Loading...
HomeMy WebLinkAbout1992-06-16; City Council; 11737; ACCEPTANCE OF FIRE STATION NO. 2 REMODELI_ * g &; t~,. 2 .. z 0 E $ a z 3 0 0 GI& UP GAHLSUAD - AGEN BILL $5- (.2&l - w AB# y737 TITLE MTG. 06/' 16/92 DEPT. U&M NO. 2 REMODEL CITY Am! CITY MGR: ACCEPTANCE OF FIRE STATION - RECOMMENDED ACTION: Staff recommends acceptance of work in accordance with Contract No. U/M 92-4, as complete and requests direction to the City Clerk to have the Notice of Completion recorded and to release the bonds thirty-five (35) days after recordation. ITEM EXPLANATION: In EY88-89 a total of $225,000 was allocated in the General Capital Construction fund for the renovation of Fire Station No. 2. An architect was hired and a preliminary design, based upon the program needs at that time, was developed but subsequently rejected because the construction cost estimate of $350,000 greatly exceeded the available funding. At the same time, it was discovered that the underground fuel storage tank would need to be removed at a cost of $11,800. In FY90-91 a more cost effective alternative approach was identified by City staff to renovate the station utilizing the remaining funding. The existing footprint of the facility was to be retained to minimize costs. Utilities and Maintenance would accomplish the design "in-house" and manage the project by dividing it into several small contracts. In addition, staff would purchase most of the equipment/material directly from the distributors. Although resulting in a greater administrative burden, this approach coupled with extremely favorable market conditions, maximized the amount of work that could be accomplished with the remaining funding. On December 10, 1991, the City Council awarded contract No. U/M 92-4, in the amount of $81,600, to Vincent C. Cramer, General Contractor, for the major portion of the remodeling work at Fire Station No. 2. Minor change orders amounting to $7,722 resulted in a total contract amount of $89,322. Additional contracts and procurements, that did not require Council approval, totaled $1 08,522. These contracts were for such items as the cabinets/casework, carpeting, systems furniture, fixtures, appliances, a new diesel exhaust system, a new roof and a complete overhaul of the communication system. This brought the total project cost, including the preliminary design and the fuel tank removal, to $229,213. The actual construction took a total of 122 days from start to finish, is now complete and the General contractor's work is acceptable to the Utilities and Maintenance Director. 4 0 0 PAGE 2 OF AB# FISCAL IMPACT: A summary of the final project cost is as follows: Preliminary design 19,569 Removal of underground fuel tank 11,800 General construction contract 89,322 Other contracts and procurements 108,522 Total project cost 229,213 . Total project appropriation General Capital Construction fund 225,000 * General Fund - Major Maintenance 4,213 * The balance of the funding required was allocated from the Utilities and Maintenance Major Maintenance account. EXHIBITS: 1. Notice of Completion 'I F CITY OF CARLSBAU When yecorded mail to: City Clerk City of Carlsbad 1200 Elm Avenue Carl sbad, CA 92008 I i 0 .- :n ' Space above for Recorder's Use