HomeMy WebLinkAbout2000-12-12; City Council; 16004; Phase 2 Cole Library RemodelCITY OF CARLSBAD -AGENDA BILL
APPROVAL OF RATIFICATION OF DEPT. HD.
MTG. 12/l 2/00 ACCEPTANCE OF BIDS, APPROPRIATION
DEPT. CD
PROJECT
RECOMMENDED ACTION:
Staff recommends the City Council ADOPT RESOLUTION NO. a&X? l 380 approving
a Ratification of Amendment No. 1 to the existing architectural agreement, accepting bids,
approving the appropriation of additional funds, and awarding a contract for the
construction of Phase 2 of the Georgina Cole Library Remodel Project, City Project No.
33841.
ITEM EXPLANATION:
On October 17, 2000, the City Council approved the plans and specifications and
authorized the advertisement of bids for the construction of Phase 2 of the Georgina Cole
Library Remodel Project. On November 28, 2000, seven (7) sealed bids for the project
were received as follows:
CONTRACTOR BASE BID SCHEDULE “A’ TOTAL BID
Hafner / Bergman Corporation
Chino, California
$587,937 $38,902 $626,839
Marcotte & Hearne
San Diego, California
$605,000 $29,650 $634,650
Alexander & Associates
Orange, California $614,572 $50,974 $672,546
Pullman Engineering
San Diego, California
$563,908 $77,479 $68 1,806
Golden Springs Construction
Santee, California
$624,507 $62,150 $686,657
Har Construction
National City, California
$756,549 $44,092 $800,641
SMC Construction
Costa Mesa, California
$764,230 $62,800 $847,030
City’s Construction Estimate: $750,000
Bonds, licenses, and references have been reviewed and verified for the lowest
responsive, responsible bidder. Staff recommends the bids received by the City for this
project be accepted and a contract awarded to Hafner / Bergman Corporation in the
amount of $626,839 for both the Base Bid as well as Schedule “A.”
Construction is estimated to begin in early January and require approximately 4 months to
complete, weather permitting. As indicated in previous presentations, the work associated
/
PAGE 2 OFAGENDklLL NO. /6! 004
with this project is focused upon the exterior of the Georgina Cole Library building. At no
time during the construction will the building be closed to the public.
FISCAL IMPACT:
Previously, the City Council approved a total of $2,132,862 in the CIP budget for the 2
phases of this project. The source of funds for this project is Public Facilities Fee funds.
The first phase, the extensive remodeling and upgrade of the interior of the Cole Library
facility, was completed in April of this year with a final project cost of $1,385,697. This
leaves an estimated $706,834 for the second phase. Staff requests the City Council
approve an additional appropriation of $200,000 from the Public Facilities Fee Fund for
soils testing, inspection, construction management, contingencies, and the Ratification of
Amendment No. 1 to the existing architectural agreement that will be required of this
second phase of the project. Funds are available for this appropriation.
Ratification of Amendment No. 1 to the existing design agreement with the City’s Library
Architects from McGraw / Baldwin Architects in the amount of $40,696 is required due to
the following design scope changes:
1. Development of additional design alternatives;
2. Screen wall study and subsequent removal;
3. West window elevation structural design;
4. Required exit study and design of automatic door openers;
5. Lighting design modifications and coordination;
6. Structural design modifications and coordination;
7. Various plan set revisions, new exhibits, and additional meetings.
Staff recommends approval of this Ratification of Amendment No. 1
EXHIBITS:
1. Resolution No2000-380 regarding Phase 2 of the Georgina Cole Library
Remodel Project.
2. Ratification of Amendment No. 1 with McGraw / Baldwin Architects.
3. Bids on file in the Purchasing Department.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
RESOLUTION NO. 2000-380
A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF CARLSBAD, CALIFORNIA, APPROVING A
RATIFICATION OF ARCHITECTURAL AGREEMENT
AMENDMENT NO. 1, ACCEPTANCE OF BIDS,
APPROPRIATION OF ADDITIONAL PROJECT FUNDS,
AND AWARD OF CONTRACT FOR PHASE 2 OF THE
GEORGINA COLE LIBRARY REMODEL PROJECT
WHEREAS, on October 17, 2000, the City Council of the City of Carlsbad, California,
approved the plans and specifications and authorized the solicitation of bids for the construction
of Phase 2 of the Georgina Cole Library Project, City Project Number 33841; and
WHEREAS, seven (7) sealed bids were received and opened by the City on November
28,200O for said project; and
WHEREAS, additional funds are required for the project construction including related
construction activities, inspection, and contingency costs; and
WHEREAS, a Ratification of Amendment No. 1 to an existing architectural design
agreement has been prepared and is hereby submitted for approval; and
WHEREAS, the City Council does hereby find it necessary, desirable, and in the public
interest to award said construction contract.
NOW, THEREFORE, BE IT RESOLVED AS FOLLOWS:
1. That the above recitations are true and correct.
2. That Ratification of Amendment No. 1 to an existing agreement with McGraw /
Baldwin Architects is hereby approved and the Mayor is authorized to execute said documents.
Following the Mayor’s execution of said documents, the City Clerk is directed to forward copies
of this resolution and the amendment to McGraw / Baldwin Architects, attention: Mr. Kennon
Baldwin, 701 B Street, Suite 200, San Diego, California 92101-g 101, and the Library and
Community Development Departments.
II
1 3. That the City Council does hereby appropriate $200,000 from the Public Facilities
2 Fee Fund to the project account as additional project funds.
3 4. That the City Council does hereby authorize the City Manager to approve necessary
4 construction change orders and incidental project modifications up to and not to exceed the value
5
6 of the available project contingency.
7 5. That the aforementioned bids received and opened by the City on November 28,
8 2000 are hereby accepted and the construction contract is hereby awarded to the lowest
9 responsive, responsible bidder, Hafner / Bergman Corporation in the amount of $626,839 for
10 both the “Base Bid” and “Schedule A” as defined within the project plans and specifications.
11
12
13
PASSED, APPROVED, AND ADOPTED at a regular meeting of the Carlsbad City Council on
the 12th dayof December ,2000, by the following vote, to wit:
14
15
16
17
AYES: Council Members Lewis, Hall, Finnila, Nygaard and Kulchin.
NOES: None
ABSENT: None
18
19
20
(ATTEST)
CLAUDE A. LEWIS, Mayor
M. WOOD, City Clerk
24
25
26
27
28 -2-
RATIFICATION OF AMENDMENT NO. 1 TO AGREEMENT
FOR SUPPLEMENTAL DESIGN SERVICES FOR PHASE 2
OF THE COLE LIBRARY REMODEL PROJECT
This Ratification of Amendment is entered into the 27th day of
December , 2000 but effective as of the 27th day of September, 2000, ratifying the
amendment of the Agreement dated April 20, 2000, by and between the City of Cartsbad, a
municipal corporation, hereinafter referred to as “City,” and McGraw / Baldwin Architects,
hereinafter referred to as “Contractor” for Phase 2 of the City’s Cole Library Remodel Project.
RECITALS
WHEREAS, the initial Agreement, dated April 20, 2000 identified a scope of work
which includes the planning, pre-design, and design of exterior improvements to the Cole
Library; and
WHEREAS, the parties to the Agreement desire to alter the scope of work to
include supplemental design services for architectural, cost estimating, structural engineering,
and electrical engineering; and
WHEREAS, a supplemental scope of work and fee schedule have been
negotiated and agreed to between the parties, and is attached hereto and incorporated herein
by reference as Exhibit “A” Scope of Services and Fee proposal letter dated September 27,
2000; and
WHEREAS, the City and Contractor desire to ratify any amended scope of work
already performed by the Contractor without benefit of this amendment of the Agreement dated
April 20, 2000.
NOW, THEREFORE, in consideration of these recitals and the mutual covenants
contained herein, City and Contractor hereby agree as follows:
1. The retroactive amendment of the Agreement is ratified.
2. Contractor shall provide services as outlined on the attached Exhibit “A”.
3. City shall pay Contractor for all work associated with Paragraph 1 above, on
a time and materials basis not-to-exceed $40,696. Contractor shall provide City on a monthly
02/04/00
basis, copies of invoices sufficiently detailed to include hours performed, hourly rates, and
related activities and costs for approval by City.
4. Contractor shall complete all work outlined on the attached Exhibit “A” by
December 15, 2000, or by expiration of the Agreement as amended hereby.
5. All other provisions of the Agreement and any amendments thereto shall
remain in full force and effect.
6. All requisite insurance policies to be maintained by the Contractor pursuant
to the Agreement and any amendments thereto shall be extended to include coverage for the
extension period.
Acknowledged and Accepted:
McGraw / Baldwin Architects 1~~.
PI,. &N x3&h
4.- -
Y- “Y’ 1 ---, -
CONTRACTOR:
&gn here) ATTEST;. ,1 -. I.. :,/ ,. ”
uh ta@umrrv
_* ,.____ .L
December 27, 2000
DATE
(Proper notarial acknowledgment of execution by Contractor must be attached.
Chairman, president or vice-president and secretary, assistant secretary, CFO or assistant
treasurer must sign for corporations. Otherwise, the corporation must attach a resolution
certified by the secretary or assistant secretary under corporate seal empowering the officer(s)
signing to bind the corporation.)
APPROVED AS TO FORM:
RONALDk. BALL, City Attorney
02104lOO
CALIFORNIA ALL-PURPOSE ACKNOWLEDGMENT
State of California
County of .r* ~)j~~~ 1
ss.
On &&IV &TIC 5: c&%X2 , before me, /tllo,: Y !z%AL?T ~rZGil’%GW, h(% i?H V Puf3 LI C ,
Date Name and Title of Ofker (e.g., ‘Jane Doe. Notary Public”)
personally appeared kiZW~ d k! - &WOW~ p.~afbJ.~~mPC R. LGaTlul IGCC. fP.,
x ersonally known to me
0 proved to me on the basis of satisfactory
evidence
Notory Pl.lI:iIC - rh!iforria
to be the person(s) whose name(s) Ware
subscribed to the within instrument and
acknowledged to me tha tAo&Mthey executed
the same in t&&m&heir authorized
capacity(ies), and that by k&&&their
signature(s) on the instrument the person(s), or
the entity upon behalf of which the person(s)
acted, executed the instrument.
WITNESS my hand and official seal.
Place Notary Seal Above
OPT/O/VA L
Though the information below is not required by law, it may prove valuable to persons relying on the document
and could prevent fraudulent removal and reattachment of this form to another document.
Description of Attached Document
Title or Type of Document: ‘%wI~-‘K.A~~~w Am@cuntni’~ NO. I .7’0 ,A- m ..;#y&,pJ~ m,ri,
Syfyuzrn~c, i]FSrbrJ 5.5t3j,c.~: Fag pws&; 2 0~ * ~LXC Cl~,~day ,Q.~vIc~J~;~
Document Date: Number of Pages:
Signer(s) Other Than Named Above:
Capacity(ies) Claimed by Signer
Signer’s Name:
0 Individual
0 Corporate Officer - Title(s):
Cl Partner - 0 Limited 0 General
q Attorney in Fact
0 Trustee
0 Guardian or Conservator
0 Other:
Signer Is Representing:
Q 1997 National Notary Association - 9350 De Soto Ave., P.O. Box 2402 - Chatswcxth. CA 91313-2402 Prod. No. 5907 Reorder: Call Toll-Free 1-600-676-6627
McGratilBalc”-in Architects EXHIBIT "A"
September 27,200O
John Cahill
Municipal Projects Manager
City of Carlsbad
1635 Faraday Avenue
Carlsbad, CA 92008
Subject: Proposal for Additional Services
Cole Library Exterior Improvements
MBA Project No. 00014
Dear John:
McGraw/Baldwin Architects finds it prudent to submit this proposal for additional services dealing with the screen wall and lighting enhancement designs and required on-going
efforts.
SCOPUSERVlCES INCLUDED
Our understanding of the known additional scope is as follows:
Screen wall design
West window fin design
Fin and screen wall structural design
Structural design coordination Automatic door opener study
Exit study
Increased lighting capacity Cost estimate
Additional team meetings
Four-week project design extension Design renderings
Removal of screen walls Redesign and coordination of Landscape drawings
COMPENSATION FOR SERVICES
We propose to increase our architectural hourly, not to exceed, budget by $27,210.00. In
addition, we request a payment increase for the following disciplines: structural
engineering, $9,750.00; cost estimation, $736.00; and electrical engineering, $3,000.00.
The total of these increases is $40,696.00, as summarized on the attached Additional
Service Proposal Task Summary dated September 27,200O.
If this proposal is acceptable to you, please indicate your,acceptance of this proposal by
signing in the space provided below and returning a copy to our office. This letter will
form the basis of our Agreement and may be terminated by either party upon not less
than seven- (7) days’ written notice. This proposal shall remain valid for ninety- (90) days.
We appreciate this opportunity and look fonvard to continuing our work on this important
project. Should you have any questions, we are available at your convenience.
Kennon W Baldwin, Architect. 41A. President James T. Ferguson, Architect, AIA. Vice President 701 5 Street, Suite 200
David E. Cummins, Architect, AIA., Senw Asscclate Christopher Knell. Architect, AIA. Senior .r\ssoclate San Diego, CA 92101-8101
Theodore R. Breunich. Jr \/ICC Presldeni, CFC Jerry Cole. Vtce President, Buslnesc Develop(ment (619) 231-0751 FAX (619) 231-4396
James S. McGraw. AIA (1942-1996) www.mbarch.com
-
John Cahill Proposal for Additional Services
September 27,200O
Page 2
Sincerely, Agreed to by:
McGraw/Baldwin Architects Inc. City of Carlsbad
P’hilip Pipe
Project Manager
CA License No. C-25595
Attachments as noted
cc: K. Baldwin, T. Breunich - M/BA
John Cahill Municipal Projects Manager
Date:
McGraw/Baldwin Architects
fvlcGrawlBalr”~n Ardhitects
McGraw I Baldwin Architects Inc.
Cole Library Exterior Upgrade
ADOlTfONAL SERVICE PROPOSAL TASK SUMMARY
PROJECT NUMBER: WOl4
PRINT DATE: 27-sep-00
ESTIMATE FOR REIMBURSABLES 5,150
a
b
c
Structural DesignlBiddinglCA
Blaylock Engineering Group
See attached fee proposal for brake down of hours
Electrical Design
Van Buuren Kimper Engineering
See attached memo from Barth Ballard for the revised scope of work
Cost Estimating
CAI
See attached invoice for work performed
9.750.00 4.350.00 14.100.00
3,ooo.oo 4.500.00 7,soo.oa
736.00 736.00
Kennon W. BaldwIn. Architact. AIA. President James T. Ferguson. Architect, AIA, Vice President 701 B Street, Suite 200
David E. Cummlns, Architect. AIA, Senior Associate Christopher Knell. Architect. AIA. Senior Associate San Diego, CA 92101-8101
Theodore R. Breuntch. Jr.. VICF: Presldeni. CFO .jerry Cole Vice Presiden!. Business Development 1619) 231.0751 FAX (619) 231-4396
James S. McGraw, AIA (194%1996) www.mbarch.com