HomeMy WebLinkAbout2003-05-20; City Council; 17182; Kelly Ranch Village E, Cannon Road Reach 2 Phase 19B# 17.187
HTG. 5/20/03
IEPT. ENG
CITY OF CARLSBAD - AGENDA BILL
TITLE:
ACCEPTANCE OF THE CANNON ROAD AND EL CAMINO
REIMBURSEMENT PROJECT NO. 3184) KELLY RANCH
VILLAGE E, CANNON ROAD, REACH 2, PHASE I,
STA. 98+35 TO 124+30
REAL PORTION OF PROJECT NO. CT 96-07 (CIP CITY ATTY.
CITY MGR.
RECOMMENDED ACTION:
Adopt Resolution No. 2o03-132 accepting the construction of the Cannon Road and El
Camino Real portions of Kelly Ranch Village E, Cannon Road, Reach 2 Phase I, Sta. 98+35 to
124+30, Project No. CT 96-07, CIP Reimbursement Project No. 31 84 as complete, and directing the
City Manager to execute the Acceptance of Public Improvements on Cannon Road and El Camino
Real.
ITEM EXPLANATION:
The Carlsbad City Council adopted the Circulation Element of the General Plan as a way to ensure
a comprehensive manner and method for the circulation of people, goods, energy, water, sewage,
storm waters, communications and services. On February 27, 2001, City of Carlsbad Council Policy
Statement No. 63 was issued to establish a policy on the acceptance or conditional acceptance of
Circulation Element roadways or portions of such roadways into the City street system. This policy
states that City Council shall consider the policies of the General Plan, the standards of the Growth
Management Plan, the safety and needs of the traveling public, which in the opinion of the City
Council are necessary and appropriate for the orderly, safe and efficient development of the
circulation system. Policy No. 63 requires formal City Council acceptance of these Circulation
Element roadways into the City’s street system. Cannon Road and El Camino Real meet the criteria
of a Circulation Element roadway.
On January 16, 2003, Shea Homes completed the work on Cannon Road and El Camino Real from
Sta. 98+35 to 124+30 as listed in Improvement Agreement No. SA728.00, Drawing Number 333-26.
The work performed by Shea Homes consisted of the construction of Cannon Road between El
Camino Real and Frost Avenue. City staff has inspected the work on Cannon Road and El Camino
Real and found it to be satisfactory.
FISCAL IMPACT:
Acceptance of the road has no financial impact. After acceptance, the maintenance of the road will be
performed by existing City maintenance crews.
EXHIBITS:
1. Location Map.
2. Resolution No. 2003-132 accepting the construction of the Cannon Road and El
Camino Real portions of Kelly Ranch Village E, Cannon Road, Reach 2 Phase I, Sta. 98+ 35
to 124+30, Project No. CT 96-07, CIP Reimbursement Project No. 3184 as complete, and
directing the City Manager to execute the Acceptance of Public Improvements on Cannon
Road and El Camino Real.
DEPARTMENT CONTACT : Skip Hamrnann (760) 602-2780 ext 7321 shamm@ci.carlsbad.ca.us
LOCATI 0 N MAP
ROAD ACCEPTANCE
NOT TO SCALE
SI
PROJECT EXHIBIT NUMBER *I
PROJECT NAME CANNON ROAD REACH 2 PHASE I FROM STA. 98+35 TO STA. 124+30 KELLY RANCH VILLAGE 'E'' CT96-07
DRAW BY: SCOTT EVANS, CARLSAD WGINEERlNG DEPT. 4/3/03 C: \DEKLOPMENT PROJECTS\CT96-07 CANNON RD.DM:
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
RESOLUTION NO. 2003-132
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
CARLSBAD, CALIFORNIA, ACCEPTING THE CONSTRUCTION
OF THE CANNON ROAD AND EL CAMINO REAL PORTIONS OF
KELLY RANCH VILLAGE E, CANNON ROAD, REACH 2 PHASE I,
REIMBURSEMENT PROJECT NO. 3184.
STA. 98+35 TO 124+30, PROJECT NO. CT 96-07, CIP
WHEREAS, the construction of CT 96-07, Kelly Ranch Village E, Cannon Road, Reach 2,
'base 1, Sta. 98+35 to 124+30, Cannon Road and El Camino Real has been completed to the
Xy’s satisfaction by Shea Homes; and
WHEREAS, Cannon Road and El Camino Real meet the criteria of a circulation element
Padway as defined in the City’s General Plan and Council Policy No. 63.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Carlsbad,
=alifornia, as follows:
1. That the above recitations are true and correct.
2. That the construction of the public improvements on Cannon Road and El Camino
qeal, from El Camino Real to Frost Avenue, Sta. 98+35 to 124+30, specifically identified on
hawing number 333-2G is deemed complete and is hereby accepted.
3. The City Clerk of the City of Carlsbad is hereby authorized and directed to execute the
qcceptance of Public Improvements on Cannon Road and El Camino Real, from El Camino Real
o Frost Avenue, Sta. 98+35 to 124+30.
I/
I/
I1
I/
/I
I1
I/
I/
I1
I1
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
4. That all bonds on the subject Project will be released in accordance with State Law
and City Ordinances.
PASSED, APPROVED AND ADOPTED at a regular meeting of the Carlsbad City Council
held on the 20th day of MAY , 2003 by the following vote, to wit:
and Kulchin
4TTEST:
-0RRAINE M.
Page 2 of 2 of Resolution No. 2003-132.
(SEAL)