLSBAD VERIFICATION OF CITY CLERK I, the undersigned, say: I am the City Clerk of the City of Carlsbad; the City Council of said City on ^j~u t^y /** , 1986, accepted the above described work as completed and ordered that a Notice of Completion be filed. I declare under penalty of perjury that the foregoing is true and correct. Executed on 4^^ ^ , 1986 at Carlsbad, California. f/ CITY OF CARLSBAD <7\, ALETHA L. RAUTENKRANZ City Clerk