HomeMy WebLinkAbout2005-12-13; City Council; 18372; City Curb and Gutter Concrete Work Contract4B# 18,372
IIITG. 12/13/05
IEPT. PW/GEN
RECOMMENDED ACTION:
/' - TITLE: REJECTING THE LOW BID AS NON-RESPONSIVE DEPT.HD.
AND AWARDING THE CONTRACT FOR CITY CURB AND GUTTER CONCRETE WORK CITY ATTY. CONTRACT NO. PWSOG-02STS
Adopt Resolution No. 2005-361 rejecting the bid of $84,921 from CH&D Construction and
accepting the bid of $1 15,747 and awarding the contract to D.G. Yeager Construction to repair and
replace curb, gutter, and sidewalks, Contract No. PWSOG-02STS.
2. D.G. Yeager Construction
3. Tri-Group Construction and Development, Inc.
4. Koch Armstrong General Engineering, Inc.
ITEM EXPLANATION:
$1 15;747.00
$1 16,127.00
$1 94,087.25
The Streets Department bids out several contracts for sidewalk, concrete curb and gutter repair per year in order to keep up with the maintenance of the City's sidewalks, curbs and gutters. It was estimated based on earlier contract unit costs that the cost of this work would be below $100,000
and, therefore, a City Council request for approving plans and specs was not initiated. The lowest responsive bid is now over $100,000 and requires City Council approval to award the contract.
Four bids were received, opened, witnessed and recorded on August 24, 2005. The bid amounts ranged from $84,921 to $194,087.25. The bids were reviewed by the Public Works Department and
were as follows:
I 1. CH&D Construction I $84,921.00 I
CH&D Construction submitted the lowest bid in the amount of $84,921. However, the bid submitted by CH&D Construction does not meet the contractual requirement that the Bidder have an active contractor's license. Therefore, staff recommends the bid from CH&D Construction be declared
non-responsive in accordance with the contract documents.
D.G. Yeager Construction submitted the lowest responsive bid. Therefore, staff recommends the
contract be awarded to D.G. Yeager Construction, the lowest responsive bidder, in the amount of $1 15,747. The contractor's registration and bonds are in order and references are satisfactory. Contract documents are on file in the General Services offices of Public Works.
ENVIRONMENTAL REVIEW:
This agreement is not a project as defined by Section 15378 of the CEQA Guidelines.
FISCAL IMPACT:
The total estimated construction cost of $1 15,747 for this project will be funded from the Streets
Department concrete maintenance account.
EXHIBITS:
1. Resolution No. 2005-361 rejecting the bid of $84,921 from CH&D Construction and accepting the bid of $115,747 and awarding the contract to D.G. Yeager Construction to repair and replace curb, gutter, and sidewalks, Contract No. PWSO6-02STS.
DEPARTMENT CONTACT: Rob Houston, (760) 434-2992, rhous@ci.carlsbad.ca.us
I
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
RESOLUTION NO. 2005361
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
CARLSBAD, CALIFORNIA, REJECTING THE LOW BID AS
THE CONTRACT FOR CURB, GUTTER, AND SIDEWALKS,
NON-RESPONSIVE AND ACCEPTING BIDS AND AWARDING
CONTRACT NO. PWSOG-02STS.
WHEREAS, bids have been solicited by the City of Carlsbad, California to replace and
repair City curb, gutter, and sidewalk facilities in various locations; and
WHEREAS, the bids were received, opened, witnessed and recorded on August 24,2005;
and
WHEREAS, the lowest bid received was submitted by CH&D Construction in the amount
Df $84,921 ; and
WHEREAS, the City of Carlsbad requires that the all bids evidence that the bidder have a
Jalid contractor’s license and that any bid that does not do so will be rejected as non-responsive;
and
WHEREAS, CH&D Construction did not possess a valid contractor’s license at the time of
Did submittal; and
WHEREAS, the lowest responsive bid received was submitted by D.G. Yeager
Construction in the amount of $1 15,747; and
WHEREAS, City curb, gutter, and sidewalk repairs are necessary to maintain City
standards; and
WHEREAS, the contract cannot be awarded without City Council approval; and
WHEREAS, sufficient funds are available in the Streets Maintenance Budget.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Carlsbad,
California, as follows:
1.
2.
?ejected.
3.
That the above recitations are true and correct.
The bid of $84,921 by CH&D Construction be declared non-responsive and be
The bid of $1 15,747 by D.G. Yeager Construction and a contingency account of
$1 1,575 is hereby accepted.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
5. That the award of this contract is contingent upon D.G. Yeager Construction, Inc.,
sxecuting the required contract and submitting the required bonds and insurance policies, as
described in the contract, within twenty (20) days of adoption of this resolution. The City Manager
may grant reasonable extensions of time.
PASSED, APPROVED AND ADOPTED at a regular meeting of the Carlsbad City Council
held on the 13th day of Demer , 2005 by the following vote, to wit:
AYES: Council Members Lewis, Hall, Kulchin, Packard, Sigafoose
4TTEST
LORRAINE M. WOOD, City Clerk (SEAL)