I RECOMMENDED ACTION:
Adopt Resolution No. %'- I*3 accepting the Magnolia Avenue, Valley Stre
Drive Sidewalks, as complete and directing the City Clerk to record a Notice o
and release bonds in accordance with State Law and City Ordinances.
ITEM EXPLANATION:
On June 11, 1996, Castello, Inc., was awarded a contract in the amount of
for construction of Magnolia Avenue, Valley Street and Park Drive Sidewalks.
Castello, Inc., completed the work on February 6, 1997. City forces have in:
work and found it to be satisfactory. Staff recommends formal acceptance
Council.
FISCAL IMPACT:
A summary of the final project cost is as follows:
a Lkl 6
2
cg: fL
z 0 F 2
1
0 z 3 0 0
-
EXHIBITS:
1. Location map.
2. Resolution No. 9 9 -io?
3. Notice of Completion.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
0 0
RESOLUTION NO, 97-103
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
CARLSBAD, CALIFORNIA, ACCEPTING THE CONSTRUCTION
OF MAGNOLIA AVENUE, VALLEY STREET AND PARK DRIVE
SIDEWALKS, PROJECT NO. 3391-3.
WHEREAS, the construction of Magnolia Avenue, Valley Street and
Sidewalks has been satisfactorily completed; and
WHEREAS, the formal project Notice of Completion has been prepared; and
WHEREAS, all project costs have been established to date.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City c
California, as follows:
1. That the above recitations are true and correct.
2. That the construction of Magnolia Avenue, Valley Street and Park Drive
specifically identified as Project No. 3391-3, is deemed complete and hereby acceptc
3. The City Clerk of the City of Carlsbad is hereby authorized and directed
the Notice of Completion and have same recorded.
4. That bonds will be released in accordance with State Law and City Ordin
PASSED, APPROVED AND ADOPTED at a regular meeting of the Ca
Council held on the 18th day of MARCH , 1997 by the following vote, to
AYES: Council Members Lewis, Finnila, Nygaard, Kulchin, Hall
NOES: None
ABSENT: None
ATTEST:
ALETHA. L. RAUTE~KRANZ, City Clerk (SEAL)
~
"-
I - LOCATION MAP m
I
- AREAS OF CONSTRUCTION
PROJECT. NAME SIDEWALKS 3 PROJECT
NUMBER 3391-3
l e 0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
RESOLUTION NO. 97-103
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
CARLSBAD, CALIFORNIA, ACCEPTING THE CONSTRUCTION
OF MAGNOLIA AVENUE, VALLEY STREET AND PARK DRIVE
SIDEWALKS, PROJECT NO. 3391-3.
WHEREAS, the construction of Magnolia Avenue, Valley Street and I
Sidewalks has been satisfactorily completed; and
WHEREAS, the formal project Notice of Completion has been prepared; and
WHEREAS, all project costs have been established to date.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City o
California, as follows:
1. That the above recitations are true and correct.
2. That the construction of Magnolia Avenue, Valley Street and Park Drive
specifically identified as Project No. 3391-3, is deemed complete and hereby acceptt
3. The City Clerk of the City of Carlsbad is hereby authorized and directec
the Notice of Completion and have same recorded.
4. That bonds will be released in accordance with State Law and City Ordir
PASSED, APPROVED AND ADOPTED at a regular meeting of the C:
Council held on the 18th day of MARCH , 1997 by the following vote, to
AYES: Council Members Lewis, Finnila, Nygaard, Kulchin, Hall
NOES: None
ABSENT: None
ATTEST:
ALETHA L. RAUTE~KRANZ, City Clerk (SEAL)
28
6 e e
Recording requested by:
CITY OF CARLSBAD
When recorded mail to:
City Clerk
City of Carlsbad
1200 Carlsbad Village Dr.
Carlsbad, CA 92008 I Space above this line for Recordel
NOTICE OF COMPLETION
Notice is hereby given that:
1. The undersigned is owner of the interest or estate stated below in the property hereinafter de,
2. The full name of the undersigned is City of Carlsbad, a municipal corporation.
3. The full address of the undersigned is 1200 Carlsbad Village Drive, Carlsbad, California 920C
4. The nature of the title of the undersigned is: In fee.
5. A work of improvement on the property hereinafter described was completed on February 6,
7. The property on which said work of improvement was completed is in the City of Carlsbad, C
San Diego, State of California, and is described as the construction of Magnolia Avenue
Street and Park Drive Sidewalks, Project No. 3391-3.
6. The name of the contractor, if any, for such work of improvement is Castello, Inc.
8. The address of said property is within the limits of the City of Carlsbad.
City Engheer
VERIFICATION OF CITY CLERK
I, the undersigned, say:
I am the City Clerk of the City of Carlsbad, 1200 Carlsbad Village Drive, Carlsbad, Californi:
the City Council of said City on March 18 , 1997, accepted the above describec
completed and ordered that a Notice of Completion be filed.
I declare under penalty of perjury that the foregoing is true and correct.
Executed on April 3 , 1997, at Carlsbad, California.
CITY OF CARLSBAD
City Clerk
,
I
April 2, 1997
Gregory J. Smith
County Recorder
Post Office Box 1750
San Diego, CA 92112-4147
RE: NOTICE OF COMPLETION
Enclosed for recordation is the following described document:
Notice of Completion
Castello, Inc.
Construction of Magnolia Avenue, Valley Street and Park Drive Sidewalks
Project No. 3391-3
Also enclosed are instructions on how the City is to be billed for the recordation fee
incurred. Thank you for your assistance in this matter.
ll.4.ZLK.P-
ALETHA L. RAUTENKRANZ, CMC
City Clerk
ALR:ijp
Enclosures
" "_
1200 Carlsbad Village Drive - Carlsbad, California 92008-1 989 - (760) 434-: