ACCEPTANCE OF A NEW ROOF
AT FIRE STATION NO. 5
CONTRACT NO. FAC02-04 CITY MGR 3
RECOMMENDED ACTION:
Adopt Resolution No.J300&001 \ accepting the work in accordance with
Contract No. FAC02-04 as complete, and direct the City Clerk to have the Notice of
Completion recorded and to release the bonds thirty-five (35) days after recordation.
ITEM EXPLANATION:
On December 4, 2001, the City Council awarded a contract to Commercial &
Industrial Roofing Company, Inc. for $72,976. Contract No. FACO2-04 is for a new
roof at Fire Station No. 5. Fire Station No. 5, which was constructed in 1989, was
due to have its roof replaced. The roof was leaking and had been repaired in recent
storms. Replacement of the roof will protect the structure and equipment inside and
will eliminate inconvenience to the occupants. Under the City's new preventive
maintenance program, the new roof can be expected to last between fifteen to twenty
years.
The actual construction took a total of 30 working days from start to finish, and this
project is now complete. The contractor work is acceptable to the Public Works
ManagerlGeneral Services and to the Public Works Supervisor - Facilities
Maintenance.
FISCAL IMPACT
The total cost for this project is $72,976. There are sufficient funds available in the
C.I.P. Program budget for this project.
EXHIBITS:
1. Adopt Resolution No. 300 a -09/ accepting the work in accordance with
Contract No. FAC02-04 as complete, and direct the City Clerk to have the
Notice of Completion recorded and to release the bonds thirty-five (35) days
after recordation.
2. Notice of Completion.
I
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
(
EXHIBIT 1
RESOLUTION NO. 2002-091
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CARLSBAD,
DIRECTING THE RECORDATION OF THE NOTICE OF COMPLETION FOR FURNISHING AND INSTALLING A NEW ROOF AT FIRE STATION NO. 5
CALIFORNIA, ACCEPTING THE WORK AS COMPLETE AND
WHEREAS, the Ci Council of the City of Carlsbad has previously appropriated funds for
urnishing and installing a new roof at Fire Station No. 5, hereinafter referred to as the "Project;"
tnd
WHEREAS, the City Council has previously awarded a contract for the Project; and
WHEREAS, the Project work has been satisfactory completed; and
WHEREAS, a Notice of Completion has been prepared for the Project; and
WHEREAS, the City Council hereby finds it necessary, desirable, and in the public interest
3 accept the completed work for furnishing and installing a new roof at Fire Station No.5.
NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of Carlsbad as
311ows:
1. That the above recitations are true and correct.
2. That the completed work is' hereby accepted and the City Clerk is directed to record
le Notice of Completion and to release the bonds thirty-five days after recordation for said
'roject.
PASSED, APPROVED AND ADOPTED at a regular meeting of the City Council of the City
If Carlsbad held on the 76th day of MARCH, 2002 by the following vote, to
lit:
AYES: Council Members Lewis,
NOES: None
ABSENT: Council Member Nygaa
rTTEST ,-
(SEAL)
DOC # 2002-0288692
QPR 05s 2002 4:28 PM
Recording requested by:
CITY OF CARLSBAD
When recorded mail to:
City Clerk
City of Carlsbad
Carlsbad CA 92008
1200 Carlsbad Village Drive
:B Space above for Recorder’s use
I 4’ NOTICE OF COMPLETION
Notice is hereby given that:
1.
2.
3.
4.
5.
6.
7.
8.
The undersigned is owner of interest or estate stated below in the property hereinafter
described.
The full name of the undersigned is City of Carlsbad, a municipal corporation.
The full addressof the undersigned is 1200 Carlsbad Village Drive, Carlsbad, California
92008.
The nature of the title of the undersigned is: In fee.
A work of improvement on the property hereinafter described wascompleted on March 18,
2002.
The name of the contractor, if any, for such work of improvement is Commercial anif
Industrial Roofing Company, Inc.
The property on which said work of improvement was completed is in the City of Carlsbad,
County of San Diego, State of California, and is described as follows:
The street address of said property is:
New Roof at Fire Station No. 5, Contract No. FACO2-04
Carlsbad Fire Station N0.5 2540 Orion Way, Carlsbad, California 92008
Public Eorks ManagedGeneral Services
VERIFICATION OF CITY CLERK I, the undersigned say:
I am the City Clerk of the City of Carlsbad, 1200 Carlsbad Village Drive, Carlsbad CA 92008;
the City Council of said City on March 26 ,2002 accepted the above work as
completed and ordered that a Notice of Completion be filed.
I declare under penalty of perjury that the foregoing is true and correct.
Executed on March 27 , 2002 at Carlsbad, California
CITY OF qARLSBAD
IC,
/L b9il
City Clerk I