AB# 20.775 AWARD OF CONTRACT FOR CONSTRUCTION OF THE
NORTHWEST QUADRANT STORM DRAIN
IMPROVEMENT PROGRAM, CONCRETE REPAIR
WORK, AND PAVEMENT MANAGEMENT PROGRAM,
PROJECT NOS. 6608, 6021, AND 6001
DEPT. DIRECTOR
MTG. 1/10/12
AWARD OF CONTRACT FOR CONSTRUCTION OF THE
NORTHWEST QUADRANT STORM DRAIN
IMPROVEMENT PROGRAM, CONCRETE REPAIR
WORK, AND PAVEMENT MANAGEMENT PROGRAM,
PROJECT NOS. 6608, 6021, AND 6001
CITYATTORNEY
DEPT. UTIL
AWARD OF CONTRACT FOR CONSTRUCTION OF THE
NORTHWEST QUADRANT STORM DRAIN
IMPROVEMENT PROGRAM, CONCRETE REPAIR
WORK, AND PAVEMENT MANAGEMENT PROGRAM,
PROJECT NOS. 6608, 6021, AND 6001 CITY MANAGER ^
RECOMMENDED ACTION:
Adopt Resolution No. 2012-007 accepting bids and awarding the contract to Burtech Pipeline,
Inc. forthe construction ofthe Northwest Quadrant Storm Drain Improvement Program, Concrete Repair
Work, and Pavement Management Program, Project Nos. 6608, 6021, and 6001.
ITEM EXPLANATION:
The Northwest Quadrant Storm Drain Improvement Program is a multi-year program to address non-
master drainage plan needs within the northwest quadrant ofthe City. Site locations have been identified
and prioritized based on recommendations from field observations. The locations of the sites, status and
current priority are included in Exhibit 2. Four segments have been added to the program since project
inception.
One site consisting of two locations is included in this contract request as shown on Exhibit 1. Storm
drain improvements are proposed for Madison Street and Roosevelt Street between Carlsbad Village
Drive and Grand Avenue and include construction of 420 feet of 18" diameter reinforced concrete pipe,
56 feet of 12" diameter polyvinyl chloride pipe, four catch basins, and four cleanouts that connect to the
existing storm drain systems in Grand Avenue and Carlsbad Village Drive. In addition to drainage
improvements, and through the Concrete Repair Work project, the two midblock crossings will also be
reconstructed to improve street surface drainage and pedestrian circulation. These improvements will
meet current American Disabilities Act requirements. Upgrades to the irrigation systems and electrical
systems will also be accomplished with this contract through the Concrete Repair Work project. At the
completion of the storm drain improvements and concrete repairs, the two street segments will be
overlayed through the Pavement Management Program.
On May 10, 2011, through Resolution Number 2011-086, Agenda Bill 20,536, Council approved the
plans and specifications and authorized the advertisement for bids for the Northwest Quadrant Storm
Drain Improvement Program, Concrete Repair Work, and Pavement Management Program, Project Nos.
6608, 6021, and 6001. On June 15, 2011 four sealed bids were received, opened and witnessed forthe
construction ofthe project On July 12, 2011, through Resolution Number 2011-166, Agenda Bill 20,621,
Council rejected all bids because of bid irregularities. The project was rebid.
On December 14, 2011, seven (7) sealed bids were received, opened and witnessed for the construction
of this project as shown in the following Table 1.
DEPARTMENT CONTACT: Sherri Howard 760-602-2756 Sherri.Howard(a>carlsbadca.gov
FOR CITY CLERKS USE ONLY
COUNCIL ACTION: APPROVED CONTINUED TO DATE SPECIFIC •
DENIED • CONTINUED TO DATE UNKNOWN •
CONTINUED • RETURNED TO STAFF •
WITHDRAWN • OTHER-SEE MINUTES •
AMENDED •
Page 2
TABLE 1
NORTHWEST QUADRANT STORM DRAIN IMPROVEMENT PROGRAM, CONCRETE REPAIR WORK, AND
PAVEMENT MANAGEMENT PROGRAM, PROJECT NOS. 6608, 6021, & 6001
CONTRACTOR BID LUMP SUM
1. Burtech Pipeline, Inc $396,998.00
2. Southland Paving, Inc. $407,987.00
3. RSB Group, Inc. $408,547.00
4. Palm Engineering Construction Company, Inc, $410,877.00
5, Waters Edge Contracting Company $411,118.75
6. Don Hubbard Contracting Company $424,368.00
7. Garcia Juarez $428,520.00
The Engineer's estimate for this project is $420,000. All bid documents submitted by Burtech Pipeline, Inc.
have been reviewed by staff and were found to be in order. Staff recommends awarding the construction
contract to Burtech Pipeline, Inc. in the amount of $396,998.00
ENVIRONMENTAL IMPACT:
The project is exempt from the California Environmental Quality Act (CEQA) per State CEQA Guidelines
Section 15301(b) - minor alteration of existing facilities of public utility services involving negligible or no
expansion and Section 15302(c) - replacement or reconstruction of existing utility systems and/or facilities
involving negligible or no expansion of capacity. The Planning Director filed a Notice of Exemption on March
18, 2011.
FISCAL IMPACT:
Table 1 shows the current status of the applicable projects:
TABLE 1
SUMMARY OF CURRENT PROJECT EXPENSES
NORTHWEST QUADRANT STORM DRAIN IMPROVEMENT PROGRAM
PROJECT NO. 6608
TASK DESCRIPTION APPROPRIATED
TO DATE
EXPENDITURES/
ENCUMBRANCES
TO DATE
REMAINING
BALANCES
Design $668,469 $471,011 $197,458
Construction, Inspection, Materials Testing $1,906,365 $816,123 $1,090,242
Environmental Mitigation & Monitoring $19,170 $10,549 $8,621
TOTAL $2,594,004 $1,297,683 $1,296,321
CONCRETE REPAIR WORK
PROJECT NO. 6021
TASK DESCRIPTION APPROPRIATED
TO DATE
EXPENDITURES/
ENCUMBRANCES
TO DATE
REMAINING
BALANCES
Design $20,000 $1,078 $18,922
Construction, Inspection, Materials Testing $730,000 $367,475 $362,525
TOTAL $750,000 $368,553 $381,447
<5—
Page 3
PAVEMENT
PF
MANAGEMENT PROGRAM
lOJECT NO. 6001
TASK DESCRIPTION APPROPRIATED
TO DATE
EXPENDITURES/
ENCUMBRANCES
TO DATE
REMAINING
BALANCES
Design $53,519 $38,181 $15,338
Construction, Inspection, Materials Testing $9,026,382 $2,943,891 $6,082,491
TOTAL $9,079,901 $2,982,072 $6,097,829
The total estimated project cost is shown in Table 2.
TABLE 2 - PROJECT CONSTRUCTION COST ESTIMATE
NORTHWEST QUADRANT STORM DRAIN IMPROVEMENT PROGRAM,
PROJECT NO. 6608
ESTIMATED
COSTS
Construction Contract $233,135.50
Construction Contingency $45,000
Construction Management and Inspection $25,000
Testing $12,500
TOTAL ESTIMATED CONSTRUCTION COSTS $315,635.50
PROJECT AVAILABLE BALANCE $1,296,321
ADDITIONAL APPROPRIATION ANTICIPATED FOR CONSTRUCTION -0-
CONCRETE REPAIR WORK
PROJECT NO. 6021
ESTIMATED
COSTS
Construction Contract $107,927.50
Construction Contingency $30,000
Construction Management and Inspection $11,000
Testing $5,500
TOTAL ESTIMATED CONSTRUCTION COSTS $154,427.50
PROJECT AVAILABLE BALANCE $381,447
ADDITIONAL APPROPRIATION ANTICIPATED FOR CONSTRUCTION -0-
PAVEMENT MANAGEMENT PROGRAM
PROJECT NO. 6001
ESTIMATED
COSTS
Construction Contract $55,935
Construction Contingency $20,000
Construction Management and Inspection $6,000
Testing $3,000
TOTAL ESTIMATED CONSTRUCTION COSTS $84,935
PROJECT AVAILABLE BALANCE $6,097,829
ADDITIONAL APPROPRIATION ANTICIPATED FOR CONSTRUCTION -0-
Page 4
Sufficient funds have been appropriated from the General Capital Construction Fund, Gas Tax Fund and
TransNet-Local Fund to fund this project. Annually, funds are added to these projects through the Capital
Improvement Program. This funding source is not subject to State or Federal restrictions regarding
prevailing wage. Therefore, pursuant to Carlsbad Municipal Code Section 3.28.130, prevailing wages are
not required for the construction of Northwest Quadrant Storm Drain Improvement Program, Concrete
Repair Work, and Pavement Management Program, Project Nos. 6608, 6021, and 6001.
EXHIBITS:
1. Location map.
2. Northwest Quadrant Storm Drain Program Project List.
3. Resolution No. 2012-007 accepting bids and awarding the contract to Burtech Pipeline,
Inc. for the Northwest Quadrant Storm Drain Improvement Program, Concrete Repair Work, and
Pavement Management Program, Project Nos. 6608, 6021, and 6001.
LOCATION MAP
LEGEND:
SITES - MADISON ST. NORTH OF CARLSBAD VILLAGE DR
- ROOSEVELT SI NORTH OF CARLSBAD VILLAGE DR
PACIFIC OCEAN
WOT TO SCALE
PROJECT NAME NORTHWEST QUADRANT STORM DRAIN PROGRAM
(MADISON STREET AND ROOSEVELTSTREET)
PROJECT
NUMBER
6608
EXHIBIT
1
DRAWN BY: SCOTT EVANS: CARLSBAD UTIUTIES DEPI J/16/11 C: XUWTIES DEPARniENT\DESIGN DIVISI0N\H0WARD\6608-2.DWG
r
EXHIBIT 2
NORTHWEST QUADRANT STORM DRAIN
IMPROVEMENT PROGRAM PROJECT LIST - FY 2011-12
Number Site Location Priority Status
1 Mountain View and Pacific Avenue 2 Authorization to Bid
2 iVladison Street, Grand Avenue to Arbuckle Place 2 Authorization to Bid
3 Oak Avenue and Lincoln Street 7 Pre-Design
4 Roosevelt Street n/o Beech Avenue 2 Authorization to Bid
5
Roosevelt Street and Madison Street, Carlsbad
Village Drive to Grand Avenue 2 Bidding
6 Ocean Street north of Oak Avenue 3 Pre-Design
7 Valley Street and Buena Vista Way 3 Pre-Design
8 Valley Street north of Carlsbad Village Drive 3 Pre-Design
9 Cynthia Lane to Pio Pico Drive 1 Complete
10 Rio Pico Drive and Forest Avenue 1 Complete
11 Elmwood Street and Laguna Drive 4 Pre-Design
12 Wilson Street north of Buena Vista Way 4 Pre-Design
13 Macarthur Avenue and Sunnyhill Drive 4 Pre-Design
14 Chestnut Avenue and Pio Pico Drive 1 Complete
15 Chestnut Avenue and Adams Street 1 Complete
16 Adams Street and Palm Avenue 6 Pre-Design
17 Adams Street north of Magnolia Avenue 6 Pre-Design
18 Adams Street north of Tamarack Avenue 6 Pre-Design
19 Basswood Avenue and Valley Street 4 Pre-Design
20 Linda Lane Cul de Sac's 5 Pre-Design
21 Donna Drive west of Chestnut Avenue 5 Pre-Design
22 Palisades Drive and East Pointe Avenue 5 Pre-Design
23 Calavo Court 5 Complete
24 Ridgecrest Drive 1 Complete
25 Adams Street south of Hoover Street 2 Pre-Design
26 Park Drive, Monroe Street to Woodvale Drive 7 Complete
27 Monroe Street, Alder Drive and Sunnyhill Drive 7 Complete
28 Park Drive, Cove Drive to Marina Drive * 6611
29 Sevilla Way 7 Removed from Program
30 Park Drive east of Valencia Avenue 7 Complete
31 Harrison Street south of Chinquapin Avenue 2 Authorization to Bid
32 Crest Drive Drainage Project 1 Complete
33 Hillside Drive downdrain west of Park Drive -Complete
34
Highland Drive between Magnolia and
Chinquapin 3 Design
* - Moved to separate CIP project due to project size and environmental considerations,
Decembers, 2011
lo
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
RESOLUTION NO. 2012-007
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
CARLSBAD, CALIFORNIA, ACCEPTING BIDS AWARDING A
CONTRACT FOR THE NORTHWEST QUADRANT STORM
DRAIN IMPROVEMENT PROGRAM, CONCRETE REPAIR
WORK, AND PAVEMENT MANAGEMENT PROGRAM,
PROJECT NOS. 6608, 6021, and 6001.
WHEREAS, on May 10, 2011, the City Council of the City of Carlsbad, through
Resolution No. 2011-086, has previously approved the plans and authorized to advertize for bids
to construct the Northwest Quadrant Storm Drain Improvement Program, Concrete Repair Work,
and Pavement Management Program, Project Nos. 6608, 6021, and 6001; and
WHEREAS, seven (7) sealed bids were received on December 14, 2011, by the City of
Carlsbad for the construction of said project; and
WHEREAS, the lowest responsive and responsible bid was submitted by Burtech
Pipeline Company, Inc in the amount of $396,998; and
WHEREAS, funding for said project has been appropriated from the General Capital
Construction Fund, Gas Tax Fund and TransNet Fund to cover all project costs and is sufficient;
and
WHEREAS, Section 3.28.040 (c)(5) of the Carlsbad Municipal Code authorizes the City
Manager to approve change orders in the amount equal to the contingency set at the time of
project award.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Carlsbad,
California, as follows:
1. That the above recitations are true and correct.
2. That the low bid of $396,998.00 submitted by Burtech Pipeline, Inc., for the
construction of the Northwest Quadrant Storm Drain Improvement Program, Concrete Repair
Work, and Pavement Management Program, Project Nos. 6608, 6021, and 6001, is accepted and
the Mayor is hereby authorized to execute a contract with Burtech Pipeline, Inc. for the Northwest
n
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
Quadrant Storm Drain Improvement Program, Concrete Repair Work, and Pavement
Management Program, Project Nos. 6608, 6021, and 6001.
3. That the City Manager is hereby authorized to approve construction change
orders up to $95,000.
4. That the award of this contract is contingent upon the bidder submitting the
lowest responsible bid executing the required contract and submitting the required bonds and
insurance policies, as described in the contract, within twenty (20) days of adoption of this
resolution. The City Manager may grant reasonable extensions of time.
///
///
///
///
///
///
///
///
///
///
///
///
///
///
///
///
///
///
6