HomeMy WebLinkAbout1988-12-13; City Council; 9772; APPROVAL OF CHANGE ORDER NO. 3 FOR PALOMAR AIRPORT ROAD WEST ASSESSMENT DISTRICT PROJECT NO. 3151BILL VI-
RECOMMENDED ACTION:
Adopt Resolution No. 88-Y26 approving Change Order Number 3 for
the construction of the Palomar Airport Road West Assessment District, Project No. 3151.
ITEM EXPLANATION:
The Palomar Airport Road West Assessment District project is currently under construction. Attached Change Order Number 3 is
the addition of necessary drainage and erosion control measures required for the project in advance of the 1988-89 rainy season.
The contractor will apply a straw mulch and spray adhesive to all permanent cut slopes on the north side of Palomar Airport Road to
assist in the stabilization of slope erosion. This area totals
283,215 square feet at a cost of $0.05 per square foot for a
total of $14,160.75. Staff recommends approval of the attached change order.
FISCAL IMPACT:
The total cost of Change Order Number 3 is $14,160.75 which is to
be charged against the Assessment District. There is a sufficient balance of contingency funds available in the project account number 320-820-1840-3151 to enable approval of this
additional project expense.
EXHIBITS :
1. Location map.
2.
\
Resolution No.@?Y& approving Change Order Number 3 for the
Palomar Airport Road West Assessment District project.
3 0 0
& e W
I LOCATION MAP ..... ;'
0. .. .. .. .. .. .. .. .. .. .. -. - -.-.
............. ,.
LEGEND
......... ASSESSMENT 'D I STRICT
BOUNDARY
VIclNfTY w
N. T. S.
L
PROJECT NAME PALOMAR AIRPORT ROAD WEST PROJ- NO* EXHIBIT
ASSESSMENT DISTRICT & IMPROVEMENT PROJECT 3151 1' -
~~
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
a w
RESOLUTION NO. 88-426
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CARLSBAD, CALIFORNIA, APPROVING CHANGE ORDER
NO. 3 FOR THE PALOMAR AIRPORT ROAD WEST ASSESSMENT DISTRICT, PROJECT NO. 3151
WHEREAS, the City Council of the City of Carlsbad, ha
undertaken proceedings in accordance with State law approvin
the formation of the Palomar Airport Road West Assessmen
District; and
WHEREAS, said project is currently under constructio
requiring approval of necessary modifications which are hereb
found to be necessary, desirable and in the public interest
and
WHEREAS, attached Change Order Number 3 is consisten
with the previous findings regarding the formation of sai
Assessment District.
NOW, THEREFORE, BE IT RESOLVED as follows:
1. That the above recitations are true and correct.
2. That Change Order Number 3 for the Palomar Airpor
Road West Assessment District, Project No. 3151, is hereb
approved and the Mayor is authorized and directed to execut
said Change Order. Following the Mayor's signature of sai
Change Order, the City Clerk is further authorized and directe
to return the original of Change Order Number 3, as well as
copy of this Resolution to the Municipal Projects Department fo
processing.
///
///
///
1
2
3
4
5
6
7
8
9
10
11
12
13
I*
15
16
17
18
19
20
21
22
23
24
25
26
27
28
0 0
3. That the Purchasing Officer is authorized a
directed to issue a purchase order change in the amount
$14,160.75 representing the approved cost of said Change Ord
Number 3.
PASSED, APPROVED AND ADOPTED at a regular meeting of t
Carlsbad City Council held on the 13th day of December
1988, by the following vote, to wit:
AYES: Council Members Lewis, Kulchin, Pettine and Mamaux
NOES: None
ABSENT: None
ABSTAIN: Council Member Larson
ATTEST:
aaktl& j.Qf*+ ALETHAJW RAUTENKRANZ, Cit3 Clerk L,
(SEAL)
e CITY OF CARLSBAD w
PUBLIC WORKS PROJECT CHANGE ORDER NO. 3
(More than $5,000)
CONTRACT NO. 3151 PURCHASE ORDER NO. 5744 ACCOUNT NO. 320-820-1840-3151
CONTRACTOR'S NAME CHILCOTE , INCORPORATED
CONTRACTOR'S ADDRESS 2160 Fletcher Parkway, El Cajon, CA 92020
The contractor is directed to make the following changes. Changes shall include labc
material and equipment; payment stated on this change order includes all charges direct
indirect arising out of this additional work. The requirements of the specificatior
where pertinent and not in conflict with this order shall apply to these changes,
This change order is not effective unless signed by the Mayor.
CHANGE :
Apply straw mulch and spray adhesive to north side slopes which totals
approximately 283,215 sq. ft.
REASON FOR CHANGE:
Additional erosion control measure as requested by the City Engineer.
COST: 283,215 sq. ft. x $O.O5/sq. ft. = $14,160.75TIME CHANGE: -
Unit prices X Both Add days -0- Deduct days -0- - Lump sum
Total this extra T 14,T5075 Add/deducrd-his change 7
Previous add/deduct days -0-
Original contract days 300
New contract time 300
PI -27
Date
//AT,/
Chstrulstion ,TKZL Inspector , Da t d
White - Job File Pink - Project Inspector Ye1 1 ow - Contractor Gold - Purchasing with P.O. Change