HomeMy WebLinkAbout2009-11-10; City Council; 20038; Pipe Replacement Program State St and Oak AveCITY OF CARLSBAD - AGENDA BILL
x^^/ ^AB# 20.038
MTG. 11/10/09
DEPT. ENG
APPROVAL OF PLANS AND SPECIFICATIONS AND
AUTHORIZATION TO ADVERTISE FOR BIDS FOR THE
CORRUGATED METAL PIPE REPLACEMENT PROGRAM -
STATE STREET AND OAK AVENUE, PROJECT NO. 6607
DEPT. HEAD^y^
CITY ATTY. £$0^*
CITY MGR. (jj ^
RECOMMENDED ACTION:
Adopt Resolution No.2009-284 approving plans and specifications and authorizing the City
Clerk to advertise for bids for the Corrugated Metal Pipe Replacement Program - State Street and
Oak Avenue, Project No. 6607.
ITEM EXPLANATION:
The Corrugated Metal Pipe (CMP) Replacement Program was established as a five-year program to
replace, repair or remediate deteriorated CMP storm drain systems throughout the City. The pipelines
included in the program were identified after City staff inspected the interior of the storm drain pipe
and assessed the condition of CMP pipelines. The program includes the eventual replacement or
remediation of 25 storm drain pipelines. The locations of the pipelines and status are included in
Exhibit 2.
The State Street storm drain pipeline project will construct a new larger pipeline in State Street
between Beech Avenue and the unnamed street that provides an auxiliary access to the Carlsbad
Village Coaster Station parking lot. The pipeline will connect to an existing storm drain in the North
County Transit District right-of-way. The new reinforced concrete storm drain pipeline will replace an
existing corroded 24-inch corrugated metal pipe storm drain with pipe varying in size from 18 inches
to 36 inches. New curb inlets and manholes will be constructed. The existing storm drain pipeline,
which is located under the sidewalk, will be filled with concrete slurry and abandoned in place. All
work associated with the State Street storm drain project will be completed as night work to minimize
disruptions to local businesses.
The Oak Avenue storm drain replaces an existing corroded 12-in corrugated metal pipe with an 18-
inch reinforced concrete storm drain pipe between Lincoln Street and Washington Street. Three new
manholes will be constructed with this pipeline.
ENVIRONMENTAL IMPACT:
The project is exempt from the California Environmental Quality Act (CEQA) per State CEQA
Guidelines Section 15301(b) - minor alteration of existing facilities of public utility services involving
negligible or no expansion. A portion of the project located in Oak Avenue is located in the coastal
zone. However, repair and maintenance activities not described in Carlsbad Municipal Code Section
21.201.070 do not require a Coastal Development Permit. A portion of the project is located in the
Village/Redevelopment Zone. Housing and Redevelopment staff has reviewed the project and
determined the project is exempt from a Redevelopment Permit.
DEPARTMENT CONTACT: Sherri Howard 760-602-2756 Sherri.Howard@carlsbadca.gov
FOR CITY CLERKS USE ONLY
COUNCIL ACTION: APPROVED
DENIED
CONTINUED
WITHDRAWN
AMENDED
El
D
D
D
D
CONTINUED TO DATE SPECIFIC
CONTINUED TO DATE UNKNOWN
RETURNED TO STAFF
OTHER -SEE MINUTES
D
D
D
D
Page 2
FISCAL IMPACT:
Table 1 shows the current status of the CMP Replacement Program:
TABLE 1 - CMP REPLACEMENT PROGRAM - PROJECT NO. 6607
TASK DESCRIPTION
Design
Construction, Inspection, Materials Testing
Environmental Mitigation & Monitoring
Real Property Acquisition
TOTAL
APPROPRIATED
TO DATE
$501,000
$1,247,700
$31,000
$29,300
$1,809,000
EXPENDITURES/
ENCUMBRANCES
TO DATE
$309,778
$141,767
$50
$24,300
$475,895
REMAINING
BALANCES
$191,222
$1,105,933
$30,950
$5,000
$1,333,105
An Engineer's Estimate of the construction cost for the State Street and Oak Avenue pipeline
replacement was prepared by Harris and Associates, the consulting engineer of work for this project,
on August 6, 2009, and totals $530,000. The total estimated construction cost is shown in Table 2.
TABLE 2 - PROJECT CONSTRUCTION COST ESTIMATE
CMP REPLACEMENT PROGRAM - STATE STREET AND OAK AVENUE
PROJECT NO. 6607
Construction Contract (Engineer's Estimate)
Construction Contingency (10%)
Construction Management and Inspection (10%)
Testing (5%)
TOTAL ESTIMATED CONSTRUCTION COSTS (STATE STREET AND OAK
AVENUE)
PROJECT AVAILABLE BALANCE
ADDITIONAL APPROPRIATION ANTICIPATED FOR CONSTRUCTION
ESTIMATED
COSTS
$530,000
$53,000
$53,000
$26,500
$662,500
$1,333,105
-0-
Sufficient funds have been appropriated from the Infrastructure Replacement Fund (IRF) to fund this
project. Annually, funds are added to the project through the Capital Improvement Program. This
funding source is not subject to State or Federal restrictions regarding prevailing wage. Therefore,
pursuant to Carlsbad Municipal Code Section 3.28.130, prevailing wages are not required for the
construction of CMP Replacement Program, Project No. 6607. Staff recommends approving the plans
and specifications and authorizing the City Clerk to advertise for bids for the construction of CMP
Replacement Program - State Street and Oak Avenue, Project No. 6607.
PageS
EXHIBITS:
1. Location map.
2. CMP Replacement Program Project List.
3. Resolution No. 2009-284 approving plans and specifications, and authorizing the
City Clerk to advertise for bids for the Corrugated Metal Pipe Replacement Program - State
Street and Oak Avenue, Project No. 6607.
LOCATION MAP
SITE
SITE
NOT TO SCALE
SITE
VICINITY
MAP
NOT TO
SCALE
PROJECT NAME
CORRUGATED METAL PIPE REPLACEMENT PROGRAM
STATE STREET & OAK AVENUE
PROJECT
NUMBER
6607
EXHIBIT
1
DRAWN BY: SCOTT EVANS, CARLSBAD ENGINEERING DEPT. 9/22/09 C: \CAPITAL\HOWARD\6607 CMP PROGRAU_STATE-OAK.DWG
Exhibit 2
CMP Replacement Program Project List
Fiscal Year
2008/2009
2009/2010
2010/2011
2011/2012
2012/2013
Site No.Site Status
Environmetally
Sensitive Site
3
10
15
19 and 20
21
23
25
31
Westfield Shopping Center north end of Monroe Street
State Street from Laguna Drive to Beech Avenue
In driveway off Park Drive just south of May Court
Easement off Via Libertad
On Oak Avenue from Lincoln Street to Washington Street
Entrance to Flower Fields Apartments off Avenida de Anita
Highland Drive to James Drive between Tamarack Avenue and
Chinquapin Avenue
On Carlsbad Village Drive between Victoria Avenue & Chatham
Road
Design
Requesting Authorization to Bid
Private **
Design
Requesting Authorization to Bid
Private **
Design
Complete
No
No
No
Yes
No
No
No
Yes
13 and 77
14
68 and 69
70 and 71
Easement on the west side of ECR to Cameo Road
From Holly Brea Lane in an easement to ECR
Easement between Alder Avenue and ECR
Easement between Alder Avenue and ECR
Complete
Design
Design
Design
No
Yes
Yes
Yes
6
29
86 and 87
Crossing Jefferson Street between I-5 and Marron Road
Easement east of the corner of Oak Avenue & Washington Street
crossing RR
In an Easement southwest of Hoover Street to the Agua Hedionda
Lagoon
Pre-Design
Pre-Design
Pre-Design
Yes
No
Yes
43
47 and 48
60
Easement off Van Allen Way
On Costa Del Mar to an easement - entrance to La Costa Resort
At the end of cul-de-sac on Badajoz Place to an easement
Pre-Design
Pre-Design
Pre-Design
No
Yes
No
34
42
35
38
39 and 40
57 and 66
63
Crossing Highland Drive at Adams Street
Crossing Adams Street just down from Highland Drive
Crossing Bruce Road at 1729 to 1751 Bruce Road
Easement off Cannon Road on Strawberry Fields
From Garfield Street between Date Avenue and Olive Avenue in
an easement to Agua Hedionda Lagoon
Easement off La Costa Avenue at #2433 La Costa Avenue
Easement at Romeria Street and Gibraltar Street
Pre-Design
Pre-Design
Pre-Design
Pre-Design
Design *
Pre-Design
Pre-Design
Yes
Yes
No
No
Yes
No
No
- Moved forward at request of Operations and Maintenance due to condition
* - Removed from program
1 RESOLUTION NO. 2009-284
2 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
CARLSBAD, CALIFORNIA, APPROVING PLANS AND
3 SPECIFICATIONS AND AUTHORIZING TO ADVERTISE FOR BIDS
FOR THE CORRUGATED METAL PIPE REPLACEMENT
4 PROGRAM - STATE STREET AND OAK AVENUE, PROJECT NO.
6607.
5
WHEREAS, the City Council of the City of Carlsbad, California, has determined it
6
necessary, desirable, and in the public interest to construct the Corrugated Metal Pipe (CMP)
Replacement Program - State Street and Oak Avenue; and
8
WHEREAS, the plans and specifications for furnishing of all labor, materials, tools,
9
equipment, transportation, and other expenses necessary or incidental to the CMP Replacement
10
Program - State Street and Oak Avenue, Project No. 6607, have been prepared and are on file in
11
the Public Works-Engineering Department of the City of Carlsbad and are incorporated herein by
reference; and13
WHEREAS, funding for said project has been appropriated from the Infrastructure
14
Replacement Fund (IRF) to cover all project costs and is sufficient.15
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Carlsbad,16
California, as follows:
1. That the above recitations are true and correct.18
2. That the plans, specifications, and contract documents for the CMP Replacementi y
Program - State Street and Oak Avenue, Project No. 6607 are on file in the Public Works-
Engineering Department of the City of Carlsbad and are hereby approved.21
22
23
24
25
26
27
28
3. The City Clerk of the City of Carlsbad is hereby authorized and directed to
publish, in accordance with State law, a Notice to Contractors Inviting Bids for the CMP
Replacement Program - State Street and Oak Avenue, Project No. 6607, in accordance with the
plans, specifications, and contract documents referred to herein.
1
2
3
4
5
6
7
8
9
10JL V
11
12
13
15
16
17
18
19
20
21
22
23
24
25
26
27
28
PASSED, APPROVED AND ADOPTED at a Regular Meeting of the City Council
of the Citv of Carlsbad on the 1 0th dav of November, 2009, bv the following vote to wit:
AYES: Council Member Lewis, Kulchin, Hall, Packard, and Blackburn.
NOES: None.
ABSENT: None.