HomeMy WebLinkAbout2009-07-21; City Council; 19900; Batiquitors sewer manhole rehabilitationCITY OF CARLSBAD - AGENDA BILL AB# 19,900 MTG. 7/21/09 DEPT. ENG ACCEPTING BIDS AND AWARD OF CONTRACT TO SANCON ENGINEERING INC. FOR NORTH BATIQUITOS INTERCEPTOR SEWER MANHOLE REHABILITATION, PROJECT NO. 3538 DEPT. HEAD 1^1",T CITYATTY. jfcj^_ CITY MGR. / i/L RECOMMENDED ACTION: Adopt Resolution No. 2009-188 accepting bids and award of contract to Sancon Engineering Inc. for the North Batiquitos Interceptor Sewer Manhole Rehabilitation, Project No. 3538. ITEM EXPLANATION: The North Batiquitos Interceptor Sewer (NBIS) is divided into reaches NB1 through NB9 and begins near the north shore of the Batiquitos Lagoon at Columbine Drive, just west of El Camino Real. From that beginning point the NBIS pipeline alignment continues westerly along the north shore of the lagoon to the North Batiquitos Lift Station, located near Gabiano Lane. From the lift station the alignment goes northwesterly under Interstate 5 and continues north to the Encina Water Pollution Control Facility. The NBIS was constructed in the early and mid 1970s, with the final upper reaches being completed in 1976. This manhole rehabilitation project includes reaches NB1 through NB4 of the NBIS, a 1.9 mile long section of the sewer that follows the north shoreline of the lagoon between El Camino Real and Gabiano Lane. Much of the alignment is in or near a public trail with the remaining portions of the alignment traversing the Four Seasons Resort golf course, agricultural property and property owned by the Batiquitos Lagoon Foundation. During its most recent cleaning and inspection, the pipeline in reaches NB1 through NB4 was found to be in good condition. However, 41 manholes in this alignment were found to be severely corroded with considerable ground water infiltration present, and therefore in need of replacement or rehabilitation. In consideration of the sewer's sensitive location, specific methods of trenchless rehabilitation have been selected. Manholes will be rehabilitated without excavation, using low impact work methods designed to eliminate direct impacts to the surrounding habitat. In order to anticipate and minimize any impacts the project could have on the properties, City staff corresponded with the Aviara Masters Association, Four Seasons Resort, State of California, and Batiquitos Lagoon Foundation during the design phase of the project. Since much of the alignment is on or near the public trail and the resort golf course, a continued effort will be made to coordinate construction activities in an effort to minimize any inconveniences to the users of the properties during the construction phase. On April 14, 2009, through the adoption of Resolution No. 2009-069, the Carlsbad City Council approved plans and specifications and authorized the City Clerk to advertise to receive bids for the North Batiquitos Interceptor Sewer Manhole Rehabilitation, Project No. 3538. On June 25, 2009, two (2) sealed bids were received for the construction of this project, which are summarized in the table below: '<" "-..•'"•;... GQftOTtACTQR 1. Sancon Engineering Inc. 2. Erreca's Inc. .CITY/STATE Huntington Beach, CA Lakeside, CA TOf^L $262,155 $389,975 DEPARTMENT CONTACT: Mark Biskup, (760) 602-2763, mark.biskup@carlsbadca.qov FOR CITY CLERKS USE ONLY. COUNCIL ACTION: APPROVED DENIED CONTINUED WITHDRAWN AMENDED &n D nn CONTINUED TO DATE SPECIFIC CONTINUED TO DATE UNKNOWN RETURNED TO STAFF OTHER - SEE MINUTES D Dn D Page 2 The Engineer's Estimate for this project is $475,000. Staff has completed its review of all documents and finds that they are in order. Therefore, staff recommends that Sancon Engineering Inc. be awarded the contract. ENVIRONMENTAL IMPACT: A Coastal Development Permit (CDP 07-13), Mitigated Negative Declaration (MND) and Mitigation Monitoring and Reporting Program (MMRP) were prepared for the Batiquitos Interceptor Sewer Rehabilitation Project pursuant to the California Environmental Quality Act (CEQA). The initial study (EIA Part II) prepared in conjunction with the project identified potentially significant effects on the environment with respect to biology and hydrology/water quality. However, mitigation measures have been employed, which reduce those effects to a less than significant level. Planning Commission Resolutions 6463 and 6464 approving the CDP, MND and MMRP were approved by the Planning Commission on September 17, 2008. No further environmental review is required. FISCAL IMPACT: PROJECT COST SUMMARY FOR THE DESIGN, ENVIRONMENTAL AND CONSTRUCTION PHASES OF THE NORTH BATIQUITOS SEWER MANHOLE REHABILITATION (PROJECT NO. 3538) DESIGN & ENVIRONMENTAL Environmental Engineering Design DESIGN & ENVIRONMENTAL SUBTOTAL CONSTRUCTION PHASE Manhole & Pipeline Cleaning and Assessment Construction Contract (Sancon Engineering) with 15% Contingency Construction Management and Inspection (8% Estimated) Environmental Monitoring (Planning Systems) CONSTRUCTION SUBTOTAL TOTAL PROJECT COST (Manhole Rehabilitation) CURRENT APPROPRIATION $48,789 $52,945 $101,734 $68,780 $301 ,479 $24,000 $7,000 $401,259 $502,993 $1,199,000 Sufficient funds are available for the completion of the manhole rehabilitation construction. The project is funded from the Sewer Replacement Fund. Aforementioned, Resolution No. 2009-069 determined payment of prevailing wages was not in the City's best interest and the contract reflects that determination. EXHIBITS: 1. Location Map. 2. Resolution No. 2009-188 accepting bids and award of contract to Sancon Engineering Inc. for the North Batiquitos Interceptor Sewer Manhole Rehabilitation, Project No. 3538. 7 LOCATION MAP ENCINA WASTEWATER OLLUTION CONTROL FACILITY CITYOFCARLSi NOT A PART NBIS UPPER REACHES NB5 THROUGH NB9 ORTH BATIQUITOS IFT STATION PROJECT ALIGNMENT NBIS REACHES NB1 THROUGH NB Legend NBIS Reaches 1-4 (Project Alignment) NBIS Upper Reaches (not a part of project) Interstate 5 Street City Boundary 0 0.25 0.5 1 PROJECT NAME: NORTH BATIQUITOS INTERCEPTOR SEWER MANHOLE REHABILITATION, PROJECT # 3538 EXHIBIT 1 3 1 RESOLUTION NO. 2009-188 2 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF 3 CARLSBAD, CALIFORNIA, ACCEPTING BIDS AND AWARD OF CONTRACT TO SANCON ENGINEERING INC. FOR NORTH 4 BATIQUITOS INTERCEPTOR SEWER MANHOLE REHABILITATION. PROJECT NO. 3538. 5 6 WHEREAS, the City Council of the City of Carlsbad, California, desires to rehabilitate 7 41 existing manholes in reaches NB1 through NB4 in the North Batiquitos Interceptor Sewer in 8 conformance with the Sewer Master Plan; and 9 WHEREAS, a Coastal Development Permit (CDP 07-13), Mitigated Negative Declaration 10 (MND) and Mitigation Monitoring and Reporting Program (MMRP) were prepared for the Batiquitos 11 Interceptor Sewer Rehabilitation Project in compliance with the California Environmental Quality 12 Act. Planning Commission Resolutions 6463 and 6464 approving the CDP, MND and MMRP 13 were approved by the Planning Commission on September 17, 2008 and no further environmental 14 review is required; and 15 WHEREAS, on April 4, 2008, through the adoption of Resolution No. 2008-069, the 16 Carlsbad City Council approved plans and specifications and authorized the City Clerk to advertise 17 to receive bids for the North Batiquitos Interceptor Sewer Manhole Rehabilitation, Project No. 18 3538; and 19 WHEREAS, the City Council has determined, through the adoption of Resolution No. 2008- 20 069, that the payment of prevailing wages is not in the City's best interest and that determination is 21 reflected in the contract; and 22 WHEREAS, two (2) sealed bids were received on June 25, 2009 by the City of Carlsbad for 23 the construction of said project; and 24 WHEREAS, the lowest responsive and responsible bid to construct said project was 25 submitted by Sancon Engineering Incorporated, in the amount of $262,155; and 26 WHEREAS, funds in the Sewer Connection Fee Fund are sufficient to complete said 27 project. 28 1 NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Carlsbad, 2 California, as follows: 3 1. That the above recitations are true and correct. 4 2. That the bid in the amount of $262,155 submitted by Sancon Engineering 5 Incorporated, for the construction of the North Batiquitos Interceptor Sewer Manhole 6 Rehabilitation, Project No. 3538, is accepted and the Mayor is hereby authorized to execute a 7 contract with Sancon Engineering Incorporated. o 3. The City Manager is hereby authorized to approve construction change orders up to 9 $39,324. 1Q 4. That the award of this contract is contingent upon the bidder submitting the lowest 1. responsible bid executing the required contract and submitting the required bonds and insurance policies, as described in the contract, within twenty (20) days of adoption of this resolution. The City Manager may grant reasonable extensions of time. 1 *J 14 '" 16 '" 17 "' 18 "' 19 '" 20 '" 21 "' 22 '" 23 "' 24 '" 25 '" 26 "' 27 "/ 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 PASSED, APPROVED AND ADOPTED at a Regular Meeting of the City Council of the City of Carlsbad on the 21st day of July, 2009, by the following vote to wit: AYES: Council Members Lewis, Kulchin, Hall, Packard and Blackburn. NOES: None. ABSENT: None. ATTEST: LORRAINE (SEAL)