HomeMy WebLinkAbout2004-07-13; City Council; 17706; Traffic Signal at Camino De Los CochesB# 17,706
ITG. 711 3/04
1EPT. ENG
Sutherlin Contracting, Inc. $124,150
HMS Construction $142,500
R&M Electrical Contracting $163,460
Moore Electrical Contracting $167,553
Lekos Electric $168,000 AEC Construction $169,860 .
CITY OF CARLSBAD -AGENDA BILL
DesignIAdministration
Construction
Construction Inspection 8 Administration (15%)
Construction Contingencies (1 5%)
Total Project Cost
Total Amount Appropriated for this Project
E: ACCEPTING BIDS AND AWARDING A
CONTRACT FOR THE CONSTRUCTION OF THE
TRAFFIC SIGNAL AT CAMINO DE LOS COCHES AND
CALLE ACERVO, PROJECT NO. 3916-1
$4.050 $124,150
$18,622
$18,622
$165,444
$190,000
CITY OF CARLSBAD -AGENDA BILL
E: ACCEPTING BIDS AND AWARDING A
CONTRACT FOR THE CONSTRUCTION OF THE
TRAFFIC SIGNAL AT CAMINO DE LOS COCHES AND CITY ATTY.
CITY MGR. CALLE ACERVO, PROJECT NO. 3916-1
LOCATION MAP
NOT TO SCALE
LOCATION: TRAFFIC SIGNAL AT CAMINO DE LOS COCHES
AND CALLE ACERVO, PROJECT 3916-1
EXHIBIT
I
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
RESOLUTION NO. 2004-231
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
CARLSBAD, CALIFORNIA, ACCEPTING BIDS AND AWARDING A
CONTRACT FOR THE CONSTRUCTION OF THE TRAFFIC SIGNAL AT CAMINO DE LOS COCHES AND CALLE ACERVO,
PROJECT NO. 3916-1.
WHEREAS, the City Council of the City of Carlsbad, California, has determined it
iecessary, desirable and in the public interest to construct the traffic signal at Camino De Los
:oches and Calle Acervo; and
WHEREAS, six (6) sealed bids were received on June 17, 2004 for the project; and
WHEREAS, the lowest responsive, responsible bid for the project was submitted by
jutherlin Contracting, Inc., in the amount of $124,150; and
WHEREAS, there are sufficient appropriations available to complete construction of the
-affic signal.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Carlsbad,
:alifornia, as follows:
1.
2.
That the above recitations are true and correct.
That the low bid submitted by Sutherlin Contracting, Inc., in the amount of
;124,150, is hereby accepted and the Mayor is hereby authorized to execute a contract on behalf
if the City for the construction of the traffic signal at Camino De Los Coches and Calle Acervo.
3.
ip to $18,622.
I/
That the City Manager is hereby authorized to approve construction change orders
Y
3
1
2
3
4
5
6
7
6
9
10
11
12
13
14
15
6(
17
18
19
20
21
22
23
24
25
26
27
28
4. That the award of this contract is contingent upon the bidder submitting the lowest
responsive bid executing the required contract and submitting the required bonds and insurance
policies, as described in the contract, within twenty (20) days of adoption of this resolution.
The City Manager may grant reasonable extensions of time.
PASSED, APPROVED AND ADOPTED at a regular meeting of the Carlsbad City Council
held on the 13th dayof Julv , 2004 by the following vote, to wit:
AYES: Council Members Lewis, Kulchin, Hall and Packard
NOES: None
ABSENT: Council
CLAUDE A. LEWIS,
ATTEST: A
LWS%INE M) WOOD, City Clerk (SEAL)