HomeMy WebLinkAbout2011-07-26; City Council; 20634; CONTRACT PIPE REPLACEMENT PROGRAMCITY OF CARLSBAD - AGENDA BILL
AB# 20.634
MTG. 7/26/1 1
DEPT. ENG
AWARD OF CONTRACT FOR
THE CORRUGATED METAL PIPE REPLACEMENT PROGRAM
LJ/"M i w DDAC 1 AMEZ/CI f^Ak/IIMf"^ DCAI UII^LJI AKir\ā HULLY bKAb LANc/bL uAMINU KbAL, rlloHLANU
DRIVE/JAMES DRIVE AND MALLORCA PLACE, PROJECT
NO. 6607
DEPT. HEADb/[JfC^
CITYATTY. rfZ^'
CITY MGR. ( Uā '
RECOMMENDED ACTION:
Adopt Resolution No. 2011-175 accepting bids and awarding the contract to New Century
Construction, Inc. for the Corrugated Metal Pipe (CMP) Replacement Program - Holly Brae Lane/El
Camino Real, Highland Drive/James Drive and Mallorca Place, Project No. 6607.
ITEM EXPLANATION:
The CMP Replacement Program was established as a five-year program to replace, repair or
remediate deteriorated CMP storm drain systems throughout the City. The pipelines included in the
program were identified after City staff inspected the interior of the storm drain pipe and assessed the
condition of CMP pipelines. The program includes the replacement or remediation of 25 storm drain
pipelines. The program has had six pipelines systems added in the last year based on condition
assessments.
The Holly Brae Lane to El Camino Real project will construct a new curb inlet to replace an outdated
and unsafe inlet and install a cured-in-place liner into an existing deteriorated storm drain pipeline that
conveys runoff from Holly Brae Lane down to El Camino Real a distance of 420 feet. The Highland
Drive to James Drive project will construct a new standard inlet to replace an undersized non-
standard inlet and install 160 feet of cured-in-place liner into an existing deteriorated storm drain
pipeline from the new inlet to a catch basin. The project also includes the installation of a cleanout at
the junction of the pipeline to a larger pipeline in James Drive that will allow maintenance crews
access for routine cleaning and inspection. A pipeline added to the program in 2011, the Mallorca
Place project will install 155 feet of cured-in-place liner into a damaged pipeline that was discovered
during routine maintenance activities. During the bid period, 133 feet of cured-in-place liner for a
pipeline in Monroe Street at Alder Avenue was added to the project and program after crews
observed that the pipeline had deteriorated.
DEPARTMENT CONTACT: Sherri Howard, (760) 602-2756, Sherri.Howard@carlsbadca.gov
FOR CITY CLERKS
COUNCIL ACTION:
USE ONLY.
APPROVED
DENIED
CONTINUED
WITHDRAWN
AMENDED
4
D
D
D
CONTINUED TO DATE SPECIFIC
CONTINUED TO DATE UNKNOWN
RETURNED TO STAFF
OTHER - SEE MINUTES
D
D
D
D
Page 2
On June 21, 2011, three (3) sealed bids were received for the construction of this project as shown on
the following table.
CONTRACTOR
1 . New Century
2. Charles King
3. Don Hubbard
Construction, Inc.
Company, Inc.
Contracting Company
v ,.RTQIM. ā¢,,
AMOUNT OF BID
$151,615
$168,902
$179,860
All bid documents submitted by New Century Construction, Inc. have been reviewed by staff and were
found to be in order. Staff recommends awarding the construction contract to New Century
Construction, Inc. in the amount of $151,615.
ENVIRONMENTAL IMPACT:
The project is exempt from the California Environmental Quality Act (CEQA) per state CEQA
Guidelines Section 15301(b) - minor alteration of existing facilities of public utility services involving
negligible or no expansion.
FISCAL IMPACT:
Table 1 shows the current status of the CMP Replacement Program:
TABLE 1 - CMP REPLACEMENT PROGRAM - PROJECT NO. 6607
TASK DESCRIPTION
Design
Construction, Inspection, Materials Testing
Environmental Mitigation & Monitoring
Real Property Acquisition
TOTAL
APPROPRIATED
TO DATE
$543,476
$1,712,224
$31,000
$29,300
$2,316,000
EXPENDITURES/
ENCUMBRANCES/
OBLIGATIONS TO
DATE
$466,497
$989,277
$90
$24,300
$1,480,164
REMAINING
BALANCES
$76,979
$722,947
$30,910
$5,000
$835,836
An Engineer's Estimate of the construction cost for the CMP Replacement Program - Holly Brae
Lane/El Camino Real, Highland Drive/James Drive and Mallorca Place, was prepared by staff on
March 11, 2011, and totals $133,000. The estimate was increased during the bid period to $150,000
with the addition of 133 lineal feet of pipe lining. The total estimated construction cost is shown in
Table 2.
Page 2
TABLE 2 - PROJECT CONSTRUCTION COST ESTIMATE
CMP REPLACEMENT PROGRAM - HOLLY BRAE LANE/EL CAMINO REAL,
HIGHLAND DRIVE/JAMES DRIVE AND MALLORCA PL, PROJECT NO. 6607
Construction Contract
Construction Contingency
Construction Management and Inspection
Testing
TOTAL ESTIMATED CONSTRUCTION COSTS
PROJECT AVAILABLE BALANCE
ADDITIONAL APPROPRIATION ANTICIPATED FOR CONSTRUCTION
ESTIMATED
COSTS
$151,615
$30,000
$16,000
$8,000
$205,615
$835,836
-0-
Sufficient funds have been appropriated from the Infrastructure Replacement Fund (IRF) to fund this
project. Annually, funds are added to the project through the Capital Improvement Program. This
funding source is not subject to State or Federal restrictions regarding prevailing wage. Therefore,
pursuant to Carlsbad Municipal Code Section 3.28.130, prevailing wages are not required for the
construction of CMP Replacement Program, Project No. 6607.
EXHIBITS:
1.
2.
3.
Location Maps.
CMP Replacement Program Project List.
Resolution No. 2011-175 accepting bids and awarding the contract to New Century
Construction, Inc. for the Corrugated Metal Pipe Replacement Program - Holly Brae Lane/El
Camino Real, Highland Drive/James Drive and Mallorca Place, Project No. 6607.
LOCATION MAP
NOT TO SCALE
SHEET J OF 2
PROJECT NAME
CORRUGATED METAL PIPE REPLACEMENT PROGRAM
PROJECT
NUMBER
6607
EXHIBIT
1
DRAW BY: SCOTT CVAHS. CARLSBAD I/TUBES KPT. 3/14/tl C \UHU7KS DCPMTUO1T\KSKN OM9CH\HOW*XD\OIP RtPLM&KNT PROCRAHWALLCKA-HtCHUWl.DK
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
LOCATION MAP
NOT TO SCALE
SHEET 2 OF 2
PROJECT NAME
CORRUGATED METAL PIPE REPLACEMENT PROGRAM
PROJECT
NUMBER
6607
EXHIBIT
1
K SCOTT [VMS, OWLSBAO UTILITIES OEPT1 J/14/II O \UDUTES D£P/(RTVfNr\DRffiN Om30N\HOIKWD\aMP RCPUCBiOiT PKXSUI\fUiiafKA-HCHUWD.DWC
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
Exhibit 2
CMP Replacement Program Project List
Fiscal Year
2008/2009
2009/2010
2010/2011
2011/2012
2012/2013
Added to
Drogram
2010/2011
Site No.
3
10
15
19 and 20
21
23
25
31
13 and 77
14
68 and 69
70 and 71
43
60
86 and 87
6
29
34
42
47 and 48
35
38
39 and 40
57 and 66
63
Site
Westfieid Shopping Center north end of Monroe Street
State Street from Laguna Drive to Beech Avenue
In driveway off Park Drive just south of May Court
Easement off Via Libertad
On Oak Avenue from Lincoln Street to Washington Street
Entrance to Flower Fields Apartments off Avenida de Anita
Highland Drive to James Drive between Tamarack Avenue
and Chinquapin Avenue
On Carlsbad Village Drive between Victoria Avenue &
Chatham Road
Easement on the west side of ECR to Cameo Road
From Holly Brae Lane in an easement to ECR
Easement between Alder Avenue and ECR
Easement between Alder Avenue and ECR
Easement off Van Allen Way
At the end of cul-de-sac on Badajoz Place to an easement
In an Easement southwest of Hoover Street to the Agua
Hedionda Lagoon
Crossing Jefferson Street between I-5 and Marron Road
Easement east of the corner of Oak Avenue & Washington
Street crossing RR
Crossing Highland Drive at Adams Street
Crossing Adams Street just down from Highland Drive
On Costa Del Mar to an easement - entrance to La Costa
Resort
Crossing Bruce Road at 1729 to 1751 Bruce Road
Easement off Cannon Road on Strawberry Fields
From Garfield Street between Date Avenue and Olive Avenue
in an easement to Agua Hedionda Lagoon
Easement off La Costa Avenue at #2433 La Costa Avenue
Easement at Romeria Street and Gibraltar Street
Mallorca Place to La Costa Avenue Portion to Remove and
Replace
Campground Cavern Fill and Ponto Interchange Storm Drain
Abandonment
Mallorca Place to La Costa Avenue Portion to line
Highland Drive/Etmwood Street at Buena Vista Way
Carlsbad Blvd north of Batiquitos Lagoon
Alder Avenue Monroe Street at Sunnyhill Drive
Status
Complete
Complete
Private **
Complete
Complete
Private **
Award of Contract
Complete
Complete
Award of Contract
Complete
Complete
Private **
Design
Design
Design
Design
Design
Design
Private **
Complete*
Private "
Complete*
Complete*
Complete*
Complete*
Complete*
Award of Contract*
Design
Complete
Award of contract*
* - Moved forward at request of Operations and Maintenance due to condition
** - Removed from program
Updated June 27, 2011
1
RESOLUTION NO. 2011-175
2 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
ā CARLSBAD, CALIFORNIA, ACCEPTING BIDS AND6 AWARDING A CONTRACT FOR CONSTRUCTION OF THE
CORRUGATED METAL PIPE REPLACEMENT PROGRAM -
4 HOLLY BRAE LANE/EL CAMINO REAL, HIGHLAND
DRIVE/JAMES DRIVE AND MALLORCA PLACE, PROJECT
5 NO. 6607.
6 WHEREAS, on May 10, 2011, the City Council of the City of Carlsbad approved plans
7 for construction of the Corrugated Metal Pipe Replacement Program - Holly Brae Lane/El Camino
8 Real, Highland Drive/James Drive and Mallorca Place, Project No. 6607; and
9 WHEREAS, three (3) sealed bids were received on June 21, 2011 by the City of
10 Carlsbad for the construction of said project; and
11 WHEREAS, the lowest responsive and responsible bid to construct said project was
12 submitted by New Century Construction, Inc., in the amount of $151,615; and
13 WHEREAS, there are sufficient funds available to complete the project; and
14 WHEREAS, subsection 3.28.040(C)(5) of the Carlsbad Municipal Code authorizes the
15 City Manager to approve change orders in the amount equal to the contingency set at the time of
16 project award.
17 NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Carlsbad,
18 California, as follows:
10 1. That the above recitations are true and correct.
20 3. That the low bid of $151,615 submitted by New Century Construction, for the
21 construction of the Corrugated Metal Pipe Replacement Program - Holly Brae Lane/El Camino
22 Real, Highland Drive/James Drive and Mallorca Place, Project No. 6607, is accepted and the
23 Mayor is hereby authorized to execute a contract with New Century Construction, Inc. for the
24 Corrugated Metal Pipe Replacement Program - Holly Brae Lane/El Camino Real, Highland
25 Drive/James Drive and Mallorca Place, Project No. 6607.
4. That the City Manager is hereby authorized to approve construction change
27 orders up to $30,000. ,, ,
28 /
1 5. That the award of this contract is contingent upon the bidder submitting the
2 lowest responsible bid executing the required contract and submitting the required bonds and
3 insurance policies, as described in the contract, within twenty (20) days of adoption of this
4 resolution. The City Manager may grant reasonable extensions of time.
5 ///
6 ///
7 ///
8 ///
9 ///
10 ///
11 ///
12 ///
13 ///
14 ///
15 ///
16 ///
17 ///
18 ///
19 ///
20 ///
21 ///
22 ///
23 ///
24 ///
25 ///
26 ///
27 /// F
28 °
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
PASSED, APPROVED AND ADOPTED at a Regular Meeting of the City Council
of the City of Carlsbad on the 26th day of July, 2011, by the following vote to wit:
AYES: Council Members Hall, Blackburn, Douglas and Packard.
NOES: None.
ABSENT: Council Member Kulchin.
MAff (HALL,'Mayor
ATTEST:
LORRAINE M. WOOD, City Clerk
(SEAL)
'