AWARD OF CONTRACT FOR THE
FARADAY AVENUE AND EL CAMINO REAL
TITLE:
TRAFFIC SIGNAL CITY MGR~&--
Adopt Resolution No. 8777 accepting bids and awarding Project No. 3225,
for the construction of the Faraday Avenue and El Camino Real traffic
signal to D. 8. X., Inc. ($67,000).
ITEM EXPLANATION:
On July 8, 1986, the City Council authorized the advertisement for bids for
this project. Five (5) sealed bids were received on August 6, 1986, as
follows :
1. D. B. X., Inc.
2. MCR Electrical Contractors, Inc.
3. McCain Construction Company, Inc.
4. D. & H. Perry, Inc.
5. Steiny & Co.
$67,000
$68,230
$70,794
$81,000
$82,915
The Engineer's estimate for this project was $69,000. References have been
verified on the low bidder and Staff recommends the award of this contract
to D. 8. X., Inc. Staff will seek to expedite the construction of this
traffic signal system to insure installation prior to occupation of the
Public Safety and Service Center in November.
FISCAL IMPACT:
As a condition of approval for Carlsbad Tract No. 84-10, the Koll Company
has deposited funds in the amount of $40,000 towards one-half of the cost
of the installation of this signal. Additionally, funds in the amount of
$40,000 are budgeted in Account No. 330-840-1840-3225 for the remaining
fifty percent (50%) of the cost of this project.
cost estimate for construction of the signal was $69,000.
Project inspection, testing, and administration costs are
estimated at $7,000.
Engineering staff's
EXHIBITS :
1. Location Map.
2. Resolution No. 8777 accepting bids and awarding Contract No. 3225 for the construction of the Faraday Avenue and El Camino Real traffic signal to D.B.X., Inc.
, LOCATION MAP
4 \ /CITY \\ I SAFETY I CENTER \ \- BECKMA N INSTRUMENTS \\ \\’ h ab?
LEGEND
I
\% \
PALOMAR AIRPORT B\
BECK
TE
MAN INSTRUMENTS
-. - .- ........... ............ ........... ............ ........... ............ ........... ........... .......... SITE OF FUTURE
VlCINriY MAP
N. T. S.
QROJECT NAME PROJ. NO- EXHIBIT
SIGNAL- EL CAMINO REAL AND FARADAY AVE I 3225 I I
I
? c
4
E
7
E
s
IC
12
12
15
16
17
18
19
22
23
24
25
26
28
RESOLUTION NO. 8777
A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF CARLSBAD, CALIFORNIA, ACCEPTING BIDS AND
AUTHORIZING THE EXECUTION OF PROJECT NO. 3225
FOR THE CONSTRUCTION OF THE FARADAY AVENUE AND
EL CAMINO REAL TRAFFIC SIGNAL
WHEREAS, bids have been received by the City of Carlsbad for the
construction of a traffic signal system at Faraday Avenue and El Camino
Real, Contract No. 3225; and
WHEREAS, the low bid received for the said traffic signal was
submitted by DBX Inc., in the amount of $67,000; and
WHEREAS, funds in the amount of $40,000 are on deposit with the City
from an adjacent private developer to be utilized for this project;
WHEREAS, City funds have been budgeted and are available in Account
No. 330-840-1840-3225 for this project;
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of
Carlsbad, California, as follows:
1. That the above recitations are true and correct.
/// .
///
///
///
///
///
///
///
///
///
///
1
2
3
4
5
6
7
a
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
2. The bid of $67,000 by D. B. X., Inc. for Contract No. 3225 for
the construction of the Faraday Avenue and El Camino Real traffic signal is
hereby accepted, and the Mayor and City Clerk are hereby authorized to
execute a contract thereafter.
PASSED, APPROVED AND ADOPTED at a regular meeting of the Carlsbad City
Council held on the 26th day of August , 1986 by the following vote,
to wit:
AYES: Council Members Casler, Lewis, Kulchin, Chick, and Pettine
NOES: None
ABSENT: None
dRY H. CASLER, Mayor
ATTEST:
ALETHA L. RAUTENKRANZ, City Clerk