HomeMy WebLinkAbout2001-09-25; City Council; 16371; Relocation Of Transmission Lines Cannon RoadCITY OF CARLSBAD - AGENDA BILL c+
AB# 16 \ 37 1 TITLE: APPROVACOF AN AGREEMENT WITH
SDG&E FOR THE RELOCATION OF TRANSMISSION LINES MTG. 9/25/o 1 WITHIN THE CANNON ROAD WEST RIGHT-OF-WAY
DEPT. ENG PROJECT NO. 3184
RECOMMENDED ACTION:
Adopt Resolution No. WI- aqv approving an agreement with San Diego Gas and Electric
(SDG&E) for the relocation of a transmission line.
ITEM EXPLANATION:
Cannon Road West Reach 2 Segment 2 (Segment 2)‘ which will extend Cannon Road to El Camino
Real, is proposed to start construction in September 2001. The project requires the relocation of a
SDG&E transmission line located within the Segment 2 alignment. Kelly Land Company (KLC) has
been conditioned to construct Segment 2. Segment 2 is funded through Bridge and Thoroughfare District No. 3 (BTD). The BTD funds all improvements required to grade the full roadway right-of-
way.
The Segment 2 project required the relocation or reconstruction of several SDG&E facilities.
Since SDG&E has prior rights over the easements, the City must pay for the relocation costs of the
transmission line. The original fee letters were provided in 1998 and 1999. Detailed information
regarding these facilities is included in the attached Table A.
KLC planned to piggy back the construction of Segment 2 after completing the Segment 1
improvements. However, the California Coastal Commission appealed the tentative map and related
discretionary actions after approval by the City Council. This appeal delayed the construction of the
roadway for several years.
The power pole relocation requires the grading of a pad outside of the right-of-way. This grading is
part of the Kelly Ranch Core project by KLC. In the last few years, costs associated with
constructing the new power pole have escalated. In addition, costs incurred in the construction of
the other facilities exhausted the funds provided to SDG&E previously. The cost estimate to
complete the two-pole structure is $43,686. The City has previously paid SDG&E $231,965 for the
design and relocation or reconstruction of facilities located within the Cannon Road West alignment.
Staff recommends approving the agreement with SDG&E to relocate the power pole.
ENVIRONMENTAL IMPACT:
The Planning Director has determined that the requested action is consistent with prior CEQA
review. The project was reviewed in the Cannon Road Reach 1 Environmental Impact Report, the Kelly Ranch Environmental Impact Report and the Mitigated Negative Declaration for Reach 2.
Significant environmental impacts identified by those CEQA documents were determined to be mitigable to levels of less than significant. Permits from the resource agencies have been received.
FISCAL IMPACT:
The estimated cost for the relocation of the two-pole structure is $43,686. Totals costs for the
relocation or reconstruction of all SDG&E facilities are $275,671. The BTD anticipated a cost of
$333,259 for the relocation or reconstruction of all SDG&E facilities. Sufficient funds are available in the project account.
Page 2 of Agenda Bill No. I b I 3 7 1
EXHIBITS:
1. Location Map.
2.
3.
Table A, SDG&E Facility Relocations in Cannon Road West.
Resolution No. do0 kdq8 approving an agreement with San Diego Gas and Electric
Company for the relocation of facilities within the Cannon Road West right-of-way.
4. Agreement for Transmission Line Relocation Cannon Road West Reach 21, Project No.
3184.
5. Letter from SDG&E dated July 18,200l.
REACH 2 I
I
:XHIBIT
NOT To SCALE
r PROJECT NAME - 1 .,.,A., -h 1 A ,.,-m-r CAN/VU/V HUAV VVtW
EXHIBIT 2
Table A: Completed SDG&E Facility Relocations in Cannon Road West
WorkOrder Number 1 713868-010 1 605166-040 1 650166-060 1 Totals I I I I
Materials and Labor $ 50,179.45 $ 145,477.63 $ 15,549.41 $ 211,206.49
Engineering $ 13,022.77 $ 11,690.02 $ 1,263.48 $ 25,976.27
Subtotal $ 63.202.22 $ 157.167.65 $ 16.812.89 $ 237.182.76
Balance of all projects1 $ (1,735.15)ISDG&E wrote off this total I I
4
2
3
4
5
6
7
6
9
10
11
12
RESOLUTION NO. 2001-298
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CARLSBAD, CALIFORNIA, APPROVING AN AGREEMENT WITH
SAN DIEGO GAS AND ELECTRIC COMPANY FOR THE RELOCATION OF A TRANSMISSION LINE WITHIN THE
CANNON ROAD WEST RIGHT-OF-WAY. PROJECT NO. 3184.
WHEREAS, the City Council of the City of Carlsbad, California has reviewed the need for
the relocation of the San Diego Gas and Electric transmission lines and determined it to be in the
best interest of the Cannon Road project to relocate the transmission line with the Cannon Road
grading; and
WHEREAS, a mutually satisfactory agreement for the relocation has been negotiated with
San Diego Gas and Electric Company agreement (the “Agreement”); and
WHEREAS, the City Council recognizes the need to have the transmission line
relocated; and
13 WHEREAS, the project is in full compliance with the California Environmental Quality
I4 Act; and
15 WHEREAS, the Agreement with San Diego Gas and Electric has been prepared and
16 submitted hereto; and
17 WHEREAS, it is in the best interest of the City to approve the Agreement.
16 NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Carlsbad,
1g California, as follows:
20
21
1. That the above recitations are true and correct.
2. That the Agreement, a copy of which is attached as Exhibit 3 and made a part
hereof,
22
Ill
23 ill
24 Ill
25 Ill
26 Ill
27 I//
28 Ill
is hereby approved.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
3. That sufficient funds are available for the relocation of the San Diego Gas and
Electric transmission line.
4. That the Mayor is hereby authorized and directed to execute the Agreement.
PASSED, APPROVED AND ADOPTED at a regular meeting of the Carlsbad City Council
held on the 25th day of September , 2001 by the following vote, to
wit:
AYES: Council Members Lewis, Kulchin, Finnila, and Hall.
AI-I-EST:
LO$&UNE M. WOOD, Cit$&lerk (SEAL)
SEP-04-2001 09: 49 CITY OF CRRLSBFID 760 431 5769 P.02/11
AGREEMENT FOR TRANSMISSION LtNE RELOCAltON
CANNON ROAD WEST REACtI 2
PROJECT NO. 3184
THJS AGREEMENT is made and entered into this 2nd day Of October , 2001,
by and between the City of Cartsbad, a municipal corporation, hereinafter referred to as “City”
and San Diego Gas and Electric Company, hereinafter referred to as “SDG&E”, regarding the
foliowing facts:
WHEREAS, City is directing as a public works project, certain road improvements for
Cannon Road West Reach 2; and
WHEREAS, SDG&E has existing transmission facilities, being a (1) two-pole structure,
within the Cannon Road right-of-way; and
WHEREAS, an element of the Improvements is the Relocation of the (1) two-pole
structures; and
WHEREAS, City has requested SDG8E conduct this Relocation incident to the
Improvements; and
WHEREAS, because said Relocation is to be accomplished within an area of Prior
Rights and not within an area subject of the franchise, City will be responsible for all costs
associated therewith; and
WHEREAS, City will agree to pay for the Relocation; and
WHEREAS, SDGBE will agree to effect the Relocation pursuant to the City’s
request; and
WHEREAS, the estimated cost of the Relocation portion of the public works
Improvement is more than $25,000 and, therefore, the approval of the City Council is required.
SEP-84-ZfXIl B9 : 49 CITY OF CRRLSBIXI 768 431 5769 P.B3fll
NOW, THEREFORE, in consideration of the foregoing recitals, for other valuable
consideration, receipt of which is hereby acknowledged, CITY and SDGBE agree as follows:
1. Transmission. Line Relocation
a. Specifications. SDG&E shall relocate the (1) two-pole structure and
complete associated line work pursuant to the plans and specifications as sat forth in SIX&E
Work Order No. 713868-640.
b. Timing of Work. CITY, by and through its Engineering Department, is
coordinating the Improvements. SDG&E estimates that the Relocation will require
approximately forty (40) working days after the execution of this agreement to comptete, and
SDG&E will utilize its best efforts to so complete the Relocation; provided, however, CITY and
SDG&E acknowledge and agree that certain events and occurrences can disrupt the
contemplated schedule including, but not limited to, the requirement or need not to otherwise
curtail the electric supply throughout the SDG&E service territory, timely approval by the CA
IS0 for the associated line outage, weather, work stoppages or the discovery of unforeseen
conditions in the fietd which cause revisions or modifications to the plans for the Relocation
and/or Improvements. SDGdE wifl commence the Relocation within a reasonable time after
notification from the CITY that CITY is ready to have the Relocation portion uf the
Improvements begun and will diligently pursue the completion of the work.
c. Payment. SDG&E has estimated the cost of the Retocation to be
$43,086, which estimate includes contractor’s charges, equipment and materials, SDG&E
personnel and employee labor and engineering charges including labor additives. CITY has
previously paid, and SDGBE acknowledges receipt of $231,965 as a deposit for the following
items of work:
Work Order Number 713666-010 60516~040 605166-060 TOTALS
Nfaterials & Labor $50, i 79.45 145477.63 15,549.41 211.20649
Engineering 13.022.77 11.690.02 1 z263.48 25.97627
Sub total 638202.22 153,346.89 16,812.89 237,‘l82.76
2
SEP-84-2801 09:49 CITY I?F CQRLSBFID 760 431 5769 P. 84/11
Salvage 8 Depreciation -1,572.23 -1,910.38 0 (3,482.61)
Total 61.629.99 155.257.27 16812.89 233,700-l 5
Payment from City 79,200.oo 152,765.OO 0 231,965.OO
Balance 17,570.Ol -2492.27 -16,812.89 (1,735.15)
The balance credit of funds was transferred to the monies due, balance due Of
$1.735.15 was written off by SDG&E and the projects were completed in accounting
Prior to the commencement of the Relocation, CITY shall pay to SDG&E, the balance of
the Relocation estimated charges, being $43,686.
Upon compMion of th8 Relocation, SDGLE shall, consistent with past practices between
CITY and SDG&E for the payment of utifity Relocation charges, provide CITY with an accounting of
the costs incurred by SDG&E for labor, material and equipment to complete the Relocation. If
the costs for the Relocation are less than the estimated charges, SDCXE shall remit to the
CITY, together with the accounting, SW&E’s check payable to CITY for the difference. .If the
costs of the Relocation are more than the estimated charges, the accounting so provided shall
be deemed an additional invoice from SDG&E to CITY, and CITY shall remit to SDG&E the
balance due within thirty (30) days of the CKY’s receipt of the accounting/Invoice. Differences
of less than $75.00 will not be billed or refunded.
SDGBE represents to ClTY that as a matter of practice, SDG&E maintains records
which adequately and accurately show the actual costs which are contemplated to be incurred
for this Relocation for a period of three (3) years following compfetion of the Relocation.
2. Responsibility for Relocation
The Relocation shall be accomplished by SDG&E at its sole direction and in compliance
with such rules and orders governing design, construction and maintenance of transmission
lines a6 promulgated by the Public Utilities Commission of the State of California. SDG&E wi{l
and does agree to indemnify, d8fend. save and hofd harmless CITY, its officerq employees and
agents, from and against any and all toss, cost, damage, expense, claim, suit, demand or
3
SEP-84-2081 89:58 CITY OF CWLSEMD 768 431 5769 P.BS/ll
liability to person or property, including attorney’s fees, arising from or relating to any
negligence by SOG&E, its officers, employees or agents in the performance of the Relocation.
3. Affirmation of SDG&E Prior Riahts
Nothing in this agreement shall be construed in any way to alter, modify, or terminate
any prior rights of SDG&E within the area of the Relocation, the Improvements, or the area of
Prior Rights from which the existing portions of the transmission line is to be relocated.
4. Cancellation of &reement
In the event the CITY shall cancel or modify the improvements of which the Relocation
subject of the Agreement is a part, and the result of such cancellation or modification in the
elimination of the Relocation from the Improvements altogether, CIN may thereupon terminate
this Agreement upon written notice thereof from CIN to SIX&E. In the event this Agreement
is so terminated, CITY shall nonetheless be responsible and liable to SDG&E for alI costs
incurred by SDG&E for the Relocation up to and including the date of the termination, including
any cancellation or penalty charges which SDG&E may incur from any of its contractors or
subcontractors. Upon receipt of notice of termination, CITY and SCKXE shall implement the
accounting and payment adjustment procedures described in paragraph 1 (c) hereof.
5. c
This Agreement shall be effective upon signature hereon by the Mayor of the City of
Carlsbad, pursuant to a Resolution of adoption by the City Council of the City of Carl&ad.
6. Entire Aareement
This Agreement constitutes &he entire agreement between the CITY and SDG&E
relating to the subject matter hereof. Any agreements or representations not speciftcally set
forth herein are void and of no force or effect; any modifications or amendments to this
Agreement shall furthermore be of no force or effect unless set forth in a writing signed by both
parties.
SEP-84-2881 09:50 CITY OF CQRLSEQD 76B 431 5769 P.06111
7. Notices
Any notice, invoice or other communication that either party may or is required to give
the other shall be in writing, shall be personally delivered, transmitted by facsimile, or by U. S.
Mail, regular delivery. Notices are deemed received on the same day if by personal delivery or
by facsimile, and upon the third day after mailing if defivered by mail. Notices shal be directed
to:
San Diego Gas and Electric Company 8315 Century Park Court, #210 San Diego, CA 9X23-1550 Attention: Mr. Dennis Buss
City of Carlsbad 1635 Faraday Avenue Carisbad, CA 92008 Attention: Public Works Director
IN WITNESS WHEREOF, ClTY AND SDG&E have executed this Agreement.
By:
SAN DIEGO GAS 8 ELECTRIC COMPANY
&y&Q J/W (Sign Here)
f%ilLL~P J. ZECu3LS
(Print Name)
Pt@Jm ManlWX lwebwa
(Title)
ATfEST:
(Date)
APPROVED AS TO FORM:
Deputy City Attorney
5
San Diego Gas & Electric n
FILE NO. PiA 590
PROJ# 713868-040
July 18, 2001
Sherri Howard
City of Carlsbad
1635 Faraday Ave
Cartsbad, Ca 92008
Dear Sherri:
Subject: Cannon Road pole relocations
The purpose of this correspondence is to update the City on the final costs associated with
previous transmission pole relocation work and additional costs associated with remaining work.
The original job (713868-010) cost estimate of $79,629.99 was to relocate two-twin transmission
poles. The design and costs were calculated two years prior to actual construction and not
updated to reflect current costs. The costs actually had increased thus accounting for some of
the discrepancy between the actual and quoted costs.
The first two-pole structure was relocated per plan. However, a change was made to the design
to accommodate additional work around the second two-pole structure. This location would
require “surcharge” or fill, settle & re-compact. Thus postponing the second relocation until
now.
SDG&E has calculated the cost to complete the (713868-040) second two-pole structure at
$43,686.00. See attached note from Allen Sojourner.
There was also 1 steel transmission pole relocation (605166-040) required to accommodate the
improved Cannon Rd. with a cost estimate of $145,477.63. During construction the soil was
found to be unstable thus requiring (605166-060) a field change to add extensive additional
concrete, masonry machinery, labor and cost to complete.
h July 18, 2001
The final costs associated are as follows:
Proiect number 713868-010
Materials & Labor $50,179.45 145477.63 15,549.41
Engineering 13.022.77 11.690.02 1,263.48
Sub total 63,202.22 157,167.65 16,812.89
Salvage & Depreciation -1,572.23 -1,910.38 0
Total 61,629.99 1553257.27 16,812.89
Actual P’mt from City 79,200.OO 152,765.OO 0
Balance 17,570.Ol -2492.27 -16,812.89
605166-040 605166-060
The balance credit of funds was transferred to the monies due accounts and the balance due
1,735.15 was written off and projects completed in accounting.
If you wish to complete the last pole relocation please enclose a check for the amount of
$43,686.00 in the enclosed envelope. Upon completion of work the City will receive a final
accounting of work completed and will either be billed or credited any differences between the
actual and estimated costs.
Your cost, as cited herein, are subject to change at any time. All cost calculations are based
upon SDG&E’s filed tariffs, SDG&E’s internal costs, and all applicable governmental or
regulatory statutes, regulations, codes and rules. Should any change in, or addition to, those
tariffs, costs, statues, or regulations, codes or rules in any way impact these cost calculations,
you will be subject to any resulting increase or decrease.
After we complete the work, we will determine the actual cost of the job. Should the job cost
more than the estimate you will be billed the difference. If the job is less than the estimate, we
will refund the difference to you. Differences of less than $75.00 will not be billed or refunded.
If I may be of further assistance or if you have any questions, please call me at the number
listed below. Our hours are from 7:00 AM - 4:00 PM, Monday through Friday.
h
Sincerely,
Dennis E. Buss
Governmental Liaison Planner
Project Management Metro
Office Phone (858) 636-5716
Cel(760) 310-2538 Fax (858) 636-5714
July 18, 2001
k Srmpra Ert~rgy’~
INTERNAL CORRESPONDENCE
TO: D. Buss
FROM: A. Sojourner
SUBJECT: CONSTRUCTION FEE:
TIE LINE NO.:
WORK ORDER:
DPSS NO.:
DATE: June 25,ZOOl
FILE:
Cannon Road Extension
13802
2800846
713868-040
A construction fee is required in order for Transmission Engineering to implement the
construction phase of the proposed project. The following sections describe the
estimated costs (Construction Fee), project scope and schedule for constructing the
project. Transmission Engineering has completed the preliminary engineering and
design to relocate one 2-pole structure.
CONSTRUCTION COSTS:
The estimated construction fee is $43,686.00. This fee will provide for construction of
the project based on the project scope and schedule described below. This cost is in
addition to all previously collected engineering and material fees.
SCOPE:
This project is required to accommodate the city’s proposed grading in our existing
right-of-way along Tie Line 13802. The project requires relocating one 138kV two-pole
structure.
I
SCHEDULE:
The following project schedule is based on the information currently available.
TASK EXPECTED COMPLETION
1. Issue Construction Bid Package Two - Four weeks after receipt of
construction fee.
2. Begin Construction Two - Four weeks after contract
award.
3. Complete Construction Two - Four weeks after start of
construction.
SIX&E will attempt to accommodate the customer’s schedule whenever possible,
contingent on site availability, other wotkloads, material delivery, outage approval by
the Independent System Operator (ISO) and other factors not controlled by SDG&E. In
the event that the scope of the project changes, the schedule and cost will be impacted.
This is an estimate only, the developer will pay Actual Cost Billing. SDG&E will refund
overestimated costs, and will bill the customer for any underestimate.
It is the developer’s responsibility to make arrangement for the relocation of
telecommunication and TV cables.