HomeMy WebLinkAbout2012-11-27; City Council; 21048; Approval Simon Wong Bridge Railing Project No 6014CITY OF CARLSBAD - AGENDA BILL AB# 21.048 APPROVAL OF AN AGREEMENT WITH SIMON WONG ENGINEERING TO PROVIDE PROFESSIONAL SERVICES FOR PRELIMINARY ENGINEERING FORTHE BRIDGE RAILING IMPROVEMENTS OF PROJECT NO. 6014 DEPT. HEAD MTG. 11/27/12 APPROVAL OF AN AGREEMENT WITH SIMON WONG ENGINEERING TO PROVIDE PROFESSIONAL SERVICES FOR PRELIMINARY ENGINEERING FORTHE BRIDGE RAILING IMPROVEMENTS OF PROJECT NO. 6014 CITY ATTY. C^^. DEPT. TRANS APPROVAL OF AN AGREEMENT WITH SIMON WONG ENGINEERING TO PROVIDE PROFESSIONAL SERVICES FOR PRELIMINARY ENGINEERING FORTHE BRIDGE RAILING IMPROVEMENTS OF PROJECT NO. 6014 CITY MGR. RECOMMENDED ACTION: Adopt Resolution No. 2012-251 to approve an agreement with Simon Wong Engineering for the Bridge Railing Improvements, Project No. 6014. ITEM EXPLANATION: Bridge railing improvements are needed for the bridge located above the Encinas discharge channel (Warm Water Jetty), approximately half-mile north of Cannon Road on Carlsbad Boulevard (Project No. 6014). On August 19, 2009, Resolution No. 6635 was adopted requiring Poseidon Resources to install and secure with appropriate security as provided by law, a bridge rail to Caltrans standards on the easterly side of Carlsbad Boulevard over the Encinas discharge channel. At this time, a reimbursement agreement was going to be prepared between Poseidon Resources and the city so that both sides of the bridge railing could be completed at the same time. On May 13, 2010, Federal Highway Administration (FHWA) authorized, via Caltrans Local Assistance, funds for preliminary engineering for bridge rail improvements for the bridge located on Carlsbad Boulevard over the Encinas discharge channel (warm waters). On June 17, 2010, a Request for Proposals was issued for engineering services to improve the bridge railing over the Encinas discharge channel. On August 6, 2010, out of 30 interested consultants only one bid was submitted. Discussions with Caltrans Local Assistance resulted in allowing the work to be performed by Simon Wong, since other consultants were made aware of the opportunity and did not pursue the project. On September 11, 2012, Poseidon Resources decided to have their own contractor proceed with design and construction of the easterly bridge railing. Therefore, on October 5, 2012, Simon Wong prepared a revised scope and fee and after receiving authorization from Caltrans Local Assistance to proceed with design of the westerly bridge railing only and a fee was negotiated for preparation of construction plans, permits, applications, specifications, and estimates for bidding purposes in the amount of $112,373. Request for authorization of construction funds for the westerly bridge railing, via Caltrans Local Assistance, is anticipated to be August 2013. DEPARTMENT CONTACT: Brandon Miles, 760-602-2745 Brandon.Miles(S)carlsbadca.gov FOR CITY CLERKS USE ONLY COUNCIL ACTION: APPROVED CONTINUED TO DATE SPECIFIC • DENIED • CONTINUED TO DATE UNKNOWN • CONTINUED • RETURNED TO STAFF • WITHDRAWN • OTHER-SEE MINUTES • AMENDED • Page 2 Based on a review of the negotiated fee, staff recommends awarding the preliminary design engineering contract to Simon Wong Engineering, in the amount of $112,373. ENVIRONMENTAL IMPACT: The project is exempt from California Environmental Quality Act (CEQA) per State CEQA Guidelines Section 15301(d) - Existing Facilities - restoration or rehabilitation of existing facilities that are deteriorated or damaged and are required to meet current standards of public health and safety involving negligible or no expansion of use. City staff filed a notice of exemption for the project with the County Clerk on June 4, 2012. FISCAL IMPACT: City staff has received authorization for $168,750 in funding from Caltrans for preliminary engineering for the bridge railing improvements as outlined in Table 1. A total of $99,483 (88.53%) is eligible for reimbursement on this contract, via Federal funds provided through Caltrans. The remaining amount will be funded via local match funds (TransNet-Local) and totals $12,890 (11.47%). TABLE 1 - BRIDGE RAIL IMPROVEMENTS PROJECT NO. 6014 - ENCINAS DISCHARGE TASK DESCRIPTION ESTIMATED COST FEDERAL COST (88.53%) LOCAL MATCH (11.47%) Authorized by Caltrans $168,750 $149,394 $19,356 Preliminary Engineering - Simon Wong $112,373 $99,483 $12,890 The table below shows the current status of the project: TABLE 2 - BRIDGE RAIL IMPROVEMENTS PROJECT NO. 6014 - ENCINAS DISCHARGE BRIDGE RAILING IMPROVEMENTS - 6014 ESTIMATED COSTS Preliminary Engineering - Simon Wong $112,373 Project Management - City Staff (15%) $16,856 TOTAL ESTIMATED DESIGN COST $129,229 Authorized by Caltrans - Appropriation $168,750 Expenditures/Encumbrances $28,335 Remaining Balance $140,145 ADDITIONAL APPROPRIATION :i::iiiiii^:^::i:::|1iii:aiii^^^ Sufficient Federal funds and TransNet-Local funds are available for this request. z Page 3 EXHIBITS: 1. Project Location Map. 2. Resolution No. 2012-251 approve the agreement with Simon Wong Engineering to provide professional sen/ices for preliminary engineering for the bridge railing improvements of Project No. 6014. 3. Agreement for Professional Engineering Services, Simon Wong Engineering, Inc. 3 LOCATION MAP PACIFIC OCEAN NOT TO SCALE VICINITY MAP NOT TO SCAL£ PROJECT NAME BRIDGE RAILING IMPROVEMENTS PROJECT NUMBER 6014 EXHIBIT 1 PLOTTED BY: SCOTT EVANS PLOT DATE: 11/7/12 PATH:C:\TRANSP0RTAT10N DEPARTklENT\DESI&l DIVISI0N\UILES\6014.DWG 10 11 12 13 14 19 20 21 22 23 24 25 RESOLUTION NO. 2012-251 1 2 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF 3 CARLSBAD, CALIFORNIA, AUTHORIZING THE APPROVAL OF AN AGREEMENT WITH SIMON WONG ENGINEERING TO 4 PROVIDE PROFESSIONAL SERVICES FOR PRELIMINARY ENGINEERING FOR THE BRIDGE RAILING IMPROVEMENTS 5 OF PROJECT NO. 6014. 6 WHEREAS, the City Council of the City of Carlsbad, California, has determined it is 7 necessary and in the public interest to improve the bridge railing above the Encinas discharge 3 channel; and g WHEREAS, a request of Federal funding in the amount of $168,750 was approved by Caltrans for Preliminary Engineering; and WHEREAS; sufficient funding has been approved by Caltrans and is currently available in Project No. 6014 for this request; and WHEREAS; the amount programmed for the local match portion totals $19,356, or 11.47%, and will be provided through TransNet-Local funds; and WHEREAS, Simon Wong will provide professional services at $112,373 for the preliminary design of the Bridge Railing Improvement, Project No. 6014 which will be paid for using 16 a combination of Federal funds and local match funds. 17 NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Carlsbad, 18 California, as follows: 1. That the above recitations are true and correct. 2. That there are sufficient Federal funds and TransNet-local funds available for this request. 3. That a consultant agreement with Simon Wong Engineering, for engineering services for Bridge Railing Improvements for Project No. 6014, as described in the attached agreement, is hereby approved and the Mayor is hereby authorized and directed to execute said agreement /// 26 /// 27 /// 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 PASSED, APPROVED AND ADOPTED at a Regular Meeting of the City Council of the City of Carlsbad on the 27th day of November, 2012, by the following vote to wit: AYES: NOES: Council Members Hall, Kulchin, Blackburn, Douglas, Packard None. ABSENT: None. MATTf HALL, Mayor ATTEST: LORRAItJE %yi/OQJD, Cjg/^lerk Karen R. Kundtz, Assistant City Clerk (SEAL) TRAN955 AGREEMENT FOR PROFESSIONAL ENGINEERING SERVICES FOR THE CARLSBAD BOULEVARD ENCINAS DISCHARGE RAILING IMPROVEMENTS (SIMON WONG ENGINEERING) IIS AGREEMENT is made and entered into as of the "Af^ day of /ani^ ^ > , 20 by and between the CITY OF CARLSBAD, a municipal corporation, ("City"), and SIMON WONG ENGINEERING, a California corporation, ("Contractor"). RECITALS A. City requires the professional sen/ices of a civil engineering consultant that is experienced in staictural engineering and bridge railing Improvements. B. Contractor has the necessary experience in providing professional sen^ices and advice related to bridge railing improvements, located on Carlsbad Boulevard at the Encinas discharge channel. C. Contractor has submitted a proposal to City and has affirmed its willingness and ability to perform such work. NOW, THEREFORE, in consideration of these recitals and the mutual covenants contained herein, City and Contractor agree as follows: 1. SCOPE OF WORK City retains Contractor to perform, and Contractor agrees to render, those sen^ices (the "Sen/ices") that are defined in attached Exhibit "A", which is incorporated by this reference in accordance with this Agreement's terms and conditions. 2. STANDARD OF PERFORMANCE While performing the Services. Contractor will exercise the reasonable professional care and skill customarily exercised by reputable members of Contractor's profession practicing in the Metropolitan Southem Califomia Area, and will use reasonable diligence and best judgment while exercising its professional skill and expertise. 3. TERM The tenn of this Agreement will be effective for a period of two (2) years from the date first above written. The City Manager may amend the Agreement to extend it for one (1) additional one (1) year periods or parts thereof in an amount not to exceed one hundred twelve thousand three hundred seventy three dollars ($112,373) per Agreement year. Extensions will be based upon a satisfactory review of Contractor's perfomiance, City needs, and appropriation of funds by the City Council. The parties will prepare a written amendment indicating the effective date and length of the extended Agreement. 4. TIME IS OF THE ESSENCE Time is of the essence for each and every provision of this Agreement. 5. COMPENSATION The total fee payable for the Sen/ices to be performed during the initial Agreement term will be one hundred twelve thousand three hundred seventy three dollars ($112,373). No other compensation for the Sen/ices will be allowed except for items covered by subsequent amendments to this Agreement. The City resen/es the right to withhold a ten percent (10%) retention until City has accepted the work and/or Services specified in Exhibit "A". City Attorney Approved Version 2/17/12 7 Incremental payments, if applicable, should be made as outlined in attached Exhibit "A". 6. STATUS OF CONTRACTOR Contractor will perform the Services in Contractor's own way as an independent contractor and in pursuit of Contractor's independent calling, and not as an employee of City. Contractor will be under control of City only as to the result to be accomplished, but will consult with City as necessary. The persons used by Contractor to provide services under this Agreement will not be considered employees of City for any purposes. The payment made to Contractor pursuant to the Agreement will be the full and complete compensation to which Contractor is entitled. City will not make any federal or state tax withholdings on behalf of Contractor or its agents, employees or subcontractors. City will not be required to pay any workers' compensation insurance or unemployment contributions on behalf of Contractor or its employees or subcontractors. Contractor agrees to indemnify City within thirty (30) days for any tax, retirement contribution, social security, overtime payment, unemployment payment or workers' compensation payment which City may be required to make on behalf of Contractor or any agent, employee, or subcontractor of Contractor for work done under this Agreement. At the City's election, City may deduct the indemnification amount from any balance owing to Contractor. 7. SUBCONTRACTING Contractor will not subcontract any portion of the Sen/ices without prior written approval of City. If Contractor subcontracts any of the Services, Contractor will be fully responsible to City for the acts and omissions of Contractor's subcontractor and of the persons either directly or indirectly employed by the subcontractor, as Contractor is for the acts and omissions of persons directly employed by Contractor. Nothing contained in this Agreement will create any contractual relationship between any subcontractor of Contractor and City. Contractor will be responsible for payment of subcontractors. Contractor will bind every subcontractor and every subcontractor of a subcontractor by the terms of this Agreement applicable to Contractor's work unless specifically noted to the contrary in the subcontract and approved in writing by City. 8. OTHER CONTRACTORS The City reserves the right to employ other Contractors in connection with the Services. 9. INDEMNIFICATION Contractor agrees to indemnify and hold hannless the City and its officers, officials, employees and volunteers from and against all claims, damages, losses and expenses including attomeys fees arising out of the performance of the work described herein caused by any negligence, recklessness, or willful misconduct of the Contractor, any subcontractor, anyone directly or indirectly employed by any of them or anyone for whose acts any of them may be liable. The parties expressly agree that any payment, attorney's fee, costs or expense City incurs or makes to or on behalf of an injured employee under the City's self-administered workers' compensation is included as a loss, expense or cost for the purposes of this section, and that this section will survive the expiration or eariy termination of this Agreement. 10. INSURANCE Contractor will obtain and maintain for the duration of the Agreement and any and all amendments, insurance against claims for injuries to persons or damage to property which may arise out of or in connection with performance of the services by Contractor or Contractor's agents, representatives, employees or subcontractors. The insurance will be obtained from an insurance earner admitted and authorized to do business in the State of Califomia. The City Attorney /Approved Version 2/17/12 insurance carrier is required to have a cun-ent Best's Key Rating of not less than "A-:VH". OR with a surplus line insurer on the State of California's List of Eligible Surplus Line Insurers (LESLI) with a rating in the latest Best's Key Rating Guide of at least "A:X". 10.1 Coverages and Limits. Contractor will maintain the types of coverages and minimum limits indicated below, unless Risk Manager or City Manager approves a lower amount. These minimum amounts of coverage will not constitute any limitations or cap on Contractor's indemnification obligations under this Agreement. City, Its officers, agents and employees make no representation that the limits of the insurance specified to be carried by Contractor pursuant to this Agreement are adequate to protect Contractor. If Contractor believes that any required insurance coverage Is inadequate, Contractor will obtain such additional insurance coverage, as Contractor deems adequate, at Contractor's sole expense. 10.1.1 Commercial General Liabilitv Insurance. $1,000,000 combined single-limit per occurrence for bodily injury, personal injury and property damage. If the submitted policies contain aggregate limits, general aggregate limits will apply separately to the wort< under this Agreement or the general aggregate will be twice the required per occurrence limit. 10.1.2 Automobile Liabilitv (if the use of an automobile is involved for Contractor's work for City). $1,000,000 combined single-limit per accident for bodily injury and property damage. 10.1.3 Wori<ers' Compensation and Emplover's Liabilitv. Woricers' Compensation limits as required by the California Labor Code. Workers' Compensation will not be required if Contractor has no employees and provides, to City's satisfaction, a declaration stating this. 10.1.4 Professional Liabilitv. Errors and omissions liability appropriate to Contractor's profession with limits of not less than $1,000,000 per claim. Coverage must be maintained for a period of five years following the date of completion of the work. I I If box is checked. Professional Liability City's Initials Contractor's Initials Insurance requirement is waived. 10.2. Additional Provisions. Contractor will ensure that the policies of insurance required under this Agreement contain, or are endorsed to contain, the following provisions: 10.2.1 The City will be named as an additional insured on Commercial General Liability which shall provide primary coverage to the City. 10.2.2 Contractor will obtain occun'ence coverage, excluding Professional Liability, which will be written as claims-made coverage. 10.2.3 This insurance will be in force during the life of the Agreement and any extensions of it and will not be canceled without thirty (30) days prior written notice to City sent by certified mail pursuant to the Notice provisions of this Agreement. 10.3 Providing Certificates of Insurance and Endorsements. Prior to City's execution of this Agreement, Contractor will furnish certificates of insurance and endorsements to City. 10.4 Failure to Maintain Coverage. If Contractor fails to maintain any of these insurance coverages, then City will have the option to declare Contractor in breach, or may purchase City Attorney Approved Version 2/17/12 7 replacement insurance or pay the premiums that are due on existing policies in order to maintain the required coverages. Contractor is responsible for any payments made by City to obtain or maintain insurance and City may collect these payments from Contractor or deduct the amount paid from any sums due Contractor under this Agreement. ' 10.5 Submission of Insurance Policies. Citv reserves the right to require, at anytime, complete and certified copies of any or all required insurance policies and endorsements. 11. BUSINESS LICENSE Contractor will obtain and maintain a City of Carisbad Business License for the term of the Agreement, as may be amended from time-to-time. 12. ACCOUNTING RECORDS Contractor will maintain complete and accurate records with respect to costs incurred under this Agreement. All records will be clearly identifiable. Contractor will allow a representative of City during normal business hours to examine, audit, and make transcripts or copies of records and any other documents created pursuant to this Agreement. Contractor will allow inspection of all work, data, documents, proceedings, and activities related to the Agreement for a period of three (3) years from the date of final payment under this Agreement. 13. OWNERSHIP OF DOCUMENTS All work product produced by Contractor or its agents, employees, and subcontractors pursuant to this Agreement is the property of City. In the event this Agreement is terminated, all work product produced by Contractor or its agents, employees and subcontractors pursuant to this Agreement will be delivered at once to City. Contractor will have the right to make one (1) copy of the work product for Contractor's records. 14. COPYRIGHTS Contractor agrees that all copyrights that arise from the services will be vested in City and Contractor relinquishes all claims to the copyrights in favor of City. 15. NOTICES The name of the persons who are authorized to give written notices or to receive written notice on behalf of City and on behalf of Contractor under this Agreement. For Citv For Contractor Name Brandon Miles Name Mark Creveling Title Associate Engineer Title Vice President Department Transportation Address 9968 Hibert Street, Suite 202 City of Carisbad San Diego, CA 92131 Address 1635 Faraday Avenue Phone No. 858-566-3113 Carisbad, CA 92008 Email mcreveling@simonwongeng.com Phone No. 760-602-2745 Each party will notify the other immediately of any changes of address that would require any notice or delivery to be directed to another address. City Attorney Approved Version 2/17/12 Id 16. CONFLICT OF INTEREST Contractor shall file a Conflict of Interest Statement with the City Clerk in accordance with the requirements of the City of Carisbad Conflict of Interest Code. The Contractor shall report investments or interests in all four categories. 17. GENERAL COMPLIANCE WITH LAWS Contractor will keep fully informed of federal, state and local laws and ordinances and regulations which in any manner affect those employed by Contractor, or in any way affect the performance of the Services by Contractor. Contractor will at all times observe and comply with these laws, ordinances, and regulations and will be responsible for the compliance of Contractor's sen/ices with all applicable laws, ordinances and regulations. Contractor will be aware ofthe requirements ofthe Immigration Refomi and Control Act of 1986 and will comply with those requirements, including, but not limited to, verifying the eligibility for employment of all agents, employees, subcontractors and consultants whose services are required by this Agreement. 18. DISCRIMINATION AND HARASSMENT PROHIBITED Contractor will comply with all applicable local, state and federal laws and regulations prohibiting discrimination and harassment. 19. DISPUTE RESOLUTION If a dispute should arise regarding the performance of the Services the following procedure will be used to resolve any questions of fact or interpretation not othen^/ise settled by agreement between the parties. Representatives of Contractor or City will reduce such questions, and their respective views, to writing. A copy of such documented dispute will be fonA/arded to both parties involved along with recommended methods of resolution, which would be of benefit to both parties. The representative receiving the letter will reply to the letter along with a recommended method of resolution within ten (10) business days. If the resolution thus obtained is unsatisfactory to the aggrieved party, a letter outlining the disputes will be fonA/arded to the City Manager. The City Manager will consider the facts and solutions recommended by each party and may then opt to direct a solution to the problem. In such cases, the action of the City Manager will be binding upon the parties involved, although nothing in this procedure will prohibit the parties from seeking remedies available to them at law. 20. TERMINATION In the event of the Contractor's failure to prosecute, deliver, or perform the Services, City may terminate this Agreement for nonperfonnance by notifying Contractor by certified mail of the termination. If City decides to abandon or indefinitely postpone the work or sen/ices contemplated by this Agreement, City may terminate this Agreement upon written notice to Contractor. Upon notification of termination. Contractor has five (5) business days to deliver any documents owned by City and all work in progress to City address contained in this Agreement. City will make a detemiination of fact based upon the work product delivered to City and of the percentage of work that Contractor has perfomied which is usable and of worth to City in having the Agreement completed. Based upon that finding City will determine the final payment of the Agreement. Either party upon tendering thirty (30) days written notice to the other party may terminate this Agreement. In this event and upon request of City, Contractor will assemble the wori< product and put it in order for proper filing and closing and deliver it to City. Contractor will be paid for work perfomied to the termination date; however, the total will not exceed the lump sum fee City Attomey Approved Version 2/17/12 (I payable under this Agreement. City will make the final determination as to the portions of tasks completed and the compensation to be made. 21. COVENANTS AGAINST CONTINGENT FEES Contractor wan'ants that Contractor has not employed or retained any company or person, other than a bona fide employee working for Contractor, to solicit or secure this Agreement, and that Contractor has not paid or agreed to pay any company or person, other than a bona fide employee, any fee. commission, percentage, brokerage fee, gift, or any other consideration contingent upon, or resulting from, the award or making of this Agreement. For breach or violation of this warranty, City will have the right to annul this Agreement without liability, or, in its discretion, to deduct from the Agreement price or consideration, or othenAdse recover, the full amount of the fee, commission, percentage, brokerage fees, gift, or contingent fee. 22. CLAIMS AND LAWSUITS By signing this Agreement. Contractor agrees that any Agreement claim submitted to City must be asserted as part of the Agreement process as set forth in this Agreement and not in anticipation of litigation or in conjunction with litigation. Contractor acknowledges that if a false claim is submitted to City, It may be considered fraud and Contractor may be subject to criminal prosecution. Contractor acknowledges that California Govemment Code sections 12650 et seg.. the False Claims Act applies to this Agreement and, provides for civil penalties where a person knowingly submits a false claim to a public entity. These provisions include false claims made with deliberate ignorance of the false information or in reckless disregard of the truth or falsity of information. If City seeks to recover penalties pursuant to the False Claims Act, it is entitled to recover its litigation costs, including attomey's fees. Contractor acknowledges that the filing of a false claim may subject Contractor to an administrative debarment proceeding as the result of which Contractor may be prevented to act as a Contractor on any public work or improvement for a period of up to five (5) years. Contractor acknowledges debannent by another jurisdiction is grounds for City to temiinate this Agreement. 23. JURISDICTIONS AND VENUE Any action at law or in equity brought by either of the parties for the purpose of enforcing a right or rights provided for by this Agreement will be tried in a court of competent jurisdiction in the County of San Diego, State of Califomia, and the parties waive all provisions of law providing for a change of venue in these proceedings to any other county. 24. SUCCESSORS AND ASSIGNS It is mutually understood and agreed that this Agreement will be binding upon City and Contractor and their respective successors. Neither this Agreement or any part of it nor any monies due or to become due under it may be assigned by Contractor without the prior consent of City, which shall not be unreasonably withheld. 25. ENTIRE AGREEMENT This Agreement, together with any other written document referred to or contemplated by it. along with the purchase order for this Agreement and its provisions, embody the entire Agreement and understanding between the parties relating to the subject matter of it. In case of conflict, the terms of the Agreement supersede the purchase order. Neither this Agreement nor any of its provisions may be amended, modified, waived or discharged except in a writing signed by both parties. City Attomey Approved Version 2/17/12 26. AUTHORITY The individuals executing this Agreement and the instruments referenced in it on behalf of Contractor each represent and wanrant that they have the legal power, right and actual authority to bind Contractor to the terms and conditions of this Agreement. CONTRACTOR SIMON WONG ENGINEERING, a California corporation By: CITY OF CARLSBAD, a municipal corporation of the State of California (S^nheref Mayor (print name/titlfe)^ ATTEST: By: sign here) (print name/title) / City Clerk If required by City, proper notarial acknowledgment of execution by contractor musf'be^^ attached. If a corporation. Agreement must be signed by one corporate officer from each of the following two groups. Group A Chairman, President, or Vice-President Group B Secretary, Assistant Secretary, CFO or Assistant Treasurer Otherwise, the corporation must attach a resolution certified by the secretary or assistant secretary under corporate seal empowering the officer(s) signing to bind the corporation. APPROVED AS TO FORM: RONALD R. BALL, City Attomey BY: Assistant City Attorney \ City Attomey Approved Version 2/17/12 (3 Exhibit "A' SIMON WONG ENGINEERING SCOPE OF ENGINEERING SERVICES PROJEa: POWER PLANT DISCHARGE CHANNEL BRIDGE RAIUNG IMPROVEMENTS CLIENT: City of Carlsbad DATE: October 5,2012 ^ ^ PROJEa DESCRIPTION This project proposes to install railing on the Westerly side of the Encina Power Plant Discharge Channel Bridge along Carlsbad Boulevard NRG Energy (NRG) is the property owner of the Encina Power Plant and will complete the design and construction of the Easterly bridge railing along with the required improvements and legal documents. The Discharge Channel provides for warm water discharge from the Encina Power Station to the Pacific Ocean. Currently, no vehicular bridge railing exists on either side ofthe bridge. Chain link fendng and sidewalks are provided on both sides ofthe roadway within the bridge limits. As-bullt drawings and the latest Caltrans maintenance report dated 2009 show the bridge was originally constructed In 1954 by SDG&E. Current right-of-way (ROW) documents indicate the bridge Is owned by the atv of Carlsbad. Verification of bridge ownership and maintenance responsibility will be further explored in this contract. A component of the scope for this project is to establish the existing ROW and to provide temporary and permanent easement requirements if required for the proposed barrier improvements. A visual investigation of the stmcture will determine construction modifications necessary to install the appropriate railing. Coordination with NRG and Caltrans will be required throughout the design and construction phases. This scope of work indudes the development of bridge railing design and PS&E. It is anticipated that the proposed bridge railing will have fencing Installed on top and be the length of the existing diain link fence up to the entrance gate posts. A draft barrier design report will provide preliminary railing concepts for consideration of the structural, civil, and environmental issues. Preliminary opinions of construction costs will be provided for each railing alternative. Final design indudes design calculations, independent design calculations, plans, specifications, and final engineer's estimate of probable construction costs. A resident engineer's pending file will be provided prior to construction and will indude the items listed above and any other pertinent documents. 1.0 Project Management SWE shall provide overall management of consultant and sub consultant personnel. Monthly progress report shall be provided indicating the work accomplished In the last period, anticipated woric to be completed in the next period, issues that require resolution, milestone achieved, meetings held problems encountered and actions taken, potential extra work items, approval actions required, coordination issues and schedule impacts. SWE will schedule a kick-off meeting upon receMng the notice-to-proceed. The City and project team will discuss the preferred style of railing, target dates for team meetings, format for meeting agendas, meeting minutes, monthly status reports, and involdng. SWE will attend all team meetings and issue tailored agendas for ea*. Not all subconsultants are required to attend each team meeting. Meeting minutes will be Issued following each meeting. Attendees will have one week to comment on the draft meeting minutes. Final meeting minutes will be distributed to the project team. Monthly progress reports will be I of 4 Simon Wcmg Engineering Power Plant Discharge Channel Bridge Railing Imptwements Scope o/ Bn^neerkig Services Octobers, 2012 provided to the Gty. They will reflect milestone status and updates that detail the progress and budget at the individual task level. 2.0 Investigation Qvil engineering services include a new sun/ey to establish horizontal and vertical control, existing ROW, utilities, and as-built conditions. Records research will be conducted to locate easements, utilities, parcel maps in the vicinity of the bridge, etc. This Information, along with a legal description and appropriate AutoCAD drawings provided by the Qvil subconsultant, will assist the City of Carisbad In negotiating a temporary construction easement and a permanent easement (If necessary) for the proposed improvements. All sun/ey and mapping data will be supplied in AutoCAD fonnat using NAD '83 horizontal and NGVD '29 vertical datums with ASCII point files for all sun/ey ties made. A visual Investigation will be perfomied by SWE to evaluate the integrity of the structure and the condition of detectable utilities. Following investigation work, a draft Bamer Design Report (BDR) will be prepared with various barrier alternatives and accompanying cost estimates. The BDR will also be utilized to Identify the limits and potential for environmental Impacts (PES). Additional coordination with adjacent property owner NRG, utility owners, potential permitting agencies and other stakeholders Is anticipated for developing a final BDR. 3.0 Engineering Services A multi-disdpllne review will be prepared at the 50% design level but no formal submittal will be made. Design plans and detailing will be submitted at tiie 90% and 100% design levels. This task includes Index sheet; layout sheets, construction detail sheets, utility sheets, a conceptual traffic contorol sheet and bridge railing plans, which are based on Caltrans manuals and procedures. Plans will contain the railing altemative chosen by the City of Carlsbad in the final BDR and will sen/e as the baseline in estimating our final design cost Design tasks Indude calculations based on the latest Caltirans design standards and technical manuals and the Highway Design Manual (HDM). SWE will prepare "checked" bridge railing plans at tfie 90% submittal level and will provide intemal quality control review for all submittal levels. Summarized review comments and responses to the 90% plans will be submitted with the 100% plans. A final mylar bid plan set will be submitted for signatures to tfie Qty at tfie end of the review cycle. A complete Independent check will be done on the bridge railing design and details and by an engineer who was not Involved with the initial design. The "checker" will provide a stand-alone set of calculations tfiat are based on the design details and a complete red-line-yellow-mark set of reviewed plans. The "checker" comments will be resolved with the designer and revisions Incorporated in the 90% submittal. Plat and legal description will be prepared for enaoachment onto NRG property for items such as the barrier, maintenance gate, and temporary construction access. It is assumed that the City will be responsible for obtaining approval for encroachment from the property owner and negotiate all easements forthe proposed railing improvements. Prior to construction, a Resident Engineer's file will be prepared and delivered to the City. The file shall contain, at a minimum, all relevant correspondences, design calculations, preliminary and final construction quantities and cost estimates, plans, total work quantities witii matching woric Item names shown on all bid documents, permits, agreements and relevant technical memos and reports. 2 of 4 / Slnxm Wong Engineering Power Plant Dbdmrge Otannel Bridge RtriBng Improvements scope af Engineering Services October 5,2012 4.0 Permitting and Processing SWE and Hon Environmental Consulting (HON) will attend a Field Review Meeting with Caltrans local assistance representative to define the extent of the project needs. An Environmental Impact Assessment (EIA) and a Preliminary Environmental Study (PES) fomis will be prepared with SWE input Pennitting agency initial coordination will be established by HON. The consultant team will pursue a NEPA Categorical Exdusion (CE) and submit the necessary documentation for approval of an Area of Potential Effects Map (APE) as part ofthe Historic Property Survey Report (HPSR) should it be requested by Caltrans. It Is assumed a Local Coastal Development Permit may be required and will be processed by the City with SWE input 5.0 Preparation of Spedfications and Estimates Special provisions for the project will be prepared for the 90% and 100% submittal levels with conespondlng comment revisions. Special provisions covering bridge railing related improvements vt/ill follow the 2012 version of the Standard Specifications for Public Worics Construction ("Greenbook"). Oty front-end and Federal spedfications will be used as this project uses Federal funds. An electronic version ofthe spedfications will also be submitted In MSWord format The engineer's estimate of probable cost will be completed at the 90% submittal level and revised witii Gty comments for a final estimate at the 100% submittal level. 6.0 OPTIONAL SERVICES Bidding and Construction Support Services SWE will attend one pre-bid meeting, address questions from bidders, and respond to bid phase RFIs related to the bridge railing improvements. In addition, SWE is able to conduct bid mariceting efforts and prepare up to two (2) addendums. Caltrans Coordination SWE will coordinate with Caltrans on structural deficiency determination, structure ownership, easement establishment, and ROW requirements. 7.0 ITEMS NOT INCLUDED IN CURRENT FEE PROPOSAL Coastal Commission Permits Structural Rehabilitation Repairs Water Pollution Control Plans Services During Bidding and Construction Coordination with Caltrans Bridge Seismic and Structural Capacity Evaluations Permitting and Outside Agency Fees 3 of 4 S/mofi Wong Engineering Power Plant Discharge Oiannel Bridge IMIIng Improvemena Scope o/fiig/neeiAig Services Octobers, 2012 8.0 INFORMATION TO BE PROVIDED BY OTHERS Agency Coordination with Caltrans, Homeland Security, Endna Power Plant (NRG), and Poseidon (Gty) Entry permits (City) Payment for All Permits, Processing, MOU and Entry Fees (Gty) Title Sheet Template (Gty) ROW Easement Agreements or Negotiations (Gty) Local Coastal Approvals (City) Environmental Documents and Permits (City) Storm Water Data Report (Gty) Traffic Technical Memo (City) 4 of 4 n 9906 Hkwt Sbstl. M Floor Sin Diego. CAK131 Octobers. 2012 POWER PLANT DISCHARGE CHANNEL BRIDGE RAIUNG IMPROVEMENTS PM« DESIGN CIVR. HON SAMPO TOTAL STASE SWE RBF CONSULTING' ENGMEERMG* SUB CONSULTANT FEES TOTAL PROJECT MANAGEMENT f iOJOOO 1.372 S U72 f 11.372 INVESnOATtON 11.342 1 sg2 20O 11.902 S 12.754 f 24.095 EN6INEERIN6 SERVICES f 2SJ38 f 10.323 100 S 10.423 f 35.758 PERMTTING AND PROCESSING 3J53 f 1J0O S 1.300 f 4.853 PRB>ARATION OF SPEQFICATIONS AM3 ESTIMATES IIJSB < 3.1S5 f . « S 3.155 14.544 MRECT COSTS f 1250 f 200 $ S 200 1.450 SUBTOTAL $ S2470 S 15.442 $ 1«>0 $ 11.982 $ 29.20* t 91 Tlw fMt llttMl abow ara iMMd on tht talowino aMunqiilon*: 1. EnvtonmenlaldoaHiwiilewllwpapeadbyNieClyofGailMw^ 2. No enytonwntol eludlee ei» eiWclliilid 3. NoimidunlmliaMMonmpatiMineludad 4. CoiiDitoniuifNepMeiikiglihdudid 9. WalarPoMDnCommlPlmaienoianiielgMed 5. SeivloM during bkMlng and CMilnielionM not Muded 7. Cl|ftogravUtCtfmmeooidlM8on 8. Cl^ to pmvUe Encina PotverPlMtt and PotaUonoooidlnadon and Enliy Pemil* 9. Cly to oaonflnato wUl Hometond Secuty and oUato psfflilB as necanaiy 10. CIrto pay alpsnii*. pmcaeiing. MOU and EniqrIlMa 11. Bridge aeMe and (feudunl eapacay avakMlbns ara not kictaded 12. ROWae»nmtotobapRwldeby«wClyw«icoonikiadantoySWE 13. Due to «w unknown nahm or liiaexMng ROW, tldipnpesaiassuRiesBto besiaadmatolnitgairiatolilgcalonand iMUga ownenh^ AnUdpatadUDBEO Participation 14M% optional S«rvte— Total S1,S73 STAGE TOTAL BIDDING AND CONSTRUCTION SUPPORT SERVICES f iJOOO CALTRANS COORDINATION f lOXNX) PHASE 11SA - ALLIED GEOTECH f SJSOO SUBTOTAL OPTIONAL SERVICES t OTAL BASE AND OPTIONAL SERVICeS 18 112.373] 9968 hibert street, 2nd Roar San CNego, CA92131 Octobers, 2012 TASK ANALYSIS COST SUMMARY PER FIRM FIRM NAME Sbnon Wong Enolneerfaig RBF Hon Consultino Sampo Enolnsarlng Allied Oaetschnleal TOTAL DBE DBE OPTIONAL SERVICES 1.0 Protect Manaaemant $ $ $ t i 1.1 PfOject Manaoement A AdmlnMratlon $ 3,389.04 $ t $ % t 3.36904 i2 Kidi-Off Meeting S 1,340.82 $ % $ % S 1,349.82 1.3 Team MeMtio* $ 2,143.62 $ 1,372.N t $ t t 3,917.62 1.4 Monthly Status Reports $ 1,303.38 $ s $ % t 1.303.36 1.3 Meetina Mhiutes S 989.92 1 s t $ 88992 1.t Sctwdde $ 642.26 $ t % $ 842.28 TA8K 1.00 SUBTOTAL S 9.BS9.82 S 1.372.00 % s S 11.371.82 2.0 Imnstlgallon s % s 2.1 Survey S 528.82 t t $ S 528.82 Hortiantal and Vsrtleal Control S 304.42 i t $ 3.040.78 t S 3,345.20 nght-of-Wiy Mapping S 1,484.92 t % t 3,114.06 % % 4,596.98 Final Desian Survey S 304.42 s t $ 2,397.83 % % 2,702.23 Easements 1 1,180.50 % t S 914.08 % S 2,094.38 Record Reseatcli $ s s S 818.29 % S 616.29 UtiBv tdanWcatlan and Mapping s s S 741.90 s $ 741.00 Meeting* end Coonllnatkin S 1,798.36 % s J 1,134.79 $ i 2.833.15 2.2 Struduia Invesdaatton $ s s 1 $ J Power Plant OtKhatge Channel S i $ $ $ % Existing UtiHes S 189.12 % s $ $ % 169.12 Structural tnveibo ation > 2,022.76 s s $ s % 2,022.76 2.J Prepare Barrier Oeslon Report S 3,348.18 % 392.00 S 200.00 $ s S 4,340.18 2.4 Phase 1 Envlnnmenlal • Inliai SHa Assessment (Optional Seivloes) $ $ $ $ 9,900.00 J SUBTOTAL TASK 2.00 t 11.341.50 $ 592.00 $ 200.00 t 11,981.88 % S 24,095.19 1.0 Enolneefino Services s $ $ $ t t 3.1 S0« - Plans (Not Submitted) t 1,155.70 $ $ t s % 1,195.70 Piepaie or levlsa the toDowkig sheets: $ $ f % $ THe Sheet $ 304.42 $ s s S 304.42 Kay Map/Une Index Sheet t $ s t t Layout Shsala S $ 3,933.00 s $ $ 3,039.00 ConstiuetiDn Detal Sheets s $ } $ UilSty Sheets t 842.88 i 828.00 % $ i S 1,47086 Conceptual Traffic Control Sheet t t 828.00 t % $ 62e.x 32 Strudum Oeslon - S0% Bildoe Plana (Not SubmMad) S 528.82 S s t S 528.82 Potver Plant Otschama Channel, 90% Plana (Not Submlted) $ 8.327.56 s s % t 8,327.56 3.i 80%-Plans S 928.62 i % S 928.62 MuRWIsClpllne ConslMsncy Review - 50% Plana S 1.832.18 $ 148.00 s s s $ 1,980.18 Prepare or reviae tha tolbwtng sheets: $ 1 s $ $ Typical Cross S«ctlon Sheets S s s % Kay Map/Une IniSex Sheet $ s i s Layout Sheets t S 1,870.00 s s s S 1,870.00 Construction DetaB Sheets t s % Conceptual Traffic Control Sheet s $ 414.00 t % S 414.00 J.4 90% Stmcture Design S 928.82 % % s S 928.82 Power PlanI Olsdiaiae Channel. 00% Plans $ 7.648.98 S $ % S 7,640.96 2S 100%. Plans $ 928.82 s s t $ 926.82 Summartza Revisw Comment* to the 90% Plans $ 888.02 S 138.W t I s S 1,127.82 Ptepsra or Rsvlsa the Folowmo Sheets: s $ $ s s % Typical Cross Section Sheets % S $ $ $ Key Mao/Une Index Sheet % s $ Layout Sheets S $ 1,881.00 s s $ S 1,691.00 Construction Oetai Sheet* % s $ $ t Conceptual Traffic Control Siwel t S 471.00 s f S 471.00 3.B 100%SlniclureDe«lBn i 528.82 t s 100.00 t $ 628.82 Power Plant Dischafoe Channel. 100% Plans $ 1.989.74 s $ t S 1.980.74 37 Final Storni Waiar Data Report $ $ $ 36 Final TrafRc Tachnleal Memo s $ s SUBTOTAL TASK 3.00 $ 25.336.2« S 10.323.00 $ 100.00 $ S 39.799.26 4.D Permlttlna and Procesabio t t s 8 4.1 Field Revlaw Meeting and EIA «)d PES Ibmis S 1,303.38 { S 400.00 s $ S 1.703.38 4.2 PermHIno Aoencv InnkI Coonlkialion $ 180.12 t s 100.00 { $ 269.12 4.3 Envln>nmentBl Documentation (CE/CC) S 628.88 S 400.00 t $ $ 1,026.88 4.4 invfeuiuneiital PermRtinQ S 828.88 $ 200.00 $ $ 828.88 4.S Ceaalal Development PanMis $ 820.88 S 200.00 $ $ 828.68 SUBTOTAL TASK 4.00 S 3.333.12 t 1J00.X t t $ 4,663.12 5.0 Preparsdon of SpacMeatlana and Eatbnstea t t % $ s 5.1 S0%-Plana s i t s Oulftie of SoedRcationa t 482J6 t 298.00 s t $ S 778.58 IdenUlY Chanpaa to Cl/a Tachnleal Spaca $ 329.84 S 902.00 t % $ S 917.64 Lht of Expected Bid Items $ 338.24 S 592.00 $ s t S 930.24 5.2 m-SubmKal $ $ $ s t s CompMe Set of SpadRcationa S 4,178.88 $ 888 00 t s i t 5.066.88 Enelneets Eattmata of Probable Cost $ 1.598.76 S 148 00 t s $ t 1,748.78 100%-Submittal t $ s $ Address Ciys Comments on 90% SutHnttal t 818.09 t 106.00 $ $ $ $ 1,111.08 Revbed SpedAcadons $ 2.789,13 t 298.00 $ $ { S 3.089.13 Revised Englneen EsOmale of PmbalMe Cost S 759.37 $ 148.00 $ t % $ 907.37 SUBTOTAL TASK a.00 S 11,388.87 } 3.159.00 t s s 1 14,543.87 TASK 1.00- &00 SUBTOTAL t 51,419.75 t 19,442.00 S 1,800.00 S 11,961.69 $ S 79,091 .U DIfKtCoeta t 1,290.00 s S 200.00 t $ S 1,490.W BASE SCOPE TOTALS S 82.888.97 f 18.442.00 t 1,100.x t 11J81J8 t 81,873J6 OPTIONAL SERVICES. PtlASe 1 OA $ 8.800.00 1 of 1