HomeMy WebLinkAbout1988-03-08; City Council; 9322; Presentation of draft report for preliminary phaseGIT' JF CARLSBAD - AGEND, JILL
AB#
DEPT
932 a.
03/08/88
MP
TITLE: PRESENTATION OF DRAFT REPORT FOR
THE PRELIMINARY ENGINEERING PHASE OF
THE BATIQUITOS LAGOON ENHANCEMENT PROJECT
DEPT. HD^yt^
CITY ATTY ^O5
r*iTV MfSD^i^L^i^l i i nn u n. ^*\
o§
o
oo
RECOMMENDED ACTION:
Accept and file the Draft Preliminary Design Report for the
preliminary engineering phase of the Batiquitos Lagoon
Enhancement Proj ect.
ITEM EXPLANATION:
On April 14, 1987, the City Council adopted Resolution No. 9022
approving an agreement with the City of Los Angeles through its
Board of Harbor Commissioners (Port of Los Angeles) for the
preparation of preliminary engineering studies for the Batiquitos
Lagoon Enhancement Project. Thereafter, on April 21, 1987, the
City Council adopted Resolution No. 9028 approving a consultant
agreement with the firm of CH2M Hill, Incorporated, for the
preliminary engineering studies and related technical work for
this project.
In accordance with the terms of the City's agreement with CH2M
Hill, an Interim Report was prepared by the consultants and
submitted for City Council review on October 13, 1987.
The City Council will receive at this meeting a formal
presentation by the consultant group summarizing the Draft
Preliminary Design Report for the project. The following study
issues are addressed in detail in the report:
Existing lagoon sediment characteristics, qualities, and
quantities.
Volume of dredged/excavated material by type and location
for the three (3) enhancement alternatives.
Dredged/excavated material disposal sites and methods.
Dredging/excavation depths and boundaries including detailed
grading plans for the three (3) alternatives.
Tidal inlet design recommendation.
Beach nourishment design recommendation.
Hydraulic modeling including circulation, flushing, and
water quality analysis.
Lagoon sedimentation and sediment control management plan.
Existing bridge placement and methods of protection.
Page Two of Agenda Bill No.
Avifaunal surveys completed to date.
Engineering cost estimates of all project components.
Attached is a copy of the Draft Preliminary Design Report's
Executive Summary summarizing the study's findings. Copies of
the larger Draft Preliminary Design Report and Technical Appendix
have been previously distributed to the City Council.
FISCAL IMPACT;
The study for the preliminary engineering phase of the Batiquitos
Lagoon Enhancement Project is funded entirely by the Port of Los
Angeles as set forth in the City of Carlsbad/City of Los Angeles
agreement .
EXHIBITS ;
1. Executive Summary, Draft Preliminary Design Report,
Batiquitos Lagoon Enhancement Project.
2 . Draft Preliminary Design Report and Technical Appendix for
the Batiquitos Lagoon Enhancement Project on file in the
Office of the City Clerk.
Executive Summary
Draft Preliminary Design
Report - February 1988
BATIQUITOS LAGOON
ENHANCEMENT PROJECT
Prepared by
CKMHIUL
Tekmarine
BATIQUITOS LAGOON ENHANCEMENT PROJECT
DRAFT FINAL REPORT
EXECUTIVE SUMMARY
OVERALL STUDY OBJECTIVES
The Batiquitos Lagoon Enhancement Project Preliminary Design
Report represents a detailed engineering study and analysis
to evaluate the feasibility of the engineering aspects and
associated costs of the enhancement project. The enhance-
ment project endeavors to fulfill the goals set forth in the
California Coastal Conservancy Draft Batiquitos Lagoon
Enhancement Plan: to restore tidal flushing by creating
adequate tidal prism while conserving and enhancing existing
wildlife habitat values and establishing new habitats. The
draft enhancement plan was developed over a period of more
than 2 years through a public process involving state,
federal, and local public agencies; property owners; envi-
ronmental and citizen groups; and interested individuals.
This report reviews the methodology and findings of the
following:
o Existing lagoon sediment characteristics,
qualities, and quantities
o Volume of dredged/excavated material by type and
location for three enhancement alternatives
o Excavated/dredged material disposal methods
o Excavated/dredged material disposal sites
o Excavation/dredging depths and boundaries
(detailed grading plans) for three alternatives
o Tidal inlet design recommendation
o Beach nourishment design recommendation
o Hydraulic modeling (circulation and flushing) and
water quality analysis within the lagoon for
three alternatives
o Lagoon sedimentation (SED-4 modeling results)
o Sediment control management plan
o Existing bridges relative to the lagoon enhance-
ment project and methods for their protection
DDHl/007
o Avifaunal surveys to date
o Engineering cost estimates of project components
SUMMARY OF FINDINGS
LAGOON SEDIMENTS
The sediments proposed to be removed from the lagoon are not
hazardous, containing trace or lesser amounts of pollutants,
and are well below threshold limit concentrations as defined
by the California Administrative Code, Title 22. Therefore,
the sediments may be disposed of by conventional land dis-
posal methods.
Sediments in the western half of the lagoon are composed
predominantly of sands and are suitable for beach-front dis-
posal, beach nourishment, and least tern nesting areas^
Sediments in the eastern half of the lagoon consist of
elastic silts, fat clays, and sands. These sediments can be
used as an impermeable capping or lining material, a non-
structural fill, or, if mixed properly with other material,
as structural fill.
DREDGING/EXCAVATION AND DISPOSAL CONCEPTS
The three enhancement alternatives require differing amounts
of soil removal, as follows:
o Alternative A: 3,096,000 yd3
o Alternative B: 2,632,000 yd3
o Alternative C: 2,347,000 yd3
Approximately 380,000 yd3 of the above quantities will be
used as fill material within the lagoon boundaries to form
least tern nesting sites and a freshwater marsh.
The sand in the west and central basins is relatively easy
to dispose of because it can be placed on adjacent and near
beaches as nourishment. The material comprising most of the
east basin is more difficult to dispose of because of its
wet cohesive consistency, which creates transport and place-
ment problems.
The recommended dredging and disposal scheme is to remove an
additional depth of sand in the central lagoon, thereby
creating a "pit" that can accommodate the material from the
east lagoon. A sand cap will then be placed over the
relocated material. This method requires moving additional
quantities of material locally, using efficient hydraulic
dredge equipment. Even though this recommendation requires
the dredging of nearly 2 million additional cubic yards for
DDH1/007
Alternative A (over the quantity shown above), the estimated
cost is lower than the most economical land disposal option.
This is an efficient construction technique for in-lagoon
sediment disposal that will not alter predicted habitats of
the final enhancement project. In addition, it creates more
beach nourishment material, reduces the total project con-
struction time, and reduces offsite project impacts.
As an option to the recommendation discussed above, the most
preferred dry land disposal of the east basin material is in
the Green Valley area just south of the eastern end of the
lagoon. Even though the material would be placed on dry
land, hydraulic dredging would be most attractive and cost-
effective because the material could be easily conveyed the
relatively short distance required of dredge pipe. If a
disposal site is selected more than 3 miles away, soil
removal in the east basin would best be handled using con-
ventional grading equipment. The east basin could be diked
off and dried, and San Marcos and Encinitas Creeks tempora-
rily rerouted. The material would be hauled to a disposal
site by truck.
The nesting season of the California least tern was taken
into account when determining the construction schedule to
minimize effects to the bird's nesting and foraging habitats.
Maintenance dredging will be required periodically. For
Alternative A, approximately 25,000 yd3 of material could
accumulate in the western portion of the lagoon each year
from marine sources. Alternative B could accumulate
17,000 yd3, and Alternative C could accumulate 13,000 yd3.
In addition, it is estimated that 3,500 yd3 of sediment will
be caught in the east basin sediment trap. This study
contains a maintenance program to ensure that the cumulative
effects of sedimentation will not affect the long-term
viability of the enhancement project.
TIDAL INLET
A comprehensive study has been made of various alternatives
for a tidal inlet design. Particular attention has been
given to the following:
o History of Batiquitos Lagoon and the surrounding
area
o Longshore sediment transport
o Characteristics of other Southern California
coastal inlets
DDH1/007
o Function and purpose of the inlet
o Constructibility
o Maintenance
With respect to all these considerations, the preferred
concept is a small armored channel configuration. The
design emphasizes short, low profile jetties with the
objective of nominal disruption to the longshore sediment
transport.
BEACH NOURISHMENT CONCEPT
The beach nourishment operations are proposed to take
advantage of a large amount of sandy material greater than
0.15 mm in median diameter available from the recommended
planned dredging in the lagoon. Considering the recommended
central basin disposal pit scheme, approximate total amounts
of the sand in the beach nourishment size range are
3,180,000 yd3 under Alternative A, 2,600,000 yd3 for
Alternative B, and 2,450,000 yd3 under Alternative C.
Although some amounts of this sand will be used for
construction of the least tern nesting sites, most is
available for beach nourishment. As much as 60 percent of
this material is finer than 0.20 mm and is subject to easy
washout by wave action. Selection of nourishment sites was
made where the presence of cobbles and reduced wave energy
(caused by wave divergence) will make this material useful
for beach nourishment.
Two specific areas have been evaluated for beach nourish-
ment: a 3,000-foot shoreline segment near Batiquitos Lagoon,
and a 5,700- to 6,500-foot shoreline segment at the Encinas
Creek outlet. Both of these sites provide excellent beach
access and have provisions for a sizable public parking
facility. The Batiquitos site is limited in size and can
only accept about 114,000 yd3. The material would be placed
on the surface of a regraded cobble berra to improve the
amount of time it would remain at the site. A useful period
at this site could be 3 years, although a variation from
normal ocean conditions could cause substantial variations
in duration, either shorter or longer. It should be noted
that the proposed maintenance dredging of the inlet area
would replenish the Batiquitos site on a continual basis.
The natural loss of material from this beach will benefit
the downcoast shoreline for a distance of approximately
2 miles, including Leucadia and the northern reach of
Encinitas.
DDH1/007
At the Encinas Creek site, sand placement totaling as much
as 2.1 to 3.1 million yd3 will push the shoreline seaward •
485 to 640 feet. The length of time that nourished sand
remains at this beach is variable. One possible scenario
could be:
1. Half the width of beach would disappear under a
severe low frequency occurring storm.
2. Sand would remain for approximately 15 years under
average weather conditions.
3. Longer residency would be obtained if nourished
periodically with maintenance dredging, or if
unusually calm weather prevails.
The beach fill at the Encinas Creek site will serve as a
major source of littoral sediment for the shoreline at South
Carlsbad State Beach.
HYDRAULIC MODELING AND WATER QUALITY EVALUATION
Current meters and tide gauges were placed at strategic
locations inside Batiquitos Lagoon prior to removal of the
natural cobble bar at the mouth of the lagoon in May 1987.
Current and tide information obtained from these instru-
ments, combined with profile mapping of the ocean bottom
conditions, enabled the calibration of hydrodynamic (cir-
culation and flushing) and water quality models comparable
to actual conditions.
The models show the alternatives are capable of achieving
85 to 90 percent of the potential tidal prism, indicating
the design of the entrance channel is effective in allowing
continuous tidal exchange. This estimate is consistent with
previous tidal prism estimates including that computed by
the Coastal Conservancy.
The tidal prisms of the three alternatives fall into the
range of 2.1 to 2.6 million yd3. This volume of water
amounts to more than 50 percent of the total volume of water
in the lagoon (at +5.0 feet mllw) for any of the three
dredging plans. This continual exchange of ocean water will
serve to reduce the potential impacts of long-term stagna-
tion, as now occurs.
The normal water quality of the lagoon should be similar to
the ocean throughout the year except during major storm
events, which would result in large volumes of fresh water
from the uplands. However, the time needed to return to
normal water quality would be relatively short throughout
the basin. The habitat for fish and other aquatic life
should be greatly improved over existing conditions
because of improved tidal circulation and water quality
DDH1/007
with more consistent levels of salinity, concentrations of
nutrients, dissolved oxygen, and food chain organisms.
SEDIMENTATION AND SEDIMENT MANAGEMENT
Existing data indicate the inlet closure at Batiquitos
Lagoon was not a result of filling by upland sediments and
subsequent loss of effective tidal prism. Inlet closure
appears to be a result of bridge constrictions near the
mouth. The constrictions reduced the scouring ability of
the tidal flows leading to sedimentation and closure of the
inlet. When the inlet is closed, fine sediments that may
normally move through the lagoon (to the sea) are instead
trapped in it.
Previous estimates of upland sediment delivery to the lagoon
appear to be significantly higher that what is expected in
the future. This result is due in part to overly conserva-
tive estimating techniques and in part to the decreasing
effects of development on sediment load.
The use of sediment traps as a management technique may not
be effective. Under low to moderate flood events, the
sediment loads may not be large enough to be of concern.
Under extreme flood events the sediment traps may be inef-
fective. Sediment basin placement must be considered in
relation to the potential for increasing flooding (San
Marcos Creek) and interference with naturally existing
sediment traps (Encinitas Creek). In both cases, there are
strong arguments for placing such structures lagoonward from
the bordering highways. For the small creeks entering the
lagoon, management of sediment and erosion at construction
sites should be sufficient. Construction of permanent sedi-
ment traps should be considered only if the sedimentation
problem clearly is not transient.
The most serious sedimentation problem is the transport of
sand through the inlet. Above mllw, the adjacent beach is
currently composed of cobbles. However, sufficient sand for
transport into the inlet appears to be present on the beach
below low water. Beach nourishment by the implementation of
the enhancement plan will also add to the supply. Two im-
portant consequences are evident: the inlet is the most
critical part of a lagoon enhancement design, and the inlet
will have to be armored on its sides.
EXISTING BRIDGES
Existing information has been obtained on all five of the
bridges crossing the lagoon. To accommodate the proposed
dredging, all of the bridges will require either a form of
structural modification or foundation protection. The western
portion of Carlsbad Boulevard Bridge may possibly require
DDH1/007
extensive footing modifications; however, that cannot be
determined until the water level in the lagoon subsides and
an investigation of the existing footings can be made.
AVIFAUNAL SURVEYS
Six avifaunal surveys have been completed to date. Addi-
tional surveys will be conducted to complete a 1-year sampling
period. Bird use fluctuates with seasonality, with waterfowl
populations remaining high through winter and shorebirds
decreasing after summer breeding. Water elevations also
affect bird usage, as shorebird use continues to decline
with high winter water levels (and inundation of habitat).
The California least tern (federally listed endangered species)
was noted during the breeding seasons and not observed during
the winter season (when the bird is typically in Central
America and Mexico). The state-designed endangered species/
Belding's savannah sparrow, was noted during all six surveys
but fluctuated significantly according to season.
Construction Costs and Schedule
Budget level construction cost estimates and an anticipated
construction schedule have been prepared.
The total project costs for the various alternatives are
summarized as follows:
Central Basin Disposal Green Valley Disposal
Alternative A $23,488,000 $34,848,000
Alternative B $20,465,000 $29,798,000
Alternative C $19,626,000 $26,119,000
The recommended central basin disposal construction scenario
will require a construction contract of 1-1/2 years. Ninety
percent of the entire project, including all dredging, will
take place in & 5-1/2 month period during the first fall and
winter season. The west and central basins will be complete
and tidally influenced after this period and the west basin
and Park and Ride least tern nesting sites will be finished.
The east basin will have been dredged, but finish grading
work will need to be done after the basin has had time to
dry out somewhat.
If the Green Vallfey or similar offsite disposal scenario is
used, the total construction time will remain at about
1-1/2 years. Tito lagoon west of 1-5 will still be complete
at 5-1/2 months, but the east lagoon dredging will be a
slower process, attending over the entire contract length.
DDHl/007