HomeMy WebLinkAbout2006-02-07; City Council; 18437; Library Learning CenterCITY OF CARLSBAD - AGENDA BILL Yl AB# MTG. DEPT. 18,437 2/07/06 ENG TITLE: AUTHORIZATION TO ADVERTISE FOR BIDS FOR THE LIBRARY LEARNING CENTER AND APPROPRIATION OF ADDITIONAL FUNDS, PROJECT NOS. 3771 AND 4001 DEPT. HD> CITY ATTY \Un CITY MGR^^V RECOMMENDED ACTION: Adopt Resolution No. 2006-032 approving plans and specifications and authorizing the City Clerk to advertise for bids for the construction of the Library Learning Center, Project Nos. 3771 and 4001, and Appropriation of Additional Funds. ITEM EXPLANATION: On October 28, 2003, through Resolution No. 2003-288, the City Council directed staff to obtain architectural services to design concepts for a permanent Learning Center at a location to be determined by the City Council. The Learning Center would house the Centra de Informacion, the Adult Learning Program, a homework center, a computer lab, and community meeting rooms. On April 27, 2004, through Resolution No. 2004-139, the City Council authorized the purchase of the Carlsbad Girls Club property at 3368 Eureka Place. The property included a "main building" and an adjacent house. Community Development Block Grant (CDBG) funding was obtained for the property acquisition. The Library subsequently hired Manuel Oncina Architects, Inc., to design building and site improvements to locate the Library Learning Center at this site, which will house the Adult Learning and Centra de Informacion Programs. When the City acquired the Eureka Place property, it acquired the current lease with Neighborhood House Association (NHA), which operates Head Start in the main building. With the acquisition of the lease the City receives revenue from the tenants. The current lease ends in June 2006 with NHA's option to extend for two, one-year terms. They have indicated a desire to extend through June 2007. The City retains a legal obligation to NHA through June 2008. To accommodate NHA, on April 19, 2005, through Resolution No. 2005-111, the City Council authorized purchase of a modular building to be located on the northeast corner of the property. The modular building will be used to house the Head Start Program for the remainder of the lease with NHA. The modular building will be purchased from Williams Scotsman Company with CDBG funding. On September 9, 2005, through Resolution No. 2005-269, the City Council authorized Amendment No. 1 to the agreement with Manuel Oncina Architects, Inc. The purpose of Amendment No. 1 was to revise the project from upgrades to the main building to adding a second story. Plans and specifications for the Library Learning Center have now been completed which includes the following: • Removal of the existing house to provide additional parking space. • The addition of a second story to the existing main building to provide an additional 5,403 square feet, resulting in a total building area of 11,393 square feet. • Furnishing and installation of a 4,800 square feet modular building to be used initially by Head Start. • Upgrades to the standard modular building to add fire sprinklers, 3-phase electrical power, and upgraded windows. • Removal of existing site improvements and construction of a new onsite parking lot, sidewalks, landscaping, fencing, and playground area. • Provisions for furniture, fixtures, and information technology equipment. Page 2 ENVIRONMENTAL REVIEW: On April 20, 2005, the Planning Commission approved a Negative Declaration and CUP No. 04-12 for the project by Resolution Nos. 5893 and 5894, respectively. FISCAL IMPACT: LIBRARY LEARNING CENTER PROJECT COST AND FUNDING Purchase of Property from Carlsbad Girls Club Design/ Administration/Environmental: 1 . Preliminary and Final Design of Main Building and Site (Manuel Oncina Architects, Inc.) 2. Geotechnical Report (GeoSoils, Inc.) 3. Asbestos Survey on House (Marc Boogay Consulting Engineer) 4. Church of the Coast Relocation Cost 5. SDG&E Electrical Power Design Services 6. County of San Diego Health Department Plan Check for Recycled Water 7. Miscellaneous Expenses TOTAL OF DESIGN/ADMINISTRATION/ENVIRONMENTAL Construction Of Main Building And Site Improvements: 1. Engineer's Estimate for Construction of Improvements to Main Building, Site Improvements, and Demolition of Existing House and Site Improvements (PreCon West) 2. Additional Expense for Phasing the Construction and Inflation to Mid-Point of Construction (Engineering Department) 3. Estimated Cost for Information Technology Infrastructure and Peripherals ^Information Technology Department) 4. Estimated Cost for Furniture (Interior Architecture, Inc.) 5. Cost for Public Art Work through Arts Department at 1 % of Construction 6. Head Start Playground Relocation Expense 7. SDG&E Installation of 3-Phase Power Extension TOTAL ESTIMATED CONSTRUCTION COST FOR MAIN BUILDING & SITE Purchase And Installation Of Modular Building: 1 . Cost for Modular Building from Williams Scotsman 2. Cost for Modular Building Upgrades from Williams Scotsman TOTAL COST FOR MODULAR BUILDING Construction Inspection, and Administration (7%) Construction Contingencies (10%) TOTAL PROJECT COST Funding: General Capital Construction (GCC) Community Facilities District No. 1 (CFD#1) Community Development Block Grant (CDBG) TOTAL AMOUNT APPROPRIATED FOR THIS PROJECT TOTAL ADDITIONAL APPROPRIATION REQUIRED $278,000 $285,725 4,250 975 4,000 894 345 3,811 $300,000 $2,038,000 150,000 255,000 400,000 28,000 15,000 34,000 $2,920,000 $435,000 75,000 $510,000 $202,000 $290,000 $4,500,000 $600,000 1 ,497,398 958,163 $3,055,561 $1,444,439 The project cost breakdown is shown above and totals approximately $4.5 million. Since the project has three funding sources with appropriations totaling approximately $3.1 million, an additional appropriation of $1.4 million is required to complete the project. It is recommended that the additional appropriation be obtained from the Community Facilities District No. 1 Fund. PageS There are three main reasons for the cost increase above the CIP budget including additional expense for building, site and utility improvements, non-inclusion of architect's design fee in the CIP budget, and increases for furniture, IT equipment, special reports and construction management. These are detailed in the table below: COST ITEM Main Building, Site and Utilities Architect's Design Fee Furniture & IT Equipment Special Reports & studies Construction Management TOTAL EXPENSE CIP BUDGET $1,136,000 -0- $493,000 -0- $120,000 $1,749,000 CURRENT ESTIMATE $2,038,000 $286,000 $655,000 $12,000 $202,000 $3,193,000 TOTAL INCREASE ($3,193,000 - $1 ,749,000) = $1 ,444,000 Project Options Because of the cost increase, staff has considered three options for this project. Following is a description of each option. Option No. 1 is to construct the project as designed with the addition of the second story, installation of the modular building, and fully utilizing the Learning Center, by combining the programs of the Centre de Informacion and Adult Learning Program in one facility. Head Start would occupy the modular building under a lease through NHA. The total project cost is estimated at $4.5 million, resulting in the need for an additional appropriation of $1.4 million. Option No. 2 is to phase the two-story building addition. The current building could be remodeled as a two-story structure, but the second story would not initially be finished inside. Centro de Informacion would occupy the first floor immediately. A modular building would be placed on the east side of the property and be occupied by Head Start. The Adult Learning Program would continue to occupy leased space off-site, until future funding would enable completion of the second floor. Option No. 2 results in an estimated project cost of $3.6 million by eliminating the interior finish, walls, electrical, plumbing, furniture, elevator, and IT equipment in the second story, but maintaining fire alarms and emergency lighting. This option will need an additional appropriation of $0.6 million. Option No. 3 is to return to the original concept for the Learning Center by remodeling the existing one-story main building and placing the modular building on the east side of the property. The Centro de Informacion would occupy the main building, thereby eliminating their leased space. Head Start would initially occupy the modular building. The Adult Learning Program would continue to lease space for their program until the legal obligation to house Head Start terminates, then they would relocate to the modular building. Option No. 3 has an estimated project cost of $2.8 million, and no additional appropriation is required. If the City Council elects either Option No. 2 or 3, staff will need to return to the City Council with a new resolution to reflect Council's direction. EXHIBITS: 1. Location Map. 2. Resolution No. 2006-032 approving plans and specifications and authorizing the City Clerk to advertise for bids for the construction of the Library Learning Center, Project Nos. 3771 and 4001, and Appropriation of Additional Funds. 3. Background Information and Option Analysis. DEPARTMENT CONTACTS: William Plummer, (760) 602-2768, bplum@ci.carlsbad.ca.us Heather Pizzuto, (760) 602-2056, hpizz@ci.carlsbad.ca.us LOCATION MAP SITE NOT TO SCALE SITE VICINITY MAP NOT TO SCALE PROJECT NAME LIBRARY LEARNING CENTER 3368 EUREKA PLACE PROJECT W 4001 EXHIBIT 1 DRAW BY: SCOTT EVANS, CARLSBAD ENGINEERING DEPT. 1/18/06 C: \CAPITAL\3771-4001.DWG 1 RESOLUTION NO. 2006-032 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 27 28 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CARLSBAD, CALIFORNIA, APPROVING PLANS AND SPECIFICATIONS, APPROPRIATION OF ADDITIONAL FUNDS, AND AUTHORIZING THE CITY CLERK TO ADVERTISE FOR BIDS FOR THE CONSTRUCTION OF THE LIBRARY LEARNING CENTER, PROJECT NOS. 3771 AND 4001. WHEREAS, the City Council of the City of Carlsbad, California, has determined it necessary, desirable, and in the public interest to construct the Library Learning Center; and WHEREAS, the plans and specifications for furnishing of all labor, materials, tools, equipment, transportation, and other expenses necessary or incidental of said project have been prepared and are on file in the Engineering Department of the City of Carlsbad and are incorporated by reference herein; and and WHEREAS, said project was included in the 2005/2006 Capital Improvement Program; WHEREAS, the estimated project cost for the Library Learning Center is $4,500,000 including land purchase cost, a new 4,800 square foot modular building, addition of a 5,400 square foot second story to the main building, and site improvements; and WHEREAS, the existing appropriation is $3,055,561 from CDBG Funds, GCC Funds and Community Facilities District No. 1 Funds; and WHEREAS, an additional appropriation in the amount of $1,444,439 is required to complete the project which will be obtained from Community Facilities District No. 1 Fund. NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Carlsbad, California, as follows: 1. That the above recitations are true and correct. 2. That the plans, specifications, and contract documents on file in the Engineering Department of the City of Carlsbad are hereby approved. 26 /// 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 3. The City Clerk of the City of Carlsbad is hereby authorized and directed to publish, in accordance with State law, a Notice to Contractors Inviting Bids for the construction of the Library Learning Center, Project Nos. 3771 and 4001, in accordance with the plans, specifications, and contract documents referred to herein. 4. That an additional appropriation in the amount of $1,444,439 will be obtained from the Community Facilities District No. 1 Fund to pay for the project cost. PASSED, APPROVED AND ADOPTED at a regular meeting of the Carlsbad City Council held on the 7th day of February , 2006 by the following vote, to wit: AYES: Council Members Lewis, Hall, Kulchin, Packard, Sigafoose NOES: None ABSENT: CLAUDE A. LE (SEAL) •c -c » Page 1 of 7 EXHIBIT 3 BACKGROUND INFORMATION AND OPTION ANALYSIS CARLSBAD CITY LIBRARY LEARNING CENTER PROJECT OPTIONS GROWTH MANAGEMENT STANDARD: The City of Carlsbad's Growth Management Plan was approved in July 1986. This plan implements a Local Facilities Management Plan, which includes requiring a specific amount of space to provide library services. The City's Growth Management Plan states that 800 square feet per 1,000 population of library space must be scheduled for construction within five years. With the current amount of "owned" library space, and utilizing SANDAG population projections, the City will need to provide residents with additional library space in the year 2013. However, the "owned" square footage of the Eureka Place property is not currently being used to deliver library services because Head Start is occupying the building. Therefore, by taking the current square footage amount used to deliver library services, and using SANDAG projections, the City will need to provide residents with additional library space in the year 2009. By developing the full use of the Learning Center planned for Eureka Place, the Library will be able to meet the Growth Management Standard until 2015 which is estimated as follows (i.e., 99,745 SF/800 SF x 1,000 population = 124,681 population). The required Library space population can be compared to SANDAG population, as indicated below. Facility Cole Library Dove Library Centra ALP Current Learning Center Future LC 1 -Story Future LC 2-Story TOTAL Current Owned/ Leased Space (Square Feet) 24,352 64,000 1,440 1,359 5,723 96,874 Current Owned/ Leased Space Used to Deliver Library Services (Square Feet) 24,352 64,000 1,440 1,359 91,151 Future Learning Center 1st Story (Square Feet) 24,352 64,000 5,990 94,342 Future Learning Center 2nd Story (Square Feet 24,352 64,000 11,393 99,745 SANDAG ESTIMATES YEAR Jun-05 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 POPULATION 95,146 99,754 104,362 108,970 113,578 118,189 119,572 120,955 122,338 123,721 125,104 7 Page 2 of 7 FUNDING SOURCES IDENTIFIED: Community Facilities District No. 1 (CFD #1): The Georgina Cole Library is scheduled for replacement in the City's Capital Improvement Program. The total amount of money identified for this project is approximately $14 million, funded from two sources. The CFD #1 is scheduled to fund $4.4 million of the Cole Library project in the year 2010++. The Learning Center project has currently "borrowed" $1.5 million against this funding source. This money is planned to be repaid through fundraising efforts by the Carlsbad Library and Arts Foundation (CLAF). Any monies not repaid to the CFD #1 equates to less funding available for the future Cole Library project. The Library and CLAF are highly motivated to work toward repaying those borrowed funds. CLAF has already invested $47,000 in the services of a fundraising consultant and developing a capital campaign plan. The CFD #1 funding source is finite. Once these monies have been expended, the City will need to utilize the Public Facilities Fund (PFF) as a funding source. Nine million four hundred thousand dollars ($9.4 million) has been identified in this fund for the Cole Library project. Current predictions indicate the overall PFF fund will realize a shortfall of approximately $5 million in the year 2010++. This shortfall could impact the future Cole Library replacement project. The CFD #1 available fund balance for the Cole Library project is approximately $3 million. These funds can be used to pay the additional amount required to complete the Learning Center. General Capital Construction (GCC): The General Fund has provided $600,000 toward the Learning Center project. The Library provided this contribution. The maximum amount of General Fund monies that can be applied to the project is limited to $1 million. An additional $400,000 could be appropriated for the Learning Center project. Community Development Block Grant (CDBG): Funds have been appropriated to the Learning Center project for the past two years. An additional application has been submitted for this year. This year's maximum amount of funding available for this project is $223,000. Three other applicants are being considered. The CDBG Advisory Committee will develop recommendations on February 22, 2006, to be presented to Council at a later date. Any monies received will reduce the amount of CFD #1 funds needed to complete the Learning Center. Page 3 of 7 PROJECT OPTIONS: Three project options have been identified that would comply with City Council direction for the Library learning Center. The cost for each option is shown in the table below. TABLE 1 - PROJECT COST BREAKDOWN OPTIONS: Purchase cost of Property from Girls and Bovs Club Design/Administration/Environmental 1. Main Building and Site design cost (Manuel Oncina Architects, Inc.) 2. Geotechnical Report (GeoSoils Inc.) 3. Asbestos Survey on House (Marc Boogay Consulting Engineer) 4. Church of the Coast Relocation Cost 5. SDG&E Electrical Power Design Services 6. County of San Diego Health Dept Plan Check for Recycled Water 7. Miscellaneous Expenses TOTAL OF DESIGN/ADMINISTRATION/ENVIRONMENTAL Construction Costs 1. Engineer's Estimate for Construction of Improvements to Main Building, Site Improvements, and Demolition of Existing House and Site Improvements 2. Additional Expense for Phasing the Construction and inflation to mid point of construction (Engineering Department) 3. Estimated cost for Information Technology Infrastructure & peripherals 4. Estimated cost for furniture 5. Cost for public art work through Arts Office at 1 % of construction 6. Head Start Playground Relocation Expense 7. SDG&E 3-Phase Power Extension TOTAL ESTIMATED CONSTRUCTION COST Purchase and Installation of Modular Buildinq 1 . Cost for Modular Building from Williams Scotsman 2. Cost for Modular Building Upgrades from Williams Scotsman TOTAL COST FOR MODULAR BUILDING Construction Inspection, and Administration (7%) Construction Contingencies (10%) TOTAL PROJECT COST LESS SAVINGS AND/OR REVENUE TOTAL NET PROJECT COST Funding General Capital Construction (GCC) Community Facilities District No. 1 (CFD#1) Community Development Block Grant (CDBG) TOTAL AMOUNT APPROPRIATED FOR THIS PROJECT TOTAL ADDITIONAL APPROPRIATION REQUIRED No. 1 FULL TWO-STORY $278,000 $285,725 $4,250 $975 $4,000 $894 $345 $3,811 $300,000 $2,038,000 $150,000 $255,000 400,000 $28,000 $15,000 $34,000 $2,920,000 $435,000 $75,000 $510,000 $202,000 $290,000 $4,500,000 ($ 311,000) $4,189,000* $600,000 $1,497,398 $958,163 $3,055,561 $1,444,439 No, 2 PHASED TWO-STORY $278,000 $285,725 $4,250 $975 $4,000 $894 $345 $3,811 $300,000 1,707,000 110,000 150,000 225,000 22,000 15,000 34,000 2,263,000 $435,000 $75,000 $510,000 138,000 200,000 3,689,000 ($257,000) $3,432,000** $600,000 $1,497,398 $958,163 $3,055,561 $613,439 No.3 ONE-STORY $278,000 $285,725 $4,250 $975 $4,000 $894 $345 $3,811 $300,000 1,023,000 76,000 150,000 225,000 15,000 15,000 34,000 1,538,000 $435,000 $75,000 $510,000 88,000 126,000 $2,840,000 ($257,000) $2,583,000*** $600,000 $1,497,398 $958,163 $3,055,561 0 * See Option #1 Analysis. ** See Option #2 Analysis. *** See Option #3 Analysis. ANALYSIS OF OPTIONS: When the City acquired the Eureka Place property, it acquired the current lease with Head Start. This lease gave the City the right to receive the revenues from Head Start. The current lease ends in June 2006 with Head Start's option to extend for two one-year terms. They have indicated a desire to extend through June 2007. The City retains a legal obligation to Head Start through June 2008. The lease for FY 05-06 allows the City to collect $7,119.83 per month. On July 1, 2006, the monthly amount will increase to $7,333.42. This revenue, and additional cost savings described in the analysis of each option, is applied to each option in the table. Page 4 of 7 OPTION NO. 1: TWO-STORY BUILDING. FULL COMPLETION This option constructs the fully envisioned Learning Center, combining the programs of the Centro de Informacion and Adult Learning Program in one facility with additional opportunities to provide family literacy, learning assistance, a computer lab and meeting rooms for tutoring. A modular facility would be placed on the east side of the property to house the Head Start program, or other future tenants. This option implements the Council's initial direction to staff in 2003. The Carlsbad Library and Arts Foundation would enter into a complete fundraising campaign based on pursuing the original concept of the Learning Center's services. Advantages: • Reduction in operating costs realized by eliminating the Centro and ALP leased space • Continued revenue received from Head Start (or future tenants) • One-time construction is more cost-effective and results in no disruption to library services • Achievement of the City's growth management standard obligation until the year 2015. • Maximized CLAF fundraising potential Disadvantages: • Additional funding needs to be appropriated to cover project costs. • Net Project Cost: In calculating the net project cost, the ALP and Centro program leases are not new costs to the Learning Center project, each having been in existence for several years. Ideally, only new costs or savings are shown when considering project impacts. However, to highlight this option's impact to the net project costs, the changes occurring to the leases and those costs and/or savings for one year are shown. 1.Annual savings achieved from eliminating leases: Savings Subtotal 2. 3. Revenue received to-date from tenants at Eureka Place: Projected revenue to be received from Head Start through June 2007 (they have exercised one extension option, to date: Revenue Subtotal Total Savings and Revenue TOTAL PROJECT COST LESS SAVINGS AND REVENUE TOTAL NET PROJECT COST ALP $27,360 Centro $12,000 $39,360 $141,374 $130,720 $272,094 $311,454 $4,500,000 ($311,454 $4,188,546 <0 Page 5 of 7 Impact to Funding Sources: The Carlsbad Library and Arts Foundation (CLAF) has committed to fundraising efforts targeted at $1.5 million less campaign costs. They will provide fundraising proceeds to the City to reimburse the amount borrowed against CFD#1. They have also indicated a desire to continue those fundraising efforts beyond that targeted amount. When the Learning Center repayment is achieved, the monies will be used toward a Cole Library replacement facility. It is the Library's desire to repay all funds borrowed from CFD #1 to benefit the future Cole Library project. The Library has submitted an additional application for CDBG funding. The CDBG/HOME Funding Advisory Committee will determination recommendations for funding amounts to applicants on February 22, 2006, to be presented to Council at a later date. Any funding received through CDBG reduces the amount of money needed through the GCC or CFD #1 sources. The GCC funding source is capable of supporting the project with another $400,000. Any additional funding allocated toward the Learning Center project reduces the amount of money needed through the CFD #1 source. Additionally, all future revenues collected through leasing the modular facility repays the GCC contribution. OPTION NO. 2: PHASED TWO-STORY BUILDING The current building would be remodeled as a two-story structure; however, the second floor would remain unfinished and unoccupied. This remodel would enable the Centra de Information to occupy the first floor immediately. A modular facility could be placed on the east side of the property and occupied by Head Start. The Adult Learning Program would continue to occupy leased space off-site, until future funding would enable completion and their occupancy of the second floor. This option would require the Carlsbad Library and Arts Foundation to modify its fundraising campaign to reflect a longer timeframe for completion of the Learning Center concept, but it could still pursue the components of its existing fundraising plan. Advantages: A permanent home for the Centra eliminates lease costs Continued revenue received from Head Start (or future tenants) Achievement of the City's growth management standard obligation until 2010 Reduced immediate additional funding required for the project. Project identity enabling the Carlsbad Library and Arts Foundation to fundraise Disadvantages: Construction costs will increase, in general, due to phased construction and time Final building permit may need to be reissued including updated fees and costs Plans and specifications need to be revised at future additional cost Additional funding will need to be secured for each phase Continued lease of space for the Adult Learning Program until future completion of second floor Disruption of service and potential additional risk costs associated from construction occurring while the building is occupied Page 6 of 7 Net Project Cost: In calculating the net project cost, the ALP and Centre program leases are not new costs to the Learning Center project, each having been in existence for several years. Ideally, only new costs or savings are shown when considering project impacts. However, to highlight this option's impact to the net project costs, the changes occurring to the leases and those costs and/or savings for one year are shown. 1. 2. Annual savings to maintain Adult Learning Program lease Annual savings achieved from eliminating Centra lease Cost Subtotal 3. 4. Revenue received to-date from tenants at Eureka Place Projected revenue received from Head Start through June 2007 (they have exercised one extension option, to date): Revenue Subtotal Net Revenue TOTAL PROJECT COST LESS NET REVENUE TOTAL NET PROJECT COST ($27,360) $12,000 ($15,3601 $141,374 $130,720 $272,094 $256,734 $3,689,000 ($256,734) $3,432,266 Impact to Funding Sources: Same as Option #1, except this option reduces the amount of borrowing needed from CFD #1. OPTION NO. 3: ONE-STORY BUILDING The original concept for the Learning Center could be implemented by remodeling the current one-story main building and placing modulars on the east side of the property. The Centra de Information would be able to move into the main building, thereby eliminating their leased space. The City would fulfill its legal obligation to Head Start by moving them into the modular facility. ALP would continue to lease space for their program until the legal obligation to house Head Start terminates, then relocate to the modular facility. Staff considered co-locating ALP and Centra together in the main building. While this option is possible, it does not fulfill Council's original direction to provide a computer lab and meeting rooms. Additionally, the concept does not allow the programs to use the advantage of working together to deliver enhanced services. The Carlsbad Library and Arts Foundation would need to modify its fundraising plan, which involves promoting the services and programs made possible by shared spaces and joint programs. The target of $1.5 million in fundraising would need to be re-evaluated. Advantages: • A permanent home for the Centra eliminates lease costs • Continued revenue received from Head Start until legal lease obligation expires • Achievement of the City's growth management standard obligation until 2010 • Reduced additional funding required for the project. Page 7 of 7 Disadvantages: • Continued lease of space for the Adult Learning Program until our legal obligation to Head Start ends • Loss of potential future revenues from tenants (Head Start or others) • Plans and specifications may need to be revised at future additional cost • Reduced efficiency of joint use space and merged functions between the Centre and Adult Learning Program • Opportunity for CLAF to successfully fundraise compromised by loss of project identity; loss of $47,000 already invested *** Net Project Cost: In calculating the net project cost, the ALP and Centre program leases are not new costs to the Learning Center project, each having been in existence for several years. Ideally, only new costs or savings are shown when considering project impacts. However, to highlight this option's impact to the net project costs, the changes occurring to the leases and those costs and/or savings for one year are shown. 1. 2. Annual cost to maintain Adult Learning Program lease Annual savings achieved from eliminating Centra lease Cost Subtotal 3. 4. Revenue received to-date from tenants at Eureka Place Projected revenue received from Head Start through June 2007 (they have exercised one extension option, to date): Revenue Subtotal Net Revenue TOTAL PROJECT COST LESS NET REVENUE TOTAL NET PROJECT COST ($27,360) $12,000 ($15,360) $141,374 $130,720 $272,094 $256,734 $2,840,000 ($256,734) $2,583,266 Impact to Funding Sources: Same as Option #1, except this option reduces the amount of borrowing needed from CFD #1. LIBRARYLEARNING CENTER Library Learning CenterLocationSITE Library Learning CenterSite PlanEUREKA PLACEDemolish existing HouseNew ModularAdd 2ndStory to Main Bldg.N Library Learning CenterElevation View Library Learning CenterEstimated Project Cost$510,000Modular Building Cost$1,444,439Additional Appropriation Required$3,055,561Amount Appropriated$492,000Contingency & Inspection$4,500,000Total Project Cost$2,920,000Construction, Furniture, IT Equip$300,000Design / Engineering Cost$278,000Property Purchase Cost Library Learning CenterProject OptionsŠOption 1 –Construct second floor addition, install modular building $4.5 millionŠOption 2 –Construct second floor addition without finishing for occupancy, install modular building $3.6 millionŠOption 3 –Remodel existing building no second floor addition + modular $2.8 million Library Learning CenterOption 1ŠEliminate leases for Centro & ALP ŠConsolidate the two programsŠContinued revenue from Head StartŠCost-effective construction & no disruption in library servicesŠMaximized CLAF fundraising potentialŠCity’s growth management standard met until the year 2015Advantages:ŠAdditional appropriation requiredDisadvantages: Library Learning CenterRecommendationOption 1 –Construct second floor addition, install modular building