HomeMy WebLinkAbout2010-02-16; City Council; 20126; Update Power Plant and CA Energy CommissionCITY OF CARLSBAD - AGENDA BILL 16
AB#
MTG.
DEPT.
20.126
2-16-2010
CM
UPDATE ON PROPOSED POWER
PLANT AND CALIFORNIA ENERGY
COMMISSION PROCEEDINGS
DEPT. DIRECTOR
CITY ATTORNEY
CITY MANAGER
RECOMMENDED ACTION:
Receive staff update on the California Energy Commissions proceedings regarding NRG's
proposal to construct a new power plant.
Background
On September 14, 2007, Carlsbad Energy Center, LLC, (the Applicant) submitted an
Application for Certification (AFC) to the California Energy Commission (CEC) for the Carlsbad
Energy Center Project (CECP). Carlsbad Energy Center LLC is an indirect wholly-owned
subsidiary of NRG Energy, Inc. (NRG), which owns the existing Encina Power Station. The
proposed project is to be located on the 32-acre parcel of land, northeast of the existing Encina
Power Station, east of the rail lines and west of Interstate 5.
CEC Process
As established by the Warren Alquist Act, (PRC § 25000 et. seq.) the CEC has exclusive
jurisdiction to license power plants of 50 MW or greater in the State of California. The CEC
process is quasi-judicial in nature and the CEC review and licensing process is a regulatory
program certified by the Secretary of the Resources Agency which provides for the CEC's
process may be submitted in lieu of an EIR (PRC § 21080.5(9)). Its' program; however, must
consider all relevant environmental impacts. The CEC licensing process can best be described
in the following stages:
• Project application
• Staff Fact finding and analysis
• Commission Preliminary project review and decision
• Commission Final project review and decision, and
• Appeal
The CEC licensing process is intended to take approximately 12 months. However, based on
the complexity of the project, the CECP has progressed at an appreciably slower pace.
DEPARTMENT CONTACT: Joe Garuba 760-434-2820 ioe.qaruba@carlsbadca.gov
FOR CITY CLERK'S USE ONLY.
COUNCIL ACTION: APPROVED
DENIED
CONTINUED
WITHDRAWN
AMENDED
D
D
D
D
D
CONTINUED TO DATE SPECIFIC
CONTINUED TO DATE UNKNOWN
RETURNED TO STAFF
OTHER -SEE MINUTES
Dn
$ Accepted
Report
Evidentiary Hearings
On February 1-4, 2010, the CEC held a series of workshops, called Evidentiary Hearings, in
Carlsbad. The purpose of these hearings was for the CEC Siting Committee to gather
information about the CECP. These hearings represented the first time that the CEC
Commissioners were briefed about the CECP in detail, and provided an opportunity for those
involved, including the City, the Housing and Redevelopment Agency, and the community-at-
large to present information gathered to date. Information collected by the Siting Committee will
result in the issuance of a preliminary decision. This preliminary decision is expected to be
released in the 3rd Quarter of 2010.
CEC Schedule
The CEC identified the following schedule as part of the Evidentiary Hearings. This schedule is
subject to change.
• February 12, 2010 Parties submit potential topics for briefs
• February 19, 2010 CEC sends out topics for briefs
• March 22, 2010 Opening Briefs due
• April 14, 2010 Reply Briefs due
• June/July 2010 CEC Preliminary Decision released for review
Staff will present an update to the City Council on the upcoming CEC proceedings.
FISCAL IMPACT:
The fiscal impact from the CECP is uncertain at this time. If constructed the CECP will result in
increased revenue to the City in the form of property tax and franchise fees from natural gas
usage in the range of $2 -$5 million annually. However, this revenue would be realized if the
project were to be located at an alternate site within the City. Impacts from the CECP on the
broader tourism industry in the City have not yet been analyzed. The City will continue to
review the fiscal impact from the project as more information becomes available through the
licensing process.
ENVIRONMENTAL IMPACT:
The CEC, not the City of Carlsbad, serves as lead agency under its certified regulatory program
which is commonly known as the functional equivalent of CEQA for the proposed CECP and
performs the environmental review as part of its exclusive jurisdiction to license the proposal.
No Environmental Impact Report (EIR) is required; however, the CEC certification process is
subject to certification by the Secretary of the Resources as the functional equivalent of CEQA;
therefore, the CEC must analyze all potential environmental impacts resulting from the project.
The Preliminary Staff Assessment and the Final Staff Assessment produced by CEC staff have
so far provided the project environmental analysis.
As noted herein, city staff believes the proposed CECP, if approved by the CEC, would cause
significant land use, fire safety, and visual impacts and potentially other impacts as well.
EXHIBITS:
None
Proposed
Power Plant Project
Agua Hedionda
Lagoon
14 stories tall
10 stories tall
6 stories tall
Evidentiary Hearings
February 1-4, 2010
35+ hours of testimony
8 hours of Public Comment
HUGE Public Involvement (600+
people)
3 AH HA Moments
Proposed Changes to Encina
Location and need for CECP
Contract status w/SDG&E
Schedule
March 22 Briefs due
April 14 Rebuttal Briefs due
Summer 2010 Preliminary Decision
PMPD Public Comment
Override consultation
Revised PMPD
Full Commission consideration
Other agencies
Questions ?
Agua Hedionda
Lagoon
Existing Power Plant
I-5 (Widened)
Strawberry Fields
RR
Future
Desal
Plant
Sewer Line & Rail Trail
Lift Station
186 ac.
LEGEND: Owned by NRG Owned by SDGE
Acreage of Cannon Corridor Properties