NOTICE OF COMPLETION FOR THE CONSTRUCTION
CONTRACT ON THE INDUSTRIAL PARK PIPELINES
FOR THE ENCINA BASIN WATER RECLAMATION
PROGRAM, PHASE II PROJECT,
PROJECT NOS. 3887-C, 3667, AND 3930
DEPT. HEAD
CITY ATTY.
CITY
RECOMMENDED ACTION:
Adopt Resolution No. 2006-315 accepting the construction contract on the Industrial Park
Pipelines for the Encina Basin Water Reclamation Program, Phase II, Project Nos. 3887-C, 3667, and
3930 as complete, and directing the City Clerk to record a Notice of Completion and release bonds in
accordance with State Law and City Ordinances.
ITEM EXPLANATION:
On January 18, 2005, J. Fletcher Creamer & Son, Inc. was awarded a contract in the amount of
$9,171,466 for the construction of the Industrial Park Pipelines for the Encina Basin Water
Reclamation Program, Phase II, Project Nos. 3887-C, 3667, and 3930.
J. Fletcher Creamer & Son, Inc. substantially completed the pipeline work on August 2, 2006. City
staff has inspected the work and found it to be satisfactory. After the pipeline was completed,
Engineering requested additional work be performed. The final change order was fully executed on
October 12, 2006 and the work has been completed. Staff recommends formal acceptance of the
improvements by the City Council.
ENVIRONMENTAL IMPACT:
The approval of a Notice of completion is a ministerial process and is exempt from the requirements
of CEQA pursuant to Section 15268 of the State CEQA Guidelines.
FISCAL IMPACT:
INDUSTRIAL PARK PIPELINES FOR THE ENCINA BASIN
WATER RECLAMATION PROGRAM, PHASE II, PROJECT
NOS. 3887-C, 3667, AND 3930
(J. FLETCHER CREAMER & SON, INC.)
Construction Award:
Construction Contingency:
Total:
Construction Expenditures:
Remaining Balance:
$ 8,775,466.00
$ 396,000.00
$ 9,171,466.00
$ 8,503,050.00
$ 668,416.00
FOR CITY CLERKS USE ONLY.
COUNCIL ACTION: APPROVED
DENIED
CONTINUED
WITHDRAWN
AMENDED
/
D
D
D
D
CONTINUED TO DATE SPECIFIC
CONTINUED TO DATE UNKNOWN
RETURNED TO STAFF
OTHER -SEE MINUTES
D
D
D
D
Page 2 of Agenda Bill No.
EXHIBITS:
1. Resolution No. 2006-315 accepting the construction contract on the Industrial Park
Pipelines for the Encina Basin Water Reclamation Program, Phase II, Project Nos. 3887-C,
3667, and 3930.
2. Site map.
3. Notice of Completion for the Industrial Park Pipelines for the Encina Basin Water Reclamation
Program, Phase II, Project Nos. 3887-C, 3667, and 3930.
DEPARTMENT CONTACT: Gary Goodman 760-602-2780 x7310 ggood@ci.carlsbad.ca.us
2
LOCATION MAP
CRY OF OCttNSK
PROPOSED RECYCLED WATERLINES
EXISTING RECYCLED WATERLINES
PROJECT
AREA
NOT TO SCALE
VICINITY
MAP
NOT TO
SCALE
PROJECT NAME
CONSTRUCTION OF THE INDUSTRIAL PARK PIPELINES FOR
THE ENCINA BASIN WATER RECLAMATION PROGRAMPHASE II PROJECT
PROJECT
NUMBER
3887-C
EXHIBIT
WMHW BK SCOTT EVANS CARLSBAD ENQMEEKWG DOT. 5/5/04 &\CAPiTAL\AHtIS\3aS7~C.01K
1
RESOLUTION NO. 2006-315
2
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
CARLSBAD, CALIFORNIA, ACCEPTING THE CONSTRUCTION
CONTRACT ON THE INDUSTRIAL PARK PIPELINES FOR THE
ENCINA BASIN WATER RECLAMATION PROGRAM, PHASE II,
3
4 n
PROJECT NOS. 3887-C. 3667. AND 3930
5
WHEREAS, the construction of the Industrial Park Pipelines for the Encina Basin Water
6
Reclamation Program, Phase II was substantially completed to the City's satisfaction by J.
Fletcher Creamer & Son, Inc. on August 2, 2006; and
WHEREAS, the final change order was fully executed on October 12, 2006; and
WHEREAS, the formal project Notice of Completion has been prepared; and
WHEREAS, all project costs have been established to date.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Carlsbad,
California, as follows:
1. That the above recitations are true and correct.
2. That the Industrial Park Pipelines for the Encina Basin Water Reclamation
Program, Phase II, specifically identified as Project Nos. 3887-C, 3667, and 3930, is deemed
complete and is hereby accepted by the City Council of the City of Carlsbad.
3. The City Clerk of the City of Carlsbad is hereby authorized and directed to
execute and record the Notice of Completion for the Industrial Park Pipelines for the Encina Basin
Water Reclamation Program, Phase II, Project No. 3887-C, 3667, and 3930.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
PASSED, APPROVED AND ADOPTED at a Regular Meeting of the City Council
of the City of Carlsbad on the 7th day of November, 2006, by the following vote:
AYES: Council Members Lewis, Hall, Packard, Sigafoose
NOES: None
ABSENT: Council Member Kulchin
A LEWIS, Mayor
ATTEST:
LORRAINE M. WOOD, City Clerk '
(SEAL)
RECORDED REQUESTED BY
CITY OF CARLSBAD
AND WHEN RECORDED PLEASE
MAIL TO:
City Clerk
City of Carlsbad
1200 Carlsbad Village Drive
Carlsbad, California 92008
Space above this line for Recorder's use.
PARCEL NO: N/A
NOTICE OF COMPLETION
Notice is hereby given that:
1 .
2.
3.
4.
5.
6.
7.
8.
The undersigned is owner of the interest or estate stated below in the property hereinafter described.
The full name of the undersigned is City of Carlsbad, a municipal corporation.
The full address of the undersigned is 1200 Carlsbad Village Drive, Carlsbad, California 92008.
The nature of the title of the undersigned is: In fee.
A work or improvement on the property hereinafter described was completed on October 12, 2006.
The name of the contractor for such work or improvement is J. Fletcher Creamer & Son, Inc.
The property on which said work or improvement was completed is in the City of Carlsbad, County of
San Diego, State of California, and is described as follows: Industrial Park Pipelines for the Encina
Basin Water Reclamation Program, Phase II Project, Project Nos. 3887-C, 3667 & 3930.
The street address of said property is in the City of Carlsbad.
CITY OF CARLSBAD
Conrad C. Hammann, Jr.
City Engineer
VERIFICATION OF CITY CLERK
I, the undersigned, say:
I am the City Clerk of the City of Carlsbad, 1200 Carlsbad Village Drive, Carlsbad, California,
92008; the City Manager of said City on ^CnXrrriLjt^ T^ 200U . accepted the above
described work as completed and ordered that a Notice of Completion be filed.
I declare under penalty of perjury that the foregoing is true and correct.
Executed on vf]o?.'g^\£oer> *1 . 20CLp. at Carlsbad, California.
CITY OF CARLSBAD
lORRAINE M. WOOD
City Clerk
Word\Masters\Forms\Notice of Completion (Cily)'. x •£• * vv
•''//,.Tfcflft^