HomeMy WebLinkAbout1988-09-27; City Council; 9662; 2020 Facilities Plan and Phase IV ExpansionAB#_
MTG Q-77-RR
DEPT._§ML
BILLCIPCOF CARLSBAD - AGEN
—l««e
TITLE:
CONSIDER APPROVAL OF ENCINA WPCF YEAR
2020 FACILITIES PLAN AND PHASE IV EXPANSION
O
|
O
RECOMMENDED ACTION:
Staff recommends that Council adopt resolutions approving the Year 2020 Encina
WPCF Facilities Plan and the Phase IV Project and authorize the filing of Notice
of Determination. ft^ §£•- 353
ITEM EXPLANATION:
Facility Plan
The Year 2020 Facility Plan reviews facilities needs and evaluates various
treatment technologies available to meet those needs through the year 2020. The
resulting analysis has defined a Phase IV Project designed to process 36.0 million
gallons per day (MGD) of liquid wastes with solids content equivalent to 38.0 MGD.
The sewer outfall system has been designed to accommodate the 38.0 MGD, providing
a balance with the Encina solids treatment capacity. The plan anticipates
treating 36.0 MGD of flow at the Encina WPCF, 0.75 MGD flow at Leucadia's Gafner
Water Reclamation Plant, and 1.25 at the Shadowridge Water Reclamation Facility.
Solids from the reclamation plants would be treated at Encina.
The proposed Phase IV Expansion will provide Carlsbad an additional 3.52 MGD of
treatment capacity, raising the existing total capacity from 5.72 to 9.24 MGD.
Staff projects that the 3.52 MGD will provide up to 10 years of capacity. The
proposed expansion represents a compromise between agency projected needs and
those presented by the SANDAG Series 7 Population Projections. Total basin
population and demand factors are summarized on the attached Tables II1-2 and
V-6.
Alternatives
The Facilities Plan evaluated five alternatives, as described in the attached
Summary and Recommendation. Three alternatives were designed for full secondary
treatment and two were evaluated as advanced primary under the 301(h) Waiver
Program. The selected alternative extends the existing treatment methods at full
secondary treatment. Elements of the selected S-l alternative are delineated on
the attached Figure X-8.
Outfall Capacity
It should be pointed out that at the completion of the Phase IV expansion, the
capacity constraints will exist in the ocean outfall. Phase IV incorporates the
addition of two outfall pumps and extension of the outfall surge tower which are
designed to increase the existing outfall capacity from 40 MGD to 65 MGD.
Assuming a peaking factor of 2.13, the existing outfall will only accommodate 30.5
MGD of flow. To match the 38 MGD projected, it was necessary to provide flow
storage facilities to store peak flows until outfall capacity is available. This
"Equalization" storage was provided by construction of future aeration basins
and secondary clarifiers (see Figure X-8).
PAGE TWO OF ABI
The Phase V Project will deal with additional construction of flow equalization
facilities or construction of a parallel outfall. Given Carlsbad's requirement
to maintain 5 years of capacity, planning for Phase V should begin as soon as
Phase IV is under construction.
The Year 2020 Facilities Plan fully documents all design assumption and costs
involved in the proposed $49,000,000 project. The plan is available in the City
Manager's office and has been distributed to the libraries for public review.
Environmental Impacts
An Environmental Impact Report has been prepared for the proposed Phase IV
expansion. Leucadia County Water District acting as lead agency held numerous
public meetings and hearings on the document. On August 11, 1988, the Leucadia
Board certified the report as complete. The City of Carlsbad and the other Encina
Agencies as the primary financial backers of the project are considered as
"responsible agencies" under State Law. A responsible agency, prior to approval
of a project, must review and consider the "findings" and give notice of its
approval to the County Clerk. The attached resolutions certify to Council's
review of the E.I.R., its findings and directs submittal of the Notice of the
Determination of the Council's action.
A summary of the E.I.R. findings are attached as Exhibit A to the approval
resolutions. The final E.I.R. has been submitted to the Council under separate
cover.
The E.I.R. has identified two significant impacts that cannot be mitigated:
sludge disposal and growth inducement. The report recognizes that increased flows
will produce increased sludge whose disposal has not been fully resolved and will
likely entail future environmental impacts of an undisclosed nature. The E.I.R.
also stipulates that the proposed project will accommodate growth beyond the Year
2020 Series 7 SANDAG Population Projections. All other impacts are insignificant
or mitigated by the project design.
In approving the E.I.R., Council will be recognizing the Statement of Overriding
Considerations dealing with sludge disposal and growth inducement.
FISCAL IMPACT:
The City will be required to make available to the EAA by March 31, 1989,
$11,278,000 to fund its share of Phase IV Expansion. As reported by the Finance
Director to the Council at its September 6, 1988 meeting, insufficient funds exist
in the Sewer Construction Fund to provide for this obligation. It has been
proposed that the City join with other Encina Agencies to seek bond financing to
raise these funds. In the absence of bond financing, the City would have to
dedicate all available Sewer Construction Funds and borrow an additional $4 to
$5 million from other funds. This action would delay other sewer projects
currently budgeted and impact other unspecified projects.
PAGE THREE OF AB» °l (& (Q £b
Delaying the Phase IV expansion could result in failure to meet Growth Management
Standards, which would stop development and further retard City revenues.
Staff continues to support bond financing for the City's share of the Phase IV
expansion.
EXHIBITS:
1. Table III-2 Sewer Service Area Population Projections.
2. Table V-6, EWPCF Average Daily Flow Projections Using Year 2010 Allocations
(MGD).
3. Figure IV-3 Flow Schematic.
4. Figure X-8, Alternative S-l Phasing.
5. Chapter 11, Summary and Recommendations.
6. Resolution No. &fe- 363 approving Phase IV Project and causing Notice
to be filed with County Clerk.
7. Resolution No. 88- £5 Y approving the EWPCF Year 2020 Facility Plan.
6. Notice of Determination.
TABLE III-2
EWPCF FACILITY PLAN
SEWER SERVICE AREA POPULATION PROJECTIONS
Service
Vista (1)
Carlsbad
Buena
Vista (2)
San Marcos (3)
Leucadia
Encinitas
Totals
SANDAG Series 7
1980
35,300
24,400
5,500
0
20,800
25,000
7,000
118,000
189,440
1990
54,900
56,500
15,900
3,000
45,000
48,000
8,300
231,600
- (1986) (4)
Year
1995
57,400
69,000
22,800
6,100
52,500
61,000
8,900
277,700
263,630
2000
60,600
81,500
24,100
6,100
61,500
74,000
16,600
324,400
293,007
2010
68,100
106,500
29,100
6,100
84,500
92,000
20,200
406,500
353,277
(1) Includes portion of Oceanside served by Vista.
(2) Portion of City of Vista within the Buena Sanitation District service
area.
(3) Includes projected CSUSD populations.
(4) Actual 1986 population. No projections available for 1990.
TABLE V-6
EWPCF FACILITY PLAN
EWPCF AVERAGE DAILY FLOW PROJECTIONS
USING YEAR 2010 ALLOCATIONS (MGD)
Service Area
Vista
Carlsbad
Buena
Vista (1)
San Marcos
Leucadia
Encinitas
Totals
1990
5.62
5.65
0.93
0.30
4.50
4.05
1.24
22.29
1995
5.85
6.79
1.38
0.37
5.40
5.08
1.41
26.28
Year
2000
6.05
7.81
1.78
0.44
6.21
6.01
1.56
29.86
2005
6.24
8.73
2.15
0.50
6.94
6.85
1.70
33.11
2010
7.50
9.24
2.26
0.55
7.54
7.11
1.80
36.00
(1) Portion of Vista within Buena service area.
BUENA OUTFALL
METER
X—+)(CARLSBAD
OUTFALL METER
(FUTURE)
SAN MARCOS
OUTFALL METER
A|R ..„
AIR ,
TO SECONDARY TREATMENT
TO OCEAN
OUTFALL
LEGEND
WA8TEWATER
SLUDGE
RECYCLE FLOW SCHEMATIC
FIGURE IV-3
•ENCINA WPCF FACILITY PLAN-
CHAPTER II
SUMMARY AND RECOMMENDATIONS
SUMMARY
SERVICE AREA. The Encina service area is located in the northwest
portion of San Diego County, and covers approximately 120 square
miles. The Encina Water Pollution Control Facility (EWPCF) serves the
Cities of Carlsbad and Vista, the Buena Sanitation District, the San
Marcos County Water District, the Leucadia County Water District, and
the Encinitas Sanitary District. The facility is owned and operated
through a joint powers agreement.
Each member agency has projected wastewater flows to the Encina
WPCF through the year 2010. The year 2010 total wastewater flow was
estimated at 41.40 M6D. This flow would serve a population greater than
projected by SANDAG Series 7. For this reason, about 87 percent of the
agency requested flow, 36.0 MGD, will be used as the basis of facility
sizing to better coincide with SANDAG projections. This flow would
serve an estimated 355,000 people. Using a decreasing rate of increase
model, the year 2015 and 2020 flows would be 38.04 MGD and 39.61 MGD,
respectively. These projections have been used as the basis for
establishing future facility needs.
EXISTING FACILITIES. The EWPCF incorporates preliminary, primary,
and secondary treatment processes. Solids removed during treatment,
solids disposed of by septage haulers, and solids discharged from up-
II-l
\
stream reclamation plants are stabilized and dewatered. Currently, the
sludge is hauled to a San Diego County landfill. The treated wastewater
is disposed of through an ocean outfall to the Pacific Ocean. A portion
of the flow is reclaimed and reused throughout the plant.
Wastewater Treatment. The treatment facilities are well operated
and maintained. They are capable of meeting the existing waiver treat-
ment requirements or secondary treatment requirements. The nominal
capacity of the plant is 22.5 million gallons per day (MGD). Most of
the unit processes are capable of treating loadings beyond this rate.
The capacity of individual units has been taken in account in projecting
future needs. The peak hydraulic capacity of interconnecting channels
and piping has been sized for a flow of at least 90 MGD.
Sludge Disposal. The stabilized sludge is dewatered by belt pres-
ses before disposal. The presses concentrate the sludge to about 16
percent solids by weight. This level exceeds State requirements of 15
percent for landfill disposal. However, a higher cake solids of 18 to
20 percent may be desireable once the preferred solids residual program
is implemented. This program would minimize landfill disposal. The
sludge would be composted, and the compost could be recycled as a soil
amendment. A solids content of 16 precent could increase composting
costs. The EWPCF staff is continuing evaluations in an attempt to
achieve a higher cake with the existing equipment.
Ocean Outfall. The ocean outfall extends 7,800 feet into the
Pacific Ocean. The outfall discharges at a mean depth of 150 feet. The
II-2
ultimate hydraulic capacity of the outfall is 65.0 MGD. A new outfall
or effluent flow equalization would be required within the planning
period.
At highest recorded tide, 32.7 MGD of effluent from the EWPCF can
flow by gravity into the outfall. At higher flow rates, the effluent is
pumped. There are two pumps, each rated at 40.5 MGD. Allowing one unit
as standby, an additional pump would be required in the near future.
Cogeneration Facilities. The EWPCF incorporates both electrical
and mechanical cogeneration. There are 3 engine-generators rated at 475
kilowatts each. They are fueled by natural gas purchased from the San
Diego Gas and Electric Company (SDG&E). As dictated by air pollution
control permits, only two units can. be operated at a time. In 1986, an
average of 436,850 kilowatt hours (KWHR) per month of electricity was
produced for use within the plant versus only 1,920 KWHR per month
purchased from SDG&E. The average cost of production is estimated at
$0.098 per KWHR including an allowance for facility replacement and
$0.087 without the allowance. A detailed cost breakdown is shown in
Chapter IV. The unit cost would decrease as the plant's electrical
demand increases. The generators are currently operating at about 55
percent of capacity. If all power were purchased from SDG&E, the 1986
cost would have averaged $0.10 per KWHR.
There are two engine driven blowers that comprise the mechanical
cogeneration facilities. Each blower is rated at 10,000 cubic feet per
minute. The air is required for the activated sludge process, grit
II-3
! chamber agitation, and channel agitation. The engines are fueled by
digester gas, a product of the anaerobic digestion stabilization pro-
; cess. Only one engine may be operated at a time due to APCD permit
limitations. In 1986, 173,000 cubic feet of digester gas was used on an
average daily basis. At residential gas rates, the value of this
resource is estimated at $190,000 per year.
Heat is recovered from the engine jacket water and exhaust sys-
tems. The recovered heat is used for two purposes; one to heat influent
sludge to the anaerobic digesters and two, to heat and cool buildings.
The use of this heat further offsets the need to purchase electricity
and natural gas for space conditioning. Using the engines as a heat
source, the need for hot water boilers is eliminated.
WASTEWATER FLOWS AND LOADINGS. Wastewater flows and characteristic
records have been analyzed for the past 5 years of record. Per capita
flows and loadings, in conjunction with the operation of upstream re-
clamation plants and septage haulers, have been determined. These were
used to project future conditions.
Wastewater Flows. The 1986 average daily flow rate to the EWPCF
was 16.4 MGD. This represents 73 percent of the nominal plant capa-
city. Upstream reclamation flows, which are discharged to the ocean
outfall through the fail safe line, averaged 1.4 MGD.
Overall Encina per capita flows have averaged between 94 and 102
gallons per capita per day. This includes the contribution from
commercial and industrial users. The relative contribution from these
II-4
V___ _y
users would not be expected to change in the future. A per capita flow
of 100 gallons per capita per day (gpcd), which is typical for other
agencies, has been used to project future flows for all the agencies
except the Buena Sanitation District and the City of Vista. The Buena
Sanitation District has requested a future per capita rate of 137
gpcd. The increase is a result of a projected large proportional
contribution from commercial/industrial dischargers. Vista requested a
future per capita flow of 115 gpcd, based on General Plan land use
designations. Taking into account the future operation of the
reclamation plants, projected average daily flows to the EWPCF are:
Year Flow (MGD)
2000 29.86
2010 36.00
2020 39.61
Bar screen, grit chamber, and outfall capacity is based on peak wet
weather flow. A peaking factor of 2.0 for the EWPCF is recommended as a
basis of scheduling improvements. This factor should be continually
evaluated as major storm events occur. Peak outfall flows are projected
to be:
Year Flow (MGD)
2000 61.72
2010 74.00
2020 81.22
The flow includes the discharge from the upstream reclamation
plants to the failsafe line. The flows from the Shadowridge and Gafner
satellite plants are assumed to be equalized, thereby eliminating any
need of a peaking factor from these sources.
II-5
Wastewater Loadings. Loadings have been evaluated for biochemical
oxygen demand (BOD) and suspended solids (SS). Sources include the
normal wastewater contribution, septage, and the sludge produced at the
upstream reclamation plants. The sludges removed are discharged back to
the sewer for stabilization at the EWPCF.
Per capita loadings of 0.17 and 0.18 pounds per capita per day for
BOD and suspended solids respectively have been determined from histori-
cal records. These values are similar to those reported for other
agencies. They do not include septage or satellite sludge loadings.
In 1986, septage represented 2 percent of the total BOD load and 6
percent of the total suspended solids load. The liquid volume of 11,000
gallons per day is not significant. Seventy percent of the septage
comes from outside the service area.
The sludges removed from the upstream satellite plants are returned
to the sewer for stabilization and dewatering at the EWPCF. The charac-
teristics of the sludges are similar to those removed at the EWPCF.
Sludge from the upstream plants made up about 9 percent of the 1986
suspended solids loadings and 6 percent of the BOD loading.
Future influent concentrations are expected to decrease somewhat as
the relative contribution of high strength septage and reclamation
solids decreases.
WATER QUALITY AND EFFLUENT LIMITATIONS. The existing National
Pollutant Discharge Elimination System permit limits, established joint-
ly by the Environmental Protection Agency and Regional Water Quality
II-6
Control Board, San Diego Region are based on the 1982 California State
Water Quality Control Plan for Ocean Waters referred to as the Ocean
Plan. The Ocean Plan requires 75 percent suspended solids removal and
maintenance of the receiving water quality at levels needed to protect
designated beneficial uses. The current permit was issued under Section
301(h) of the Federal Clean Water Act which provides for a waiver from
secondary treatment. Secondary treatment would require at least 85
percent removal of BOD and suspended solids and that concentrations of
either constituent not exceed 30 milligrams per liter. Five of the
member agencies have adopted a policy to treat to the secondary
treatment level once reasonable and reliable sludge disposal is
available.
The EWPCF has met all discharge requirements under the present
permit except for one suspended solids violation in February 1986 during
a storm event. This would not be expected to reoccur.
The EWPCF is capable of meeting probable future discharge require-
ments, assuming that the source control program will continue to
maintain the low level of heavy metals and toxic compounds discharged
into the collection system. However, due to the dynamic behavior of
regulations, prediction of future numerical discharge requirements is
very difficult. Present concerns regarding future discharge include
required disinfection of treated effluent, and treatment of discharged
volatile organic compounds from the treatment process. These and other
changes in regulations could result in additional cost and land
II-7
D-*••£-
requirements. Additional treatment facilities would be needed beyond
22.5 MGD of flow.
ALTERNATIVE ANALYSIS. Five alternatives were identified that would
be capable of meeting discharge requirements at future flows. Three
would meet secondary treatment requirements. Two were evaluated for
achieving the existing waiver conditions. The alternatives have been
designated as:
Secondary Treatment Description •
S-l Activated Sludge
S-2 Series Trickling Filter/Activated
Sludge
S-3 Parallel Trickling Filter/Activated
Sludge
California Ocean Plan
(Waiver) Description
W-l Primary Treatment/Activated
Sludge
W-2 Advanced Primary/Activated
Sludge
Alternative S-l would consist of expanding the existing activated
sludge process with similar units. Alternative S-2 would utilize bio-
towers to reduce the BOD loading prior to final treatment in the acti-
vated sludge process. The blotowers would offset aeration require-
ments. The third Alternative S-3 would use biotowers in parallel with
the existing activated sludge process. The biotowers would be sized to
produce an effluent with the same quality as the activated sludge.
For the waiver condition, Alternative W-l would consider operating
the EWPCF in the mode as currently used. Only the preliminary, primary,
11-8
and solids handling units would need expansion. The existing activated
sludge processes would be of adequate capacity to provide enough eff-
luent to blend with primary effluent to meet 75 percent suspended solids
removal through the year 2020. Alternative W-2 would use the addition
of ferric chloride and polymer to the primary clarifiers. The chemical
addition would enhance primary clarifier performance to produce an
effluent meeting the waiver requirements. The activated sludge process
would be operated as needed for on-site reuse or potential off-site
reclamation.
Comparative costs for the alternatives are summarized in Table II-l
for year 2010. Total capital costs as well as annual capital,
operation, and maintenance costs are shown. From a total annual cost
standpoint, Alternatives S-l and W-l appear the best alternatives for
the two treatment scenarios. They have other advantages as to: 1)
compatibility with existing facilities; 2) site master planning; 3)
aesthetics, and 4) ability to reclaim effluent for future potential off-
site use.
Cogeneration Facilities. The cogeneration facilities have been
evaluated to identify the most effective means of operation to minimize
energy costs. The evaluation considered modifying air pollution con-
trols to use more digester gas in the engines. Proposed changes in
SDG&E rate structures were considered. Sale of electricity, digester
gas, and waste heat were evaluated. Continued use of the cogeneration
facilities appears to be cost-effective when compared to purchase of
11-9
\
TABLE II-l
EWPCF FACILITY PLAN
ALTERNATIVE COST COMPARISON
YEAR 2010
Alternative
Secondary
S-l
S-2
S-3
Waive r
W-l
W-2
Estimated
Project
Cost ($)
33,724,000
45,035,000
34,453,000
13,101,000
13,468,000
Estimated
Annual Capital
Cost ($/Yr)
3,786,000
5,056,000
3,868,000
1,471,000
1,512,000
Comparative
O&M Cost
($/Yr)
3,053,500
3,360,400
3,020,500
2,523,500
2,689,000
Total
Annual
Cost
($/Yr)
6,839,500
8,416,400
6,888,600
3,994,500
4,201,000
Relative
Ranking
1
3
2
1
2
(1) ENRLA 5500
11-10
•- v\
electricity from SDG&E. The continued favorable natural gas rates as
required by PURPA for cogeneration facilities has a bearing on the
economics. New air pollution controls should be considered that would
allow full use of digester gas in all of the engines.
The EWPCF is expected to produce excess heat, recovered as hot
water, from the cogeneration facility. It appears that it would be
beneficial to use the hot water for heating and air conditioning at a
future, contiguous private development. The heat could be sold at a
favorable rate while providing a net income to the EWPCF.
RECLAMATION. Four of the member agencies own satellite reclamation
plants. They are:
Owner Facility Capacity
San Marcos County Water Meadowlark Water 2.0 MGD
District Reclamation Plant
Buena Sanitation District Shadowridge Water 1.25 MGD
(planned)
Reclamation Plant 1.00 MGD
(presently)
Leucadia County Water Gafner Water 0.75 MGD
District Reclamation Plant
City of Carlsbad Lake Calavera Hills Water 1.2 MGD
Reclamation Plant
A portion of the total effluent is reclaimed, and the remainder is
disposed of through the fail safe line to the ocean outfall. The Lake
Calavera Hills Plant is not currently in operation.
Secondary effluent is reused within the EWPCF for odor scrubbers,
general washdown, engine cooling water, and landscape irrigation.
11-11
Current use is 3.5 MGD. This is expected to increase to 4.4 MGD as
additional facilities are constructed. The cost for disinfection,
pumping, and facility replacement for on-site reuse is estimated to be
$231 per million gallons. If potable water were used for the above
purposes, costs would be about four times higher since potable water
costs $1,070 per million gallons at present.
Until recently, the JAC policy was that reclaimed effluent for uses
offsite would be provided by one of the four existing satellite
plants. For comparative purposes, the cost has been developed for a 2.0
MGD, tertiary reclamation plant at the EWPCF. The effluent would be
acceptable for unrestricted reuse as defined by Title 22 of the Califor-
nia Administrative Code. The cost, including capital and operation and
maintenance has been estimated at $1,460 per million gallons to produce
Title 22 quality water for unrestricted use. This does not include the
cost for treatment to secondary, pump stations, distribution pipelines,
or irrigation systems nor does it reflect the offsetting revenue if
reclaimed water were sold to users. Compared to present potable water
costs, additional reclamation is not currently cost-effective. This
condition could be affected by the availability of future water supply
in Southern California. Water supply limitations could favor increased
wastewater reclamation in the future.
RECOMMENDED PLAN. Five of the six member agencies have passed
resolutions to return to full secondary treatment once permanent sludge
disposal facilities are in place. For comparison two recommended plans
11-12
\
have been described, one for the waiver and one for secondary
treatment. Each would be capable of treating flows through the year
2020. The 2020 facility needs are summarized below.
Preliminary Treatment. Preliminary treatment needs would be iden-
tical for the two effluent quality scenarios. One additional bar screen
would be installed in the existing channel, and two additional grit
chambers would need to be constructed.
Primary Treatment. Six additional primary clarifiers would be
needed for both scenarios* These would be located west of the existing
units and would provide sufficient treatment capacity to ultimate
year. Common wall construction would be utilized. For the waiver mode,
no additional liquid treatment processes would be built. The existing
activated sludge processes would be of sufficient capacity to provide an
overall blended effluent meeting the waiver requirements. For secondary
treatment, all of the primary effluent would be treated further by an
expanded activated sludge process.
Activated Sludge. For the waiver, about half of the primary ef-
fluent would receive secondary treatment. The remaining primary ef-
fluent and activated sludge effluent would be blended prior to dis-
charge. The blend would meet the requirements of the California Ocean
Plan. No expansion of the existing activated sludge processes would be
needed, however, one additional DAF thickener is required to handle the
increase in solids loading.
11-13
-W
For secondary treatment, one aeration basin, a motor driven blower,
four secondary clarifiers, and associated return and waste sludge pumps
would be needed. Two dissolved air flotation thickeners would be con-
structed in addition to the two existing tanks. The waste activated
sludge would be thickened prior to digestion.
Sludge Stabilization. Sludges removed from the primary clarifiers
and dissolved air flotation thickener would be stabilized by anaerobic
digesters. One additional digester would be needed for the waiver, and
two new units would be needed for secondary treatment. The size should
match existing Unit No. 4 built during Phase III.
Sludge Dewatering. Digested sludge would be dewatered by belt
filter presses then hauled to a landfill for disposal. Two additional
belt presses would provide dewatering capacity for the nonwaiver
condition, while one additional belt press would be needed for the
waiver condition. The addition of the belt presses requires the
expansion of the existing dewatering building. The expansion would
provide room for a total of four future belt presses.
Odor Control. Odor control facilities are provided for the
screenings building, and dewatering building. With the addition of a
future grit chamber and channels to the screenings building no
additional odor control equipment is expected to be required. For the
dewatering building expansion, additional odor scrubber facilities may
be required. This would be verified pending planned improvements to the
existing exhaust system. Odor control facilities would be master
11-14
'*"%,
planned for the activated sludge process. They would be provided only
if a definite need is demonstrated.
Miscellaneous Facilities. In addition to the treatment facilities,
the existing Operations Building would need to be expanded. The main-
tenance storage building will need to be relocated or replaced when the
second new digester is built under the secondary treatment scenario.
Other improvements identified include programmable controller/computer
improvements, air pollution control modifications to the existing co-
generation engines.
Ocean Outfall/Effluent Flow Equalization Storage. The ocean
outfall capacity would be increased to 65.0 MGD by the addition of two
effluent pumps and extension of the surge tower. Once peak flows
approach the capacity of the existing outfall, effluent flow
equalization or a second ocean outfall paralleling (at least in part)
the first would be required. Additional effluent capacity is projected
to be needed by the year 1994 at a peaking factor of 2.5.
Using effluent equalization, a basin volume of 21 MGAL would be
required for ultimate year, and would provide equalization for a peaking
factor of 2.5. This peaking factor should be further refined through
future storm monitoring and evaluations. During the interim period
through to the year 2010, effluent equalization would be provided,
assuming a 2.0 peaking factor, by the construction of an extra secondary
clarifier and aeration basin beyond treatment needs.
11-15
Costs. Total project costs through the year 2020 are estimated to
be:
Unit I
Treatment
Unit J Ocean
Outfall/
Equalization
$41,975,000 $29,394,000
$22,295,000 $29,394,000
Total
$71,369,000
$51,689,000
S-l, Secondary Treatment
W-l, Waiver
The costs are at today's level (ENRLA 5500) and include allowances
for engineering and contingencies. For secondary treatment, the Unit I
capital cost equates to $2.45 per gallon of capacity at the 2020 projec-
ted flow. This is less than the Phase III/IIIA, Unit I cost of $2.75
per gallon. Phase III/IIIA costs were escalated to ENRLA 5500. Phase
III/IIIA did include many facilities that would be large enough for the
year 2020 flows. However, the value of 5 existing primary clarifiers
and Digesters 1 through 3 was not included in the comparative figure.
PHASING. The first phase of construction, Phase IV, would serve
treatment needs through the year 2010 (36.0 MGD). At that time, the
next phasing of unit processes, Phase V, would need to be constructed.
Phase V would handle projected flows to at least the year 2020 (39.61
MGD). With the exception of the aeration basins and digesters
sufficient treatment capacity would be provided during Phase V for the
ultimate design flow (45 MGD).
Phase IV would include the following major treatment units.
11-16
v>
Needed Units in Each Alternative
Phase IV
Unit Process Waiver Secondary
Bar Screen 1 1
Grit Chamber 1 1
Primary Clarifiers 4 4
Aeration Basins 0 1
Blower 0 1
Secondary Clarifiers 0 3
DAF Thickeners 0 1
Digester 1 2
Belt Presses 0 2
In addition, Phase IV would include two new effluent pumps
extension of the surge tower, and provision for interim effluent flow
equalization. Initially, flow equalization would be provided by
construction of an additional fourth aeration basin and eighth secondary
clarifier. These would serve as the needed equalization volume until
needed for treatment after the year 2010. Dedicated equalization or a
parallel outfall would then be needed. These additional interim
equalization units are not included above.
Estimated project costs for each scenario excluding permanent
disposal facilities are: ;
Phase IV I
Waiver $24,035,000
Secondary $48,792,000
These include both Unit I and J and provide an allowance for engi-
neering and contingencies. The costs have been escalated to the mid-
point of construction.
SCHEDULE. The Phase IV schedule would include separate design and
construction contracts for the treatment plant and ocean outfall
facility expansion, Units I and J, respectively. Key dates are:
11-17 jj.
J
Unit I Unit J
Begin Design February 1988 September 1987
Advertise for Bids April 1989 June 1988
Begin Construction August 1989 September 1988
Complete Construction August 1991 August 1991
Planning for separate Phase V construction would not need to be
started until 2007.
Based on the schedule, a cash flow has been prepared for Phase
IV. The projected costs, by fiscal year are given below:
Combined Approx.
Fiscal Year Phase IV % of Total
1987/88 904,000 2
1988/89 2,788,000 6
1989/90 20,858,000 43
1990/91 22,576,000 46
1991/92 1.666,000 3
Totals 48,792,000 100
Most of the capital would be required in fiscal years 1989/90 and
1990/91. The above cash flow is for secondary treatment, and the costs
are escalated to midpoint of construction.
COST ALLOCATION. Costs have been allocated among the member
agencies. New ownership percentages have also been determined. The
allocations have taken into account:
1) Existing ownership;
2) Year 2010 needs for both Units I and J;
3) Balancing of future needs to future ownership;
4) Reflection of projected solids loading from upstream
reclamation plants;
11-18
\
and 5) Effective credits and buyins reflecting revised ownerships.
The methodology establishes a system for future capacity and cost
adjustments.
Projected ownerships and costs are:
Ownership
Unit I Solids
Unit I Liquid
Agency
Vista
Carlsbad
Leucadia
San Marcos
Buena
Encinitas
(%)
22.35
25.68
19.75
20.96
6.26
5.00
(MGD)
8.05
9.24
7.11
7.54
2.26
1.80
and Unit J
(%)
21.05
24.19
20.78
19.74
9.53
4.71
(MGD)
8.05
9.24
7.86
7.54
3.51
.1.80
Cost
($1,000)
($)
5,020
11,278
12,898
11,902
6,147
1,547
(%)
10.29
23.11
26.44
24.39
12.60
3.17
Totals 100.00 36.0 100.00 38.0 48,792 100.00
It is anticipated that Encinitas' need will decrease once their General
Plan is adopted. Actual cost by agency will be based on the final
engineer's estimate following completion of Phase IV construction.
RECOMMENDATIONS
Existing Facilities
1) Further evaluate the effect of dewatered cake solids content
on costs of the preferred solids disposal alternative. New
belt presses capable of producing drier cake may be
warranted. Replacement of existing presses may also be
warranted.
Flows and Loadings
2) Continue monitoring of the wet weather peaking factor to
better define the timing of outfall facilities. A minimum
peaking factor of 2.0 is recommended.
11-19
J
o
Water Quality and Effluent Limitations
3) Continue testing activated sludge effluent for both total and
carbonaceous BOD. If secondary permit is issued, apply for a
revision in the NPDES permit allowing nitrification inhibited
BOD tests if nitrogenous oxygen demand results in total BOD
values exceeding 30 mg/1.
4) Establish policy restricting the use of the EWPCF for disposal
of wastewater as part of hazardous waste cleanups. Such
disposal would be subject to the Resource Recovery and Conser-
vation Act requirements if brought into the plant via truck or
designated pipeline, and could impair the effluent and sludge
quality for reclamation and resource recovery.
5) Maintain aggressive pretreatment program in service area.
6) Monitor regulations under review (Proposition 65, Ocean Plan,
Air Quality) to identify early on additional facilities
required.
Energy Utilization
7) Modify the existing engine air pollution control devices to
allow full digester gas utilization. This would probably be
accomplished by demonstrating performance to the Air Pollution
Control District initially on one engine.
8) Continue efforts with SDG&E and the Public Utilities
Commission to assure that future utility rates are fair to the
EWPCF.
9) Implement other energy utilization recommendations summarized
in Chapter VII.
Reclamation
10) Establish policy that would maintain the total dissolved
solids of the EWPCF effluent at 1,000 mg/1 or less. This
quality would allow for future offsite reclamation.
11) Continue existing on-site reclamation of secondary effluent.
On-site reclamation is less costly as compared to purchased
potable water.
12) Further review JAG policy as to the desireability and timing
of providing reclamation treatment at the EWPCF for offsite
uses in concert with the County Water Authority reclamation
effort in the Encina service area.
11-20
Recommended Plan
13) Continue designing Phase IV, Unit J on an expedited schedule
to assure that there is sufficient outfall pumping capacity in
case there occurs at the same time a high tide and peak wet
weather flow when one unit is down for maintenance.
14) Phase IV design, Unit I includes secondary treatment
facilities. Actual construction would be dependent on the
future discharge requirements (waiver versus secondary).
15) Undertake a comprehensive building program analysis to define
the best use of the existing Operations Building and to ex-
plore the need for a future Administration Building. This
should be done as part of or prior to Phase IV design.
Effluent Equalization
16) Continue evaluation of equalization as a cost-effective
alternative to a new ocean outfall.
17) Work to limit future peaking factors to 2.0 by controlling
sources of inflow.
18) Pursue the acquisition of off-site land in order to provide
space for the master planned 21 MGAL total effluent
equalization storage.
19) Construct the fourth aeration basin and the eighth secondary
clarifier during the Phase IV expansion in order to utilize
the excess treatment basins for equalization storage to
postpone the requirement for a separate dedicated storage
basin or second parallel outfall.
20) Construct fourth aeration basin and eighth secondary clarifier
basins to operate on a gravity fill type mode.
Septage
21) Evaluate fee structure to reflect solids management program
costs.
11-21
J
NOTICE OF DETERMINATION
TO: Office of Planning and Research
1400 Tenth Street, Room 121
Sacramento, GA 95814
XX Qounty -Clerk
County of San Diego
1600 Pacific Highway
San Diego, CA 92101
FROM: (Public Agency) ...City of Carlsbad on behalf of
Encina Hater Pollution Control Facility
6200 Avenida Encinas
Carlsbad, CA 92009-0171
SUBJECT: Filing of Notice of Determination in compliance with Section 21108 or
21152 of the Public Resources Code.
Encina Water Pollution Control Facility Expansion
Project Title
88041308 Betty Meyer (619) 438-3941
State Clearinghouse Number
(If Submitted to Clearinghouse)
6200 Avenida Encinas, Carlsbad, CA
Contact Person Area Code/Number/Extension
Project Location
Expansion of existing wastewater treatment plant to meet planned growth in the
Project Description
Encina service area.
City of CarlsbadThis is to advise that the
(B_$6iX#$&M#X&# Responsible Agency)
has approved the above described project on 9-27-88 and has made the follow-
(Date)
ing determinations regarding the above described project:
1. The project X will, will not have a significant effect on the
environment.
2. X An Environmental Impact Report was prepared for this project
pursuant to the provisions of CEQA.
A Negative Declaration was prepared for this project pursuant to
the provisions of CEQA.
3. Mitigation measures X were, were not made a condition of the ap-
proval of the project.
4. A statement of Overriding Considerations _X_was, was not adopted for
this project.
This is to certify that the final EIR with coranents and responses and record of
project approval is available to the General Public at:
Encina WPCF, 6200 Avenida Encinas, Carlsbad, CA 92009
Date Received for Filing and Posting at OPR
Signature (Public Agency)Title
Revised March 1986
RESOLUTION NO. 88"- 35.>**r
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CARLSBAD
APPROVING THE PHASE IV PROJECT AND CAUSING NOTICE
TO BE FILED WITH THE COUNTY CLERK
WHEREAS, the City of Carlsbad is a party to a Joint Powers
Agreement, commonly Known as the Basic Agreement for the
ownership, operation and maintenance of'the Encina Joint Sewer
System; and
WHEREAS, there exists a need to increase the capacity of
said Joint Sewer System to serve the future needs of inhabitants
of the City of Carlsbad as well as the future inhabitants of the
areas served with sewer service by the Leucadia County Water
District, the City of Vista, the San Marcos County Water
District, the Encinitas Sanitary District and the Buena
Sanitation District; and
WHEREAS, pursuant to the California Environmental Quality
Act, the Leucadia County Water District has been, and still is,
acting as the Lead Agency on behalf of the Encina Joint Powers
for said Phase IV Project; and
WHEREAS; on August 11, 1988, the said Leucadia County
Water District completed the Environmental Impact Report process
and certified said Report as complete, and
WHEREAS, in considering and evaluating the said
Environmental Impact Report, the Leucadia County Water District
made certain findings as required by law, copies of which are
attached hereto and incorporated herein by reference; and
WHEREAS, the City of Carlsbad is a "responsible agency" as
defined in Section 21069 of the California Public Resources Code;
and
WHEREAS, V«*ihe City of Carlsbad has renewed and considered
the "findings' of the Final Environmental Impact Report and
desires to approve the Phase IV Project and give notice of such
approval to the County Clerk of the County of San Diego; and
WHEREAS; the Joint Advisory Committee to the Encina Joint
Powers has heretofore unanimously approved the Phase IV Project
after considering the "findings" of the Environmental Impact
Report caused to be prepared and certified by the Leucadia County
Water District; and
WHEREAS, upon completion thereof the Phase IV Project will
increase the treatment capacity of the Encina Water Pollution
Control Facility from 22.5 million gallons per day to 36.0 MGD
liquid and 38.0 MGD solids by the year 2010.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
CARLSBAD AS FOLLOWS:
Section 1. The City of Carlsbad hereby approves and adopts
the findings contained in Exhibit "A" attached hereto and
incorporated herein by reference.
Section 2. The City of Carlsbad hereby approves the Phase IV
Project.
Section 3. The officers and employees of the City of
Carlsbad are hereby authorized and instructed to prepare or cause
to be prepared a Notice to the County Clerk of the County of San
Diego within five days after adoption of this resolution that the
City of Carlsbad approves the Phase IV Project, and intends to
carry out the Project together with the other five (5) member
agencies of the Encina Joint Powers, that the Project will have a
significant impact on the environment and that an Environmental
impact Report fw the Project has been cer1s*£ied as complete by
the Leucadia County Water District; and that said Environmental
Impact report is available to the general public.
PASSED, APPROVED, AND ADOPTED at a regular meeting of the
City Council on the 27th day of September , 1988, by the
following votes, to wit:
AYES: 5 NOES: None „ ABSENT: „ None
JLAUDE A.TLEWIS,Mayor
ATTEST:
ALETHA L. RAUTENKRANZ, City Clerk
^CANDIDATE FINDINGS AND STATEMENT
OF OVERRIDING CONSIDERATION
Encina Water Pollution Control Facility Expansion
SCH No. 2304130$
The California Environmental Quality Act (CEQA) 'requires that no public agency shall
approve or carry out a project for which a Final Environmental Impact Report (EIR)
identifies one or more significant effects thereof, unless such public agency makes one or
more of the following findings:
(1) Changes or alterations have been required in,
or incorporated into, such project which rrudgate or
avoid the significant environmental effects thereof as
identified in the completed environmental impact
report
(2) Such changes or alterations are within the
responsibility and jurisdiction of another public
agency, and such changes have been adopted by
such other agency or can and should be adopted by
such other agency.
(3) Specific economic, social, or other considera-
tions make infeasible the mitigation measures or
project alternatives identified in the environmental
impact report
(Section 21081 of the California Environmental
Quality Act)
CEQA further requires that, where the decision of the public agency allows the occurrence
of significant effects which are identified in the Final EIR but are not at least substantially
mitigated, the agency shall state in writing the specific reasons to support its action based
on the Final BIR and/or other information in the record (Section 15093 of the CEQA
Guidelines)..
-19-EXHIBIT A
FINDINGS
The following findings are made relative to the conclusions and recommendations of the
Final EIR for the Encina Water Pollution Control Facility (EWPCF) expansion
(SCH No. 87042206). These findings have been prepared pursuant to Section 21081 of
the California Public Resources Code and Sections 15091 and 15093 of the California
Administrative Code.
A. The member agencies of the Encina Joint Powers, having reviewed and considered
the information contained in the Final EIR and record for the EWPCF expansion, find that
the following changes or alterations are being required in, or have been incorporated into
the project, which mitigate or avoid the significant environmental effects identified in the
EIR. Specifically:
Land Use
Impacts: The project site is designated for public utilities use in the City of
Carlsbad General Plan, with wastewater treatment identified as the primary onsite
use by virtue of a General Plan Amendment Because of this designation and the
fact that all proposed expansion facilities would be within the existing EWPCF
site, no significant land use impacts are expected as a result of the proposed
project
A number of offsite facilities are generally discussed in relation to the proposed
project, including a new ocean outfall or flow equalization structure, and a sludge
reuse/disposal facility. All of these facilities could potentially impact offsite land
uses through construction and operation activities.
Findings: The EWPCF will obtain and comply'with all pertinent federal, state, and
local discretionary and non-discretionary permits associated with the proposed
expansion. This will allow implementation of the proposed project without
t
significantly affecting land use designations or character in the project site vicinity.
No offsite structures are specifically proposed for the current EWPCF expansion.
Construction of a new ocean outfall, flow equalization structure, or sludge
reuse/disposal facility would require the preparation of a site-specific
-20-
environmental analysis to identify potential impacts related to land use and other
appropriate resource values.
Ocean Water Quality and Oceanography
Impacts: Both the proposed project and waiver scenario alternative would result in
the increased discharge of effluent. On the basis of current monitoring data,
however, it is not expected that this increased discharge would have significant
impacts to ocean water quality in the zone of initial dilution (ZID), the
accumulation of organic material, or the direction of deposition in the area of
discharge. Increased discharge could affect the rate of deposition, although the
interaction between flow rates, mass load, and currents will ultimately determine
the potential for deposition.
Bacterial loads in the discharged effluent would likely be maintained at existing
levels or reduced slightly under full secondary treatment, due to the combined
effects of higher treatment levels and increased effluent quantities. Under the
waiver scenario, total bacterial content in the discharged effluent would increase
due to higher flows. It is possible that there will be a minor but increased risk of
permit exceedence for bacterial content in the discharged effluent, particularly
during the winter months.
The potential for viruses will increase due to population growth; however, the
potential risk from this increase cannot be identified at the present time and with the
existing monitoring program. There would be an increased potential for aerosol
dispersion of viruses in the surf zone and nearshore zone; however, this mode of
transmission is still under study and no conclusions should be drawn at the present
time.
Findings; Adherence to appropriate regulations and requirements would reduce
impacts related to effluent discharge below levels of significance. This would
include restrictions on the quality of both effluent (NPDES permit) and influent
(source control program) associated with the EWPCF. Viruses will be removed to
a degree in the secondary process but will not be removed completely. Existing
data has not identified significant adverse effects associated with viral loading in
-21-
effluent discharge, although no regulatory standards have yet been developed and
methodology is not well established.
Marine Bioloyv
Impacts: No significant impacts to the wide diversity of marine organisms and
habitats in the area of discharge would be anticipated from either the proposed
project or waiver scenario.
Findings: The proposed project would increase both the total quantity of effluent
discharge and the associated level of treatment, resulting in no significant impacts
to the marine environment. The waiver scenario would increase the total quantity
of pollutants emitted due to increased discharge volumes. This would not be
expected to result in significant impacts to marine biological resources because of
existing discharge quality and monitoring requirements.
Public Health
Jmpacty Neither the proposed project or the waiver scenario would be expected to
result in significant impacts related to public health concerns, assuming pertinent
regulatory guidelines are met.
Findings; The proposed project would likely maintain or slightly reduce the
existing levels of bacteria in the discharged effluent, due to increases in both
treatment levels and discharge volumes. Bacterial discharge levels for the waiver
scenario would increase somewhat because of greater effluent volumes, and would
increase the potential for permit exceedence, especially during the winter months.
Viral loading would likely increase under both the proposed project and waiver
scenarios due to increased flows. No known specific regulatory guidelines exist
for the determination of public health risks associated with viral loading, although
existing data has not yielded any statistically significant evidence for increased
health risks associated with viral loading from effluent discharge.
-22-
Sludye Disposal
Impacts: Sludge production for the EWPCF is projected to increase significantly
with flow rates under either the proposed project or waiver scenario. This increase
will represent a significant impact due to the increasing restrictions on current
disposal methods.
Findings: Both interim and long-term potential sludge reuse/disposal methods
have been identified and are currently under investigation. Agreement has been
reached regarding interim (up to 5-year) use of stabilized sludge as fertilizer/soil
amendment for agricultural operations. Both interim and long-term sludge
reuse/disposal systems will require implementation during the life of the proposed
Phase IV project to accommodate projected sludge quantities. The long-term
project may generate a number of potential environmental impacts depending on
the alternative method and site selected. It will be necessary, therefore, to conduct
appropriate environmental and technical studies prior to implementation, and to
generate site-specific mitigation measures as required. The long-term disposal of
sludge generated at Encina remains a potentially significant effect
Energy Consumption and Conservation
Impacts: No significant impacts are expected in regard to energy consumption and
conservation for either the proposed project or waiver scenario.
Findings: Expansion of the EWPCF would likely produce an operating energy
deficit under either the proposed or waiver scenario. Increases in energy
consumption would likely include additional requirements for electricity, natural
gasi and diesel fuel (for hauling increased quantities of sludge). Onsite energy
needs would be met by purchasing electricity and natural gas from San Diego Gas
and Electric at variable rates, depending on periods of use, etc. The project design
incorporates a number of measures to maximize cogcneration and the potential sale
of excess digester gas and waste heat to offsite users. Additional diesel fuel
consumption related to sludge hauling is not considered significant due to the
relatively low number of truck trips involved.
-23-
Construction-Related Impacts
Impacts: Construction-related activities would be expected to produce adverse
effects related to noise, air quality, and traffic under both the proposed project and
the waiver scenario. These would be related to the operation of heavy equipment
and associated vehicles, excavation and grading activities, and the generation of
traffic due to importation of equipment, employee ingress-egress, etc. These
potential impacts are not expected to be significant, however, due to existing
regulatory requirements and guidelines, and the traffic capacities of local
circulation systems.
Findings: Although no significant construction-related impacts are anticipated, a
number of adverse noise, air quality, and traffic effects are likely. Appropriate
mitigation measures related to hours of operation, dust abatement, equipment
maintenance and traffic control have been recommended to minimize adverse
construction-related effects.
Noise
Impacts: No significant impacts are anticipated in relation to long-term operational
noise levels for either the proposed project or waiver scenario.
pndings: The nature of the proposed facilities and the ambient noise levels in the
EWPCP vicinity are such that no significant increase in noise levels is anticipated
This conclusion is based in field measurements of existing noise levels and
estimation of noise generation for proposed facilities.
LBC&CJ&: The proposed project would require the use of one additional engine
blower and engine generator, which would result in exceedence of existing
regulatory emission limits. Another potential concern is the release of volatile
organic compounds through the aeration process. The potential for greater overall
release of such compounds would occur with implementation of the proposed
project, due to the increased volume of aeration. The issue of volatile organic
compound release is currently being investigated by the State Water Resources
-24-
Control Board (SWRCB), although to date no regulatory requirements or
recommendations have been issued. No significant impacts would result from
implementation of the waiver scenario.
Findings: A new Air Pollution Control District (APCD) permit (including
additional air pollution emission controls) would be obtained during
implementation of the proposed project. This would mitigate potential air quality
impacts below levels of significance for the proposed project, with no mitigation
measures required for the waiver scenario. The results of the SWRCB
investigation on volatile organic compound release will be incorporated into the
project design (as appropriate) when available.
Odors
Impacts: No significant impacts related to the generation of offrite odors would be
anticipated from implementation of either the proposed project or waiver scenario.
Findings; The proposed project design incorporates a number of measures to
mitigate potential odor-related impacts, such as the expanded use of odor control
covers, ducting, and scrubbing towers. Additionally, the EWPCF maintains an
odor control program whereby public odor complaints are logged and investigated,
with additional system modifications incorporated as appropriate.
Traffic
Impacts: No significant impacts related to traffic are expected from either the
proposed project or waiver scenario.
Findings: Expansion of the EWPCF under either the proposed or waiver scenario
would not significantly increase long-term traffic generation within the project site
and vicinity. Such traffic would be limited to ingress and egress associated with a
small number of additional employees and a relatively few additional truck trips
related to sludge removal. The existing local circulation system is adequate to
accommodate this traffic without significant effects.
-25-
Geofechnical
Impacts; Based on previous geotcchnical investigations of the site, no significant
adverse impacts are anticipated,
A number of offsite improvements have been discussed in relation to expanding
the existing plant, including a sludge reuse/disposal site and a new ocean outfall or
flow equalization structure. These facilities could involve significant geotechnical
constraints and would require site-specific environmental analyses prior to
implementation.
Findings: The standards established for excavation, grading, and construction in
the previous geotechnical investigations of the site will reduce potential impacts
below levels of significance. If construction activities result in unexpected
subsurface conditions or unmitigated geologic impacts, further geotechnical
investigation would be conducted as required.
All potential offsite development will be subject to site-specific geotechnical
analysis prior to implementation. Such evaluations will be conducted by a
qualified geotechnical consultant, with all identified mitigation measures included
in the subsequent facilities design.
HydrologyAyater Quality
Impacts: The proposed expansion of the EWPCF would not be expected to
produce any significant impacts to surface or groundwater hydrology under either
the secondary treatment or waiver scenarios.
Findings; Potential water quality impacts include the contamination of surface
runoff into the flood control channel and the influx of reclaimed effluent into local
groundwater tables. Regulatory requirements and protective measures contained in
the project design (e,g., containment berms) are expected to reduce these potential
impacts below levels of significance.
-26-
Biological Resources
Impacts: Implementation of either the proposed or waiver scenario expansion
would not be expected to result in significant impacts to terrestrial biological
resources. Selection of future offsite facility locations, however, may require
additional biological investigation.
Findings: Previous investigation of the EWPCF site did not identify any sensitive
biological resource values. The current filled and graded nature of the site likely
precludes the occurrence of any significant terrestrial biological resources there.
Cultural Resources
Impacts: No significant impacts to cultural resources are expected from
implementation of either the proposed project or waiver scenario. Offsite
improvements, however, would require site-specific archaeological investigations
to determine potential impacts.
Findings: Previous cultural resource investigations and the disturbed nature of the
site likely precludes the occurrence of any significant cultural resources there.
Visual Resources
Impacts: No significant impacts to visual resources are anticipated from either the
proposed project or waiver scenario. This is due to the fact that all proposed
structures would be similar to existing facilities, and would be contained within the
existing site.
Findings: Although no significant visual impacts are anticipated from the proposed
or expansion scenarios, a number of mitigation measures have been recommended
to minimize adverse visual effects. These include the use of additional landscaping
and the submission of detailed landscape and grading plans with the City of
Carlsbad Precise Development Plan application.
-27-
Growth Inducemen|
Impacts; The proposed project would provide treatment capacity in excess
(approximately 2 percent for Phase IV and 5 percent for Phase V) of demands
associated with populations and flows projected from SANDAG Series 7
forecasts (although less than those projected as necessary by individual member
agencies). Consequently, it is considered growth-inducing under strict
interpretation of the definitions contained in CEQA and S ANDAG guidelines.
findings: Much of the excess capacity associated with the proposed expansion is
attributable to the modular design of the plant, in which individual facilities have
inherent, fixed capacities. This makes it virtually impossible to match projected
populations and flows exactly. The project design incorporates phasing schedules
to coordinate facility use with demand as fully as possible. In addition, treatment
capacity needs incorporate septage flows from outside the service areas and
daytime flows from the proposed California State University at San Diego North
County Campus (CSUSD), which are not reflected in SANDAG Series 7 figures.
B. The member agencies of the Encina Joint Powers, having reviewed and considered
the information contained in the Final EIR and record for the EWPCF expansion, find that
no changes or alterations contained therein which mitigate on avoid significant
environmental effects are within the responsibility and jurisdiction of another public
agency.
C. The member agencies of the Encina Joint Powers, having reviewed and considered
the information contained in the Final BIR and record for the EWPCF expansion, find that
specific economic, social, or other considerations make infeasible the project alternatives
identified in the Final EIR as outlined below:
1. No Project
Under the no project alternative the EWPCF would remain in its present
condition with no expansion of treatment capabilities. The capacity of the existing facilities
would not change, and the overall plant capacity would remain at 22.5 millions gallons per
day (MOD). Based on projected wastewater flow rates, this capacity would be exceeded
prior to 1995.
-28-
While the no project alternative would eliminate the potential environmental
impacts associated with the proposed plant expansion, it would not meet the stated
objectives. The EWPCF sendee area would be faced with inadequate wastewater treatment
capacity within five years, and a moratorium of new sew hookups would likely be imposed
by the member agencies of the Encina Joint Powers.
2. Engineering Alternatives
Five potential expansion alternatives were identified in the EWPCF facility
plan, including three for secondary treatment and two for the waiver scenario. Of these,
one alternative was selected as the proposed project for each treatment scenario, with the
remaining three designated as engineering alternatives as described below.
a. Full Biofilter Treatment
The first engineering alternative would allow for secondary
treatment by utilizing biofilters to treat all effluent before it enters the aeration basins. This
would reduce loading rates to the basins and increase their capacity, although the resultant
hydraulic retention times would still require construction of an additional aeration basin.
The potential environmental impacts for this alternative would be similar to the proposed
project with the exception of the 20-foot biotowers being more visible, producing 18 cubic
yards per day less sludge, and requiring 3.4 percent less energy that the proposed
facilities. These latter two reductions are not considered significant in relation to overall
sludge production and energy use. Total annual expenditures for this alternative would
exceed the proposed project by approximately $ 1,500,000 due to the distribution of capital
costs over time. Therefore, while this alternative is capable of meeting the stated project
objectives, it offers no significant reduction in environmental impacts and would result in a
substantial increase in capital costs.
b. Partial Biofilter Treatment
This alternative would provide secondary treatment by utilizing
biofilters in parallel with aeration basins. Existing aeration basins would treat effluent up to
their nominal capacity, with a two-stage biofUter treating the remaining flow. Potential
environmental impacts for this alternative would be similar to the proposed project with the
exception of the biotowers being more visible, producing 22 cubic yards per day less
sludge, and requiring 3.4 percent less energy than the proposed facilities. These
-29-
"^f^ ^w^reductions are not considered significant with respect to overall sludge production and
energy use. Total annual expenditures for the alternative exceed those for the proposed
project by approximately $50,000. Therefore, while this alternative is capable of meeting
the project objectives, it offers no significant reduction in environmental impacts and would
result in a slight increase in capital costs.
C. Waiver Alternative Usinp Chemical Addition
This alternative utilizes chemical additives to increase treatment
levels such that all primary effluent (except that used for reclamation purposes) could be
diverted directly to the ocean outfall. Potential environmental impacts associated with this
alternative would be similar to the preferred waiver scenario, with the exception of
requiring 12 percent less energy and producing approximately 4 cubic yards per day of
additional sludge. Total annual costs for this alternative would exceed those for the
proposed project by approximately $200,000. This alternative would be capable of
meeting the project objectives with a significant reduction in energy demand, although it
would increase sludge production and raise annual expenditures by approximately
5200,000.
3. Use of Satellite Treatment Facilities
There are currently three operating satellite treatment plants in the EWPCF
service area, with a fourth scheduled to come in line in the early 1990s. The combined
ultimate capacity of all four plants is 5.2 MOD, with the ability to utilize this total
dependent on market and environmental factors. Even with full satellite treatment capacity,
however, the combined EWPCF/satellite capacity of 27.7 MOD would be exceeded prior
to 1995. The use of satellite treatment plants therefore does not meet the project objectives
of providing adequate treatment capacity through the year 2020 and is not considered a
viable project alternative in and of itself.
4. Water Reclamation
Effluent suitable for various reclamation uses is currently produced at the
operating satellite treatments plants and the EWPCF. By treating more wastewater at the
satellite plants, the capacity requirements for the EWPCF plant could be reduced.
However, solids treatment capacity requirements would remain unchanged since all
wastewater solids are treated at the EWPCF. Any use of reclaimed (and hence treated)
-30-
water from the satellite plants would reduce flows to the outfall. However, the capacity for
failsafe disposal through the outfall would still be required pursuant to Regional Water
Quality Control Board (RWQCB) requirements.
Assuming full use and reclamation of satellite treatment capacity
(5.2 MOD) and 2.0 MOD of offsite reclamation use from the EWPCF, available effluent
reclamation in the EWPCF service area would total 7.2 MOD. Based on flow projections
listed in the Final EIR, the existing EWPCF capacity would still be exceeded prior to the
year 1995, even with maximum available reclamation use. Utilizing maximum reclamation
would reduce total flow to the ocean outfall by 7.2 MOD, although outfall capacity needs
would remain the same due to fail-safe discharge requirements. Thus, water reclamation in
itself does not meet the project objectives and is not considered a viable stand-alone
alternative to the proposed project.
5. Phasing Alternative,
This alternative involves providing capacity to the year 2000 under the
designation of Phase IV, with subsequent development to the year 2010 designated as
Phase V.
Potential environmental impacts associated with the phasing alternative
would be similar to those for the proposed phasing scheme, as the ultimate level of
development would be the same. By combining construction activities to the year 2010
into a single Phase IV project, the overall impact period associated with construction
activities would be reduced. Short-term (Phase IV) capital costs are lower for the
alternative phasing scheme as it involves less Phase IV construction. Overall costs for this
alternative, however, would be approximately 3 percent higher due to the economics of
conducting separate construction operations (i.e., Phase IV and V). Also, based on
member agency growth forecasts, the Phase IV project capacity would be exceeded well
before the year 2000. Thus, this alternative would provide the same overall capacity as the
recommended project, although no technical, environmental, or economic benefits would
result, a longer construction period would ensue, and the Phase V project could be
required shortly after Phase IV is brought into service.
-31-
STATEMENT OF OVERRIDING CONSIDERATIONS
The member agencies of the Encina Joint Powers, having reviewed and considered the
information contained in the Final EIR and record for the EWPCF expansion make the
following statements of overriding considerations:
Although the project would result in sludge disposal and growth-inducement impacts which
are not fully mitigated, to the extent that these impacts would occur, specific beneficial
economic and social effects associated with the project would override these impacts.
Population within the service area is projected to increase from the current figure of
200,000 to at least 380,000 by the year 2020. With this assumption, the current capacity
of the EWPCF will be exceeded around the year 1991. The proposed phased expansion is
designed to provide full secondary treatment capacity for projected population in the
EWPCF service area through the year 2020 (Phase IV would provide capacity through the
year 2010; Phase V would provide capacity to the year 2020). This is seen as a public
benefit. In lieu of expanding the EWPCF facility, the service area member agencies would
be compelled to provide adequate treatment capacity by some additional means and/or limit
service area growth to reflect existing capacity.
The proposed expansion would also provide additional local employment during the
construction period, incrementally increasing regional income and employment in the
San Diego region.
Therefore, the member agencies of the Encina Joint Powers find that the need to provide
wastewater treatment capacity to meet projected population growth in the EWPCF service
area overrides the impacts which would result from this project
-32-
RESOLUTION NO.
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CARLSBAD
APPROVING THE ENCINA WATER POLLUTION CONTROL FACILITY
YEAR 2020 FACILITY PLAN
WHEREAS, the City of Carlsbad is a party to a Joint Powers
Agreement, commonly known as the Basic Agreement for the
ownership, operation and maintenance of the Encina Joint Sewer
System; and
WHEREAS, prudent planning requires that the member agencies
of the Encina Joint Powers establish, approve and adopt a plan
for providing sewer service to and for certain areas within
Northern San Diego County; and
WHEREAS, such a plan has been developed up to the year 2020
based on SANDAG Series 7 projections; and
WHEREAS, the Leucadia County Water District has acted as the
Lead Agency in causing to be prepared and certified as complete
the Environmental Impact Report for said Plan which is commonly
known as the Encina Water Pollution Control Facility Year 2020
Facility Plan; and
WHEREAS, said Plan includes expansion of the Encina Water
Pollution Control Facility in two phases, namely Phase IV and
Phase V, both of which Phases are included in the aforesaid
Environmental Impact Report; and
WHEREAS, pursuant to the California Environmental Quality
Act, the Leucadia County Water District has been, and still is,
acting as the Lead Agency on behalf of the Encina Joint Powers
for said Year 2020 Facility Plan; and
WHEREAS; on August 11, 1988, the said Leucadia County
Water District completed the Environmental Impact Report process
and certified said Report as complete, which Report is designated
by the State of California as SCH NO. 88-041308, and
WHEREAS, in considering and evaluating the said
Environmental Impact Report, the Leucadia county Water District
made certain findings as required by law, copies of which are
attached hereto and incorporated herein by reference, and are
hereby adopted and approved by the City of Carlsbad;
WHEREAS, the City of Carlsbad is a "responsible agency" as
defined in Section 21069 of the California Public Resources Code;
and
WHEREAS, the City of Carlsbad hereby desires to approves
and adopt the Year 2020 Facility Plan and desires to give
notice of such approval to the County Clerk of the County of San
Diego; and
WHEREAS, the City of Carlsbad has heretofore approved the
Phase IV Project as included in the above mentioned Environmental
Impact Report, and the Notice of Determination of the Encina
Water Pollution Control Facility Expansion to be filed with the
County Clerk of San Diego County may include include notice of
approval of the Phase IV Project;
WHEREAS; the Joint Advisory Committee to the Encina Joint
Powers has heretofore unanimously approved the Year 2020 Facility
Plan and the Phase IV Project ; and
WHEREAS, upon completion of the Encina Water Pollution
Control Facility Expansion, the treatment capacity will increase
to 39.61 HGD liquid/ 41.61 MGD solids.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OP THE CITY OF
CARLSBAD AS FOLLOWS:
Section ,1. The city of Carlsbad hereby approves and adopts
the findings contained in Exhibit "A" attached hereto and
incorporated herein by reference.
Sectionn2« The City of Carlsbad hereby approves and adoptts
the Encina Water Pollution Control Facility Year 2020 Facility
Plan; and
Section 3. The officers and employees the City of
Carlsbad are hereby authorized and instructed to prepare or
cause to be prepared a Notice to the County Clerk of the County
of San Diego within five days after adoption of this resolution
that the City of Carlsbad approves the Encina Water Pollution Control
Facility Year 2020 Facility Plan which notice may be included
with the notice that the City of Carlsbad has also approved the
Phase IV Project and intends to carry out said Project together
with the other five (5) member agencies of the Encina Joint
Powers, that the Project will have a significant impact on the
environment and that an Environmental Impact Report for the
Project has been certified as complete by the Leucadia County
Water District, and that said Environmental Impact report is
available to the general public.
PASSED, APPROVED, AND ADOPTED at a regular meeting of the
City Council on the 27th day of September , 1988, by the
following votes, to wit:
AYES:5 NOES: None ABSENT: None
ATTEST:
ALETHA L. RAUTENKRANZ, City
Mayor
IDATE FINDINGS AND STATEMENT
OF OVERRIDING CONSIDERATION
Encina Water Pollution Control Facility Expansion
SCHNo. 39041302
The California Environmental Quality Act (CEQA) 'requires that no public agency shall
approve or carry out a project for which a Final Environmental Impact Report (EIR)
identifies one or more significant effects thereof, unless such public agency makes one or
more of the following findings:
(1) Changes or alterations have been required in,
or incorporated into, such project which mitigate or
avoid the significant environmental effects thereof asidentified in the completed environmental impact
report
(2) Such changes or alterations are within the
responsibility and jurisdiction of another public
agency, and such changes have been adopted by
such other agency or can and should be adopted by
such other agency.
(3) Specific economic, social, or other considera-
tions make infeasible the mitigation measures or
project alternatives identified in the environmental
impact report
(Section 21081 of the California Environmental
Quality Act)
CEQA further requires that, where the decision of the public agency allows the occurrence
of significant effects which are identified in the Final EIR but are not at least substantially
mitigated, the agency shall state in writing the specific reasons to support its action based
on the Final BIR and/or other information in the record (Section 15093 of the CEQA
Guidelines)..
-19-EXHIBIT A
FINDINGS
The following findings are made relative to the conclusions and recommendations of the
Final EIR for the Encina Water Pollution Control Facility (EWPCF) expansion
(SCH No. 87042206). These findings have been prepared pursuant to Section 21081 of
the California Public Resources Code and Sections 15091 and 15093 of the California
Administrative Code,
A. The member agencies of the Encina Joint Powers, having reviewed and considered
the information contained in the Final EIR and record for the EWPCF expansion, find that
the following changes or alterations are being required in, or have been incorporated into
the project, which mitigate or avoid the significant environmental effects identified in the
EIR. Specifically:
Land Use
Impacts; The project site is designated for public utilities use in the City of
Carlsbad General Plan, with wastewater treatment identified as the primary onsite
use by virtue of a General Plan Amendment Because of this designation and the
fact that all proposed expansion facilities would be within the existing EWPCF
site, no significant land use impacts are expected as a result of the proposed
project
A number of offsite facilities are generally discussed in relation to the proposed
project, including a new ocean outfall or flow equalization structure, and a sludge
reuse/disposal facility. All of these facilities could potentially impact offsite land
uses through construction and operation activities.
Findings: The EWPCF will obtain and comply'with all pertinent federal, state, and
local discretionary and non-discretionary permits associated with the proposed
expansion. This will allow implementation of the proposed project without
significantly affecting land use designations or character in the project site vicinity.
No offsite structures are specifically proposed for the current EWPCF expansion.
Construction of a new ocean outfall, flow equalization structure, or sludge
reuse/disposal facility would require the preparation of a site-specific
-20-
<•»*».
environmental analysis to identify potential impacts related to land use and other
appropriate resource values.
Ocean Water Oyalitv and Oceanography
Impacts: Both the proposed project and waiver scenario alternative would result in
the increased discharge of effluent. On the basis of current monitoring data,
however, it is not expected that this increased discharge would have significant
impacts to ocean water quality in the zone of initial dilution (ZID), the
accumulation of organic material, or the direction of deposition in the area of
discharge. Increased discharge could affect the rate of deposition, although the
interaction between flow rates, mass load, and currents will ultimately determine
the potential for deposition.
Bacterial loads in the discharged effluent would likely be maintained at existing
levels or reduced slightly under full secondary treatment, due to the combined
effects of higher treatment levels and increased effluent quantities. Under the
waiver scenario, total bacterial content in the discharged effluent would increase
due to higher flows. It is possible that there will be a minor but increased risk of
permit exceedence for bacterial content in the discharged effluent, particularly
during the winter months.
The potential for viruses will increase due to population growth; however, the
potential risk from this increase cannot be identified at the present time and with the
existing monitoring program. There would be an increased potential for aerosol
dispersion of viruses in the surf zone and nearshore zone; however, this mode of
transmission is still under study and no conclusions should be drawn at the present
time.
Findings: Adherence to appropriate regulations and requirements would reduce
impacts related to effluent discharge below levels of significance. This would
include restrictions on the quality of both effluent (NPDES permit) and influent
(source control program) associated with the EWPCF. Viruses will be removed to
a degree in the secondary process but will not be removed completely. Existing
data has not identified significant adverse effects associated with viral loading in
-21-
effluent discharge, although no regulatory standards have yet been developed and
methodology is not well established.
Marine Biology
Impacts: No significant impacts to the wide diversity of marine organisms and
habitats in the area of discharge would be anticipated from either the proposed
project or waiver scenario.
Findings: The proposed project would increase both the total quantity of effluent
discharge and the associated level of treatment, resulting in no significant impacts
to the marine environment. The waiver scenario would increase the total quantity
of pollutants emitted due to increased discharge volumes. This would not be
expected to result in significant impacts to marine biological resources because of
existing discharge quality and monitoring requirements.
Public Health
Impacts; Neither the proposed project or the waiver scenario would be expected to
result in significant impacts related to public health concerns, assuming pertinent
regulatory guidelines are met.
Findings: The proposed project would likely maintain or slightly reduce the
existing levels of bacteria in the discharged effluent, due to increases in both
treatment levels and discharge volumes. Bacterial discharge levels for the waiver
scenario would increase somewhat because of greater effluent volumes, and would
increase the potential for permit exceedence, especially during the winter months.
Viral loading would likely increase under both the proposed project and waiver
scenarios due to increased flows. No known specific regulatory guidelines exist
for the determination of public health risks associated with viral loading, although
existing data has not yielded any statistically significant evidence for increased
health risks associated with viral loading from effluent discharge.
-22-
Sludge Disposal
Impacts: Sludge production for the EWPCF is projected to increase significantly
with flow rates under either the proposed project or waiver scenario. This increase
will represent a significant impact duo to the increasing restrictions on current
disposal methods.
Findings: Both interim and long-term potential sludge reuse/disposal methods
have been identified and are currently under investigation. Agreement has been
reached regarding interim (up to 5-year) use of stabilized sludge as fertilizer/soil
amendment for agricultural operations. Both interim and long-term sludge
reuse/disposal systems will require implementation during the life of the proposed
Phase IV project to accommodate projected sludge quantities. The long-term
project may generate a number of potential environmental impacts depending on
the alternative method and site selected. It will be necessary, therefore, to conduct
appropriate environmental and technical studies prior to implementation, and to
generate site-specific mitigation measures as required. The long-term disposal of
sludge generated at Encina remains a potentially significant effect
Enerpv Consumption and Conservation
Impacts: No significant Impacts are expected in regard to energy consumption and
conservation for either the proposed project or waiver scenario.
Findings: Expansion of the EWPCF would likely produce an operating energy
deficit under either the proposed or waiver scenario. Increases in energy
consumption would likely include additional requirements for electricity, natural
gas*, and diesel fuel (for hauling increased quantities of sludge). Onsite energy
needs would be met by purchasing electricity and natural gas from San Diego Gas
and Electric at variable rates, depending on periods of use, etc. The project design
incorporates a number of measures to maximize cogeneration and the potential sale
of excess digester gas and waste heat to offsite users. Additional diesel fuel
consumption related to sludge hauling is not considered significant due to the
relatively low number of truck trips involved.
-23-
Construction-Related Impacts
Impacts: Construction-related activities would be expected to produce adverse
effects related to noise, air quality, and traffic under both the proposed project and
the waiver scenario. These would be related to the operation of heavy equipment
and associated vehicles, excavation and grading activities, and the generation of
traffic due to importation of equipment, employee ingress-egress, etc. These
potential impacts are not expected to be significant, however, due to existing
regulatory requirements and guidelines, and the traffic capacities of local
circulation systems.
Findings: Although no significant construction-related impacts are anticipated, a
number of adverse noise, air quality, and traffic effects are likely. Appropriate
mitigation measures related to hours of operation, dust abatement, equipment
maintenance and traffic control have been recommended to minimize adverse
construction-related effects.
Noise
Impacts: No significant impacts are anticipated in relation to long-term operational
noise levels for either the proposed project or waiver scenario.
findings: The nature of the proposed facilities and the ambient noise levels in the
EWPCP vicinity are such that no significant increase in noise levels is anticipated.
This conclusion is based in field measurements of existing noise levels and
estimation of noise generation for proposed facilities.
AirOuaHtv
The proposed project would require the use of one additional engine
blower and engine generator, which would result in exceedence of existing
regulatory emission limits. Another potential concern is the release of volatile
organic compounds through the aeration process. The potential for greater overall
release of such compounds would occur with implementation of the proposed
project, due to the increased volume of aeration. The issue of volatile organic
compound release is currently being investigated by the State Water Resources
-24-
Control Board (SWRCB), although to date no regulatory requirements or
recommendations have been issued. No significant impacts would result from
implementation of the waiver scenario.
Findings; A new Air Pollution Control District (APCD) permit (including
additional air pollution emission controls) would be obtained during
implementation of the proposed project. This would mitigate potential air quality
impacts below levels of significance for the proposed project, with no mitigation
measures required for the waiver scenario. The results of the SWRCB
investigation on volatile organic compound release will be incorporated into the
project design (as appropriate) when available.
Odors
Impacts: No significant impacts related to the generation of offsite odors would be
anticipated from implementation of either the proposed project or waiver scenario.
Findings; The proposed project design incorporates a number of measures to
mitigate potential odor-related impacts, such as the expanded use of odor control
covers, ducting, and scrubbing towers. Additionally, the EWPCF maintains an
odor control program whereby public odor complaints are logged and investigated,
with additional system modifications incorporated as appropriate.
Traffic
Impacts; No significant impacts related to traffic are expected from either the
proposed project or waiver scenario.
Findings: Expansion of the EWPCF under either the proposed or waiver scenario
would not significantly increase long-term traffic generation within the project site
and vicinity. Such traffic would be limited to ingress and egress associated with a
small number of additional employees and a relatively few additional truck trips
related to sludge removal. The existing local circulation system is adequate to
accommodate this traffic without significant effects.
-25-
Geotechnical
Impacts: Based on previous geotechnical investigations of the site, no significant
adverse impacts are anticipated
A number of offsite improvements have been discussed in relation to expanding
the existing plant, including a sludge reuse/disposal site and a new ocean outfall or
flow equalization structure. These facilities could involve significant geotechnical
constraints and would require site-specific environmental analyses prior to
implementation.
Findings: The standards established for excavation, grading, and construction in
the previous geotechnical investigations of the site will reduce potential impacts
below levels of significance. If construction activities result in unexpected
subsurface conditions or unmitigated geologic impacts, further geotechnical
investigation would be conducted as required.
All potential offsite development will be subject to site-specific geotechnical
analysis prior to implementation. Such evaluations will be conducted by a
qualified geotechnical consultant, with all identified mitigation measures included
in the subsequent facilities design.
Hydrolofv/Water Quality
Impacts: The proposed expansion of the EWPCF would not be expected to
produce any significant impacts to surface or groundwater hydrology under either
the secondary treatment or waiver scenarios.
Findings; Potential water quality impacts include the contamination of surface
runoff into the flood control channel and the influx of reclaimed effluent into local
groundwater tables. Regulatory requirements and protective measures contained in
the project design (e.g., containment berms) are expected to reduce these potential
impacts below levels of significance.
-26-
Biological Resources
Impacts; Implementation of either the proposed or waiver scenario expansion
would not be expected to result in significant impacts to terrestrial biological
resources. Selection of future offsite facility locations, however, may require
additional biological investigation.
Findings: Previous investigation of the EWPCF site did not identify any sensitive
biological resource values. The current rilled and graded nature of the site likely
precludes the occurrence of any significant terrestrial biological resources there.
Cultural Resources
Impacts: No significant impacts to cultural resources are expected from
implementation of either the proposed project or waiver scenario. Offsite
improvements, however, would require site-specific archaeological investigations
to determine potential impacts.
Findings: Previous cultural resource investigations and the disturbed nature of the
site likely precludes the occurrence of any significant cultural resources there,
Visual Resources
Impacts: No significant impacts to visual resources are anticipated from either the
proposed project or waiver scenario. This is due to the fact that all proposed
structures would be similar to existing facilities, and would be contained within the
existing site.
Findings: Although no significant visual impacts are anticipated from the proposed
or expansion scenarios, a number of mitigation measures have been recommended
to minimize adverse visual effects. These include the use of additional landscaping
and the submission of detailed landscape and grading plans with the City of
Carlsbad Precise Development Plan application.
-27-
Growth Inducement
Impacts; The proposed project would provide treatment capacity in excess
(approximately 2 percent for Phase IV and 5 percent for Phase V) of demands
associated with populations and flows projected from SANDAG Series 7
forecasts (although less than those projected as necessary by individual member
agencies). Consequently, it is considered growth-inducing under strict
interpretation of the definitions contained in CEQA and SANDAG guidelines.
Fjndings: Much of the excess capacity associated with the proposed expansion is
attributable to the modular design of the plant, in which individual facilities have
inherent, fixed capacities. This makes it virtually impossible to match projected
populations and flows exactly. The project design incorporates phasing schedules
to coordinate facility use with demand as fully as possible. In addition, treatment
capacity needs incorporate septage flows from outside the service areas and
daytime flows from the proposed California State University at San Diego North
County Campus (CSUSD), which are not reflected in SANDAG Series 7 figures.
B. The member agencies of the Encina Joint Powers, having reviewed and considered
the information contained in the Final EIR and record for the EWPCF expansion, find that
no changes or alterations contained therein which mitigate on avoid significant
environmental effects are within the responsibility and jurisdiction of another public
agency.
C. The member agencies of the Encina Joint Powers, having reviewed and considered
the information contained in the Final EIR and record for the EWPCF expansion, find that
specific economic, social, or other considerations make infeasible the project alternatives
identified in die Final EIR as outlined below:
1. No Project
Under the no project alternative the EWPCF would remain in its present
condition with no expansion of treatment capabilities. The capacity of the existing facilities
would not change, and the overall plant capacity would remain at 22.5 millions gallons per
day (MOD). Based on projected wastewater flow rates, this capacity would be exceeded
prior to 1995.
-28-
While the no project alternative would eliminate the potential environmental
impacts associated with the proposed plant expansion, it would not meet the stated
objectives. The EWPCF service area would be faced with inadequate wastewater treatment
capacity within five years, and a moratorium of new sew hookups would likely be imposed
by the member agencies of the Encina Joint Powers.
2. Engineering Alternatives
Five potential expansion alternatives were identified in the EWPCF facility
plan, including three for secondary treatment and two for the waiver scenario. Of these,
one alternative was selected as the proposed project for each treatment scenario, with the
remaining three designated as engineering alternatives as described below.
a. Full Biofilter Treatment
The first engineering alternative would allow for secondary
treatment by utilizing biofilters to treat all effluent before it enters the aeration basins. This
would reduce loading rates to the basins and increase their capacity, although the resultant
hydraulic retention times would still require construction of an additional aeration basin.
The potential environmental impacts for this alternative would be similar to the proposed
project with the exception of the 20-foot biotowers being more visible, producing 18 cubic
yards per day less sludge, and requiring 3.4 percent less energy that the proposed
facilities. These latter two reductions are not considered significant in relation to overall
sludge production and energy use. Total annual expenditures for this alternative would
exceed the proposed project by approximately $1,500,000 due to the distribution of capital
costs over time. Therefore, while this alternative is capable of meeting the stated project
objectives, it offers no significant reduction in environmental impacts and would result in a
substantial increase in capital costs.
b. Partial Biofilter Treatment
This alternative would provide secondary treatment by utilizing
biofilters in parallel with aeration basins. Existing aeration basins would treat effluent up to
their nominal capacity, with a two-stage biofilter treating the remaining flow. Potential
environmental impacts for this alternative would be similar to the proposed project with the
exception of the biotowers being more visible, producing 22 cubic yards per day less
sludge, and requiring 3.4 percent less energy than the proposed facilities. These
-29-
reductions are not considered significant with respect to overall sludge production and
energy use. Total annual expenditures for the alternative exceed those for the proposed
project by approximately $50,000. Therefore, while this alternative is capable of meeting
the project objectives, it offers no significant reduction in environmental impacts and would
result in a slight increase in capital costs.
c. Waiver Alternative Using Chemical Addition
This alternative utilizes chemical additives to increase treatment
levels such that all primary effluent (except that used for reclamation purposes) could be
diverted directly to the ocean outfall. Potential environmental impacts associated with this
alternative would be similar to the preferred waiver scenario, with the exception of
requiring 12 percent less energy and producing approximately 4 cubic yards per day of
additional sludge. Total annual costs for this alternative would exceed those for the
proposed project by approximately $200,000. This alternative would be capable of
meeting the project objectives with a significant reduction in energy demand, although it
would increase sludge production and raise annual expenditures by approximately
5200,000.
3. Use of Satellite Treatment Facilities
There are currently three operating satellite treatment plants in the EWPCF
service area, with a fourth scheduled to come in line in the early 1990s. The combined
ultimate capacity of all four plants is 5.2 MOD, with the ability to utilize this total
dependent on market and environmental factors. Even with full satellite treatment capacity,
however, the combined EWPCF/satellite capacity of 27.7 MOD would be exceeded prior
to 1995, The use of satellite treatment plants therefore does not meet the project objectives
of providing adequate treatment capacity through the year 2020 and is not considered a
viable project alternative in and of itself.
4. Water Reclamatiqn
Effluent suitable for various reclamation uses is currently produced at the
operating satellite treatments plants and the EWPCF. By treating more wastewater at the
satellite plants, the capacity requirements for the EWPCF plant could be reduced.
However, solids treatment capacity requirements would remain unchanged since all
wastewater solids are treated at the EWPCF. Any use of reclaimed (and hence treated)
-30-
water from the satellite plants would reduce flows to the outfall. However, the capacity for
failsafe disposal through the outfall would still be required pursuant to Regional Water
Quality Control Board (RWQCB) requirements.
Assuming full use and reclamation of satellite treatment capacity
(5.2 MOD) and 2.0 MOD of offsite reclamation use from the EWPCF, available effluent
reclamation in the EWPCF service area would total 7.2 MOD. Based on flow projections
listed in the Final EIR, the existing EWPCF capacity would still be exceeded prior to the
year 1995, even with maximum available reclamation use. Utilizing maximum reclamation
would reduce total flow to the ocean outfall by 7.2 MOD, although outfall capacity needs
would remain the same due to fail-safe discharge requirements. Thus, water reclamation in
itself does not meet the project objectives and is not considered a viable stand-alone
alternative to the proposed project.
5. Phasing Alternative
This alternative involves providing capacity to the year 2000 under the
designation of Phase IV, with subsequent development to the year 2010 designated as
Phase V.
Potential environmental impacts associated with the phasing alternative
would be similar to those for the proposed phasing scheme, as the ultimate level of
development would be the same. By combining construction activities to the year 2010
into a single Phase IV project, the overall impact period associated with construction
activities would be reduced. Short-term (Phase IV) capital costs are lower for the
alternative phasing scheme as it involves less Phase IV construction. Overall costs for this
alternative, however, would be approximately 3 percent higher due to the economics of
conducting separate construction operations (i.e., Phase IV and V). Also, based on
member agency growth forecasts, the Phase IV project capacity would be exceeded well
before the year 2000. Thus, this alternative would provide the same overall capacity as the
recommended project, although no technical, environmental, or economic benefits would
result, a longer construction period would ensue, and the Phase V project could be
required shortly after Phase IV is brought into service.
-31-
STATEMENT OF OVERRIDING CONSIDERATIONS
The member agencies of the Encina Joint Powers, having reviewed and considered the
information contained in the Final EIR and record for the EWPCF expansion make the
following statements of overriding considerations:
Although the project would result in sludge disposal and growth-inducement Impacts which
are not fully mitigated, to the extent that these impacts would occur, specific beneficial
economic and social effects associated with the project would override these impacts.
Population within the service area is projected to increase from the current figure of
200,000 to at least 380,000 by the year 2020. With this assumption, the current capacity
of the EWPCF will be exceeded around the year 1991. The proposed phased expansion is
designed to provide full secondary treatment capacity for projected population in the
EWPCF sendee area through the year 2020 (Phase IV would provide capacity through the
year 2010; Phase V would provide capacity to the year 2020). This is seen as a public
benefit. In lieu of expanding the EWPCF facility, the service area member agencies would
be compelled to provide adequate treatment capacity by some additional means and/or limit
service area growth to reflect existing capacity.
The proposed expansion would also provide additional local employment during the
construction period, incrementally increasing regional income and employment in the
San Diego region.
Therefore, the member agencies of the Encina Joint Powers find that the need to provide
wastewater treatment capacity to meet projected population growth in the EWPCF service
area overrides the impacts which would result from this project
-32-