HomeMy WebLinkAbout1988-09-06; City Council; 9630; AWARD OF CONTRACT FOR CONSTRUCTION OF THE CARLSBAD SENIOR CENTER AND CARLSBAD UNIFIED SCHOOL DISTRICT ADMINISTRATIVE OFFICE COMPLEX.. 2 0 6 : a
z 3 0 0
AUENVUILL df UP GAHLaUAU -
AB# yG36 TIT'LE:AWARD OF CONTRACT FOR CONSTRUCTION DEPT. 1
MTG. 9/6/88 OF THE CARLSBAD SENIOR CENTER AND CITY A1
DEPT. MP ADMINISTRATIVE OFFICE COMPLEX CITY M
RECOMMENDED ACTION:
Adopt Resolution No. ff/JZ{accepting bids and awarding a contra
for the construction of the Carlsbad Senior Center and Carlsb
Unified School District Administrative Office Complex.
Adopt Resolution No. ff-3aa>pproving an amendment to the existi
architectural consultant agreement for continuing architectur
services during the construction phase of this project.
ITEM EXPLANATION:
On July 12, 1988, the Carlsbad City Council authorized t advertisement of bids for construction of the Carlsbad Seni Center and Carlsbad Unified School District Administrative Offi
Complex, Project No. 3247. Nine (9) sealed bids were received August 24, 1988, as follows:
CARLSBAD UNIFIED SCHOOL DISTRICT
1. Straub Construction, Inc. $ 3,025,000
2. J. A. Stewart Construction 3 , 080 , 000
3. Quest Construction 3 , 099 , 948
4. Douglas E. Barnhart, Inc. 3 , 108 , 493
5. EVH Inc., and Associates 3 , 130,000
6. T. B. Pennick and Sons, Inc. 3 , 133 , 000
7. Net Enterprises, Inc. 3 , 139,600
8. Louetto Construction 3 , 251,000
9. M. L. Hansen Company, Inc. 3,886 , 900
The award of this construction contract for this facility will
the last major phase in completing this joint developme
project between the City of Carlsbad and the Carlsbad Unifj
School District. The project includes the construction of
combination one (1) and two (2) story joint use facilj
consisting of a 15,400 square foot Senior Center and 12,s
square foot Administration Office Complex for the Carlsl:
Unified School District. The project will be constructed
approximately 3.31 acres addressed at 801 Pine Avenue as depict
in Exhibit 1.
This project is a result of several years of negotiations betwc the City and the School District followed by a very lengthy i detailed design effort by School District representatives, 1 Carlsbad Senior Citizens Commission, City staff, and 1 architectural firm of Wolff/Lange/Christopher Architecl
Incorporated.
I
0 94347 e
Page Two of Agenda Bill No.
References have been verified on the low bidder and sta recommends the award of this contract to Straub Constructic Incorporated.
Fundamental to the successful construction of a project of th magnitude and complexity is the continued active participation the project architect. The project architect I s service
availability, and level of involvement is as extensive duri the construction phase as during any of the other project desi phases. The project architect's duties during the constructi
phase will include:
- Provide general project construction administration
I
behalf of the City. Act as architectural representative (
site and advise the City on architectural and build:
issues.
- Make bi-monthly or more frequent site visits appropriate
the stage of construction. Advise the City as to 1 progress and quality of the work.
- Determine the construction quantities completed to date .
the purposes of quantifying monthly progress payments.
- Review and approve all shop drawings, product data, samplc
and other submittals required to indicate conformance w
the design within the project plans and specifications.
- Prepare any revisions, modifications, or change ord required for minor adjustments within the project.
- Conduct inspections to determine substantial and fi completion, and issue a final certificate for payment u approval.
- Generally insure construction quality control during phases of construction.
Staff recommends approval of the attached agreement amendm with Wolff/Lang/Christopher Architects, Incorporated continuing architectural services during the construction ph of the project.
Construction is anticipated to begin in late September require approximately twelve (12) months for completion.
0 0
Page 3 of Agenda Bill No. %3&
FISCAL IMPACT:
A summary of the estimated project budget based upon receipt construction bids is as follows:
Construction $ 3,025,000
Construction Contingency (8%) 242,000
Interior Furnishings 150,000
Building Construction Inspection and
Telephone System Installation 10,000
Geotechnical Services 50,000 Architectural Design fees 233,000
Architectural Construction Administration 41,000
Miscellaneous Project Management and Administration
37,000
TOTAL ESTIMATED PROJECT BUDGET $ 3,800,000
Project Appropriations:
1987-88 General Capital Construction Funds $ 300,000
3,500,000 1988-89 Tax Allocation Bond Sale Proceeds
TOTAL PROJECT BUDGET APPROPRIATIONS $ 3,800,000
Engineering Design fees 12,000
during project design and construction
EXHIBITS :
1. Location map.
2. Resolution No.ffe32#accepting bids and awarding a contri
for the construction of the Carlsbad Senior Center i
Carlsbad Unified School District Administrative Comp'
pro j ect .
Resolution No. &fi3d$approving an amendment to the exist
architectural agreement between the City of Carlsbad l
Wolff/Lang/Christopher Architects, Incorporated j
continuing architectural services during the construct
phase of the project.
4. Consultant Agreement.
3.
..
1
2
3
4
5
6
7
8
9
10
11
12
13
l4
15
16
17
18
l9
2o
21
22
23
24
25
26
27
28
0 e
RESOLUTION NO. 138-324
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
CARLSBAD, CALIFORNIA, ACCEPTING BIDS, AND AWARDING A CONTRACT FOR THE CONSTRUCTION OF THE CARLSBAD
SENIOR CENTER AND CARLSBAD UNIFIED SCHOOL DISTRICT
ADMINISTRATIVE OFFICE COMPLEX, PROJECT NO. 3247
WHEREAS, bids have been received by the City
Carlsbad for the construction of the Carlsbad Senior Center
Carlsbad Unified School District Administrative Off ice Compl
Project No. 3247; and
WHEREAS, the low bid received for said project
submitted by Straub Construction, Incorporated in the amount
$3,025,000; and
WHEREAS, there are sufficient funds available in
' Project Account No. 320-810-1840-3247 to award this contract
NOW, THEREFORE, BE IT RESOLVED AS FOLLOWS:
1. That the above recitations are true and correct
2. That the bid of $3,025,000 submitted by Str
Construction, Incorporated for the construction of Carls
! Senior Center and Carlsbad Unified School Distr
Administrative Office Complex, Project No. 3247 is her
accepted.
///
///
///
///
///
///
///
l
1
2
3
4
5
6
7
8
9
10
11 '
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
e 0
3. That the Mayor and City Clerk are here
authorized and directed to execute a contract thereafter.
PASSED, APPROVED AND ADOPTED by the City Council of t
City of Carlsbad at its regular meeting held on the 6th c
of September , 1988, by the following vote, to wit:
AYES: Council Members Lewis, Kulchin, Pettine, Mamaux and La
NOES: None
ABSENT: None [yJd& ,& , /iP
CLAUDE h.yLEWIS, Mayor
ATTEST:
Z, City Clerk
(SEAL)
I
'
I
. “J
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18‘
19
20:
21.
I
22,
z3
24
25
26
27
28
e 0
RESOLUTION NO. 88-325
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
CARLSBAD, CALIFORNIA, APPROVING AN AMENDMENT TO
AN EXISTING AGREEMENT BETWEEN THE CITY OF CARLSBAD
AND WOLFF/LANG/CHRISTOPHER ARCHITECTS, INCORPORATE
FOR ARCHITECTURAL SERVICES DURING CONSTRUCTION
WHEREAS, the City of Carlsbad has previously entered into
agreement with Wolff/Lang/Christopher Architects, Incorpora
for the design of the Carlsbad Senior Center and Carls
Unified School District Administrative Office Complex proje
and
WHEREAS, the City requires the services of said firm dur
the construction phase of said project; and
WHEREAS, a scope of work and fee for services has b
negotiated between the City and said firm.
NOW THEREFORE, BE IT RESOLVED, AS FOLLOWS:
1. That the above recitations are true and correct.
2. That an amendment to the existing agreement betw
City and said architects is hereby approved and the Mayor
City Clerk are authorized and directed to execute s
! amendment. Following signature of this amendment, the C
Clerk is further authorized and directed to forward a copy o
///
///
///
///
///
///
///
///
1
2
3
4
5
6
7
a
9
10
11
12
13
I4 15
16
17
18
19
20
21
22
23
24
25
26
27
28
* 0
this document to Wolf f/Lang/Christopher Architect
Incorporated, 10470 Foothill Boulevard, Rancho, Cucamonc
California, California 91730 and the Municipal Projec
Department.
PASSED, APPROVED AND ADOPTED by the City Council of the Cj
of Carlsbad at its regular meeting held on the 6th day
September , 1988, by the following vote, to wit:
AYES: Council Members Lewis, Kulchin, Pettine, Mamaux and Larson
NOES: None
ABSENT: None
ATTEST:
1 ALE EN R. KUNDTZ, Deputy Z, City City Clerk Clerk
(SEAL)
I
I
a 0 a
I LOCATION MAP
WALNUT AVE
LEGEND
VlcllYrryMAP
N.1 S.
I PROJECT NAM€ CITY OF CARLSBAD SENIOR CITZENS PROJ. NO- EXHl
1 CENTER 8 CARLSBAD UNIFIED SCHOOL DISTRICT 3247 ADMINISTRATIVE OFFICE COMPLEX
e m
AMENDMENT NO. 1 TO AGREEMENT BETWEEN THE CITY OF CARLSBAI:
AND WOLFF/LANG/CHRISTOPHER ARCHITECTS, INCORPORATED FOR
CONTINUING ARCHITECTURAL SERVICES DURING THE CONSTRUCTIOb
PHASE OF THE CITY OF CARLSBAD SENIOR CENTER PROJECT
THIS AMENDMENT NO. 1, made and entered into as of
8th day of August, 1988, by and between the CITY OF CARLSBAC
Municipal Corporation, hereinafter referred to as ttCity, It
WOLFF/ LANG/ CHRIS TOPHER ARCHITECTS, INCORPORATED, hereinaf
referred to as "Consultant. II
RECITALS
WHEREAS, the City of Carlsbad and Wolff/Lz
Christopher Architects, Incorporated, have previously entc
into an agreement on April 5, 1988 for the design of
Carlsbad Senior Center and Carlsbad Unified School Disti
Administrative Office project; and,
WHEREAS, the parties to this agreement desire
continue necessary architectural services for the construci
phase of said project as provided for in Section 6 of c
agreement; and,
WHEREAS, the City has assembled a scope of work
said necessary services to be performed by the consultant du
the construction phase of said project; and,
WHEREAS, the Consultant has formally submittec
proposal to perform the aforementioned requested services; an
WHEREAS, the Consultant possesses the necessary ski
e
-2-
abilities, qualifications, personnel, business and financ
resources, and professional background to provide said serv
to the City; and,
WHEREAS, the City Council of the City of Carlsbad,
this amendment, finds it necessary, desirable and in the pul
interest to proceed with the Consultant to provide necesi
continuing architectural services during the construction pl
of said project.
NOW, THEREFORE, in consideration of these recitals
the mutual covenants contained herein, City and Consul
hereby agree as follows:
1. Consultant shall provide continuing architect
services for City during the construction phase of said pro
in accordance with the terms, conditions, and project scope
work as outlined in attached Exhibit rrA1r which is he
incorporated and made a part of this agreement.
2. City shall pay Consultant in accordance with
fees and costs outlined in attached Exhibit rtA1r on an ho
basis, per the attached fee schedule, not to exceed $39,
City shall pay Consultant appropriate, reasonable, and custo
miscellaneous reimbursable expenses required of Consultant
perform said services as contemplated by the parties to
agreement estimated to be $2,375 as identified in atta
Exhibit "A. I*
e W
-3 -
3. Consultant shall act as City's represental
during the pre-construction, construction, and post-construcl
phases of the project in accordance with attached Exhibit IIA.'
4. All of the provisions of the aforementic
agreement entered into on April 5, 1988, between City
Consultant shall remain in full force and effect.
5. This Amendment No. 1 to the aforementic
agreement between City and Consultant shall be effective on
from the day first above written.
IN WITNESS WHERE, we have hereunto set our hands and seals.
WOLFF/LANG/CHRISTOPHER CITY OF CARLSBAD
ARCHITECTS, INCORPORATED
BY BY
CLAUDE A. LEWIS, Mavor
Title Title
APPROVED AS TO FORM: ATTESTED :
City Attorney City Clerk
(SEAL)
* e .
EXHIBIT IrA"
TO CITY OF CARLSBAD AND WOLLF/LANG/CHRISTOPHER
ARCHITECTSf INCORPORTED AGREEMENT AMENDMENT NO. 1
ZONE I. TIMELINE
- Bidding and Award 42 days I11 - Construction 270 days - Total C/A days 312 days
11. TASKS TIME NTE
- Pre-construction 4 hours $ 34c
conference (1)
44 hours 2,86C - Submittals - Job meetings (45) 225 hours 15,75C - Closeout (2) 58 hours 4,64(
13 , OOc - Zone I11 travel 400 hours
- Clerical 7 0 hours 2,45(
Subtotal 801 hours $39 , 04(
2 x 200 hours (4-RT)
111. REIMBUSRABLES
$ 2,02E - Copying, reproduction, postage 20( - Mileage (3 .22-1/2 cents/mile x (200 x 45)
- Phone-FAX 15(
Subtotal $ 2,37E
TOTAL MAXIMUM NOT-TO-EXCEED $41,26!
IV. BILLING RATES
- Prinicpal/Architect $95.OO/hr - Associates/Architect 80.00/hr - Architect/Project Manager 60.OO/hr - Designer 50.OO/hr - Draftsman 42.OO/hr - Clerical/Technical Support 35.00/hr
*,
Decreed A Legal Newspaper by the Superior Court of Sun Diego County
Moil all correspondence regarding public notice advertising to
North Coast Publishers, Inc. corporate offices: P.O. Box 878, Encinitos, CA 92024 (619) 753-6543
Proof of Publication
STATE OF CALIFORNIA, ss,
COUNTY OF SAN DIEGO,
I am a citizen of the United States and a resident of the county aforesaid;
I am over the age of eighteen years, and not a party to or interested in the above entitlec
I am principal clerk of the printer of the Carlsbad Journal a newspaper of general cit
published twice weekly in the City of Carlsbad, County of San Diego, State of California, ai
newspaper is published for the dissemination of local news and intelligence of a general charc
which newspaper at all times herein mentioned had and still has a bona fide subscription list (
subscribers, and which newspaper has been established, printed and published at regular in
the said City of Carls , County of San Diego, State of California, for a period exceeding one'
----_..- .._____ - ..-I:--- AI-- Afi+e of publication of tl .
ents which must be roperly executed, and
. The provisions of Part7, Chapter 1, of the Cdzfomia Labor Code com- '?d t O; a nd that the mencing with Section 1720 shall d is a printed copy, I apply to the Contract for work
a< - 2. Bidder's Bond Biddersareadvisedtoverifythe regular and entire iSSi issuance ofall addenda and receipt thereof one day prior to bidding. .!t in any supplement tI Submission of bids without ac- '
knowledgment of addenda may be ?'! to-wi ': cause for rejection of bid. Bonds to secure faithful per- fotmnce ofthe work and payment of laborers and materials suppliers : each in an amount equal to one ..... .h1Y' 2.7. ...... tractorshall state hisor her license hundred percent (1Wo) and fifty
' number and ,classification in the Percent (50%). respectively. of the -: . DISTRICT EDUCATION CENTER ' proposal. : ' ' ' Contract price shall be requiredfor i
CONTRACT NO. 3247 Sets of plans, special provisions work on this project i; ' '
obtained at the Purchasing Depart- ' to maintain insurance as specified . ment, City Hall, Carlsbad, Califor- in the contract Any additional cost ,, nia, for a non-refundable fee of ofsaid.insurance shall be included . .W.W per set. in the bid price. Approved by the City Council of right to reject any or all bids and to the city ofcarlsbad. California, by waive any minor irregularity or in;'. Resolution NO. 88-237, adopted on
notarized are: OTICE INVITING. BIDS, 1. Proposal
Sealed bids will be received at ,:, .3. Designation of Subcontractors Finan-
kchi-
CITY OF CARLSBAD SENIOR CENTER CARLSBAD UNIFIED SCHOOL
... . ... The work shall be performed in and Contract documents may be . TheContractorshall berequired '. .August 3. strictconformitywith the specifica- tions therefor as approved by the
.' City Council of the City of Carlsbad on file with the City Clerk Refer-
, fications for full particulars and
i description of the work
'
................. ence is hereby made to the speci- . The City ofcarlsbad reserves the
'
The City of Carlsbad encourages formality in such bids. ' ' the 12th day of July, 1988. the participation of minority and women-owned businesses.
' is made on a proposal form fur- nished by the Purchasing Depart- ment Each bid must be accompa- nied by security in a form and and 1773.1 of the California Labor ' ................................ amount required by law. The bid- ders' security of the second and third next lowest responsive bid- ders may be withheld until the Con- tract has been fully executed. The security submitted by all other un-
turned to them, or deemed void, within(l0)daysaftertheContract is
The general prevailing rate of . pate: July 19. I988 wages for each craft or type ofwork- ' KAREN R. KUNDTZ .................. ,, No bid will be received unless it er needed to execute the Contract Deputyfor ' ; ' shall be those as determined by the Director of Industrial Relations pursuant to the Sections 1770, 1773,
Code. Pursuant to Section 1773.2 of the California Labor Code. a current copy of applicable wage rates is on i
file in the Office of the Carlsbad City Clerk The Contractor to whom the Contract is awarded shall not .
Prevailing rates of wages to all . workers employed by him or her in
ALETHA L RAUTENKRANZ, City Clerk '3 4001: July 27, Aug. 3,1988
successful bidders shall be re-
awarded. Pursuant to the provi-
pay less than the said specified .
the execution of the Contract.
with provisions ofsection 1777.5 of the Califmia Labor Code and Sec-
tmcts Code, "Subletting and Sub- contracting Fair Practices Act."
I Certify under Penalty of PerJUrY that the foregoin!
correct. Executed at Carisbad, Count of an Die
California on -
day of -
Tb&J t,-9 E
-As&iT& , sions Section of 4590). law (Public appropriate Contracts securi- Code sponsible The Prime to Contractor insure compliance shall be re-
' ties may be substituted for any obligatlon required by this notice
City to ensure performance under this contract.
or for any monies withheld by the tiOn 4100 et seq. of the Publie Con- ___ - - ....
Clerk of
#202-2M-12/87