Loading...
HomeMy WebLinkAbout1993-03-23; City Council; 12123; APPROVAL OF CHANGE ORDER NO. 1 FOR PALOMAR AIRPORT ROAD AND EL CAMINO REAL WIDENING, CONTRACT NO. 3166TITLE: APPROVAL OF CHANGE ORDER NO. 1 FOR PALOMAR AIRPORT ROAD AND ECOMMENDED ACTION: Adopt Resolution No. 43-58 and El Camino Real Widening improvements. approving Change Order No. 1 for Palomar Airport R ITEM EXPLANATION: The widening of Palomar Airport Road and El Camino Real is a joint capital project fo Cities of San Marcos, Vista and Carlsbad. Funding for the project comes from the t cities and from many sources including San Diego County sales taxes (TransNet), 5 sales taxes (TDA), traffic impact fees, San Diego County airport contribution, gas tax fu and Carlsbad Municipal Water District (CMWD) capital funds. In December 1992, the construction contract for the widening of Palomar Airport Road El Camino Real was awarded to West Coast General Corporation J.V. for over $6.4 mi Council authorized City Manager approval of individual change orders of $25,000 or to a cumulative value of $650,000. Since Change Order No. 1 exceeds $25,000, the Carlsbad Municipal Code, Sei 3.28.172(c), requires that it be approved by the City Council. Carlsbad Municipal V District staff have reviewed and approved Change Order No. 1, but since this work is of a larger City project, it is appropriate for the City Council to approve the change c versus the Carlsbad Municipal Water District Board of Directors. Change Order No. 1 was required because portions of the pipe specified in the ori contract were not adequate for pressures that it will be exposed to and, therefor( upgrade is necessary. FISCAL IMPACT d u > 0 Bc e Change Order No. 1 will affect costs chargeable to the Carlsbad Municipal Water D only. CMWD capital funds totaling $4 million from major facilities fees and c replacement funds have been appropriated for this project. Currently, funds in the an of $968,000 are available in the two CMWD capital project accounts for Change ( 2 z 1. Location map. 0 a 2. Resolution No. 93-58 approving Change Order No. 1 for Palomar Airport Tto s inc and El Camino Real Widening improvements and directing the project purchase order amount by $47,548.85. 5 6 z 3 3. Change Order No. 1 0 0 I CITY OF VlSTA F CITY OF CARLSBAD BUSINESZ > 33 0 z NOT TO SCALE PROJECT E NUMBER PAR-ECR 3166 PROJECT NAME DRAW 8Y SCOTT EVANS. CARLSEAO ENGINEERING OEPT 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 0 RESOLUTION NO. 93-58 A RESOLUTION OF THE CrrY COUNCIL OF THE CITY OF CARLSBAD, CALIFORNIA, APPROVING CHANGE ORDER NO. 1 FOR PALOMAR AIRPORT ROAD & EL CAMINO REAL WIDENING, CONTRACT NO. 31 66 WHEREAS, construction of improvements on Palomar Airport Road and El Can Widening, Project No. 31 66, has necessitated contract Change Order No. 1 ; and WHEREAS, funds in the amount of $47,548.85 for said change order are av Account Nos. 505-820-1 860-31 66/506-820-1860-3166. NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of ( California, as follows: 1. That the above recitations are true and correct. 2. That Change Order No. 1 for Palomar Airport Road and El Camino Real improvements, specifically identified as Contract No. 31 66, is approved. PASSED, APPROVED AND ADOPTED at a regular meeting of the Carlsbad Cil held on the 23rd day of MARCH , 1993 by the following vote, to wit: AYES: Council Members Lewis, Stanton, Nygaard, Finnila NOES: None ABSENT: Council Member Kulchin ATTEST: &&Mil (SEAL) 0 0 CITY OF CARLSBAD PROJECT: Widening of Palomar Airport Road and El Camino Real CONTRACT CHANGE ORDER NO.l CONTRACT NO. 3166 P.O. NO. ACCOUNT NO. 505-820-1 86031 66/506-820486031 t CONTRACTOR: West Coast General Corporation J.V. ADDRESS: 12243 Hiahwav 67, Lakeside, California 92040 The Contractor is directed to make the following changes as described herein. Changes shall incluc all labor, materials, equipment, contract time extension, and all other goods and services required implement this change. Payment stated on this change order includes all charges, direct or indirec arising out of this additional work and is expressly agreed between the City and the Contractor to be tt complete and final costs hereof. The requirements of the specifications, where pertinent and not conflict with this change order, shall apply to these changes. This change order is not effective unle! signed by the City Manager and/or the Mayor. Pursuant to subsection 3-2.2.3, Agreed Prices, Standard Specifications for Public Works Constructio 1991, perform the following: Item 1: Delete item 2-1 6, 30' cement mortar lined and coated 10 gauge steel pipe, etc. from tt contract. Decrease to Contract Cost ................................. <$44,024.42 Provide and install approximately 2,134 linear feet of 30' cement mortar lined and coat( steel pipe with minimum wall thickness of .2188' including removals, excavation, beddin fittings, polywrap, thrust blocking and backfill complete and in place; 2,134 L.F. @ $37.02/LF ...................................... $79,003.d Increase to Contract Cost ..................................... $79,003.1 Delete item 2-3, point of connection (PC-2) 6 ft. rt. centerline station 108+05, etc. Decrease to Contract Cost .................................. <$6,955.00 Provide new point of connection (PC-2) 6 ft. tt. centerline station 108+05 complete ar in place including removals, steel pipe, (.135' wall thickness) and fittings. Increase to Contract Cost ...................................... $7,417.1 Delete one unit (one 16' butterfly valve) from contract pay item 2-21, 16' butterfly val including valve box assembly, complete and in place. Decrease to Contract Cost .................................. <$2,568.OC Item 2: Item 3: Item 4: Item 5: H:\LlBRAR\nENG\WPDATA\INSPECl7CHGORDER\3166-1 .CHG e Change Order #I Contract 31 66, Widening of Palornar Airport Road and El Camino Real Item 6: Provide and install class 250 16' butterfly vatve including valve box, assembly at statil 108+05 complete and in place. Increase to Contract Cost ...................................... $4,126 Pursuant to subsection 33, Extra Work, Standard Specifications for Public Works Construction, 19 perform the following as directed by the Engineer: Item 7: Upgrade Cat225B excavator to Cat235-C excavator for installation of approximately 2,l LF. of 30' CML&C steel pipe (.2188' wall thickness). Costs for upgrade shall consist move in of Cat235C and differences between rental rate of Cat225B and 235C excavat Estimated Increase to Contract Cost ............................. $5,000 TOTAL ESTIMATED INCREASE TO CONTRACT COST ........................ $47,548 H:\LIBRARY\ENG\WPDATA\INSPECT\CHGORDEf331661 .CHG 0 e Change Order #1 Contract 31 66, Widening of Palomar Airport Road and El Camino Real TIME FOR COMPLETION OF ALL WORK UNDER THIS CONTRACT SHALL NOT BE AFFECTED BY THI CHANGE ORDER. RECOMMENDED BY: APPROVED BY: CONTRACTOR (DATE) L22LuL yyy.9 <e @ATE) PRlNCfPAL INSPECTOR 7hh C.M.W.D. DISTRICT ENGINEER '(6ATE) EXECUTIVE G.M./PRESIDENT (DATE) COMM. DEV. DIRECTOR (DATE) 'i3//ah3 (DATE) DISTRIBUTION: INSPECTION FILE (ORIGINAL) PURCHASING (W/P.O. CHANGE ORDER) FINANCE CONTRACTOR H:\LlBW\RY\ENG\WPDATA\INSPECnCHGORDER\316&-1 .CHG