HomeMy WebLinkAbout1986-12-09; City Council; 8119-35; Notice of Completion Carlsbad Safety and Service Center 3006-1A 3006-1B 3006-1C 3006-1D 3006-1FCIT OF CARLSBAD — AGENDA BILL
QLU
occ:a.a.
og
o
8
ARtf X]\°l-3£'
MTG. 1?/fl9/Rfi
DEPT PM
TITLE:
NOTICE OF COMPLETION FOR CONSTRUCTION
OF THE CARLSBAD SAFETY AND SERVICE CENTER
OFPT. HD. l^v3r
CIJY ATTY V^S
CITY MQR. ~2$~
RECOMMENDED ACTION:
Accept the contractual responsibilities of each contractor as being complete.
Direct the City Clerk to have the Notice of Completion recorded and release
the bonds 35 days after recordation.
ITEM EXPLANATION
Construction of the following portions of the Carlsbad Safety and Service
Center have been satisfactorily completed per the City Engineer and Public
Works Inspector:
ORIGINAL
CONTRACT
CHANGE
ORDERS TOTAL TYPE
3006-1A Templeton
3006-1B Ted Vance & Sons
3006-1C Templeton
3006-1D Tresize Company
3006-1F Sim J. Harris
$268,950.00 $58,104.36 $327,054.36
$ 90,170.50 $ 3,310.15 $ 93,480.65
$ 19,647.00 $(7,710.00) $ 11,937.00
$394,707.00 $49,678.76 $444,385.76
$273,067.00 $84,916.08 $357,983.08
Grading
Curb & Gutter
Gunite
Sewer
A/C paving
The final project total for each contractor includes change orders handled
administratively in accordance with Administrative Order No. 7 to cover
necessary additional work.
FISCAL IMPACT
All contract amounts in total have been encumbered and those funds are
available to pay the retainage. The five (5%) percent retention will be
withheld until 35 days after the filing of the Notice of Completion.
To date, we have contracted, change ordered, and encumbered $10,240,000 of the
projected budget for Phase I of the Carlsbad Safety and Service Center.
Actual payments through December 1, 1986 are approximately $8,765,000.00.
EXHIBITS
1. Notice of Completion (5) for each contractor.
2. Letter from Public Works Inspector.
Recording Requested By and Return To:
City Clerk
1200 Elm Avenue
Carlsbad, CA 92008
NOTICE OF COMPLETION
ENGINEERING
To All Laborers and Material Men and to Every Other Person
Interested :
YOU WILL PLEASE TAKE NOTICE that on December 2, 1986, the
Engineering project consisting of gunite on the Carlsbad
Safety and Service Center on which Templeton was the
Contractor, was completed.
CITY OF CARLSBAD
City £rigineer
VERIFICATION OF CITY CLERK
I, the undersigned, say:
I am the City Clerk of the City of Carlsbad; the City
Council of said City on Pi-? At ,,-i Yr*"^^ 7 * 1^86, accepted
the above described work as completed and ordered that a
Notice of Completion be filed.
I declare under penalty of perjury that the foregoing
is true and correct.
Executed on ^J^e * t~^~t-*~ /o > 1986 at Carlsbad,
Cali f ornia.
CITY OF CARLSBAD
ALETHA L. RAUTENKRANZ
City Clerk
Recording Requested By and Return To:
City Clerk ~
1200 Elm Avenue
Carlsbad, CA 92008
NOTICE OF COMPLETION
ENGINEERING
To All Laborers and Material Men and to Every Other Person
Interested:
YOU WILL PLEASE TAKE NOTICE that on December 2, 1986, the
Engineering project consisting of grading on the Carlsbad
Safety and Service Center on which Templeton was the
Contractor, was completed.
CITY OF CARLSBA
UBBS
gineer
VERIFICATION OF CITY CLERK
I, the undersigned, say:
I am the City Clerk-of the City of Carlsbad; the City
Council of said City on &*JLsCJL~v*jLj*-' 9 > 1986, accepted
the above described work as completed and ordered that a
Notice of Completion be filed.
I declare under penalty of perjury that the foregoing
is true and correct.
Executed on / os*{-r^/+±^ /O > 1986 at Carlsbad,
California.
CITY OF CARLSBAD
ALETHA L. RAUTENKRANZ
City Clerk
Recording Requested By and Return To:
'City Clerk ~
1200 Elm Avenue
Carlsbad, CA 92008
NOTICE OF COMPLETION
ENGINEERING
To All Laborers and Material Men and to Every Other Person
Interested:
YOU WILL PLEASE TAKE NOTICE that on December 2, 1986, the
Engineering project consisting of water, sewer and storm
drain on the Carlsbad Safety and Service Center on which
Tresize Company was the Contractor, was completed.
CITY OF CARLSBAD
City
VERIFICATION OF CITY CLERK
I, the undersigned, say:
I am the City Clerk^if the City of Carlsbad; the City
Council of said City on yj g^-J>--^6-ft/'\_ *? ; 1986, accepted
the above described work as completed and ordered that a
Notice of Completion be filed.
I declare under penalty of perjury that the foregoing
is true and correct.
Executed on jT) Piffl ^ £JL*^ /° _> 1986 at Carlsbad,
Cali f ornia.
CITY OF CARLSBAD
ALETHA L. RAUTENKRANZ
City Clerk
Recording Requested By and Return To:
City Clerk
1200 Elm Avenue
Carlsbad, CA 92008
NOTICE OF COMPLETION
ENGINEERING
To All Laborers and Material Men and to Every Other Person
Interested:
YOU WILL PLEASE TAKE NOTICE that on December 2, 1986, the
Engineering project consisting of curb and gutter and
uncolored sidewalk on the Carlsbad Safety and Service
Center on which Ted Vance and Son's, Inc. was the
Contractor, was completed.
CITY OF CARLSBAD
UBBT
City (^Engineer
VERIFICATION OF CITY CLERK
I, the undersigned, say:
I am the City Clerk j>f the City of Carlsbad; the City
Council of said City on kJJLC&^^&ts^i ? , 1986, accepted
the above described work as completed and ordered that a
Notice of Completion be filed.
I declare under penalty of perjury that the foregoing
is true and correct.
Executed o n 1 ] , p ,-f t, Mr JjJL*^ I O > 1986 at Carlsbad,
C ali fornia.
CITY OF CARLSBAD
ALETHA L. RAUTENKRANZ
City Clerk
&AJ»-~
Recording Requested By and Return To:
City Clerk
^1200 Elm Avenue
Carlsbad, CA 92008
NOTICE OF COMPLETION
ENGINEERING
To All Laborers and Material Men and to Every Other Person
Interested:
YOU WILL PLEASE TAKE NOTICE that on December 2, 1986, the
Engineering project consisting of A/C paving on the Carlsbad
Safety and Service Center on which Sim J. Harris was the
Contractor, was completed.
CITY OF CARI/SBAD
B. HUBBS
C ft j(/Engineer
VERIFICATION OF CITY CLERK
I, the undersigned, say:
I am the City Clerk of the City of Carlsbad; the City
Council of said City on £^ jL^t^^J^^ ^ > 1986, accepted
the above described work as completed and ordered that a
Notice of Completion be filed.
I declare under penalty of perjury that the foregoing
is true and correct.
Executed on J^-)<jj_sC-s>-—J>*s-' /Q , 1986 at Carlsbad,
Cali fornia.
CITY OF CARLSBAD
J.
ALETHA L. RAUTENKRANZ
City Clerk
z_
NOVEMBER 7, 1986
TO:
FROM:
MIKE BROOKS
Administrative Assistant
Joe Federico
Construction Inspector
CC 3006 PUBLIC SAFETY AND SERVICE CENTER
The work done by Templeton on the grading has been completed.
I recommend that their work be accepted and placed on warranty.
JOE FEDERICO
Construction Inspector
JF:dm
NOVEMBER 7, 1986
TO: MIKE BROOKS
Administrative Assistant
FROM: Joe Federico
Construction Inspector
CC 3006 PUBLIC SAFETY AND SERVICE CENTER
The work done by Ted Vance and Son's, Inc., on the curb and
gutter and uncolored sidewalk, has been completed. I recom-
mend that the work be accepted and placed on warranty.
FEDERICO
Construction Inspector
NOVEMBER 7, 1986
TO: MIKE BROOKS
Administrative Assistant
FROM: JOE FEDERICO
Construction Inspector
CC 3006 PUBLIC SAFETY AND SERVICE CENTER
The work done by Tresize Company on the water, sewer, and storm
drain has been completed. I recommend that their work be
accepted and placed on warranty.
JOE FEDERICO
Construction Inspector
JF:dm
IB
NOVEMBER 10, 1986
TO: MIKE BROOKS
Administrative Assistant
FROM: Joe Federico
Construction Inspector
CC 3006 PUBLIC SAFETY AND SERVICE CENTER
The work done by Sim J. Harris on the road base and A/C paving has
been completed. I recommend that their work be accepted and placed
on warranty.
JOE FEDERICO
Construction Inspector