HomeMy WebLinkAbout2007-12-18; City Council; 19257; Install Synthetic Turf at Stagecoach ParkCITY OF CARLSBAD - AGENDA BILL AB# 19,257 MTG. 12/18/07 DEPT. PW/GS ACCEPTANCE OF PROJECT TO INSTALL A SYNTHETIC TURF ATHLETIC FIELD AT STAGECOACH PARK CONTRACT NO. 39371, PROJECT NO. PKS 04-03 DEPT. CITY ATTY CITY MGR. RECOMMENDED ACTION: Adopt Resolution No. 2007-318 accepting the work in accordance with Contract No. 39371, Project No. PKS 04-03, Stagecoach Park Synthetic Turf Field as complete, and direct the City Clerk to have the Notice of Completion recorded and release bonds in accordance with State Law and City Ordinances. ITEM EXPLANATION: On July 19, 2005, the City Council adopted Resolution No. 2005-231 awarding Contract No. 39371, Project No. PKS 04-03, to Western Rim Constructors, Inc. for $1,452,737 and authorized $150,000 in contingency funds to construct a synthetic turf field at Stagecoach Park. Although the construction phase of the project was completed on time, several important issues prevented the City from recording the Notice of Completion and releasing project retention. The synthetic turf subcontractor failed to provide the City with three contractually required items. The items required, but not submitted, included a bond or insurance policy guaranteeing that surety or insurance company would repair or replace any deficient items for a minimum of eight years after project acceptance, an appropriate warranty document covering all issues in accordance with the agreement for a period of eight years, and a roll of spare tan infield turf that would allow the City to make any repairs to the field as needed. General Services and the Prime Contractor, Western Rim Constructors, Inc., repeatedly notified the subcontractor of the outstanding issues and the City notified the bonding company of the discrepancies. Numerous letters were sent to all parties by the project manager detailing the outstanding issues. The City successfully procured the warranty and the insurance policy several months after the completion of the construction, however, the turf subcontractor failed to deliver the spare turf until November 2, 2007. At this time, all outstanding items have been received and the retention has been released. The synthetic turf field has been inspected by staff and is acceptable to the Public Works Manager, General Services. ENVIRONMENTAL IMPACT: The approval of a Notice of Completion is a ministerial process and is exempt from the requirements of CEQA pursuant to Section 15268 of the State CEQA Guidelines. FOR CITY CLERKS USE ONLY. COUNCIL ACTION: APPROVED DENIED CONTINUED WITHDRAWN AMENDED •r" D D D D CONTINUED TO DATE SPECIFIC CONTINUED TO DATE UNKNOWN RETURNED TO STAFF OTHER - SEE MINUTES D D D D Page 2 FISCAL IMPACT: STAGECOACH WNTHET 1C FMLB - PROJiet 39371 (Western Rim Constructors, Inc.) Construction Contract Contingency TOTAL APPROPRIATIONS Construction Contract Change Orders TOTAL CONSTRUCTION COST $1,452,737 $150,000 $1,602,737 $1,452,737 68,963 $1,521,700 The total construction cost for this project is $1,521,700. Change orders for the project totaled $68,963 of the approved contingency total of $150,000. Change Orders included relocation of existing irrigation mains, remediation of unsuitable materials, installation of vehicle barriers, repairs to the baseball backstops and installation of additional concrete surface improvements. EXHIBITS: Resolution No.2007-318 accepting the work in accordance with Contract No. 39371, Project No. PKS 04-03, Stagecoach Park Synthetic Turf Field as complete, and direct the City Clerk to have the Notice of Completion recorded and release bonds in accordance with State Law and City Ordinances. Notice of Completion. DEPARTMENT CONTACT: Dale A. Schuck, (760) 802-5788, dschu@ci.carlsbad.ca.us 1 RESOLUTION NO. 2007-318 2 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF 3 CARLSBAD, CALIFORNIA, ACCEPTING THE WORK AS COMPLETE AND DIRECTING THE RECORDATION OF THE 4 NOTICE OF COMPLETION FOR STAGECOACH PARK SYNTHETIC TURF FIELD. CONTRACT NO. 39371. PROJECT NO. PKS 04-03. 5 WHEREAS, the City Council adopted Resolution No. 2004-352 approving contract 6 documents, special provisions and specifications, and authorized the City Clerk to advertise for 7 bids to perform Contract No. 39371, Project No. PKS 04-03, Stagecoach Park Synthetic Turf Field, 8 hereinafter referred to as the "Project;" and 9 WHEREAS, the City Council has previously awarded a contract for the Project; and 10 WHEREAS, the Project work has been satisfactorily completed; and 11 WHEREAS, a Notice of Completion has been prepared for the Project; and 12 WHEREAS, the City Council hereby finds it necessary, desirable, and in the public interest 13 to accept the completed work to perform Contract No. 39371, Project No. PKS 04-03, Stagecoach 14 Park Synthetic Turf Field. 15 NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Carlsbad, 16 California, as follows: 17 1. That the above recitations are true and correct. 18 2. That the completed work is hereby accepted and the City Clerk is directed to record the 19 Notice of Completion and to release bonds in accordance with State Law and City Ordinances. 20 21 22 '" 23 '" 24 "' 25 '" 26 '" ///27 28 3 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 PASSED, APPROVED AND ADOPTED at a Regular Meeting of the City Council of the City of Carlsbad on the 18th day of December, 2007, by the following vote to wit: AYES: Council Members Lewis, Kulchin, Hall, Packard and Nygaard. NOES: None. ABSENT: None. CLAUDE"A LEWIS, Mayor ATTEST: L0RRAIN$M. WOOD^ity Cleric1 (SEAL)/ RECORDED REQUESTED BY CITY OF CARLSBAD AND WHEN RECORDED PLEASE MAIL TO: City Clerk City of Carlsbad 1200 Carlsbad Village Drive Carlsbad, California 92008 Space above this line for Recorder's use. PARCEL NO: 2230606100 NOTICE OF COMPLETION Notice is hereby given that: 1. The undersigned is owner of the interest or estate stated below in the property hereinafter described. 2. The full name of the undersigned is City of Carlsbad, a municipal corporation. 3. The full address of the undersigned is 1200 Carlsbad Village Drive, Carlsbad, California 92008. 4. The nature of the title of the undersigned is: In fee. 5. A work or improvement on the property hereinafter described was completed on November 2, 2007. 6. The name of the contractor for such work or improvement is Western Rim Constructors, Inc. 7. The property on which said work or improvement was completed is in the City of Carlsbad, County of San Diego, State of California, and is described as follows: PKS 04-03 Stagecoach Park Synthetic Turf Field. 8. The street address of said property is 3420 Camino de los Coches. CITY OF Greg Clavier Public Works Manager VERIFICATION OF CITY CLERK I, the undersigned, say: I am the City Clerk of the City of Carlsbad, 1200 Carlsbad Village Drive, Carlsbad, California, 92008; the City Council of said City on (ji^AJ^TLhjtA / % 2QQJ . accepted the above described work as completed and ordered that a Notice of Completion be filed. I declare under penalty of perjury that the foregoing is true and correct. Executed on ^jZk^/w/Q/i/f . 20 d7- at Carlsbad, California. AB 19,257 Reso 2007-318 Word\Masters\Forms\Notice of Completion (City)3/9/98