HomeMy WebLinkAbout1998-04-21; City Council; 14648; AUTHORIZATION TO ADVERTISE FOR BIDS FOR THE 1998 NORTHEAST QUADRANT PAVEMENT OVERLAY AND CONCRETE REPAIRS PROJECT$
Cl'r f OF CARLSBAD -AGENDA blLL 0 0 47
AB# 14,648
CITY ATTY. 2 PAVEMENT OVERLAY AND MTG. 4/2 1 /98
TITLE: AUTHORIZATION TO ADVERTISE FOR
BIDS FOR THE 1998 NORTHEAST QUADRANT
I CONCRETE REPAIRS PROJECT, PROJECT NO. 3558-1 DEPT. ENG - CITY MGR. 3
RECOMMENDED ACTION:
Adopt Resolution No. 98-122 approving plans and specifications and authorizing the City
to advertise for bids for the 1998 Northeast Quadrant Pavement Overlay and Concrete Repairs PI
Project No. 3558-1.
ITEM EXPLANATION:
For a number of years, the City of Carlsbad has made a strong commitment to a preven
maintenance program for city streets. The goal of the program is to extend the life of city paver
and reduce the amount of costly roadway reconstruction. To identify streets in need of rehabili
the city is systematically surveyed using a combination of visual inspection, input from the :
maintenance division, and recommendations from MicroPaver Pavement Management Softm
Once streets are identified a combination of chip seals, slurry seals, and pavement overlays are
to revitalize and protect existing pavements.
In the past the Pavement Management Program was based on a City-wide division into four quadl
A survey of all streets within one of the four quadrants determined rehabilitation needs for that .
year, Streets in the quadrants were rotated in clockwise order each fiscal year for prevenl
maintenance.
a $
e 0 I-I
4
z 0 F 0 B
-I 5 z 3 0
Starting with the current contract being advertised at this time, designated the Northeast Qua'
Overlay, the program will move away from a strictly quadrant based rotation schedule. A city
review of streets is ongoing and contracts will begin to include distressed streets not located withi
current year's quadrant. This will make the program more flexible, efficient and will allow the c
rehabilitate distressed streets which are in need of repair immediately, but are not located withi
current year's quadrant. It will also allow the city to schedule streets for construction at more effi
times of the year (i.e. streets fronting schools are constructed in the summertime instead of s(
hours, streets fronting construction sites are constructed after construction instead of durir
Eventually, the Pavement Management Program will review and rehabilitate streets solely on E
wide basis.
The following future contracts will immediately follow the northeast quadrant overlay contract fo
fiscal year: (1)Southeast Quadrant Overlay, (2)Northeast and Southeast Quadrant Slurry Seal
areas will be combined into one contract). Each will be brought to the city Council for authorizati'
bid.
Minor concrete repairs and root pruning will be performed on portions of these streets in conjun
with street overlays.
ENVIRONMENTAL REVIEW:
This project is categorically exempt from the environmental review process under Section 1530 Class 1 (C) of the Public Resources Code (California Environmental Quality Act).
I (5,
Page 2 of AB 1114,648 0 0
FISCAL IMPACT:
The estimated cost to complete this project is:
Construction (Engineer’s Estimate) Construction Contingency (1 0%)
Project Administration & Inspection (1 0%) TOTAL
$486,900 $48,690 $48.690
$584,280
One million dollars has been budgeted in the 1997-98 Capital Improvement Program that wi
pavement maintenance contracts.
Sufficient TransNeffLocal funds have been appropriated to build this project. Sewer manholes a
water valve box adjustments will be paid for by Carlsbad Municipal Water District funding, whici- estimated at $54,820.
EXHIBITS:
1. Location Maps(Exhibit 1, consisting of three sheets)
2. Resolution No. 98-122 approving plans and specifications and authorizing the C
Clerk to advertise for bids for the 1998 Northeast Quadrant Pavement Overlav a
Concrete Repairs Project, Project No. 3558-1.
e 0
- STREETS TO
BE OVERLA YED
NOT TO SCALE
PROJECT NAME
QUADRANT OVERLAY
e 0
- STREETS TO
BE 0 VERLA YED
0 0
- - STREETS ro
BE OVERLA YED
NOT TO SCALE
SHE€
QUADRANT OVERL
0 0
I RESOLUTION NO. 98-122
2
3
4
5
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CARLSBAD, CALIFORNIA, APPROVING PLANS AND SPECIFICATIONS AND
AUTHORIZING THE CITY CLERK TO ADVERTISE FOR BIDS FOR THE
1998 NORTHEAST QUADRANT PAVEMENT OVERLAY AND CONCRETE
REPAIRS PROJECT, PROJECT NO. 3558-1.
,
WHEREAS, the City Council of the City of Carlsbad, California, has determint
6 necessary, desirable, and in the public interest to repair concrete curb, gutter and sidewalks
resurface asphalt streets; and 7
8 WHEREAS, the plans and specifications for furnishing of all labor, material, t
9
prepared and are on file in the Engineering Department of the City of Carlsbad anc IO
equipment, transportation and other expenses necessary or incidental for said project have I
11 incorporated by reference herein:
12 NOW, THEREFORE, BE IT RESOLVED by the City Council 'of the City of Carl!
13 California, as follows:
I. That the above recitations are true and correct.
2. That the plans, specifications, and contract documents as presented are ht
14
15
approved.
16 3. The City Clerk of the City of Carlsbad is hereby authorized and directed to pu
in accordance with State law, Notice to Contractors Inviting Bids for the 1998 Northeast Qua 17
l8 Pavement Overlay and Concrete Repairs Project, Project No. 3558-1.
19 PASSED, APPROVED AND ADOPTED at a regular meeting of the Carlsbad City Cc
20 held on the 21 day of April , 1998 by the following vote, to wit
21 AYES:Council Members Lewis, Kulchin, Hall, Nygaard & Finnila
22
23
24
25
26 I ! ATTEST:
27 . I
28 (SEAL)