HomeMy WebLinkAbout2006-04-18; City Council; 18521; Tot Lot ImprovementsCITY OF CARLSBAD - AGENDA BILL
AB#
MTG.
DEPT.
18,521
4/18/06
PW/GS
TITLE: AWARDING THE CONTRACT TO PERFORM TOT LOT
IMPROVEMENTS 2005-2006 AND
APPROPRIATION OF ADDITIONAL FUNDS
CONTRACT NO. 39441, PROJECT NO. PKS-06-01
DEPT. HD. £
4^0
CITYATTY. &>*
CITY MGR."5^V
RECOMMENDED ACTION:
Adopt Resolution No. 2006-092 accepting the bid of $297,511.60 and awarding the contract to
Court Concepts, Inc., to perform Tot Lot Improvements 2005-2006, Contract No. 39441, Project No.
PKS 06-01 and approving appropriation of additional funds.
ITEM EXPLANATION:
Improvements are needed on tot lots at various park sites throughout the City. Specifically, certain
playground equipment that does not meet Americans with Disabilities Act (ADA) standards must be
removed and replaced with compliant equipment at four park sites. In addition, new equipment
and/or resilient surfacing will be installed at 3 additional park sites. Resilient surfacing is required by
law to meet Americans with Disabilities Act (ADA) standards, and to provide required protection from
injuries. Existing surfacing that has hardened due to age must be replaced with new resilient
surfacing to meet safety standards at all locations. Over 4,800 total square feet of cushioned
rubberized surfacing will be installed to provide access to the playground equipment.
Staff recommends that Council approve additional funding to complete the project at this time rather
than in the 2006-2007 fiscal year CIP budget. Performing the work at this time will minimize
exposure to risk of legal action for non-compliance with the ADA and will minimize risk of injury.
Listed below are the park sites where these improvements are to be installed.
Project Locations
• Holiday Park
• Hosp Grove Park
• La Costa Canyon Park
• Laguna Riviera Park
• Poinsettia Park
• Scout House
• Stagecoach Park
On February 7, 2006, City Council adopted Resolution 2006-025 approving contract documents and
special provisions, and authorized the City Clerk to advertise for bids for this project. Three bids
were received, opened, witnessed and recorded on March 29, 2006. The bid amounts ranged from
$297,511.60 to $447,888.00. The bids were reviewed by the Public Works Department and were as
follows:
Court Concepts, Inc.
Tri-Group Construction and Development, Inc.
Romero General Construction, Inc.
$297,511.60
$424,907.00
$447,888.00
Staff has reviewed the bid received from Court Concepts, Inc. and has determined that the bid is
very competitive. This bid is valid for 90 days. Delaying award until after the 2006-2007 CIP is
approved may invalidate this bid and could result in higher cost for the needed work.
Page 2
Court Concepts, Inc. submitted the lowest responsive bid. Therefore, staff recommends the
contract be awarded to Court Concepts, Inc., the lowest responsive bidder, in the amount of
$297,511.60. The contractor's registration and bonds are in order and references are satisfactory.
Contract documents are on file in the General Services offices of Public Works.
The Engineer's Estimate for the project is $259,500.00. This project will address the Council Goals
as described below.
Parks/Open Space/Trails
Acquire, develop, and maintain a broad range of open space and recreational facilities that actively
address citizen needs, which are fiscally responsible and consistent with the General Plan/GMS.
Top Quality Service
Ensure the effective and efficient delivery of exceptional services to our community on a daily basis.
ENVIRONMENTAL REVIEW:
This project has been determined to be exempt from environmental review per CEQA (14 Cal Code
Reg §15301) - minor alteration of an existing facility.
FISCAL IMPACT:
Construction Contract
Construction Contingency (10%)
TOTAL ESTIMATED PROJECT COST
TOTAL APPROPRIATIONS
ADDITIONAL APPROPRIATIONS
$297,511.60
$29,748.40
$327,260.00
$259,500.00
$67,760.00
The total estimated construction cost for this project, shown in the table above, including
construction and contingency is $327,260.00; appropriations to date are $259,500.00.
Staff notified the City Council of the possible need for additional funding to sufficiently account for
increased construction costs and contingency monies in the agenda bill approving plans and
specifications. Staff is requesting an additional appropriation of $67,760.00 from the Infrastructure
Replacement Fund. There are sufficient funds available in the Infrastructure Replacement Fund to
complete the project.
EXHIBITS:
1. Resolution No. 2006-092 accepting the bid of $297,511.60 and awarding the Contract to
Court Concepts, Inc., to perform Tot Lot Improvements 2005-2006, Contract No. 39441,
Project No. PKS 06-01 and approving appropriation of additional funds.
DEPARTMENT CONTACT: Dale A. Schuck, (760) 434-2949, dschu@ci.carlsbad.ca.us
1
RESOLUTION NO. 2006-092
2
A RESOLUTION OF THE CITY COUNCIL OF THE CITY
3
4
CONTRACT NO. 39441. PROJECT NO. PKS-06-01.
5 WHEREAS, the City Council adopted Resolution No. 2006-025 approving contract
e
documents, special provisions and specifications, and authorized the City Clerk to advertise for
bids to perform Tot Lot Improvements 2005-2006, hereinafter referred to as the "Project"; and
WHEREAS, the bids were received, opened, witnessed and recorded on March 29, 2006;
and
7
8
9
10
11
12
13
14
15
16
17
18
19
OF CARLSBAD, CALIFORNIA, AWARDING THE
CONTRACT FOR TOT LOT IMPROVEMENTS 2005-2006
AND APPROPRIATION OF ADDITIONAL FUNDS,
WHEREAS, bids have been received by the City of Carlsbad, California, to perform Tot
Lot Improvements 2005-2006; and
WHEREAS, the lowest responsive bid received was submitted by Court Concepts, Inc., in
the amount of $297,511.60; and
WHEREAS, insufficient funds are available for this project in the Capital Improvement
Project budget; and
WHEREAS, additional funds in the amount of $67,760.00 needs to be appropriated to
complete this project.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Carlsbad,
California, as follows:
2Q i That the above recitations are true and correct.
21 2. That the Finance Director is authorized to appropriate $67,760.00 from the
Infrastructure Replacement Fund to perform Tot Lot Improvements 2005-2006.
3. The bid of $297,511.60 by Court Concepts, Inc., to perform Tot Lot Improvements
2005-2006, and a contingency account of $29,748.40 are hereby accepted.24
25
26
27
28
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
4. That the Mayor of the City of Carlsbad is hereby authorized and directed to execute
a contract for Contract No. 39441, Project No. PKS 06-01, Tot Lot Improvements 2005-2006 with
Court Concepts, Inc.
5. That the award of this contract is contingent upon Court Concepts, Inc. executing
the required contract and submitting the required bonds and insurance policies, as described in
the contract, within twenty (20) days of adoption of this resolution. The City Manager may grant
reasonable extensions of time.
PASSED, APPROVED AND ADOPTED at a regular meeting of the Carlsbad City Council
held on the 18th day of APril , 2006 by the following vote, to wit:
AYES: Council Members Lewis, Ha
NOES:
ABSENT* Jfone
CLAUDE A.
ATTEST:
Kulchin, Packard' and Sigafoose
~&'dJudj&
LORRAINE M. WOOD, City Clerk (SEAL)