veb VL CI . OF CARLSBAD - AGENDA BILL
4B# 6537-#4
MTG,~'/~/G~
0 w W Q U 8i
TITLE: PASEO DEL NORTE SUBDRAINS
CONTRACT NO. 1090 CITY ArrY I CITY MGR~ . ZW- DEPT. ENG
1- RECOMMENDED ACTION:
Accept the construction of the Paseo Del Norte Subdrains, Contract No. 1090, as
complete; direct the City Clerk to have the "Notice of Completion" recorded and
to release the bonds 35 days after recordation.
ITEM EXPLANATION:
The Paseo Del Norte Subdrain contract has been satisfactorily completed. The
final contract amount of $92,996 exceeds the bid price of $81,477 by $11,519.
The additional charges are for change orders authorized by the City Council at
khe Septeinber 15, 1981 meeting.
FISCAL IMPACT:
At the September 15, 1981 meeting, Council authorized a transfer of funds to cover
the additional charges; thus, sufficient budgeted funds are available to cover
final contract payments. Ten percent of the final amount will be withheld until
35 days after the "Notice of Completion'' is recorded.
EXH I B I T :
Notice of Completion