Loading...
HomeMy WebLinkAbout2004-06-22; City Council; 17681; Dokken Engineering Agreement Amend 2CITY OF CARLSBAD - AGENDA BILL I 9B# 17,681 HTG. 6/22/04 - TITLE: AMENDMENT NO. 2 TO AGREEMENT FOR DESIGN AND CONSTRUCTION ENGINEERING SUPPORT SERVICES WITH DOKKEN ENGINEERING, INC., FOR RANCHO SANTA FE ROAD, PHASES 1 AND 2, I PROJECT NOS. 31 90,3907,3887, AND 3923 IEPT. ENG Environmental Mitigation & Monitoring Rig ht-of - W ay Construction, Inspection, Materials Testing & Public Relations CITY ATTY. @ $3,627,000 $737,000 $4,364,000 $0 $1 81,000 $1 81,000 $1 8,698,000 $20,395,000 $39,093,000 CITY MGR.m RECOMMENDED ACTION: Adopt Resolution No. 2004-207 approving Amendment No. 2 to agreement for design and construction engineering support services with Dokken Engineering, Inc., for Rancho Santa Fe Road North, Phases 1 and 2, Project Nos. 31 90,3907,3887, and 3923. ITEM EXPLANATION: The Rancho Santa Fe Road project consists of the widening and realignment of approximately 2.2 miles of Rancho Santa Fe Road from La Costa Avenue to Melrose Drive. The project will be constructed in two phases: Phase 1, from La Costa Avenue to San Elijo Road; and Phase 2, from San Elijo Road to Melrose Drive. Benefits of the project include reduced congestion, improved traffic flow, and increased safety for travelers on the road. Additionally, this project will improve a vital link in the North County region’s roadway network. The City retained Dokken Engineering in 1998 to provide professional engineering services for the design of Rancho Santa Fe Road Phases 1 and 2. Near the end of the design for these road segments Dokken Engineering was retained under a new contract that included a few remaining design tasks and construction engineering support services. The construction engineering services scope of work was based on the estimated construction schedules for both projects and tasks typical of construction projects. The design and construction work effort required to support the project to date has exceeded the estimate in the original agreement and Amendment No. 1. Among the items involved in the expanded work effort was Dokken Engineering’s coordination for construction support issues for Phase 1 that were at the time of the original agreement, unknown and based on an 18-month construction schedule. The Phase 1 schedule is now estimated to be complete in a total of approximately 22 months. Dokken also spent additional time coordinating closely with Caltrans and the City of Carlsbad to complete the Phase 2 project construction authorization. This authorization was required in order to receive federal funding. Dokken was required to incorporate design changes at the request of other agencies including the Vallecitos Water District, the City of San Marcos, and San Diego Gas & Electric. FISCAL IMPACT: Budaet The cost of the Rancho Santa Fe Road Phase 2 is summarized in the following table. Costs shown are based on actual costs and bids received. Design costs for Phase 2 were incurred in Phase 1. I TOTAL 1 $28,105,000 i a1,313,000 i $47,418,000 J The costs associated with the Dokken Engineering amendment under consideration is $1 42,035 and is included in the Design and Construction, Inspection, Materials Testing & Public Relations categories as shown in the table above. These funds have already been appropriated. Page 2 of Agenda Bill No. 17,681 Fundinq The Rancho Santa Road project will be funded with a combination of Community Facilities District No. 1 (CFD #1), proposed Community Facilities District No. 2 (CFD #2), Public Facilities Fee (PFF), Federal and State grants, and reimbursements from other agencies and developers. Funding sources are summarized below: Community Facilities District special taxes and fees will fund most of the costs for Phase 2 of the project. Sufficient amounts have been collected for the existing appropriations. ENVIRONMENTAL: The City Council at their meeting on June 2, 1992 passed Resolution No. 92-152 certifying EIR No. 91-1 for both Phase 1 and Phase 2 of the Rancho Santa Fe Road project. The City Council at their meeting on April 25, 2000 passed Resolution No. 2000-128 approving Addendum No. 2 to the final EIR No. 91-1 for Rancho Santa Fe Road. This EIR covers the realignment and widening of Rancho Santa Fe Road from La Costa Avenue to Melrose Drive. EXHIBITS: 1. Resolution No. 2004-207 approving Amendment No. 2 to agreement for design and construction engineering support services with Dokken Engineering, Inc., for Rancho Santa Fe Road, Phases 1 and 2, Project Nos. 31 90,3907,3887, and 3923. 2. Amendment No. 2 to agreement for design and construction engineering support services with Dokken Engineering, Inc., for Rancho Santa Fe Road, Phases 1 and 2, Project Nos. 31 90,3907,3887, and 3923. DEPARTMENT CONTACT: Carrie Loya-Smalley, (760) 602-2746, clova Bci.carlsbad.com 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 RESOLUTION NO. 2004-207 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CARLSBAD, CALIFORNIA, APPROVING AMENDMENT NO. 2 TO AGREEMENT FOR DESIGN AND CONSTRUCTION ENGINEERING SUPPORT SERVICES WITH DOKKEN ENGINEERING, INC., FOR RANCHO SANTA FE ROAD, PHASES 1 AND 2. PROJECT NOS. 3190,3907,3887 AND 3923. WHEREAS, the City Council of the City of Carlsbad, California, consider it necessary and n the public interest to approve Amendment No. 2 to the agreement for design and construction wgineering support services with Dokken Engineering, Inc., for Rancho Santa Fe Road, Phases 1 and 2, Project Nos. 3190,3907,3887, and 3923; and WHEREAS, the contractor, Dokken Engineering, Inc., possesses the necessary skills and qualifications to provide the services described above; and WHEREAS, Amendment No. 2 to the agreement has been prepared and submitted iereto. NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Carlsbad, =alifornia, as follows: I. 2. That the Amendment No. 2 to the agreement for design and construction mgineering support services with Dokken Engineering, Inc., for Rancho Santa Fe Road, 'hases 1 and 2, Project Nos. 3190, 3907, 3887, and 3923 is hereby approved in the amount of That the above recitations are true and correct. 6142,035 and the Mayor is authorized and directed to execute said Amendment of Agreement. ii 3 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 3. The City Clerk is authorized and directed to forward copies of the signed imendment No, 2 to Dokken Engineering, Inc., and the Engineering Department for processing. PASSED, APPROVED AND ADOPTED at a regular meeting of the Carlsbad City Council ield on the 22nd day of June , 2004 by the following vote, to wit: AYES: Council Members Lewis, Finnila, Kulchin, Hall and Packard NOES: None ABSENT: None 4TTEST Resolution No. 2004-207 page 2 (SEAL) PWENG 333 AMENDMENT NO. 2 TO AGREEMENT FOR DESIGN AND CONSTRUCTION ENGINEERING SUPPORT SERVICES FOR RANCHO SANTA FE ROAD, PHASES 1 AND 2, PROJECT NOS. 3190,3907,3887 AND 3923 WITH DOKKEN ENGINEERING INC. This Amendment No. 2 is entered into and effective as of the G?3(d day of , 200%, amending the agreement dated March 20, 2003 (the “Agreement”) by and between the City of Carlsbad, a municipal corporation, (“City”), and Dokken Engineering, Inc., (“Contractor”) (collectively, the “Parties”) for design and construction support services for Rancho Santa Fe Road, Phases 1 and 2. J fhe RECITALS A. On September 4, 2003, the Parties executed Amendment No. 1 to the Agreement to include additional design and field surveying services not anticipated under the original agreement; and B. The Parties desire to alter the Agreement’s scope of work to include additional Phase 2 design efforts to coordinate with other agencies including the Vallecitos Water District, the City of San Marcos and Caltrans, and additional Phase 1 construction support tasks; and C. The Parties have negotiated and agreed to a supplemental scope of work and fee schedule, which is attached to and incorporated by this reference as Exhibit “A”, Scope of Services and Fee NOW, THEREFORE, in consideration of these recitals and the mutual covenants contained herein, City and Contractor agree as follows: 1. In addition to those services contained in the Agreement, as may have been amended from time to time, Contractor will provide those services described in Exhibit “A“. 2. City will pay Contractor for all work associated with those services described in Exhibit “A on a time and materials basis not-to-exceed one hundred forty two thousand thirty five dollars ($142,035). Contractor will provide City, on a monthly basis, copies of invoices sufficiently detailed to include hours performed, hourly rates, and related activities and costs for approval by City. 3. Contractor will complete all work described in Exhibit “A by March 19, 2006. 4. All other provisions of the Agreement, as may have been amended from time to time, will remain in full force and effect. - 5. All requisite insurance policies to be maintained the Agreement, as may have been amended from time to time, will Amendment. Iff by Contractor pursuant to include coverage for this 1 City Attorney Approved Version #05.22.01 6. The individuals executing this Amendment and the instruments referenced in it on behalf of Contractor each represent and warrant that they have the legal power, right and actual authority to bind Contractor to the terms and conditions of this Amendment. CONTRACTOR DOKKEN ENGINEERING, INC. W (print namehitle) ’ (e-mail address) f-&hsL&d-aiL City Clerk (sign tj61e) J (e-mail address) If required by City, proper notarial acknowledgment of execution by contractor must be attached. If a Corporation, Agreement must be signed by one corporate officer from each of the following two groups. 0 *GroupA. Chairman, President, or Vice-president **Group B. Secretary, Assistant Secretary, CFO or Assistant Treasurer Otherwise, the corporation must attach a resolution certified by the secretary or assistant secretary under corporate seal empowering the officer(s) signing to bind the corporation. APPROVED AS TO FORM: RONALD R. BALL City Attorney Deputy Cib Adorney City Attorney Approved Version #05.22.01 2 CALIFORNIA ALL-PURPOSE ACKNOWLEDGMENT State of California j - POL, Name and Title of Ofiicer (e.5.. "Jane Doe, Notary Public") CQTMr CY~N +arne(s) of Signer@) personally appeared R 1 wan & P 7qg. mersonally known to me 0 proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) islare subscribed to the within instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument. Place Notary Seal Above Though the information below is not required by law, it may prove valuable to persons relying on the document and could prevent fraudulent removal and reattachment of this form to another document. Description of Attached Document Title or Type of Document: Document Date: Number of Pages: Signer(s) Other Than Named Above: C Individual 0 Corporate Officer - Title(s): 0 Partner - 0 Limited 0 General 0 Attorney in Fact 0 Guardian or Conservator Signer Is Representing: 0 1999 National Notary Association - 9350 De Solo Ave.. P.O. Box 2402 * Chatswollh. CA 9131 3-2402 * ww.nationalnotary.org Pmd. No. 5907 Reorder: Call Toll-Free 1-800-876-6827 EXHIBIT “A’ SCOPE OF SERVICES AND FEE See detailed scope of work and fee attached. TOTAL ADDITIONAL DESIGN TASKS FOR PHASE 2 TOTAL ADDITIONAL CONSTRUCTION SUPPORT TASKS FOR PHASE 1 TOTAL AMENDMENT NO. 2 $82,095 $59,940 $1 42,035 City Attorney Approved Version # 05.22.01 3 D O K K E N EXHIBIT "A" E N G IN I3 E K I N G w w w .d n IC ken c II g i II c r r i II g. c 61 111 May 12,2004 City of Carlsbad Public Works - Engineering 1635 Faraday Avenue Carlsbad, CA 92008-73 14 Attention: Doug Helming RE: Rancho Santa Fe Road North, Phase I (Project 3190) Request for Additional Construction Support Services Budget Dear Mr. Helming: Dokken Engineering is requesting the allowable budget for construction support services for Rancho Santa Fe Road North, Phase 1 (Project 3190) be increased. Unanticipated field conditions encountered during construction required additional field surveys, design and redesign services. In addition, the construction schedule has increased from 18 months to 22 months. Construction support task items not previously anticipated but requested by the City of Carlsbad are listed below. The estimated cost to complete each of the tasks below is shown on the attached table. Task 1. to reduce excavation quantities. Revised grading plans and quantity estimates to increase steepness of cut slopes Task 2. section revisions due to subgrade with low R-value. Provided recommendations and performed quantity calculations for structural Task 3. for an enlarged stockpile area. Developed contour grading plan and performed earthwork quantity calculations Task 4. field review of existing pedestrian ramps, developed drawings to construct federally-compliant pedestrian ramps, and provided signed mylar replacement sheets to Carlsbad. Researched federallycompliant pedestrian curb ramp design details, performed Task 5. crossing. Provided plan and detail for fall protection features above the planned wildlife Task 6. Elijo Road/Rancho Santa Fe Road intersecti-on. Performed design surveys to locate various existing features at the interim San 9665 CH~.SAI'LAKE DIWF, SUITE 435 SAN Dlcco, CA 9:1123-1367 TFI.. 858-514-8377 FAX. 058-514-8608 page A- 1 Task 7. Revised long term detour plan and profile at the connection between improved and existing Rancho Santa Fe Road and performed sight distance calculations. Task 8. Coordinated design surveys and revised 12” recycled waterline plan and profile to avoid recently constructed SBC utility conduits. Task 9. avoid recently constructed SBC utility conduits (Dan Boyle Engineering and Aguirre & Associates). Perfonned design surveys and revised 12” recycled waterline plan and profile to Task 10. Revised traffic handling sheets to allow for continuous 24-hour traffic control for 12” recycled waterline construction at La Costa Avenue and updated detour plan per recent commercial and residential developments in the vicinity. Task 11. system within roadway to mitigate for saturated subgrade. Attended meetings and prepared plans and quantity calculations for edge drain Task 12. signal span wire system and La Costa Avenue/Rancho Santa Fe Road. Performed structural calculations that analyzed the acceptability of a traffic Task 13. Perform future miscellaneous tasks to be determined. We are requesting our budget for construction support services be increased by $60,000. Our request will revise the available budget for Phase 1 construction support from $64,086 to $124,086. Thank you for consideration of our request. Please let me know if you have any questions or require any additional information. Sincerely, Kirk Bradbury, P.p: Project Manager Attach: Budgct by Task and Pcrson Table, 5/12/04 1058/050/52/105X-1 I63 construction suppofl.-02c.doc Page A-2 City of Cadsbad Rancho Santa Fe Road Realignmeni Pro'ect No. 3190 City Ph: D Helming 46 mDOKKEN 8 38 212 114 0 RANCHO SANTA FE ROAD NORTH (Project 3907) AMENDMENT 2 - P.O. P112579 (PWENG 333) ADDITIONAL PHASE 1 CONSTRUCTION SUPPORT SERVICE BUDGET BY TASK AND PERSON i 7,268 $ 1,120 S 4,560 S 19.504 t 10.488 t - E N GI N E E R 1 N L: w w I .do k k P n en g i II sei In E. co ni Prokc( Project I Assoelate Assistant Manager I Enpineer Englneer I Engineer I Detailer lWWd Description - ._ Revised Gradhg Plans to Increasa Steepness of Cut Slopes Structural Sectan Revisions Due lo Subgrade wlth Low R-value ,Contour Grading Plan for an Enlarged Stockpile Area rark h __ 1 __ 2 76 - 9 - __ 32 -_ 78 - 16 Lump Sum -- - % 24 Lump Sum .- -. 26 __ 70 __ 19 - $ 7,556.00 __ 5 894.00 $ 3,076.00 $ 8,244.00 t 1,828.00 s 2,400.00 _____. 6.784.W. t 2,472.00 ~__ _. $ 4,600.00 $ 2.656.00 ?.-....---- 7.1 00.00 $L-- 2,330.00 . .- E- . . . !O,O!!? 3 I Developed Drawings to Construct Federally-Compliant Pedestrian Ramps 4 5 Fall Protection Features Above the Planned Wildlife Crossing 6 Deslgn Surveys at Interim Sen Elijo RoadlRancho Santa Fe Road 7 Revised Long Term Detour Plan and Profile and Performed Sght Distance Calculatans Revised 12' Recycled Waterline Plan and Profile 8 9 Revised 12' Recyded Waterline Plan and Profile (Dan Boyle 8 Aguirre) 10 - .- 11 Traffic Handling Sheets for 24-Hour Traffic Control for Waterhe Constructic at La Costa Avenue Meeiings, Plans and Ouantlty Calculations for Edge Drain Syslem Structural Calculations of Traffic Signal Span Wire System Miscellaneous Tasks to be Determined __ __ . ~ .____ ~ ~__ 12 13 -_ . . .. . - . . .- . . . . .. .. ... . .. .. . .- -. .. . - . .-I- . .._ U18 S 59,940.W Page A-3 12-May-04 DOKKEN ENGlNEEKlNG w w w .d I) k k F n c n I I n F v I i 11 E. c 0 111 May 6,2004 City of Carlsbad Public Works - Engineering 1635 Faraday Avenue Carlsbad, CA 92008-7314 Attention: Doug Helming Re: Rancho Santa Fe Road North (Project 3907) Request for Agreement Amendment No. 2 (P.O. P112579) Dear Mr. Helming: Dokken Engineering is requesting an amendment (Amendment No. 2) to the agreement dated March 20,2003 between the City of Carlsbad and Dokken Engineering for engineering design services. The amendment is being requested to perform additional engineering design services not previously anticipated and not included within the original agreement. This letter supercedes our previous letter RE: Request for Agreement Amendment No. 2, dated February 3,2004. Below describes the various task items requested to be included within Amendment No. 2. The attached table, dated February 3,2004, summarizes the task items and the estimated hours to complete the required tasks, and the costs associated with each task. Task 1: Coordinate Plans and Specs with VWD Corrosion Consultant. The original agreement did not include coordination with the VWD-contracted corrosion engineering consultant DeCarlo and Associates. Dokken Engineering performed the following: 0 0 Coordinated with consultant by providing and receiving engineering drawings for review Coordinated with consultant by providing and receiving engineering specifications for review Revised drawings to include plan call-outs and details provided by the corrosion engineer Edited technical specifications provided by the corrosion engineer to provide a consistent format with contract specifications format and revised special provisions to include corrosion specifications Task 2: Revise Plan and Profile to Relocate 27" Waterline to Allow SDG&E Gas Line Placement. The locatjon of the planned 6" and 2" gas lines by SDG&E were unknown until after the completion of the improvement plans and waterline plans. Gas line location preference by 9665 (~ESAPEAKE DFiivE, SUIIF 435 SAN DIFGO, CA 921h-1367 TEL: 858-514-8377 FAX: 858-514-8608 Page A-4 SDG&E required revisions to 27” waterline plan and profile drawings to relocate the waterline away from planned gas lines. Dokken Engineering performed the following: Revised 27” waterline plan and profile drawings to allow 6” and 2” gas line placement by SDG&E 2” gas lines by SDG&E and additional 6” and 2” gas lines by SDG&E locations of planned 6” and 2” gas lines by SDG&E 0 Resubmitted various drawings to Carlsbad showing locations of planned 6” and Revised various drawings for clarity due to 27” waterline location change Resubmitted various drawings to Carlsbad that required revision due to 0 0 Task 3: Add Civil and Electrical Phis, Specs and Estimate for CMWD Recycled Water Metering Station. After 100% PS&E plan check review comments were addressed there was a request by CMWD staff for Dokken Engineering to prepare PS&E for a recycled water metering station located at the northwest quadrant of the Rancho Santa Fe Road/Corintia Street intersection. Dokken Engineering performed the following: 0 Prepared PS&E for the recycled water metering stations at the northwest Submitted various drawings and specifications to Carlsbad regarding the Electrical subconsultant Moraes & Pham provided electrical engineering and quadrant of Rancho Santa Fe Road/Corintia Street intersection recycled water metering station prepared PS&E for electrical components of the recycled water metering station 0 0 Task 4: Revise Bridge Plans, Specs, Estimate and Calculations to Add Electrical Transmission Facilities within Bridge Column Cell. SDG&E requested bridge plans be revised to place electrical conduit within a bridge cell rather than within bridge sidewalk as previously planned. Dokken Engineering performed the following: 0 Developed several alternatives for location of SDG&E electrical conduits within the planned southbound bridge Met with SDG&E on various occasions to coordinate electrical conduit alternative locations adjusting SDG&E drawings for conformity and clarity drawings SDG&E and incorporating notes within technical specifications Revised bid schedule and engineer’s estimate of cost for additional electrical conduit construction electrical conduit PS&E 0 Utilized SDG&E drawings within revised bridge PS&E by acquiring and Developed construction details where necessary to supplement SDG&E Revised special provisions by editing construction drawing notes by 0 0 0 Reviewed SDG&E work order documents for conformity with bridge Page A-5 Task 5: Revise Plans, Specs and Estimate to Include Planned San Marcos Soundwall, Paleontologist Requirements, Various Order of Work Requirements and NEPA Requirements. Caltrans Office of Local Assistance required revisions to the PS&E prior to issuing Authorization to Construct for Phase 2 improvements. Dokken Engineering performed the following: 0 Reviewed approved environmental document and compared special Revised special provisions to indicate a City-contracted paleontologist would Revised special provisions to more closely conform to various construction Revised plans to show the required soundwall north of Melrose Drive and provisions and environmental document for conformity be present during earthmoving operdtions operational requirements found within the approved environmental document constructed by San Marcos 0 0 0 Task 6: Revise Stage Construction and Traffic Handling Plans Per 8/03 Meeting with Dick Wygand, San Marcos. Stage Construction and Traffic Handling Plans revisions were requested by Carlsbad after the 100% PS&E was completed, per August ’03 discussions with the Dick Wygand, San Marcos. Revisions were a result of slower than anticipated progress by San Marcos on their Rancho Santa Fe Road improvements. Dokken Engineering performed the following: e Revised Traffic Handling plans including reformatting various sheets to accommodate restrictions to the Contractor’s operation operation 0 Revised special provisions to indicate restrictions to the Contractor’s Task 7: Revise Driveway Construction Details and Waterline Plans per Comments by San Marcos. Driveway construction detail revisions and waterline plan revisions were requested by San Marcos after the 100% PS&E was completed, per September ’03 written comments by Tim Regello, San Marcos. Dokken Engineering performed the following: 0 Construction details were revised and the type of standard plan driveways Locations of reset and relocated fire hydrants were revised and connection points Bid schedule and engineer’s estimate of cost were revised to reflect Replacement sheets on mylar were provided for Carlsbad and San Marcos were revised for driveways on La Costa Meadows Drive were adjusted for privately owned hydrant different driveway types approval and signature 0 0 0 Task 8: Revise Recycled Waterline Plans and Storm Drain Plans per comments by VWD. Recycled waterline profile revisions and storm drain profile revisions were requested by VWD after the final PS&E was completed, per September ’03 written comments by Ken Gerdes, VWD. Dokken Engineering performed the following: Page A-6 0 0 Revise 30” recycled waterline profile (RCW ‘A’) Revise storm drain system 13 and storm drain system 14 Task 9: Prepare Multiple Authorization to Construct Components and Perform Enhanced Caltrans Coordination. Repetitive revisions to the PS&E, evolving property acquisition status by Carlsbad, and inconsistent requirements by Caltrans, resulted in numerous Caltrans meetings and submittals required to receive Right-of-way Certification and Authorization to Construct. Previous agreement with Dokken Engineering provided compensation for Caltrans coordination based upon expected effort per previous federally funded projects. However, efforts required for Caltrans coordination exceeded anticipated efforts. Dokken Engineering performed the following: 0 Met with Caltrans Local Assistance staff and Caltrans Right-of-way staff Revised PS&E checklist, PS&E certification, Finance Letter and Authorization Prepared Right-of-way Certification (Type 3) forms and later upgraded forms on various occasions to determine current requirements for Right-of-way Certification and Authorization to Construct to Construct forms due to various changes to Right-of-way Certification (Type 1) e 0 Task 10: Purchase Preliminary Title Reports (I 1 total at $200/Each) (by subconsultant Aguirre & Associates). Dokken Engineering subconsultant Aguirre & Associates purchased current Preliminary Title Reports from Chicago Title to support Right-of-way acquisition by the City of Carlsbad. Aguirre & Associates performed the following: 0 Purchased eleven current Preliminary Title Reports at $200.00 each Task 11: Prepare Plans and Specifications for Phase 2 Clearing Construction Change Order. Plans and specifications were prepared for the clearing of the Phase 2 project site. Plans and specifications were used by the Phase I Contractor to clear the Phase 2 site by construction change order. Dokken Engineering performed the following: Prepared plans and specifications showing clearing limits and construction Revised Phase 2 specifications to indicated project site would be cleared details for clearing the Phase 2 project site previous to Phase 2 contract award 0 Task 12: Prepare SWPPP Document for Phase 2 Clearing CCO. A Storm Water Pollution Prevention Plan (SWPPP) was developed for use by the Phase 1 Contractor for the clearing of the Phase 2 project site. Dokken Engineering performed the following: Page A-7 Prepared a SWPPP for clearing of the Phase 2 project site comment, and revision Provided SWPPP to the City of Carlsbad and Phase 1 Contractor for review, Task 13: Design Curb Profile at northwest quadrant RSF RoadMelrose Drive intersection, Revise Sheets, and Mark-up San Marcos Plans. Review of improvement plans for Rancho Santa Fe Road by the City of San Marcos showed the planned curb prot’lles at the north-west quadrant of Rancho Santa Fe Road/Melrose Drive intersection provided adverse superelevation and steep grades. Dokken Engineering acquired current improvements plans from San Marcos’ consultants, reviewed the plans, and developed revised curb profiles to improve superelevation and grades. Dokken Engineering performed the following: Met with the City of Carlsbad to discuss improvement plans by the City of Coordinated with City of San Marcos’ consultants to acquire hardcopy and San Marcos electronic design files of current improvement plans for Rancho Santa Fe Road Analyzed improvement plans, developed recommendations for revised plans and provided red-line improvement plans to Carlsbad revised City of San Marcos’ improvement plans Revised City of Carlsbad’s Rancho Santa Fe Road improvement plans to match Task 14: Revise 24” RCW line Plan and Profile due to Phase 1 Changes. Construction changes in Phase 1 of the project revised the terminus of the 24” recycled waterline. The terminus of the 24” recycled waterline was revised to minimize conflicts with the existing recycled waterline. Dokken Engineering performed the following: Revised the Phase 2 plans by adjusting the plan and profile of the 24” recycled waterline per the Phase 1 construction changes Task 15: Provide Additional Mylar Sheets. Various plan revisions were performed after the initial mylar submittal to Carlsbad was completed. Plan revisions completed after the initial mylar submittal required effort to plot sheets and direct expenses for mylar media. Dokken Engineering performed the following: Plotted various plan sheets on mylar and provided mylar media for plotting Task 16: Assist in Special Provisions Formatting per Carlsbad Purchasing’s Request. Carlsbad’s Purchasing Department requested the contract Special Provisions be provided in a single-sided format. Dokken Engineering provided assistance on an expedited schedule to reformat contract Spccial Provisions and the hardcopy inserts to satisfy requests by the Purchasing Department. Dokken Engineering performed the following: Page A-8 0 Reformatted contract Special Provisions and hardcopy inserts per Carlsbad requests Please review the attached table and provide an amendment (Amendment No. 2) to the original agreement between the City of Carlsbad and Dokken Engineering. If there is any additional information I can provide to you, do not hesitate to contact me. Sincerely , (.> .rp pc*, pL&d.(: cJ ”-=? Kirk F. Bradbury, P.E. Project Manager Attach: Budget by Task and Pcrson table, datcd 5/6/04 Page A-9 City of Carlsbad Rancho SanQ Fe Road. Realignmeni Prqeci NO. 3190 City PM: D Helming RANCHO SANTA FE ROAD NORTH (Project 3907) AMENDMENT 2 - P.O. P112579 (PWENG 333) BUDGET BY TASK AND PERSON rask NO. I Deacrrption 1 ICwrdinate Plans and Specs with VWD Corrosion Consultant Revise Plan and Profile to Relocate 27" Waterline to Allow SDGBE Gas Lh Placement and Revise Various Affected Sheets Add Electrical Plans, Specs and Estimate tor CMWD Recycled Water 31 Metering Station (Moraes 8 Pham) ~.- Revise EridgePlans, Specs, Estimate and Calculations lo Add Electrical ____ .______ .____ Revise Stage Construction and Tmfli Handling Plans per 8/03 meeting with Revise Water Line Plans to Include Various Fire Hydrant Installations and Relocations per 9/03 comments by San Marcos Revise Recycled Waterline Profile and Storm Drain Profiles per comments b VWD .. -- Prepare Multiple Authorizason to Construct Components and Perform [Enhanced Caltrans Coordination 10 IPurchase Preliminary Title Reports (11 total at $ZOWEach) (Aguirra) ___.__ ____ 14 rse 24' RCW line Plan and Profile due to Phase 1 Changes 15 - - - ___ I __ - ___ - - - Pmvide Additional Mylar Plan Sheets Assisl in special ProvisiMls Formatting per Carlsbad Purchasing's Request ________ - ._ - --.- I1 I 1 TOTAL HOURS1 1 I TOTAL COSTS - 176 22 4,265.01 2.510.Ol -?-- &May-04 Page A-1 0 Rancho Santa Fe RoadRealignment & WideningConstruction Update Phase 1 Rancho Santa Fe Road•Overview of Project & Area•Recent Traffic Control Changes•Public Outreach Efforts•Estimated Schedule Rancho Santa Fe RoadRancho Santa Fe RoadPhase 2Phase 2Phase 1Phase 1Existing Rancho Santa Fe RoadExisting Rancho Santa Fe RoadNewNewRanchoRanchoSanta Santa FeFeRoad Road AveAveElijoElijoLaLaCity of CarlsbadCity of San MarcosProject OverviewProject OverviewVillages of La Costa The RidgeVillages of La Costa The OaksUniversity CommonsSanSanCostaCostaRoadRoadM e lro se D rM elro se D rMAG San Elijo Hills Rancho Santa Fe Road Rancho Santa Fe Road Phase 1Phase 1Phase 2Phase 2Phase 1Phase 1Existing Rancho Santa Fe RoadExisting Rancho Santa Fe RoadNewNewRanchoRanchoSanta Santa FeFeRoad Road AveAveElijoElijoLaLaCity of CarlsbadCity of San MarcosTraffic Control Traffic Control Villages of La Costa The RidgeVillages of La Costa The OaksUniversity CommonsSanSanCostaCostaRoadRoadM e lro se D rM elro se D rMAG San Elijo Hills Rancho Santa Fe Road Phase 1Options to Minimize Traffic ImpactsOption 1: Traffic Signal Modifications•Timing Adjustments•No increase in capacity •Implemented in a few hours•No impacts to budget Rancho Santa Fe Road Phase 1Options to Minimize Traffic ImpactsOption 2: Lane Closures•Two lanes from San Elijo Road and approaching La Costa Avenue•One lane at La Costa Avenue•No capacity increase•Implemented overnight•Estimated Cost $20,000 Rancho Santa Fe Road Phase 1Options to Minimize Traffic ImpactsOption 3: Additional Southbound Lane at La Costa Avenue Intersection•Additional through/right turn lane at La Costa Avenue•Approximately 250 feet long•Limited capacity increase•Construction duration: 10 to 14 days•Estimated Cost $20,000 Rancho Santa Fe Road Phase 1Options to Minimize Traffic ImpactsOption 4: Additional Signage•Additional Changeable Message Signs•Additional Posted Signs•No capacity increase•Implemented overnight Public OutreachMethods of CommunicationNewsletters, Mailers, Door HangersEmail to Home Owners Association ContactsProject Info. Line: 760-744-5339City’s Website: www.ci.carlsbad.ca.usNews ReleasesPhone Calls to Schools, Agencies and Org.Personal Visits to Businesses Public Outreach Targets •Over 10,600 Residents & Businesses along the Rancho Santa Fe Road corridor•Home Owners Associations•Includes areas of Carlsbad, San Marcos and the County of San Diego•Media: Newspapers & Television•Schools in Carlsbad, San Dieguito and San Marcos Districts•Agencies: NCTD, Post Offices, Water & Sewer Districts, City of San Marcos Rancho Santa Fe Road SchedulePhase 1Fall 2004End ConstructionUnder ConstructionPhase 2Spring 2006End ConstructionUnder Construction Rancho Santa Fe Road ScheduleBottom LineExpect DelaysUSE ALTERNATE ROUTES WHENEVER POSSIBLEProject Info. Line: 760-744-5339City Website: www.ci.carlsbad.ca.us